11 - WMS - Turpentine - Brick Wall
11 - WMS - Turpentine - Brick Wall
11 - WMS - Turpentine - Brick Wall
BUILDING
1. Introduction
2. Location of Works
3. Equipment and Tools (as required)
4. PPE’S to be used
5. Supervision (PERSONS INVOLVED)
6. Site preparation & Work Precaution
7. Method Statement/Safe Work Procedure
8. Safety documents to be produced before commencing the work
9. Emergency Procedures
10. Rolls and Responsibility
11. Environmental
12. Approval and review
1. Introduction:
This document covers Brick/ Block Wall for Turpentine building construction
works.
2. Location of Works:
Near Existing Turpentine Building
Page 1 of 5
AMAR/LTTS/SIBIPL/046/R-00/23-24
Measuring Tape
Hammer
Scaffolding- cup-lock type (If required)
Spade- 03 Nos
Shovel- 02 Nos
Gamela- 10 Nos
Fanti- 02 Nos
Randa- 02 Nos
Bricks
Cement
Sand
Water
Scaffolding Works
All scaffolds should be approved and inspected from LTTS
The approved Toe guard should be used for height work
Ladder should be clamp over the scaffolding pipe at top and bottom rail
The scaffolding should be checked before use the man movement or access for
works.
Yellow tagging to be fix for making the scaffolding, green tagging will be fix after
checked and okay for uses and approved by LTTS.
After Green Tag of scaffolding to be used for works
9. Emergency Procedures
The site Engineer has to report any incident to the Site Manager immediately as
per Emergency Procedure, If any person gets injured during working time
immediately send it to the nearest Plant First Aid Centre and hand it over to
medical if get more injured.
The engineer has to take control of the danger and rescue the incident.
The site manager has to inform the first aider.
Site manager to call Plant ambulance (in P&G scope) (if required).
The site manager alerts to doctor and asks for treatment (In P&G scope)
Site manager to inform Project Manager, client and concern government
authorities if required.
Safety Engineer-
Prepare JSA for the work to be done basis MOS, and get reviewed by the
Team.
Work Permit to be verified after checking the safety requirements.
To Check the Condition and review the documents of the vehicles, tools and
tackles.
Close monitoring of activity and emergency procedure.
Coordinate the Tool Box Meeting before start of work
To conduct the job specific safety training.
Coordination with site engineer for continuous monitoring of activity.
Ensure the House Keeping
Collect all the certificates and documents required for equipment, tools and
tackles and submit to site engineer for final verification
Assure the entire area has been barricaded.
Supervisor presence should be there till the work completes.
Ensure the house keeping.
11. Environmental:
This section will need to reflect environmental issues associated with the work
Noise will be within permissible limits
Reduction of dust
Page 4 of 5
AMAR/LTTS/SIBIPL/046/R-00/23-24
staff member to be finally approved All comments made should be recorded on
the approval sheet.
Name
Company SIBIPL SIBIPL SIBIPL
Title Construction Manager Safety Manager Project Manager
Signature
Date
Name
Company LTTS LTTS
Title Project Engineer/Manager Safety Engineer/Manager
Signature
Date
Page 5 of 5
AMAR/LTTS/SIBIPL/046/R-00/23-24