Existing Buildings' Operation and Maintenance - Renovation Project of Chow Yei Ching Building at The University of Hong Kong
Existing Buildings' Operation and Maintenance - Renovation Project of Chow Yei Ching Building at The University of Hong Kong
Existing Buildings' Operation and Maintenance - Renovation Project of Chow Yei Ching Building at The University of Hong Kong
Keywords: existing building; operation and maintenance; energy consumption saving retrofit; energy
audit; measurement and verification; facility improvement measures (FIM)
* Corresponding author.
sunxiaonuan@gmail.com Received 29 November 2012; revised 24 November 2013; accepted 13 January 2014
................................................................................................................................................................................
1 INTRODUCTION hottest months with high humidity, which are the highest energy
consumption period. According to the data from the Hong Kong
With the rapid development of urbanization, China’s building Observatory, there was an average rise of 0.128C per decade from
energy consumption increased year by year, which has risen to 1885 to 2009. The final energy consumption of the buildings can
.30% of the whole energy consumption. The energy consump- be affected by rising temperatures as it will reduce energy con-
tion of existing buildings cannot be ignored. Due to obsolete sumption for heating and raise demand for cooling [2, 3]. The
equipment and construction, as well as architectural forms, energy consumption of buildings in Hong Kong especially in
thermal performance and engineering equipment problems, exist- summer is so high because of the high density of the buildings
ing buildings cause a serious waste of resources and energy. Most and high energy consumption in the summer. So, the retrofit of
of the existing buildings now need to be updated to save energy. the existing buildings in Hong Kong plays a crucial role to reduce
According to the China Energy Conservation Association the energy consumption. This paper aims to find a typical and
Committee’s statistical service, the existing building area in China scientific methodology to do the retrofits to reduce the energy
is .43 billion m2, of which only 5% can achieve green building consumption especially for the cooling system in summer.
standards (http://www.cabr.com.cn/InfoViewer.aspx?BizMainClass=
2&BizSubClass=1&RowGuid=2189). These green building stan-
dards are based on the three-star green building certification system 2 DESCRIPTION OF THE PROJECT
in China. This research introduced a scientific methodology of the
energy audit (EA) before and after the retrofit. The University of Hong Kong (HKU) has contracted with Siemens
Existing buildings’ operation and maintenance has large in- Limited Hong Kong (SLHK), with project management assistance
fluence and potential to the whole energy-efficiency process. from Eco-Tech International (ETI), to provide support for
From the research perspective, the retrofit of existing building Leadership in Energy and Environmental Design (LEED) for Existing
need to solve three key issues that are EA and energy-saving po- Buildings: Operations and Maintenance (EB:OM) certification for
tential assessment before the retrofit; choosing the most opti- the Chow Yei Ching (CYC) Building. With a concerted effort, the
mized transformation measures; measurement and verification building has a chance of achieving the gold certification objective.
after the retrofit. [1]. This research that based on the real retrofit project of CYC
Hong Kong’s climate is subtropical, tending toward temperate Building at HKU will present more practical experience and
for nearly half of the year. July, August and September are the methodology.
In fact, a list of issues violating the energy conservation prin- 2.2 Form EA team
ciples, such as those outlined in the ASHRAE Standard With many technical and funding problems, building owners
100-2006 [4], was identified after the walk-through assessment need a professional team to manage the whole project. One of
as discussed in the following subsections. the most effective ways is to employ a third party which is called
energy service company (ESCO) to operate.
2.1 Scope of the EA The ESCO will promise the energy efficiency of the project
According to Figures 1 and 2, EA flow chart that described in the and profits that will come from the retrofits to the building
article EA of an educational building in a hot summer climate owners. This ESCO can reduce the risk of the project, and it can
[5], the EA process includes several tasks. The first task is to also overcome the technical hurdles and finally achieve the goal
define the scope of the EA, including the areas to be audited, the of energy saving. In the contract, the ESCO reported a guarantee
audit sophistication level and the savings anticipated. of energy savings that can be translated into profits. If the real
In this study, CYC Building is selected to be implemented with energy savings are less than the guaranteed energy savings after
EA. The building was built in 1993 and now it is a multipurpose the retrofits, the ESCO will bear the part which does not achieve
the guaranteed energy savings. In this project, SLHK has pro-
before and after each retrofit, giving advice of the appropriate tech- † FIM1: chilled water plant upgrading and optimization.
nologies, making plan according to the existing buildings’ operation † FIM2: building management system (BMS) upgrading and
and maintenance in LEED and so on Figure 3. with energy monitor and controlling (EMC).
† FIM3: lighting retrofits.
† FIM4: window film.
† FIM5: solar panel.
3 INFORMATION COLLECTING PROCESS † FIM6: green roof with condensate recycling.
BEFORE THE RETROFIT † FIM7: micro-wind turbine.
† FIM8: variable-voltage variable-frequency systems for elevators.
3.1 Budget and Payback
During the 12-month period from January 2009 to December After proposing these eight FIMs, the ESCO conducts the com-
2009, the energy requirement for CYC Building was met as fol- puter simulation to evaluate how much energy can be saved
lowing (Figure 4 and Table 1): after the retrofits. The results are shown in Table 2.
In this table, the wind turbine is not applicable in Hong Kong
Table 1. Base-year electricity consumption (data from Estate Office of the HKU).
Month Electricity consumption Electricity fee (maximum demand tariff ), $
kVA consumption kWh consumption kVA charge kWh charge Total charge
January 2009 779 208 980 $33 552 $237 639 $271 191
February 2009 863 224 400 $37 115 $250 787 $287 902
March 2009 992 258 280 $42 540 $288 642 $331 181
April 2009 801 275 740 $34 294 $316 097 $350 391
May 2009 1016 324 240 $43 586 $359 699 $403 285
June 2009 1309 384 660 $55 893 $427 920 $483 813
July 2009 980 371 210 $42 063 $409 721 $451 784
August 2009 1102 400 820 $47 196 $442 864 $490 060
September 2009 1070 418 230 $45 833 $461 169 $507 002
October 2009 1242 349 380 $53 099 $389 294 $442 393
November 2009 1218 296 280 $52 057 $332 032 $384 089
Table 2. Investment budget and return cycle (data from Estate Office of the HKU).
No FIM Estimated existing Estimated Annual Percentage Annual electricity Project cost Simple
consumption postretrofit electricity of savings savings (HKD) (HKD) payback
(kWh) consumption (kWh) savings (kWh) (%) (years)
1 Chilled water plant 1 749 705 1 013 392 736 313 42 923 631 7 973 670 8.6
upgrading
2 BMS upgrading 123 355 154 737 1 060 970 6.9
3 Lighting retrofits 604 291 390 562 213 729 35 267 162 1 717 710 7.4
4 Window film 59 242 74 312 585 000 7.9
5 Solar panels 2373 2976 388 000 130
6 Green roof 20 189 25 325 706 000 27.9
7 Micro-wind turbine N/A N/A 188 000 N/A
8 Elevators updating 374 296 273 239 101 057 27 126 767 3 800 000 30.0
Total 1 256 259 1 574 911 16 419 350
operated fully automatically. We found some of the temperature 4 DATA ANALYSIS AND FIMs PROPOSAL
readings in the BMS were manually input or in error condition
(Figure 6). 4.1 Electricity distribution
Air handling unit (AHU and PAU: precooling air handling 4.1.1 Chiller plant consumption
unit): There are totally 23 of AHUs and 9 of PAU serving the The building consumption can be divided into two groups, one
building. With the supplied chilled water from the chiller plant, is weather sensitive and the other is non-weather sensitive.
the AHUs provide cooling to each floor. Chiller plant consumption is sensitive to the weather, the
The problem is the temperature controls of the AHU and higher the temperature/humidity, the higher the plant power
PHU that are being done by standalone electronic controller. No required to provide cooling. The consumption profile is fluctu-
connection to the BMS (Figure 7). ated throughout the year depends on the weather. Apart from
Ventilation fans. There are totally 36 ventilation fans serving chiller plant, other loadings in the building are non-weather sen-
the building. All the ventilation fans are being individually con- sitive and are relative stable throughout the year. From the
trolled by the Honeywell BMS for start and stop control accord- on-site measurement, the monthly constant load is 166 MWh.
ing to the preset time schedule (Figure 8). By subtracting this constant load, the annual chiller plant con-
Fan coil units. There are totally 270 FCUs installed at different sumption profile can be obtained (Table 7).
area of each floor with the supplied air from the AHU and
PAU. All the FCUs are being zone controlled by the Honeywell
BMS for start and stop control according to the preset time 4.1.2 Air-side equipment—AHU, PAU, VF, FCU, split unit
schedule. With reasonable assumption of operating hours, the consump-
The temperature controls of FCUs are done by conventional tion of the air-side equipment can be obtained as shown in
thermostat. Table 8.
Lighting system. Various types of lighting fixtures were in-
stalled throughout the whole building. Most of them are T8
4.1.3 Lighting system
tubes. All lighting fixtures are controlled by conventional timers
With the reasonable assumption of the operating hours, the elec-
according to the preset time schedule (Table 5).
tricity consumption of the existing lighting system can be
Lift system. There are totally four lifts installed in the CYC
obtained.
Building. One of them is service lift.
The annual electricity consumption is 604 291 kWh, which is
The lift schedule is as given below (Table 6).
approximately equal to 16.1% of the building consumption.
Power quality system. To eliminate the effect of harmonic, the
University had already installed capacitor banks for power factor
improvement. During the site visit, the power quality was in 4.1.4 Lift system
very good condition, the power factor is 0.98 (Figure 9). With the estimation of the existing maintenance contractor, the
So after the survey of the mechanical and electrical systems, annual consumption of the lifts in CYC Building is approxi-
many weak points of the system can be found. The detailed ret- mately equal to 10% of the building consumption. The annual
rofits plan will be described in the Section 4. consumption is 374 296 kWh.
Area Temperature set point (8C) Measured temperature (8C) Humidity set point Measured humidity (%) CO2 set point Measured CO2 (ppm)
According to the analysis, it is proposed to install 3M NV-35 over a waterproofing membrane. Also known as ‘living roofs’,
window film at the north, south and west sides of the CYC green roofs serve several purposes for a building, such as absorb-
Building. The total area of the window film is 843 m2 (9080 ing rainwater, providing insulation, creating a habitat for wild-
square foot). life, and helping to lower urban air temperature and combat the
The author also tested the performance of 3M NV-35 window heat island effect.
film, and it improves the shading coefficient by reducing the solar By considering the condition of the existing building informa-
transmission through the window. If it is set as 100% solar trans- tion, it is suggested to build a green roof at the area just above the
mission through the existing windows (not the real value of solar concourse. The total area of the suggested green roof is 2400 m2.
transmission), the solar transmission is only 44% of the 100%
with the window film (Figures 13 and 14; Table 9).
5 MEASUREMENT AND VERIFICATION
4.2.5 Green roof AFTER THE RETROFITS
A green roof is a roof of a building that is partially or completely
6 CONCLUSION
This paper studied how to measure and compare the energy
consumption and indoor environment quality before and after
Figure 14. Measurement of the solar transmission. the renovation. It has also pointed that, in the whole project, EA
is the crucial part which is a process to detect operating pro-
blems, improve occupants comfort and optimize energy use of
Table 9. Measurement data of the window film. existing buildings. In addition, it also identified the opportun-
Measurement 3M window film Existing window
ities for energy conservation measures.
This research introduced a scientific methodology to com-
Indoor temperature (8C) 26.1 27.9 plete the EA before and after the retrofit. The first task was to
Indoor relative humidity (%) 46.4 43.9
define the scope of the EA, including the areas to be audited, the
Solar transmission (%) 44 100
audit sophistication level and the savings anticipated. The
A. Partially measured retrofit isolation Engineering calculations using short Lighting retrofit where power draw is measured
Savings are determined by partial field measurement of term or continuous postretrofit periodically. Operating hours of the lights are assumed
the energy use of the system(s) to which an ECM was measurements and stipulations. to be one half hour per day longer than store open
applied, separate from the energy use of the rest of the hours.
facility. Measurements may be either short term or
continuous.
Partial measurement means that some but not all
parameter(s) may be stipulated, if the total impact of
possible stipulation error(s) is not significant to the
resultant savings. Careful review of ECM design and
installation will ensure that stipulated values fairly
represent the probable actual value. Stipulations should
be shown in the M&V plan along with analysis.
[2] Ebinger J, Vergara W. Cimate Impacts on Energy Systems: Key Issues for Energy [5] Alajmi A. Energy audit of an educational building in a hot summer climate.
Sector Adaptation. The World Bank. 2010. Energy Build. 2011;47:122– 30.
[3] Landsberg HE. The Urban Climate (Google eBook). Academic Press, 1981, 275. [6] EVO (Efficiency Valuation Organization). M&V by International
[4] ASHRAE, ANSI/ASHRAE Standard 100 – 2006. Energy Conservation in Performance Measurement and Verification Protocol (IPMVP).
Existing Building. American Society of Heating, Refrigerating and [7] USGBC. LEED for Existing Buildings Reference Guide, U.S. Green Building
Air-Conditioning Engineers Inc., 2006. Council.