PROJECT REPORT M/s. Usha Foam PVT. LTD.
1. EXECUTIVE SUMMARY
M/s. Usha Foam Pvt. Ltd. has proposed to manufacture the product Polyurethane Foam
at K-19, Sector-15, G.I.D.A. Gorakhpur, Uttar Pradesh.
There is no forest/wild life sanctuary/eco sensitive area present within 10 Km area from
the project site.
The proposed unit will be developed in an industrial park. The land is already Non-
Agriculture. The Proposed project activity will be developed as per plan lay out shown in
Annexure – 2 of EC Application in industrial park.
The Proposed project activity will be carried out in existing Industrial shed. No additional
construction activity will carry out.
For, Electric power requirement: Unit will apply for electric connection of 150 KVA to DGVCL.
One D. G Set of capacity 2150 KVA will be installed which will be used in case of power
failure.
For proposed activity, water required for domestic & industrial purpose will be sourced from
Bore well. Domestic effluent will be disposed in to Septic tank/Soak pit system. No Industrial
effluent will be generated from process.
No solid hazardous waste will be generated from manufacturing process. Hazardous waste
generated from the other industrial activity will be stored in a separate hazardous waste
storage area and then it will be disposed by selling to register re-cyclers/re- refiners/reused.
Proper safety measures will be undertaken during storage, handling and use of hazardous
substance. Fire hydrants, Hose reel & Portable Fire Extinguishers will be provided at key
location.
[1]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
LIST OF PRODUCT
Sr. Quantity
No. Name of Product (MT/Month)
1. Polyurethane Foam 300
PROJECT PROPONENT
M/s. Usha Foam Pvt. Ltd. is a Private Limited Firm.
Ms. Priyanka and Ms. Parinaz are the Directors of the company.
M/s. Usha Foam Pvt. Ltd. is a small scale unit. It falls under the category of synthetic
organic chemical (Polyurethane Foam) industry.
M/s. Usha Foam Pvt. Ltd. will be supplying polyurethane foam to several industries. There
are numerous uses of polyurethane foams such as packaging, acoustic insulation,
filtration, sponges, seals, padding in sports shoes, paint rollers, medical applications,
textiles, furniture, Bedding and many other varied applications. Due to increase in both
national & local market demand, unit proposes to the production of Polyurethane foam.
People will get direct & indirect employment due to the project activity. Unit will hire 75
employees- (50 men + 25 women)
[2]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
3. PROJECT DESCRIPTION
3.1 TYPE OF PROJECT
The unit has proposed to manufacture synthetic organic chemical – Polyurethane foam.
3.2 LOCATION
The site is located at about 26.7393° N, 83.2765° E latitude and longitude respectively.
[3]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
The raw materials n-Butyl Alcohol (Polyol), TDI (Toluene Di Isocyanate), Catalysts (Silicon,
SO, DMEA/MI), Filler (CaOH) and MECL (Methylene Chloride) are pumped from their own
storage tank in required proportions to a common mixing chamber where the materials are
mixed at high speed and flows as cream on to a conveyor.
While passing on the conveyor the cream expands to full height to make foam blocks.
Continuous foamed blocks are cut into required block sizes by the block cutter and the cut
blocks are left for sufficient time in open atmosphere for curing.
The blocks are further cut into sheets of required size by horizontal and/or vertical cutting
machines and are packed for dispatch or cut into rolls by peeling machine.
[4]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
REACTION CHEMISTRY
MATERIAL BALANCE
Electric power requirement for proposed project is 150 KVA, which will be procured from
Dakshin Gujarat Vidyut Company Ltd. (DGVCL).
One D. G Set of capacity 250 KVA will be installed which will be used in case of power failure.
[5]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
WATER CONSUMPTION
Water
Sr.
Category Consumption
No.
(KL/day)
1. Domestic 11.0
2. Gardening 12.0
i. TOTAL 23.0
1. Process 3.0
2. Chilling Plant 0.3
ii. TOTAL 3.3
GRAND TOTAL (i + ii) 26.3
WASTEWATER GENERATION
Water
Sr.
Category Generation
No.
(KL/day)
1. Domestic 10.0
2. Gardening NIL
i. TOTAL 10.0
1. Process NIL
2. Chilling Plant NIL
ii. TOTAL NIL
GRAND TOTAL (i + ii) 10.0
Disposal of Wastewater:
No Hazardous waste will be generated from the process. Hazardous waste generated
from other industrial activity will be stored in a separate hazardous waste storage area
and it will be disposed by selling to the register re-cyclers/re-finer/reused.
[6]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
The municipal solid wastes generated during operation phase will be disposed to bin of
Industrial park.
Location of Activity
Project
[7]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
4. SITE ANALYSIS
4.1 CONNECTIVITY
The project site is well connected with all infrastructures like National Highway, Railway,
Airport, telephone, internet, fax, post, etc.
Nearest town Gorakhpur is located 2 6 K M from the project site.
Nearest railway station Gorakhpur Junction.
Nearest airport Kushinagar 30 KM from the project site.
Sr.
Title Area (m2)
No.
GROUND FLOOR
Finished product section (Cutting, Packing &
1. 932.4
Storage)
2. Raw Material Storage Area 337.0
3. D. G Set 5.0
4. Hazardous Waste Storage Area 10.0
5. Office 30.0
6. Parking Area 97.5
7. Open Space 1386.1
8. Product Curing Area 932.0
9. Process Area 189.0
10. Chilling Plant 4.0
11. Road area within premises 1450
TOTAL AREA 5373.0
4.3 TOPOGRAPHY
The project area is plain and flat surface with elevation 21 m above MSL. However, in the
NE part, the elevation is in the range of 21 – 24 m above MSL & in the SW part, the elevation
is in the range of 18 – 25 m above MSL. The general slope of the area is from
[8]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
NE to SW. In the buffer zone towards NE, E & SE, the elevation rises to 24 m and above
MSL & towards S, SW & W the elevation descend to 18 m above MSL.
Soil in the study area is primarily black & Silty clay in nature.
The proposed project is located in an industrial park. Industrial Park authority will provide
power supply, water supply, pucca road, telephone & other communication network &
drainage network in the area.
Skilled & unskilled manpower are available within area. Ambulance and emergency fire &
medical service available round the clock.
[9]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
5. PLANING BRIEF
5.1 PLANNING CONCEPT
The unit has proposed to manufacture Polyurethane Foam. Proposed project activity will be
carried out at K-19, Sector-15, G.I.D.A. Gorakhpur, Uttar Pradesh. The Proposed project
activity will be carried out in existing Industrial shed. No additional construction activity will
carry out.
All the basic facilities like tap water, sanitation & drinking water, canteen & First aid box
will be provided within premises.
The project site is well connected with the road, railway and airport. Finished products and
raw materials will be transported through road. There is no requirement for the development
of other road or railway.
[10]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
The project is located in an industrial Park. Industrial park Authority will provide power
supply, water supply, pucca road, telephone & other communication network & drainage
network in the area.
Skilled & unskilled manpower are available within area. Ambulance and emergency fire &
medical service available round the clock.
Local people will be hired for new products and they will be trained within unit. Thus, no
social infrastructure will require.
All the basic facilities like tap water, sanitation & drinking water, canteen will be provided
within premises.
First aid box, free medicines & doctor service (on call basis) will be provided.
[11]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
6. PROPOSED INFRASTRUCTURE
[12]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
The project is located within an Industrial park therefore no Rehabilitation & Resettlement
(R & R) plan is involved in proposed project.
[13]
PROJECT REPORT M/s. Usha Foam PVT. LTD.
9. ANALYSIS OF PROPOSAL
Due to proposed project it is expected that employment will increase for people who reside
nearby project area. Approx. 50 men & 25 women will get employment directly.
Due to increase in raw material and product transportation activity, indirect employment
will generate.
Due to green belt development, aesthetic value of local environment will improve.
[14]