GS118-1 Fabrication of Fixed Offshore Steel Structures To Eemua 158
GS118-1 Fabrication of Fixed Offshore Steel Structures To Eemua 158
GS118-1 Fabrication of Fixed Offshore Steel Structures To Eemua 158
Document Title
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
(Replaces BP Engineering Standard 111)
This specification supplements EEMUA 158 which has been prepared as a Joint Industry
Users document for use primarily within the UK Continental Shelf.
BP Group GS 118-1 modifies and relaxes on some of the requirements of EEMUA 158
and gives advice on interpretation and on the selections of options
AMENDMENTS
Amd Date Page(s) Description
CUSTODIAN
Welding Technology
Issued by:-
Engineering Practices Group, BP International Limited, Research & Engineering Centre
Chertsey Road, Sunbury-on-Thames, Middlesex, TW16 7LN, UNITED KINGDOM
Tel: +44 1932 76 4067 Fax: +44 1932 76 4077 Telex: 296041
CONTENTS
Section Page
FOREWORD .................................................................................................................. iii
1. INTRODUCTION..................................................................................................... 1
1.1 Scope .......................................................................................................................... 1
*2. QUALITY ASSURANCE ......................................................................................... 1
2.1 Documentation............................................................................................................ 1
* 2.1.1 General ............................................................................................................ 1
3. MATERIALS ............................................................................................................ 4
3.1 Weldable Structural Materials...................................................................................... 4
3.2 Welding Consumables ................................................................................................. 4
3.3 Miscellaneous Materials............................................................................................... 4
3.3.1 Bolts, Nuts and Washers........................................................................................ 4
3.5 Material Handling........................................................................................................ 5
3.5.2 Maintenance of Identity ......................................................................................... 5
3.5.4 Storage Conditions ................................................................................................ 5
4. QUALIFICATION OF WELDING PROCEDURES AND PERSONNEL............. 5
4.2 Approval Process for Welding Procedures ................................................................... 5
4.2.1(d) Initial Submission............................................................................................. 5
4.3 Restrictions on Welding Practices................................................................................ 5
4.4 Welding Procedure Qualification Tests ........................................................................ 7
4.4.1 General Requirements............................................................................................ 7
4.4.2 Types of Test Weld................................................................................................ 8
4.4.2.3 Single Tests and Demonstrations ........................................................................... 8
4.4.3 Inspection and NDT Requirements and Acceptance Criteria................................... 9
4.4.3(b) Non-destructive Testing................................................................................... 9
4.4.4 Mechanical Test Requirements and Acceptance Criteria......................................... 9
4.4.4(d) Hardness Survey .............................................................................................. 9
4.4.4(e) Charpy Tests.................................................................................................... 9
4.4.5 Failed Procedures .................................................................................................. 10
4.5 Essential Variables....................................................................................................... 10
4.5.1 Materials Related Variables.................................................................................... 10
4.5.2 Weld Geometry Related Variables ......................................................................... 10
4.5.4 Procedural Variables.............................................................................................. 11
4.5.5 Welding Parameter Variables ................................................................................. 11
5. CONSTRUCTION .................................................................................................... 12
5.2 Preparation and Assembly............................................................................................ 12
5.2.3 Spacing of Seams and Splices. ............................................................................... 12
* 5.2.7 Alignment and Fit Up of Welding Joints.................................................................. 12
5.3 Control of Production Welding.................................................................................... 12
5.3.2 Welding Consumables and Equipment.................................................................... 12
5.3.5 Weld Execution ..................................................................................................... 13
5.3.7 Weld Repairs ......................................................................................................... 13
5.3.9 Weld Profile and Surface Finish ............................................................................. 13
GS 118-1
PAGE i
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
5.3.11 Production Controls............................................................................................... 13
5.4 Post-Weld Heat Treatment .......................................................................................... 13
* 5.4.1 Welds Requiring PWHT................................................................................... 13
5.4.2 PWHT Procedures................................................................................................. 13
* 5.5 Bolted Connections ............................................................................................... 14
7. INSPECTION AND NON-DESTRUCTIVE TESTING.......................................... 14
7.3 Qualification of Inspection and NDT Procedures and Personnel................................... 14
7.3.1 Non-Destructive Testing Procedures...................................................................... 14
7.3.2 Qualification of Inspection and NDT Personnel...................................................... 15
7.4 Non Destructive Testing Techniques ........................................................................... 15
7.4.1 Visual Inspection ................................................................................................... 15
7.4.2 Ultrasonic Testing.................................................................................................. 15
7.4.3 Radiography .......................................................................................................... 15
7.4.4 Magnetic Particle Inspection .................................................................................. 15
TABLE 2 ......................................................................................................................... 16
TABLE 3 ......................................................................................................................... 16
TABLE 5 ......................................................................................................................... 16
TABLE 6 ......................................................................................................................... 16
ATTACHMENT 1 .......................................................................................................... 18
QUESTIONNAIRE ON PROPOSALS FOR WELDING PRACTICES ............................ 18
APPENDIX A.................................................................................................................. 21
DEFINITIONS ................................................................................................................. 21
APPENDIX B.................................................................................................................. 22
LIST OF REFERENCED DOCUMENTS......................................................................... 22
APPENDIX C.................................................................................................................. 23
SUPPLEMENTARY COMMENTARY............................................................................ 23
GS 118-1
PAGE ii
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
FOREWORD
The Introductory volume contains a series of documents that provide an introduction to the
BP Group Recommended Practices and Specifications for Engineering (RPSEs). In
particular, the 'General Foreword' sets out the philosophy of the RPSEs. Other documents in
the Introductory volume provide general guidance on using the RPSEs and background
information to Engineering Standards in BP. There are also recommendations for specific
definitions and requirements.
This Guidance for Specification clarifies certain of the EEMUA Publication 158 requirements
and lists those additional BP requirements, i.e. not fully detailed in EEMUA Publication 158.
Application
This Guidance for Specification is intended to guide the purchaser in the use or creation of a
fit-for-purpose specification for enquiry or purchasing activity.
This Guidance for Specification is based upon an industry specification and may refer to
certain local, national or international regulations but the responsibility to ensure compliance
with legislation and any other statutory requirements lies with the user. The application of this
Guidance for Specification to other sea areas or for other structures may also be appropriate,
depending on the design philosophy selected and the sea areas. BP will specify when this
specification is to be used for these other sea areas or other structures.The user should adapt
or supplement this document to ensure compliance for the specific application.
A Specification (BP Spec 118-1) is available which may be suitable for enquiry or purchasing
without modification. It is derived from this BP Group Guidance for Specification by
retaining the technical body unaltered but omitting all commentary, omitting the data page
and inserting a modified Foreword.
GS 118-1
PAGE iii
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
Principal Changes from Previous Edition
BP Engineering Standard 111, originally issued in December 1985, has been completely
revised and re-issued as this BP Group Guidance for Specification following the issue of
EEMUA Publication 158 in 1989.
Users are invited to feed back any comments and to detail experiences in the application of
BP RPSE's, to assist in the process of their continuous improvement.
For feedback and further information, please contact Standards Group, BP Engineering or the
Custodian. See Quarterly Status List for contacts.
GS 118-1
PAGE iv
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
1. INTRODUCTION
1.1 Scope
Pipeline risers and any other pipework supplied integrally with the
structure are not covered by this Specification.
The Contractor shall supply a quality manual which shall be submitted to BP with the
tender documents.
Following an order the contractor shall submit a quality plan which shall be subject to
approval by BP.
The Contractor shall ensure that the quality requirements are applied to the materials,
equipment and services provided by sub-contractors.
2.1 Documentation
* 2.1.1 General
GS 118-1
PAGE 1
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
award, and shall be subject to final approval by BP before the
commencement of fabrication. BP will specify those documents that
are required prior to and during the progress of the work only, and
those that are required for permanent record.
The documents required for any particular project shall include, but not
necessarily be limited to those covered by 2.1.2 and 2.1.3 of this
specification.
GS 118-1
PAGE 2
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
(i) Detailed procedures for non-destructive testing and inspection,
and the format of the NDT certificates.
* 2.1.3 Following completion of any part of the work the contractor shall
submit copies of the following documentation for approval by BP:
(e) NDT test reports and key plans showing final identification
numbering, test report numbers and the results.
GS 118-1
PAGE 3
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
correlated NDT during in-service sub-sea and topside
inspections.
3. MATERIALS
Batch definition which limit a batch number to a single dry blend of flux and/or a
single heat of filler are normally considered acceptable and no additional batch
testing is required. The exception being when BP are still not convinced that all
batches of the consumables would pass the welding procedure qualification tests.
Additional batch testing could be waived, however, if the contractor also achieves
the required weld metal charpy energy in additional tests from each procedure
plate at a temperature 10 below the specified temperature. In cases where BP is
not satisfied with the batch definition the contractor shall propose a batch testing
programme for BP approval.
Mild steel bolts and nuts shall be to BS 4190 Grade 4.6 and washers to
BS 4320. Mild steel stud bolts and washers shall be to BS 4882. All
threaded connections shall have a suitable locking device so that they
are incapable of becoming undone. However, locking welds shall not
be used on nuts and bolts to BS 4882 and free machining nuts and bolts
to BS 4190 Grade 4.6. In a torqued connection, the tensioned length
of the bolt shall be at least 5 diameters long and the torque requirement
shall be specified on the drawing.
For subsea applications high strength bolts, nuts and washers shall be to
BS 3692 Grade 8.8 with Chemical Composition as per BS 4882 Grade
L7. These Bolts shall be heat-treated and charpy toughness following
thread rolling to achieve an hardness of not more than 300Hv or shall
GS 118-1
PAGE 4
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
have machined threads. All bolts, nuts and washers shall be Cadmium
plated and dehydrogenated to BS 3382: Part 7: 1966.
EEMUA 158 Clause 4.3 does not prohibit the practices listed, it merely warns the
contractor of some which concern BP. If a contractor has background data which
convinces BP that is is sensible to permit one or other of these practices, then
GS 118-1
PAGE 5
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
approval may be given. To ensure that any such proposals are made clearly in the
tender, and that appropriate background data are submitted with the tender, a
questionnaire (Attachment 1) has been prepared which addresses each of the points
listed in this clause. This should be returned with the tender.
4.3(b) SMAW bead widths exceeding the lesser of 16 mm or four times the core wire
diameter.
(Modification to EEMUA 158 4.3(b))
4.3(h) SSFCAW for heat inputs exceeding 1.5 KJ/M for all welding passes other than the
root pass.
4.3(k) SSFCAW followed by any other process, including the mixing of weld metal at weld
intersections.
Past experience has shown that there can be a substantial reduction in weld metal
toughness when SSFCAW is followed by other welding processes. This is equally
true for individual butt welds and at the intersection of welds, where the first joint
involves SSFCAW and the second any other welding process. BP will require
detailed, assurance testing before this 'mixing' of weld metal is allowed to proceed.
4.3(l) Heat inputs exceeding 3KJ/mm for grade 450 material and 3.5 KJ/mm for grade 355
material.
4.3(n) Butt welds where both edges are square and are greater than 8 mm thick and T butt
welds without a bevel where the thickness of the incoming member is greater than 8
mm.
4.3(o) Included angles of bevelled welds below 45 degrees (except as covered by 4.5.2(g)).
(Modification to EEMUA 158 4.3(o))
GS 118-1
PAGE 6
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
4.3(r) Use of any welding technique in which the welder is not permitted to put the final
capping pass adjacent to the plate.
'Temper bead' means any welding technique in which the welder is not permitted to
put the final capping pass adjacent to the plate, regardless of the stated objective
for this restriction. The acceptability of such a technique will depend on the
tenderer's ability to show that the technique has no effect on hardness.
Alternatively, if there is a hardness effect, the tenderer will need to control bead
placement so as to guarantee compliance with the specified hardness limit.
4.3(t) Single-pass fillet welds (other than by submerged arc) with a design leg length greater
than 6 mm.
Problems have been experienced on past projects with poor toughness in the root
area of SSFCAW Welds. The problem was solved by ensuring a small bead size and
adequate interrun tempering. Splitting the second layer of weld metal was found to
be particularly effective.
4.3(x) Use of single bevel or K weld preparations for in-plane butt welds.
When rolled steel sections have been purchased with transverse Charpy
properties, testing in the HAZ shall also be transverse.
GS 118-1
PAGE 7
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
For fillet weld tests, the root gap shall be set at 2 mm with the two
plates fully restrained. The fillet weld leg length qualified by this test is
the actual leg length minus the 2 mm gap. Only consumables which
have been qualified on butt welds may be used.
It is assumed that all fabricators will take advantage of the opportunity to qualify
T-butt welds using plate butt (with single bevel or K preparations). For stub to
barrel welds however, the test 4.4.2.3(b) is required in addition.
The PWHT soak time of 4 hours minimum may not qualify the procedure for the
possibility of a repeat PWHT. The Contractor may wish to cover this eventually by
testing at longer soak times.
Although 30 mm plates are required for fillet weld procedure qualification, and the
preheat in the test will therefore be the one appropriate to the 90 mm combined
thickness, this is not the minimum preheat permitted for fillet welds. The ruling
clause is 4.5.4(b), which will permit the same reduction for lesser combined
thickness as BS 5135 will permit.
4.4.2.3(a) Mechanical tests shall be taken to evaluate both sides of the repair. The
requirement for PWHT or CTOD test depends on the plate thickness not on the repair
weld depth.
4.4.2.3(b) The internal weld shall not be undertaken until the single-sided weld root has
been fully visually inspected.
4.4.2.3(c) The maximum root gap which will be permitted in this test is the 12 mm limit
from section 5.2.7.
GS 118-1
PAGE 8
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
4.4.3 Inspection and NDT Requirements and Acceptance Criteria
Reference here, and in 4.4.1 and 7.2.3 of EEMUA 158 to the 'third day after the
completion of welding' result from the practice of certain fabricators of recording
only the day on which welding or NDT took place. Where the Contractor's system
includes a record of the time at which welding was completed, or PWHT or NDT
was started, then this delay time may be taken to mean 48 hours, since this is the
minimum period guaranteed by the 'third day' wording.
The root weld centreline charpy notch for the punch- through technique
shall be at the intersection of the columnar grains of the punch-through
bead.
(Addition to EEMUA 158 4.4.4(e))
GS 118-1
PAGE 9
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
* 4.4.4(f) Unless approved otherwise by BP the weld metal CTOD requirement
is 0.25 mm at a test temperature of 0°C for piles and -10°C in all other
cases.
The consumable that is proposed for use on node stub to can welds
shall require CTOD testing in the weld metal where the stub (brace) is
over 40 mm thickness. This is intended as a mandatory consumable
verification test and shall be conducted after PWHT unless specified
otherwise by BP.
HAZ CTOD tests are not required unless specified otherwise by BP.
4.5.1(a) Procedures for castings shall require qualification using cast steel base material.
4.5.1(h) If the thickness of the protective finish applied to the weld bevel is greater than
that used for the procedure qualification tests.
4.5.2(i)The qualified root gap for double sided welds is limited to a maximum of 6 mm.
4.5.2(e) In certain circumstances BP may be able to offer a relaxation on the requirement for qualification in
all of the 4 positions. As a minimum, however, the highest and lowest heat input positions will be
qualified for the range of thickness using the same fundamental procedure. In addition a single
additional test will be required, on the thickest material, in each of the remaining two positions.
GS 118-1
PAGE 10
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
4.5.4 Procedural Variables
4.5.4(c) The simplest way of complying with this clause is to allow the test plate to cool to the minimum
specified preheat before starting each pass of the cap. If this has not been done with existing
qualifications, then the measured interpass temperature in the cap becomes the minimum 'preheat'
for capping.
4.5.4(e) Where existing procedure qualifications are being offered, the depth of gouging
may not have been measured during all relevant test welds. In such a case, the
contractor may provide a single 3G demonstration plate - or 1G for any SAW
procedure involved - of the greatest thickness covered by the appropriate
procedure. In this demonstration, the backgouging should taper from nil to 10 mm
over a distance not less than 500 mm. Charpy tests should then be taken from the
bottom of the first side welded; at locations representing 1 mm steps of
backgouging depth. The minimum permissible backgouging depth will then be set 2
mm deeper than the depth beyond which all of the Charpy tests meet the normal
root Charpy test requirements.
4.5.4(f) Backgouging beyond the 10 mm limit will be permitted where the ligament
after gouging still exceeds either 10 mm or the ligament which remained after
backgouging the appropriate procedure qualification test.
4.5.5(b) Where existing procedure qualifications are being offered, it is unlikely that all runs with a
particular size of electrode will have been controlled within this tolerance on the mean value
although this would be mandatory for procedures run especially for EEMUA fabrication. If
examination of the 'as run' sheet shows that the standard deviation of the actual run lengths for fill
and cap passes exceeds 10% of the mean for that electrode diameter, then that existing qualification
is unlikely to be accepted.
4.5.5(f) The maximum heat input during production welding is limited to the lesser of
10% or 0.2 KJ/mm greater than that used during procedure qualification.
(Modification to EEMUA 158 4.5.5(f))
GS 118-1
PAGE 11
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
4.5.5(g) If the equipment used for SAW SSFCAW or GSFCAW does not indicate wire
feed speed but does indicate current, then the 5% tolerance will apply to the current.
4.5.5(i, k, l) If existing procedure qualifications are being offered and these parameters have not been
measured during procedure qualification BP may still be able to accept these procedures subject to
the acceptance of additional verification tests.
5. CONSTRUCTION
Effort should be made to ensure that the number of wide gap closure welds within
the structure are kept to a minimum. Wide gaps require a higher degree of welder
skill and they are more prone to weld root defects, poor toughness and cracking.
GS 118-1
PAGE 12
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
5.3.5 Weld Execution
Toe grinding shall not be less than 0.5 mm or more than 1.5 mm
penetration into the base metal and shall extend 0.5 mm below visible
undercut. Profile requirements for TKY joints within jackets are shown
in Fig. 5 of EEMUA 158. BP may specify additional requirements for
certain joints and this will be shown on the design drawings.
Even where the Drawing defines an as welded joint thicker than these
rules, a CTOD tested procedure is still required.
GS 118-1
PAGE 13
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
* 5.5 Bolted Connections
Where close tolerance bolts are required the hole shall be made to
within +0.5 mm and -0 mm of the specified bolt diameter.
Bolt heads and nuts shall be drawn tight against the work by a method
acceptable to BP. Bolt heads shall be tapped with a hammer while the
nut is being tightened. Having been finally tightened, the nuts shall be
locked. All high strength bolts shall be pretensioned to the proper
proof stress or shall have the torque level specified. All such bolting
details shall be subject to prior review by BP.
Where surfaces joined by bolting have a slope greater than 1:20 with
respect to the plane normal to the bolt axis, suitable tapered washers
shall be used.
All bolts shall be provided with either a lock nut, a locking washer, or
an alternative locking device. All bolt locking devices shall be subject
to prior review by BP.
Bolts shall be threaded to such a length that not more than one thread
will be within the grip of the structural members.
Bolts shall be of a length that will extend entirely through the nut, but
not more than 10 mm beyond.
GS 118-1
PAGE 14
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
7.3.2 Qualification of Inspection and NDT Personnel
7.4.3 Radiography
GS 118-1
PAGE 15
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
TABLE 2
(b) The requirements for Castings are the same as for grade 355 steel)
TABLE 3
(d) Alternative inspection requirements may also be specified for critical partial
penetration welds.
(f) For nodes where scanning from internal surfaces is not possible, examination shall be
to the Purchaser's approval (BS 3923 Level 4).
(Addition to EEMUA 158 Table 3)
(g) The option given in Table 5 of BS 3923 to delete inspection from the lower surfaces
for plate and pipe butt welds below 35 mm shall not apply.
The acceptance levels for lack of fusion defects do not apply. Lack of fusion defects are not
acceptable.
TABLE 6
Undercut shall not exceed 0.25 mm for all welds in jacket structures and piles.
GS 118-1
PAGE 16
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
TABLES 5 & 6
EEMUA 158 was published with these tables incorrectly numbered and wrongly positioned. Table 5 on page
119 should be table 6 on page 120 and table 6 on page 120 should be table 5 on page 119.
GS 118-1
PAGE 17
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
ATTACHMENT 1
Clause 4.3 of EEMUA 158 defines restrictions on a variety of welding practices, making their
use subject to the specific approval of the purchaser. Any decision on approval would be
based on an assessment of the background data submitted by the tenderer.
Tenderers are required to answer YES or NO to the questions on the list which follows
covering all of the relevant topics. This requirement has been made to encourage tenderers to
be open about their intentions prior to contract.
A 'Yes' response must be supported by data submitted with the tender that demonstrates to
the satisfaction of BP's Professional Engineer that use of the practice will provide the required
welding quality.
A 'No' response means that the practice is not proposed. BP reserve the right to hold the
Contractor to this response, and to reject any subsequent request for approval, without
explanation.
Tenderers shall also include details of the definition of a batch or lot used by the chosen
welding consumables manufacturers, and of the testing carried out by the manufacturer on
each batch or lot, as required by Clause 3.2 of EEMUA 158.
GS 118-1
PAGE 18
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
Are any of the following practices proposed for this enquiry? Answer
(YES/NO)
(4) GMAW (except for the root pass in double-sided SAW welds) __________
GS 118-1
PAGE 19
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
(18) Single-pass fillet welds (other than by SAW) with
a design leg length greater than 6 mm __________
(21) Use of single bevel or K weld preparation for in plane butt welds __________
GS 118-1
PAGE 20
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
APPENDIX A
DEFINITIONS
Definitions
third party inspectorate: an impartial body, independent of, but appointed by, BP.
Note: Any specific application of the terms and the responsibilities of the parties
defined above is a matter for the relevant Conditions of Contract.
single sided weld: applies to joints welded from one side only.
double sided weld: applies to joints welded from both sides regardless of weld
preparation.
GS 118-1
PAGE 21
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
APPENDIX B
A reference invokes the latest published issue or amendment unless stated otherwise.
EEMUA Publ. No 158 Construction specification for fixed offshore structures in the North
Sea
Available from:-
BS 3692 Specification for ISO metric precision hexagon bolts, screws and
nuts. Metric units
BS 4190 Specification for ISO metric black hexagon bolts, screws and nuts
BP Group GS 136-2 Structural steel materials for use in the fabrication of fixed offshore
steel structures
(was BP Std 109)
GS 118-1
PAGE 22
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
APPENDIX C
SUPPLEMENTARY COMMENTARY
EEMUA Publication 158 clarifies a number of points for consideration by the design
contractor(s). In particular the following should be reflected on the design drawings by the
design contractor:-
Dimensional Tolerances
Clause 6.1 of EEMUA 158 states that the 158 tolerances only apply if the drawings do not
specify alternatives, and clause 6.2.2.3 of EEMUA 158 specifically requires the drawings to
define skid beam tolerances.
Leak Testing
Clause 7.4.5 offers the option for components other than buoyancy tubes and jacket leg
sections to be leak tested; these should be designated on the drawings.
GS 118-1
PAGE 23
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158
Weld Profiles
Although Figure 5 of EEMUA 158 defines the requirements for tubular intersections, clause
7.5.2 of EEMUA 158 implies that the requirements for other welds will be stated on the
drawings.
Joint Details
Joint details for welds between materials of different strengths (e.g. between Grade 450 and
Grade 355 or castings) should be shown on the drawings.
Primary Structure
EEMUA 158 defines the requirements for fabrication work on primary structures of offshore
installations. It is important that there is a clear definition of primary structure. This should
be in the form of a single list or alternatively the design drawings should indicate the
boundaries between primary and non-primary structure.
Risers
Risers are excluded from 158; a further revision of BP Group GS 118-10 'Welding of
Transmission Pipelines; will deal with riser fabrication and installations. Until this is
available additional requirements for risers e.g. a specification for bolting and hydrostatic
testing should be indicated on the drawings.
GS 118-1
PAGE 24
FABRICATION OF FIXED OFFSHORE
STEEL STRUCTURES TO EEMUA 158