Method Statement For Pumps FF
Method Statement For Pumps FF
Method Statement For Pumps FF
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Method statement for revamping Urea plant Ammonia (NH3) AND Re-
Document Tittle
cycled Carbamate (R.C) Pumps
DOCUMENT NO:
Index
1. Introduction................................................................................................................................3
2. Safety...........................................................................................................................................4
3. NH3 & R.C Pump Specification.................................................................................................5
4. Pump Parts.................................................................................................................................9
5. Why revamp of Pumps?..........................................................................................................19
6. OEM recommendation.............................................................................................................20
7. Pump Wise Scope –.................................................................................................................23
8. Execution Methodology...........................................................................................................27
9. Reports:.....................................................................................................................................45
10. Annexures.................................................................................................................................45
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
2|Page
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
1. Introduction
M/s. GSFC is having two Urea plants at Vadodara unit producing fertilizer grade pilled Urea
having capacity of 323 and 800 MTPD each. Urea I & II plants were established way back in
year 1967 & 1969 respectively. GSFC is operating these plants for more than 50 years with
regular repair & Maintenance.
To improve the reliability and safety of very old plants along with reducing specific energy
consumption to meet the targeted energy norms stipulated by Government of India, GSFC
intends to revamp Urea-II plant with increased capacity of 1175 MTPD from existing Plant
capacity of 800 MTPD by using some of the equipment / machinery of Urea – I Plant like
use of One CO2 Compressor, Prilling Tower etc.
XU-P101C & XU-P101B:
Total 6 nos. of Pumps are being used for UREA-2 plant placed in the compressor house. 2
nos. of working for high pressure liquid ammonia feed pumps supplied by Peroni Italy
currently in working condition requiring valve modification to accommodate to licensor
requirements. [ Tag no. XU-P101C & XU-P101B].
Sens
itivit XU-P101A:
y:
This Replacement of ammonia pump XU-P101A is required. New pump and motor will be
Doc
ume procured by L&T from Peroni Pompe. Testing of foundation is required before installation of
nt is
clas
sifie
new pump to insure its adequacy. Pulsation analysis to be performed post installation.
d as
"LN
T
Gen XU-P102C:
eral
Busi
ness
".
3|Page
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
XU-P102C to be replaced as well. Spare pump and its attachments to be collected from
GSFC warehouse. Testing of foundation is required before installation of new pump to
insure its adequacy. If fails new foundation must be made as a replacement at the same
location. Pulsation analysis to be performed post installation.
XU-102B:
Pump XU-102B to be retained as it is for standby i.e., no modification or revamp activity is
required.
XU-P102A:
Modification in pump XU-102A as per the requirement suggested by the OEM. Change of
nozzle ring are required.
XU-P107:
Installation of new motor, new coupling, and non-sparking perforated coupling guard to the
pump. Replacement of gaskets O-rings and new foundation bolts
2. Safety
1. All JSA’s and Task risk assessments should be in approved form & all Work
Permits to be checked and ensured in place before the start of any work.
2. Conduct Toolbox talk before starting of any activity/shift with execution team to
ensure flawless and safe execution.
Sens
itivit 3. All required tools shall be prepared and brought into place when site conditions
y:
This allow.
Doc
ume 4. All machine such as welding / grinding / cutting machines, lifting tools and tackles
nt is
clas and any other mechanical & machinery resources shall be checked before use if
sifie
d as any damages are visible.
"LN
T
Gen
5. When crane lifting/ Hydra (at new canteen location) is required to execute the
eral
Busi
described job, then required documents for the lift shall be available.
ness
".
4|Page
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
1. All Job safety analysis (JSA) and risk assessment will be in approved state
before starting of any activities.
2. Prior to start of work all mandatory safety protocols shall be followed.
3. All hot work/ cold /height work permits, and permissions will be obtained in
advance from relevant authorities of client in accordance with client HSE
system and format.
4. Appropriate methodology statements shall be submitted on obtaining, handling
& closure of all permits by L&T HSE.
5. Single point responsibility shall be established for co-ordination of receipt of
permits from Client.
DOCUMENT NO:
DOCUMENT NO:
DOCUMENT NO:
Sens
itivit
y:
This 4. Pump Parts
Doc
ume Pumps consist of below major parts.
nt is
clas
sifie 1. Pump –
d as
"LN
a) Head
T b) Tie Rod
Gen c) Plunger
eral
Busi
ness
".
8|Page
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
The first thing you’ll notice in a compressor is its heavy and rugged frame which encloses all
the rotating components such as the crankshaft and crosshead assembly.
The frame is also called a crankcase and it has a square or rectangle shape. Its role is to
offer support to the crankshaft & cross head assembly.
2. Cylinder
The cylinder is a pressure vessel that contains the gas in the compression cycle. they are
one of the most important components of a reciprocating compressor. Double-acting
cylinders compress gas in both directions of piston travel. Most reciprocating compressors
use double-acting cylinders. Choice of cylinder material is determined by operating
Sens pressure.
itivit
y:
This
3. Distance piece
Doc
ume The distance piece provides separation between the compressor cylinder and the
nt is
clas compressor frame. t can either have a single, double, or even an extra-long compartment
sifie arrangement. the single design uses a structure where the distance between the diaphragm
d as
"LN
and cylinder packing is extended to prevent any part of the rod entering the crankcase and
T cylinder stuffing box.
Gen
eral
Busi
ness
".
9|Page
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
4. Crank shaft
The crankshaft rotates around the frame axis and drives the connecting rod, piston rod, and
piston. Crankshafts as reciprocating compressor parts are either connected to the electric
motor directly or indirectly with the use of a belt and pulley system. As the motor shaft
rotates, the crankshaft also performs a rotary motion which gives the piston the ability to
carry out its reciprocating motion inside the cylinder. But first, a rod must be connected to
the crankshaft and rod to enable the piston to perform an upward and downward movement.
5. Connecting rod
This component connects the crosshead and crankshaft, converting a rotary motion into a
motion that is reciprocating. Manufactured out of forged steel, the connecting rod also has a
drilled hole to allow for the passage of oil.
6. Cross head
A crosshead enables the piston to be inserted in the cylinder bore. The use of a crosshead
enables a compressor to use a narrow piston and it enables longer strokes and higher
efficiency.
7. Piston rod
Threaded through the piston, the piston rod is responsible for transmitting the reciprocating
crosshead into the piston. This component is traditionally manufactured out of alloy steel.
Where it is passed through the cylinder packing, the surface must be polished and
hardened.
Like the piston rod, rod packing is essential to preventing gas leakage as it is passed
through the cylinder and crank closure. Where a cooling pack is needed, stuffing boxes may
be jacketed for liquid coolant. Packing rings sit at the heard of the rod packing assembly.
Sens
itivit
y:
This
Doc 9. Piston
ume
nt is
clas
The piston is often referred to as the heart of the reciprocating compressor. The piston
sifie moves up and down in the cylinder. This movement knows as a reciprocating movement.
d as The piston sucks and compresses the air during its motion. The piston is located at the end
"LN
T of the piston rod and acts as the movable barrier in the compressor cylinder. Selection of
Gen material is based on strength, weight, and compatibility with the gas being compressed. The
eral
Busi
ness
".
10 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
piston is usually made of a lightweight material such as aluminium or from cast iron or steel
with a hollow centre for weight reduction.
During the piston movement within the cylinder, the coolant must not leak through the space
between the piston and the cylinder wall. So, this air compressor component covers with the
piston ring. The piston rings are wounded on the piston and as the piston moves up and
down the cylinder, the piston rings come in contact with the walls of the cylinder. Due to the
amount of friction created during this reciprocating motion, rings must be replaced
frequently to maintain the seamless operation of the compressor. In some cases, a wear
band or rider ring is used as an additional piston ring.
11. Bearing
Bearings located throughout the compressor frame assure proper radial and axial position-
ing of compressor components. Main bearings are fitted in the frame to properly position the
crankshaft. Crank pin bearings are located between the crankshaft and each connecting
rod. Wrist pin bearings are located between each connecting rod and crosshead pin.
Crosshead bearings are located at the top and bottom of each crosshead. Most of the bear-
ings in reciprocating compressors are hydrodynamic lubricated bearings. Pressurized oil is
supplied to each bearing through oil supply grooves on the bearing surface. The grooves
are sized to ensure adequate oil flow to prevent overheating.
The essential function of compressor valves is to permit gas flow in the desired direction
and to block all flow in the opposite (undesired) direction. Each operating end of a
compressor cylinder must have two sets of valves. The set of inlets (suction) valves admits
gas into the cylinder. The set of discharge valves is used to evacuate compressed gas from
the cylinder.
DOCUMENT NO:
Pump
RGB
Motor-RGB
Coupling
Motor Forced
Terminal Lubrication Cooling
Box System Water
Gear Box Oil Outlet
Lubrication
System
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as Head
"LN
T
Gen
eral
Busi
ness
".
12 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Connecting
Rod
Tie Rod
Water seal
nut
Stuffing box
bolts
Cooling line
outlet
Cylinder
Header
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
13 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Distance
Piece for
header.
Suction
Crankshaft Line
Casing
Opening
Lubrication
Oil Drain
Cooling
Water Line
Discharge
Line
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie Fig: Working of R.C. Pump
d as
"LN
T
Gen
eral
Busi
ness
".
14 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Discharge
Line
Turbine to
Balance RGB
Line RGB
Coupling
Suction
Line
Flush Steam
Water Line Turbine
Pneumatic
RGB-Pump Controller
Coupling
DOCUMENT NO:
Balance
Line Suction
Line
Discharge
Line
Centrifugal
Pump
Flush
Water Line
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen Fig: Working of Multistage Horizontal Centrifugal Pump
eral
Busi
ness
".
16 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Slow Suction
Electric Coupling Pulsation
Gear with guard
Motor Main Pump Damper
Reducer
Pump
Lube Oil Discharge Manifold
Discharge Suction Line
Pump Motor Line
Pulsation
Damper
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral Fig: Working of Pp NH3 Triplex Pump
Busi
ness
".
17 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral Fig: Working of a Single Stage Centrifugal Pump
Busi
ness
".
18 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
The power output and input of the pumps are required to change to be inline with
the values provided by the LICENSOR for the changes made in the UREA-II plant.
The Energy requirement will reduce from 730kW to 408kW.
B. Vibration issue
Problem of high vibration has been observed mainly urea-2 pumps. GSFC wants to
reduce the vibration issue.
Use of Pulsation analysis is required to be done pre and post
installation/modification.
C. Replacement of Pumps
The older models of pumps are not energy efficient as compared to the newer
models hence requiring proper dismantling, inspection, and replacement.
Modifications related to changes in valve are required to change the pressure and
change in flow rate to make the process more energy efficient and match the new
plant requirements.
Inlet Pressure Changes form 33kg to 35 kg
E. Foundation Suitability
Suitability / adequacy of existing pump foundation with respect to new pump and
motor with all accessory’s installation shall be checked as the foundation are nearly
50+ years old. If not adequate, new foundation shall be considered for installation of
available spare warehouse centrifugal pump along with required new accessories at
same location i.e. existing pump foundation.
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
19 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
6. OEM recommendation
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
20 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen Fig: OEM Recommended Modifications on Peroni Pumps
eral
Busi
ness
".
21 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Sens
itivit
y:
This
Doc
ume
nt is
clas Fig: Safety Valve
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
22 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
4. TAG: XU-P102C
DOCUMENT NO:
Complete unit test including MRT, performance test and NPSH test with Job
motor and Job VFD. During complete unit test, shop dampeners shall be used.
Cleaning and overhauling of the Pump Unit Parts if deemed necessary.
Replacement of any other parts or components as pre their perceived
condition and reusability.
2. XU-P101B:
3. XU-P101C:
DOCUMENT NO:
Pulsation Analysis of suction and discharge piping system as API 674 3rd
edition with residual pulsation within +/- 2%
Noise data shall be provided by supplier of the complete package and shall be
within 85 dB.
On-Site hydrotest of the pump package. M/s Peroni shall provide the hydrotest
procedure.
Mechanical & Performance Run test of pump for at least 4 hours at site under
Vendor supervision as per API 674 3rd edition.
Alignment and soft foot check According to API 686.
Insulation and heat tracing in applicable.
Complete unit test including MRT, performance test and NPSH test with Job
motor and Job VFD. During complete unit test, shop dampeners shall be used.
Cleaning and overhauling of the Pump Unit Parts if deemed necessary.
Replacement of any other parts or components as pre their perceived
condition and reusability
4. XU-P102A:
DOCUMENT NO:
Installation of New drive motor (3.3KV, 500KW, 4 Pole, AMA 400L4A BAI
type, ABB make)
Installation of New gear box suitable for revised pump operating parameters.
Installation of New couplings (between pump, gear box and motor) including
related Coupling guards (rotating parts fully enclosed)
Installation of New common base plate for pump, gear box, and motor to
accommodate for space limitations.
Installation of New LOU (Lube Oil Unit) for Pump and gear box.
Installation of New SWU (Seal water Unit) suitable for revised pump operating
conditions.
No modification at existing bearing design.
Shims, Levelling Pads, Lifting Pads, Anchor Bolts, Earthing/Grounding Bolts to
be provided by EBARA.
Heat Tracing not required. Installation of Insulation on the Pumps.
NDT of Gearbox, LOU, Mechanical Seal, auxiliary piping shall be as per
manufacture’s standard.
Hydrostatic test of pressure parts to be provided by EBARA.
Mechanical & Performance Run test of pump for at least 4 hours at site under
Vendor supervision.
EBARA to provide with lubrication detailing.
Lateral Analysis of new pump.
TPI for motor, LOU, SWU and gearbox shall be Lloyds and TPI costs be
considered by L&T.
Cleaning and overhauling of the Pump Unit Parts if deemed necessary.
Replacement of any other parts or components as pre their perceived
condition and reusability
7. XU-P107:
DOCUMENT NO:
8. Execution Methodology
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T Fig: Ammonia Safety Guidelines
Gen
eral
Busi
ness
".
27 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
28 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen Fig: Size Chart for Allen/Hex key to bolt size conversion
eral
Busi
ness
".
29 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Remove the power supply form the electric motor and other wiring connections from
the pump.
Remove top canopy from the motor, couplings and RGB.
Remove the 4 base bolts from motor, remove 4 bolts from coupling and slide the
motor backwords i.e., away from the RGB to detach the coupling.
Lift and remove the motor.
Decouple the RGB and crankshaft of the pump.
Drain the lubrication oil from the RGB from drain valve.
Motor-RGB
RGB Coupling
RGB Oil
Drain Valve
Motor
Fig: Motor-RGB Coupling
Sens
itivit
y:
This
Doc Remove all the oil lines and other attached lines from the RGB.
ume
nt is Remove 4 base bolts from the base of the RGB,
clas Remove the coupling bolts and slide it away from the Pump to remove coupling from
sifie
d as crank shaft the remove the RGB as Love Joy Coupling as used.
"LN
T
Gen
eral
Busi
ness
".
30 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Removal Dir.
Disconnect the suction, discharge, cooling water, oil lubrication and any other
connected lines from the pump. And make sure that the ammonia is clear from the
lines and is safe to proceed.
Close valves and add blinds to the valves for safety.
Remove connection cooling water inlet and outlet lines form the piston plunger
[ nos.7] and remove the connecting line.
Drain the oil from the oil drain valve [ as shown in fig].
Remove the top bolts from the head then remove head and tie rod.
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
31 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Hex Key
Water line
Sens
itivit Remove the plunger after unscrewing the water seal nut and gland nut from the
y: pump. [ Be cautious as high-pressure gas may release]
This
Doc
Remove the 4 bolts holding the stuffing box (using Allen/Hex Keys) and remove it
ume carefully using the EOT.
nt is Remove the header bolts hence, removing the header and distance piece.
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
32 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Fig: Position Of Hex Bolts Holding the Headers and Distance Piece
Open the side window panels and case opening at front from the crankshaft casing.
Remove the piston, connecting rods and other connected part from the crank shaft.
Hold the crank shaft using the EOT still inside the casing and slide out the bearings
from the front opening of the casing.
Remove the crank shaft from the casing.
Dismantle the top part of the pump casing by removing the side bolts. Remove the
base bolts and completely remove the pump casing.
Make sure if any other compliance is remaining or not in presence of GSFC and Civil
department.
Sens Hand over to the project to Civil for foundation work.
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
33 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
34 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Shutdown the pump before progressing. Remove any electrical supply to the motor.
Disengage the motor to crankshaft power transfer connection.
Disconnect or close any attached pipeline to the pump, i.e., suction line, LOU line,
discharge line, cooling water supply line, etc.
Discharge
Pulsation
Damper
Suction
Pulsation
Damper
By-pass
Discharge
Line
Line
Pump
Manifold
End Cover
Suction
Line
Make sure that the manifold is clear of all the working fluid (Ammonia) before
proceeding any further.
Loosen up the end-cover bolts (6nos.) of the manifold. {Be careful Ammonia Might
leak}
Sens To completely remove the end-cover a special L-shaped attachment will be
itivit
y: provided by GSCF under their supervision to insure proper and safe removal of the
This end-cover.
Doc
ume
After removal of end cover unscrew and remove the Allen Plug (4nos.) visible inside
nt is the manifold’s bore along with other attachments (i.e., O-ring, support rings, backup
clas rings, etc.)
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
35 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Make sure to note the order in which the attachments O-ring, support rings, backup
rings, etc. are removed for re-installation purposes (also you can check GAD for
Peroni pump).
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Fig: Cross-section of Manifold of Peroni Triplex Pump
Busi
ness
".
36 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Remove the discharge valve spring plate assembly and discharge valve spring.
The suction-discharge mono block is stuffed inside the manifold tightly and can be
removed by using a puller by applying significant amount force.
Once the mono block is out disassembling the mono block by removing the tying
bolts (4 nos.) form the Monoblock.
Suction
End
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen Fig: Discharge Valve (Left) and Suction Valve (Right)
eral
Busi
ness
".
37 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Top Bolt
End
Cover
Bottom
Bolt
DOCUMENT NO:
Shut down the turbine by shutting off the steam supply to the turbine.
Remove any other electrical connection from the turbine.
Ensure that the turbine is depressurised and cooled before accessing the turbine.
Remove the turbine casing to gain access to the old turbine nozzle.
Remove the old turbine nozzle ring carefully.
Ensure the surface the internals of the turbine are clean before installation of new ring.
Place the turbine nozzle ring on the casing carefully the with proper alignment and
torque specifications.
Make sure all the surfaces and components are clean before closing the turbine casing.
After closing the casing make sure that all the bolts are tightened properly without any
loose parts or any leak.
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Busi
ness
".
39 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Ensure the gearbox and associated machinery such as forced lubrication system are
shut down and safe to work on.
Drain the gear box from the
Gain access to the gearbox, which may involve removing covers or panels.
Locate the gear you want to change. Gears are typically labelled or identified by their
position within the gearbox.
RGB-Pump
Coupling
RGB-
Turbine
Coupling
RGB
Sens
itivit Lubrication
y: Oil Unit
This Line
Doc
ume
nt is
clas
sifie
d as
"LN
T
Gen
eral
Fig: Gear Box of Turbine Centrifugal Pump
Busi
ness
".
40 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
If the gearbox is under load, ensure it's released to prevent sudden movements when
changing gears.
Disconnect power or disengage any coupling mechanisms that connect the gearbox
to other components i.e., from the turbine side as well as from the pump side.
Remove bolts or clips, holding the gear in place.
Carefully lift or slide the gear out of its position within the gearbox. This may require
some force depending on the design of the gearbox.
Make sure that everything is checked during this time for any defects or other prob-
lems.
Ensure that every surface is cleaned and lubricated before installation.
Insert the new gear into the appropriate position within the gearbox. Ensure its prop-
erly aligned and seated.
Reinstall any retaining mechanisms to secure the new gear in place. Tighten bolts or
clips according to manufacturer specifications. If disconnected, reconnect power or
reengage coupling mechanisms.
DOCUMENT NO:
Remove pump casing find the wear ring attached to the pump bore.
Remove the ring from bore and clean the surface and casing of any kind of
surface gunk and contaminations.
Install the new ring by tapping it lightly with a mallet all around the circumference
till it fights tightly.
Clean the surfaces before re-assembling the pump casing.
Make sure that all the O-rings are replaced and not leaking before installation of
the pump.
Sens
itivit
y:
This
Doc
ume
nt is
clas
sifie
d as
After inspecting and taking over of foundation along with newly erected foundation
"LN bolts with desired measurements, base plate must be installed.
T Once the base plate is secured to the foundation we can begin erection of the
Gen
eral motor.
Busi
ness
".
42 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
Install the motor, bearing casing and the centrifugal pump of the base plate using
proper bolts.
Aling the motor to pump coupling within the given tolerances and tighten the
coupling bolts.
Connect the pipes to the pump securely and recheck the alignment of the
coupling.
Add the New coupling guard and secure it to the base plate.
Add grouting to the base plate after final inspection of the motor.
After Completion of work the site should be cleaned properly before handing over.
Work site area should be clean with no hazardous objects laying in the workplace.
Objects such as bolts, nuts, tool, etc. should be kept in their designated places to
clear the workplace.
Oil spills are a hazard to the workplace and should be attended to immediately.
Cleaning the area with dry cotton cloth.
Before ending the shift, the workplace must be completely cleaned.
The GSCF Engineer in charge shall inspect the site to provide clearance
certificate.
F. Mechanical cleaning & preassembly work:
Box-up of stage cooling water jacket, cover and cooling and cooling water inlet/outlet
line, lube oil line using new gasket, “O”-Ring, etc.
Overhauling & assembly of all suction and discharge valves with internals
Measurement od ID of bore in Peroni Pumps before inserting the suction-discharge
valve Monoblock assembly inside.
Measurement of OD of Suction valve, discharge valve bock and of complete
preassembled Monoblock before installation
O-ring cross-section, backup ring cross-section should be checked such that O-rings
thickness should not exceed that of support rings.
Installation of suction and discharge valves.
Sens Proper fastening and assembly of all the components of Monoblock before
itivit installation.
y:
This Cleaning and oiling of manifold before installation.
Doc Oiling and cleaning of Monoblock before installation.
ume
nt is
The valve seating area on the valve block and manifold shall the lean.
clas The grooves for all the O-ring installation shall be cleaned to avoid any leaks post
sifie installation.
d as
"LN The O-ring shall be checked for and damages on it.
T
Gen
eral
Busi
ness
".
43 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
When the turbine casing is opened make sure the all the dirt is removed and
cleaned.
Clean all the moving parts inside the turbine.
The nozzle ring place holder shall be cleaned thoroughly for any contaminations or
grease before installation of the nozzle ring.
The gears in the gear box shall be cleaned before closing it up.
The new gear shall be visually inspected for any deformities before installation.
The section where new gear is to be installed should cleaned.
The new gear should be lubricated before installation to avoid and wear in it.
New lubricating oil should be added to the LOU before commissioning of the pump.
The gear should be aligned properly to fit inside the gear box.
Before installation of the base plate of pump and motor the level of the foundation
must be checked.
The elevation level, distance between alternate and diagonal distances of the
foundation bolts must be check before installation of base plate.
Levelling of base plate must be done and inspected properly before installation of the
pump and motor upon it.
Box up of the pump casing along with the proper fitting of the gland & packing in the
casing.
The base plate must be levelled and bolted tightly before installation of the motor and
pump.
Wear ring must be removed skilfully as it has a tight fitting with the casing.
Overhauling & Assembly of all the inlet and outlet valves and piping.
Cleaning and oiling of the bearings before reinstallation.
All the O-rings, gaskets and attached consumables must be replaced as per
requirements.
DOCUMENT NO:
Base plate must be tightened securely and inspected before installation of the pump
and motor upon it.
Vibration the pumps shall be checked using vibrometer in most sensitive places of
the pump where the vibrations and amplitudes of forces are high.
The alignment of the rotating, vibrating or any moving part shall be checked before &
after installation of the piping and other accessories.
The OD and ID of the wear ring of SULZER pump must be checked before
installation.
The alignment of the motor should be checked and must be given clearance by
GSFC before grouting and handing over to the electrical department for supply
connections.
The O-ring shall be checked for cuts and damages on it.
OD of new gear for Turbine pump.
The length of the Gear should be measured to check for correct dimensions and
proper fitment.
Dry run/no load test run of the pumps before use of the actual working fluid.
Increasing the working load in steps, if possible, to test for and issues with the pumps
before using the pump at full load.
The input and the output pressure shall the checked using the pressure gauges
installed in the respected lines to check for and inconsistency or variation from the
actual desired pressure.
Testing of all the joints, valves connections, bolts torquing pressure shall be checked
on priority basis.
Pump and its attachments shall be checked for any leaks of any kind before
commissioning.
Contractor shall carry out all the re-commissioning activities with the working fluid,
running it an unload condition for a few hours (i.e., 4-5 hours), on full load run &
taking it into operation.
Electrical connections and reading of all the attached instrumentation shall be
Sens
itivit
checked to check for any inconsistencies or any kind of variations.
y: Vibration the pumps shall be checked using vibrometer in most sensitive places of
This the pump where the vibrations and amplitudes of forces are high.
Doc
ume Pulsation Analysis shall be carried to check for any adjoining piping to check for any
nt is mechanical in them.
clas
sifie The output RPM of the power shaft of the Turbine pump shall be checked before
d as connecting it to the pump.
"LN
T
Gen
eral
Busi
ness
".
45 | P a g e
CONTRACTOR
COMPANY
GUJARAT STATE FERTILIZERS & CHEMICALS LIMITED
REVAMPING OF UREA-II PLANT
VADODARA, GUJARAT, INDIA
DOCUMENT NO:
9. Reports:
10. Annexures
A. Inspection formats
B. IHI Operation & maintenance manual
C. OEM proposal for revamp
D. GSFC RFP document
E. CASALE datasheet
F. EBARA datasheet
G. PERONI POMPE datasheet
H. Revamp scope & 2 years spare list
I. Revamp parts list
J. Agreed deviation list.