WORK METHOD STATEMENT FOR BRICK/ BLOCK WALL OF TURPENTINE

BUILDING

Project Name: AMAR Projects


Project Venue: Sanand II, Ahmedabad, Gujrat
Parties Concerned:
Client: P&G, Ahmedabad
PMC: LTTS
Contractor: SIBIPL
MOS REF NO: AMAR/LTTS/SIBIPL/046/R-00/24-25
INDEX

1. Introduction
2. Location of Works
3. Equipment and Tools (as required)
4. PPE’S to be used
5. Supervision (PERSONS INVOLVED)
6. Site preparation & Work Precaution
7. Method Statement/Safe Work Procedure
8. Safety documents to be produced before commencing the work
9. Emergency Procedures
10. Rolls and Responsibility
11. Environmental
12. Approval and review

1. Introduction:
 This document covers Brick/ Block Wall for Turpentine building construction
works.

2. Location of Works:
 Near Existing Turpentine Building

3. Equipment and Tools (as required):

Page 1 of 5
AMAR/LTTS/SIBIPL/046/R-00/23-24
 Measuring Tape
 Hammer
 Scaffolding- cup-lock type (If required)
 Spade- 03 Nos
 Shovel- 02 Nos
 Gamela- 10 Nos
 Fanti- 02 Nos
 Randa- 02 Nos
 Bricks
 Cement
 Sand
 Water

4. PPE’S (Personal Protective Equipment) to be used


Personal protection equipment:
 Hard hats (Safety helmets)
 Safety Shoe/ Gum Boot
 Eye Protection (face shield/ goggles)
 Hand Gloves (Cotton/ Rubber/Leather/Cut resistance)
 Reflective jacket/ Leather Apron
 Shoulder pad

5. Supervision (PERSONS INVOLVED)


The site operations shall be carried by the following personal:
 Site Engineer- 01 Nos
 Safety Engineer- 01 Nos
 Skilled- 10 Nos
 Un-Skilled- 20 Nos

6. Site preparation & Work Precaution:


 Arrange the toolbox talk/specific training for the job to be executed.
 The First Aid Box should be near at site.
 Proper training to all manpower & site engineer to work safely.

7. Method Statement/ Safe Work Procedure


 The brick/ block size and sample should be approved from LTTS
 Check the mixed mortar mixed ratio are as per the approved drawing
 The setting out of brick/ block work are as reference the grid lines and column
 The brick/ block work position height and celling beam height
 All work execute are as per approved drawing
 Door, windows & cut-out open will be execute as per the approved drawing or
engineer in charges.
 The thickness of mortar not more than 12 mm
 The joint of concrete surface is deeply hacking
 Always use the suitable tools/ equipment for the job
Page 2 of 5
AMAR/LTTS/SIBIPL/046/R-00/23-24
 Complete the job in all respect in finishing

 Scaffolding Works
 All scaffolds should be approved and inspected from LTTS
 The approved Toe guard should be used for height work
 Ladder should be clamp over the scaffolding pipe at top and bottom rail
 The scaffolding should be checked before use the man movement or access for
works.
 Yellow tagging to be fix for making the scaffolding, green tagging will be fix after
checked and okay for uses and approved by LTTS.
 After Green Tag of scaffolding to be used for works

8. Safety documents to be produced before commencing the work


 Take all the Work permits for this activity
 Review of JSA with respect to the method of statement.
 Toolbox Talk should be recorded as per the format.
 Inspection of all electrical tools shall be recorded as per the format.

9. Emergency Procedures
 The site Engineer has to report any incident to the Site Manager immediately as
per Emergency Procedure, If any person gets injured during working time
immediately send it to the nearest Plant First Aid Centre and hand it over to
medical if get more injured.
 The engineer has to take control of the danger and rescue the incident.
 The site manager has to inform the first aider.
 Site manager to call Plant ambulance (in P&G scope) (if required).
 The site manager alerts to doctor and asks for treatment (In P&G scope)
 Site manager to inform Project Manager, client and concern government
authorities if required.

Mr. Munna Kumar

10. Rolls and Responsibility


Site Manager-
 Check and confirm the site clearances for safe working.
 Check and review the documents of the vehicle
 Explain the procedure to the site engineer.
 Nominate site supervisor for work location till the work completion.
Page 3 of 5
AMAR/LTTS/SIBIPL/046/R-00/23-24
 Ensure Work permit is taken before commencing the work.
Site Engineer-
 Check for the work permit is generated.
 Check and review the documents of the vehicles.
 Conduct works specific training to the workman.
 Explain the procedure to the Contractor workman.
 Coordination with safety engineer for continuous monitoring of activity.
 Conducting Tool Box Meeting before start of work.
 Ensure the House Keeping
Site Supervisor Responsibility-
 Collect all the certificates and documents required for the works and submit to site
engineer for final verification
 Assure the entire area has been barricaded.
 Supervisor presence should be there till the work completes.
 Ensure the house keeping.

Safety Engineer-
 Prepare JSA for the work to be done basis MOS, and get reviewed by the
Team.
 Work Permit to be verified after checking the safety requirements.
 To Check the Condition and review the documents of the vehicles, tools and
tackles.
 Close monitoring of activity and emergency procedure.
 Coordinate the Tool Box Meeting before start of work
 To conduct the job specific safety training.
 Coordination with site engineer for continuous monitoring of activity.
 Ensure the House Keeping
 Collect all the certificates and documents required for equipment, tools and
tackles and submit to site engineer for final verification
 Assure the entire area has been barricaded.
 Supervisor presence should be there till the work completes.
 Ensure the house keeping.

11. Environmental:
This section will need to reflect environmental issues associated with the work
 Noise will be within permissible limits
 Reduction of dust

12. Approval and review:


 This method statement should be reviewed by the site management team and a
copy of it will be circulated to those nominated for comment and the nominated

Page 4 of 5
AMAR/LTTS/SIBIPL/046/R-00/23-24
staff member to be finally approved All comments made should be recorded on
the approval sheet.

 This Method Statement has been reviewed by:

Name
Company SIBIPL SIBIPL SIBIPL
Title Construction Manager Safety Manager Project Manager
Signature
Date

 This Method Statement has been reviewed and approved by:

Name
Company LTTS LTTS
Title Project Engineer/Manager Safety Engineer/Manager

Signature

Date

Page 5 of 5