Kadiwa Stalls
Kadiwa Stalls
Kadiwa Stalls
30000.00
1 4000.00
1 FLOOR PLAN
A 1 SCALE 1 : 100 METERS
A B C D E F G H
30000.00
0.40mm THK.
CORRUGATED GI SHEET
TOP OF COLUMN
FASCIA BOARD
4200.00
2850.00
2 FRONT ELEVATION
A 1 SCALE 1 : 100 METERS
PROJECT TITLE: SHEET CONTENTS: PREPARED BY: RECOMMENDING APPROVAL: APPROVED BY: SHEET No.:
REPAIR/MAINTENANCE OF BIUAG & MALANA
ECO-PARK AS SHOWN 1
ENGR. CHINNEE M. DAQUIOAG ENGR. RODERICK L. TALAY ATTY. JOEL A. RUMA
LOCATION: ENGINEER I MUNICIPAL ENGINEER MUNICIPAL MAYOR A-1
BRGY. DUNGAN, RIZAL, CAGAYAN
2 1 1 2
1200.00
1200.00
CORRUGATED GI SHEET
0.40mm THK.
CORRUGATED GI SHEET
TOP OF COLUMN TOP OF COLUMN 150mm x 50mm TOP & BOT
CHORD - LUMBER
4200.00
4200.00
2850.00
2850.00
150mm THK. CHB PLAIN 150mm THK. CHB PLAIN
PLASTER (PAINT FINISH) PLASTER (PAINT FINISH)
150.00
150.00
FINISHED FLOOR LINE FINISHED FLOOR LINE
NATURAL GROUND LINE NATURAL GROUND LINE
H G F E D C B A
30000.00
0.40mm THK.
CORRUGATED GI SHEET
TOP OF COLUMN
4200.00
2850.00
3 REAR ELEVATION
A 2 SCALE 1 : 100 METERS
PROJECT TITLE: SHEET CONTENTS: PREPARED BY: RECOMMENDING APPROVAL: APPROVED BY: SHEET No.:
REPAIR/MAINTENANCE OF BIUAG & MALANA
ECO-PARK AS SHOWN 2
ENGR. CHINNEE M. DAQUIOAG ENGR. RODERICK L. TALAY ATTY. JOEL A. RUMA
LOCATION: ENGINEER I MUNICIPAL ENGINEER MUNICIPAL MAYOR A-2
BRGY. DUNGAN, RIZAL, CAGAYAN
A B C D E F G H
30000.00
1 4200.00
0.40mm THK.
CORRUGATED GI SHEET
FASCIA BOARD
2
1700.00
1 ROOF PLAN
S 1 SCALE 1 : 100 METERS
A B C D E F G H
30000.00
2 FOUNDATION PLAN
S 1 SCALE 1 : 100 METERS
PROJECT TITLE: SHEET CONTENTS: PREPARED BY: RECOMMENDING APPROVAL: APPROVED BY: SHEET No.:
REPAIR/MAINTENANCE OF BIUAG & MALANA
ECO-PARK AS SHOWN 3
ENGR. CHINNEE M. DAQUIOAG ENGR. RODERICK L. TALAY ATTY. JOEL A. RUMA
LOCATION: ENGINEER I MUNICIPAL ENGINEER MUNICIPAL MAYOR S-1
BRGY. DUNGAN, RIZAL, CAGAYAN
DIMENSION (mm)
MARK MAIN REINFORCEMENTS & SPACING
Bx By Tf
1 SCHEDULE OF FOOTING
S 2 N. T. S.
250.00
F.F.L.
N.G.L.
5-12mmØ
150.00
5-12mmØ
600.00
4 - 12mmØ
800.00 (By)
VERTICAL BAR
3-50mm, 3-100mm, 3-150mm &
REST SPACED @ 200mm O.C.
150.00
200.00 (Tf)
5-12mm RSB MATTING O.C.B.W.
ELEVATION
2 F1/C1 DETAILS
S 2 N. T. S.
PROJECT TITLE: SHEET CONTENTS: PREPARED BY: RECOMMENDING APPROVAL: APPROVED BY: SHEET No.:
REPAIR/MAINTENANCE OF BIUAG & MALANA
ECO-PARK AS SHOWN 4
ENGR. CHINNEE M. DAQUIOAG ENGR. RODERICK L. TALAY ATTY. JOEL A. RUMA
LOCATION: ENGINEER I MUNICIPAL ENGINEER MUNICIPAL MAYOR S-2
BRGY. DUNGAN, RIZAL, CAGAYAN
A B C D E F G H
30000.00
2000.00 2153.85 2153.85 2153.85 2153.85 2153.85 2153.85 2153.85 2153.85 2153.85 2153.85 2153.85 2153.85 2153.85
1
4200.00
2
1700.00
1200.00 4000.00
2 TRUSS DETAIL
S 3 SCALE 1 : 100 METERS
PROJECT TITLE: SHEET CONTENTS: PREPARED BY: RECOMMENDING APPROVAL: APPROVED BY: SHEET No.:
REPAIR/MAINTENANCE OF BIUAG & MALANA
ECO-PARK AS SHOWN 5
ENGR. CHINNEE M. DAQUIOAG ENGR. RODERICK L. TALAY ATTY. JOEL A. RUMA
LOCATION: ENGINEER I MUNICIPAL ENGINEER MUNICIPAL MAYOR S-3
BRGY. DUNGAN, RIZAL, CAGAYAN