0 Scope
1.1 General
This Standard Operating Procedure (SOP) is to establish requirements for the control of outsourced
processes, including the selection of suppliers. It defines controls for suppliers with independent quality
systems that provide outsourced process activities.

1.2 Application
This SOP applies to processes defined in the QMS, or are the regulatory or statutory responsibility of
Zoppas Industries Romania but are not performed by Zoppas Industries Romania employees.
Typical outsourced processes may include, but are not limited to design, development, analysis,
calibration, product warehouse and Facility Management.
The procedure is to be utilized by Purchasing, Quality, and any organization within Zoppas Industries
Romania seeking outsourced process work subject to this SOP.
2.0 References
A. POLICY-XXX Quality Manual
B. ISO 13485 Medical Devices – Quality Management Systems – Requirements for Regulatory
C. Purposes, §1.2 ¶4, §1.4 ¶4,
D. SOP-XXXX Vendor Qualification
E. SOP-XXXX Purchasing
F. Anex A. List of Outsorcing Processes in ZIR.

3.0 Terms and Definitions


1. Outsourced Process – A process that the organization needs for its quality management system and
which the organization chooses to have performed by an external party. It includes processes for
management activities, provision of resources, product realization and measurement, analysis and
improvement

4.0 Responsibility and Authority


1. Quality Manager – Responsibility includes review, approval, retention, and identification of all
Supplier Quality Agreements. The Quality Manager als performs supplier audits as necessary.
2. Purchasing Coordinator – Responsibilities as defined in SOP-XXXX Purchasing and SOPXXXX
Vendor Qualification, with respect to outsourced process suppliers.
3. Originating Department Manager – Responsible for selection of the supplier, delivery of requirements,
and establishment of the Supplier Quality Agreement. The manager shall also assist the Quality Manager
for any supplier audits.
4. Human Resources – Responsible for retention of training records.
5.0 Control Measures

5.1 Acquisition

5.1.1 Vendor Qualification

The process to be performed by the supplier shall first be examined to determine if there are any unique
certification requirements needed (e.g. a supplier performing calibration should have ISO17025
certification, a supplier performing design service should be ISO13485 certified) A review of supplier’s
ISO status shall be performed as part of the Vendor Qualification process. If ISO certified, then a focused
study of the certification shall be performed by the Quality Manager.

This may be accomplished by reviewing the scope of the certification or by reviewing relevant portions
of the Vendor’s Quality manual to verify that no sections that are needed have been excluded or
otherwise not performed as a normal part of the company’s business. If no ISO certification exists, then
the Quality Manager shall perform a full study and audit of the relevant company processes to
determine if the supplier’s processes are sufficient to support the regulatory, statutory, and QMS
requirements of . Evidence supporting these requirements shall be appended to the Vendor
Qualification Form. If the evidence supports usage of this vendor in an off-site capacity, the vendor
Qualification Form shall be positively marked to confirm the status. If the vendor is determined to be
incapable of performing the desired activities off-site, yet satisfies personnel qualifications necessary for
the activity, the supplier may be approved in an on-site capacity, provided that personnel are trained as
appropriate under the Quality System.

5.1.2 Purchase Orders

Contracting of service shall be compliant with SOP-XXXX Purchasing procedures and purchase orders
shall be used.

5.2 On-Site work

Any outsourced process work provided on premises shall conform to ’s Quality system. Any personnel
performing these activities shall be appropriately trained and training records shall be maintained by
Human Resources.

5.3 Off-Site Custom Processes

5.3.1 Outsourced Process Input Requirements

The Originating Department Manager shall provide, or provide documented approval, of requirements
for the off-site supplier, as required by ISO13485 to assure the supplier has adequate input for the
activity to be performed. A record of the transmittal and receipt shall be maintained by the Quality
Manager.

5.3.2 Supplier Quality Agreements

5.3.2.1 Contracts
A Supplier Quality Agreement shall be established by the Originating Department Manager and
approved by the Quality manager and the Outsourcing Contractor for each outsourced project. It shall
be included in, or referenced by a contract or purchase order.

5.3.2.2 Responsibilities

The agreement shall clearly indicate the interaction between ’s process and the supplier’s process. It
shall define:

Any input that the outsourced organization needs to perform its activity in accordance with ISO13485,
or IEC 62304 where relevant,

• Any output that the organization will produce,

• How the outsourced output will provide input to the next activity of ,

• Any interactions required of the activity (while it is being performed) that is outsourced, between the
outsourced organization and

• Any additional review points needed that would result from outsourcing an activity or portion of an
activity. These reviews may be joint reviews, or reviews not specifically defined in either quality system
procedures but necessary to assure compliance to ISO13485.

5.3.2.3 Audits

The Supplier Quality Agreement shall contain provisions for to audit the supplier.

5.3.2.4 Corrective Actions

The Supplier Quality Agreement shall contain provisions for mutual notifications of any corrective
and/or preventive actions that need to be addressed to assure conformity to quality system or
regulatory requirements. It shall also define the monitoring activities necessary to manage any identified
actions.

5.3.2.5 Complaints

The Supplier Quality Agreement shall identify communication methods to both parties where any issues
are detected with product related to the outsourced process.

5.3.3 Assessment of Outputs

The Originating Department manager, or designate, shall review the output of any outsourced process.

5.4 Off-Site Standardized Processes

No additional controls beyond vendor qualification and purchase orders are required for standardized
processes such as calibration.

5.5 Identification

The Quality manager shall keep a file with all currently active Supplier Quality Agreements.