Project
Technical Specifications
Project Type
Project leader
CABAX Company
PRESENTATION OF CABAX
-for the brand of the inverter i think it's clear just must provide CE certification
-for the batteries we need to know the brand that you will use and must have CE Certification and MSDS
-for the AC/DC protection we recommend to use CHINT but must have CE Mark on it and CE
Certification.
-between the PV input and the Inverter must put a rotary switch to separate the power
-between the batteries and the inverter must put FUSE and rotary switch to separate the power
-monitoring system:
1. *display inside the Cabinet to check the battery capacity, the power generates from the panels, and
the output power and error
2. *the system must be connected by COMM card 3G/4G/5G and WIFI for the possibility to check the
system by phone
-AC input must be with terminals (See picture "A")
-AC output must be with terminals (See picture "A")
-DC PV input must be connected with terminals (See picture"A")
-when Smoke sensor detect Smoke the firefighting system (Condensed Aerosol generator) turn ON,
harness and red flashing light above the Cabinet
-LED Light ON when open the door and OFF when close the door
-Air conditioner
-the Cabinet must be equipped with 4 doors (2 on the FRONT and 2 on the BACK)
-the free space must be ready with Battery Rack, if the customer need to add more batteries
-the Cabinet must be waterproof IP65
Characteristic of product
The contractor will have for the manufacture of the product the obligations
of the following stages before final validation,
• A model in DWG format 3D.
• A prototype for which modifications can be made to any time phase of
the project.
• A trial in all the terms possible that he will be able to meet during her
service life (waterfall / wind / corrosion / sealing) this list is not
exhaustive.
Reception
Documentation and instructions of use.
The contractor must provide a set of documentation in order to make it
possible for all users to operate the ENERGY BOX, the list below is not
exhaustive:
• Instructions for use in French and in English.
• Indicated the maintenance methods of the product.
• Indicated the diagram and wiring.
• Code via a QR CODE the parts in order to be able to replace them more
easily.
• Display a table with the list of error and troubleshooting codes that will
be displayed on the console ordered.
Procedure of reception
After supplying all the elements and carrying out all the tests described
above, the contractor or his representative will carry out the provisional
acceptance operations with the CABAX Company.
Following the provisional acceptance visit, the CABAX company will
submit the list of reservations to the contractor.
The Company will then have a period of 60 working days to remove all
reservations and obtain the final acceptance report in order to launch full
production of the product.
END OF SPECIFICATION