Risk Assessment
All electrical works conducted on Coles projects/sites must be preceded by the completion of a risk assessment by the electrical
worker. Where the risk assessment process or legislative requirements determine that a safety observer is necessary for any work
on or near exposed energised conductors or live conductive parts, then a safety observer should be organised by the electrical
worker and be present during works.
Permits to Work
The relevant brand permit and permit process must be observed at all times.
Competency
Electrical work (whether energised or de-energised) must only be carried out by appropriately licensed or registered electrical
workers. For more information about the applicable electrical licensing or registration laws contact the local State Electrical
Nominee.
Lock Out procedures are to be known and understood by all electrical workers that are required to deploy them.
Live Work
State and Territory electrical regulations recognise that there are a limited number of circumstances in which there may be a need
to perform ‘live work’.
‘Live access work’ (testing and fault finding) should be undertaken, where possible, in a de-energised environment using de-
energised testing methods.
Live access work can be performed except in the following situations:
• Where a risk assessment has identified that live access work cannot be performed safely
• When working outdoors on live electrical equipment during periods of inclement weather e.g. rain, hail or electrical storms
Key principles of Lock Out Tag Out (LOTO) – to be followed in all cases
Regardless of the energy type, it is mandatory for all lock outs to follow three common steps:
1. Stop: the source of energy to a lock out point is stopped, diverted or released prior to the actual lock out being performed
2. Lock & Tag: all lock out points will be secured to prevent the inadvertent de-isolation/re-energisation of the lock out point
3. Test/Try: this is testing for proof of positive isolation
Electrical Lock Out Tag Out (LOTO) & Restoration of Power May 2020
Requirement to Isolate
All electrical workers must isolate the potential danger, prevent others from operating the source by locking out the isolator,
tag the switch or isolating device, and test to ensure it is safe prior to proceeding. All electrical workers will (where such exists)
access and check on-site electrical drawings and schematics to confirm circuit and isolator details and locations prior to
commencement. Electrical workers must ensure that the fuse switch or breaker that has been isolated by LOTO is correct.
Isolating devices should be secured in the open position or zero energy state, in such a manner as to prevent inadvertent
operation by the isolator.
All potential energy sources must be isolated prior to commencement of any works. This includes all sources of supply which
may be fed from Centre Management or other external sources (e.g. sub- stations).
No work is to take place if the electrical equipment to be accessed cannot be isolated appropriately. Escalate to the Site
Manager if you are unable to isolate all appropriate power sources.
Securing the isolation
Electrical workers must ensure when isolating electrical circuits or equipment, that the correct point of isolation is identified, an
appropriate means of isolation is used, and the supply cannot be inadvertently re-energised while the work is carried out.
A fundamental principle is that the point of isolation must be under the control of the person who is carrying out the work on the
isolated conductors.
Tagging and locking systems must also be used at the point(s) of isolation. Tags must include the name of the person who has
isolated the circuit, contact details, treasons for isolation and identified the circuit isolated.
Special Note: Cables are not to be removed from a point of supply as the method of temporary isolation, as this form of isolation
cannot be adequately secured.
Electrical Lock Out Tag Out (LOTO) & Restoration of Power May 2020
Sharing of Personal Red Locks & Red Personal Danger Tags/Electrical Work Being Conducted by Multiple Electrical Workers
Personal Red Locks and Personal Red Danger tags cannot be shared. Only the lock holder who affixes the Personal Red Lock and
Personal Red Danger tag will be permitted to remove that Personal Red Lock and Personal Red Danger tag.
A specific procedure is available to cover extraordinary circumstances where removal of a Personal Red Lock or Personal Red
Danger tag may need to be done by someone else other than the person who attached the lock out gear. Refer to LOTO
Removal Checklist.
There will be one Personal Red Lock and Personal Red Danger tag affixed for every electrical worker working on a piece of plant or
circuit. The use of one Personal Red Lock and/or Personal Red Danger tag to cover multiple electrical workers is not permitted.
Multiple electrical workers are not permitted to work under one Personal Red Lock or to share keys. The deployment of an
approved multi-lock hasp is required to be used.
The snapping of multiple Personal Red Locks onto another lock is not permitted, must only be affixed via a multi-lock hasp.
Completed Personal Red Danger tags are to be affixed to each Personal Red Lock for lock out. Personal Red Danger tags must be
affixed to the Personal Red Lock by feeding the tag eyelet through the lock or affixed by use of a cable tie. The use of string to affix
tags is generally not satisfactory as string can be tampered with or come away should a string tie knot come loose.
Electrical Lock Out Tag Out (LOTO) & Restoration of Power May 2020
Isolating supply in Distribution Boards that cannot be secured with LOTO hardware affixed
Due to the design of some distribution board cabinets some cabinet doors may not be able to be closed and/or locked within LOTO
hardware affixed, when this circumstance is encountered the following guidance is provided on the appropriate method of isolation:
Distribution boards in lockable plant room:
• Fit the LOTO on the RCD and add isolation tag with electrician’s details.
• Lock plant room door and advise SM of your work
• No unauthorised persons to be allowed in the plant room
Distribution boards not in lockable plant room/BOH:
• Isolate supply to entire distribution board
• Test to confirm isolation of distribution board
• Isolate RCD by removing wires from load side and terminating them with appropriate terminal connectors
• Add the LOTO isolation tag with electrician’s details to the RCD
• Place LOTO Danger Tag on door of distribution board
• Close and lock door of distribution board
• Re-energise distribution board
• Advise the Site/Store Manager of the works
NOTE: Distribution board must be isolated prior to reinstating isolated RCD input wires.
Leaving Unfinished Work
If work is left unfinished, the workplace must be left in a safe state including, for example, by:
• terminating any exposed conductors
• physically securing any exposed conductors or surrounding metal work
• tagging, taping off the electrical equipment and the workplace area
• informing affected persons at the workplace the work is not complete and advising of potential hazards
• taking any necessary precautions to ensure that electrical equipment cannot become inadvertently re-energised
• ensuring that the status of switchboards and electrical equipment are clearly and correctly labelled
• handing over adequate information to workers taking up the unfinished work to allow them to continue the work safely
Any Personal Red Lock and/or Personal Red Danger tag that is left affixed with no electrical worker present or contact details
available for the worker undertaking electrical work in the area can be deemed a breach of LOTO procedures. A full incident
report and investigation will be required.
Upon Leaving Site
If the electrical worker is required to leave the site temporarily and will be contactable, the isolation lock and Danger tag may
remain in place, provided the worker’s name and contact details are clearly displayed. Switchboard and plant room doors must also
be secured prior to leaving site.
If the work is incomplete, for example at a change of shift, the last person removes their danger tag and lock, leaves the workplace
in a safe state and fits an Out of Service tag.
When work is resumed, the person in charge of the work completes a new isolation permit, removes the out of service tag and each
person then applies their danger tag and/or lock.
When work is finally completed, each person removes their danger tag and/or lock.
Electrical Lock Out Tag Out (LOTO) & Restoration of Power May 2020
Note: The first electrical worker and lock holder who affixed the LOTO will be the last person to remove Example: Control switches
their Personal Red Lock and Personal Red Danger tags from each lock out point. not for lock out
On removal of the Personal Red Lock the electrical worker will advise all persons involved that lock outs have been removed.
Precautions against inadvertent operation of other electrical equipment is to be considered prior to supply being restored.
All reasonable steps must be taken to ensure that restoring electricity supply following isolation does not pose risks to health and
safety at the workplace. For example:
• appropriately terminating all conductors
• carrying out appropriate testing on any new, altered or repaired electrical equipment, for example tests for insulation
resistance, earth continuity, polarity, correct connection and function testing
• removing safeguards, including temporary bonds and short-circuiting devices
• notifying all workers working on the electrical equipment and other affected workers at the workplace that electricity is
to be restored
• taking precautions as appropriate to ensure that other electrical equipment is not inadvertently energised
• following procedures for removing any locks (or other control mechanisms), tags, notices and safety signs
• carrying out a visual inspection to ensure that all tools, surplus material and waste has been removed from the workplace.
When electricity is restored tests must be carried out to confirm that polarity is correct, actives are switched and, where applicable,
phase sequences are correct before electrical equipment is used. For further information refer to AS/NZS 3017:2007 Electrical
installations – Verification guidelines.
(Note: AS/NZS 3017 provides guidance on testing of low voltage electrical installations. It is recommended that the earth be
connected first, followed by the neutral and the actives. See AS 4741 Testing of Connections to Low Voltage Electricity Networks.
Removal of LOTO by Any Other Electrical Worker Other than the Person who affixed the LOTO
No other person, other than a license electrician with an authorised work order is permitted to remove Personal Red Danger tags
and Personal Red Locks. Any such act will be deemed a breach of this lock out procedure, and a serious incident will be logged and
an investigation will take place and be led by the safety team or site manager in liaison with relevant maintenance team.
In the event of an electrical worker failing to remove their Personal Red Lock and Personal Red Danger tag prior to leaving the
work area or site, and the equipment is required for return to service, the electrical worker will be contacted and where possible
required to return to site to remove the lock and tag.
Where a person has not removed their Personal Red Danger Tag and Personal Red Lock and all reasonable efforts to contact them
have been unsuccessful, or the person cannot return to work, then the Site Manager or person in charge of the site will contact the
relevant Help Desk to escalate the issue as per normal process with the original job number. The Help Desk will organise for the
appropriate qualified person to remove the tag/lock out after their procedures have been followed to ensure safety at the site by
following LOTO Removal Checklist.
For construction projects only - Construction projects may require isolations to be in place for several days, in this case the
permit should state the period of the time that the isolation is to be in place for. The appointed Construction Site Manager will
organise for the appropriate qualified person to remove the tag/lock out after their procedures have been followed to ensure
safety at the site by following LOTO Removal Checklist.
As a part of the resultant investigation, liaison with the relevant maintenance team should occur so the involved person can be
contacted before they begin work on their next rostered shift or return to duty, and interviewed within an incident investigation
context and be required to make a full statement as to why they failed to remove their lock out.
Electrical Lock Out Tag Out (LOTO) & Restoration of Power May 2020
Warnings
Alternative sources of supply must also be identified and may include inverter/UPS systems, stand-by
generators, solar cells, neutral back feed from intermixed circuits, ring main systems, mains power
with separate auxiliary power supplies for control, transformation up (back feed from ELC controls)
multiple control supplies and luminaries supplied from emergency sources or supply. This would
extend to the possibility of circuit wiring of electrical equipment or conductors becoming energised
due to any operation of automatic control devices, such as thermostats, switches, PLCs and other
interface devices.
All other non-electrical sources of energy such as counterweight, stored hydraulic and pneumatic
energy will be identified, isolated or secured to prevent unwanted release of energy from these
potential sources.
All electrical conductors and parts including neutral and earthing conductors will be treated as
energised until proven de-energised.
DANGER
TEST BEFORE
YOU TOUCH
Useful References
Name Available from
Coles Group Health Safety and Wellbeing Policy Connect
Coles SafetyCARE System Overview Connect
SafetyCARE Contractor Management Guideline Connect
SafetyCARE Hazard Management Guideline Connect
Coles High Risk Work Requirements Connect
Electrical and Gas Isolation Work Permit Connect
Electrical Contractors Safety Report (Electrical Exposure) Connect
Lock Out Tag Out (LOTO) Kit Contents Connect
Lock Out Tag Out (LOTO) Removal Checklist Connect
AS 4741 Testing of Connections to Low Voltage Electricity Networks SAI Global
Coles Work Health and Safety Schedule Connect
Version History
Version Date Nature of amendment:
02 September 2018 Removed reference to SafetyCARE Standards and aligned with the Coles SafetyCARE System Overview.
New Coles Group template, updated Coles Group Health Safety and Wellbeing Policy, included reference to Coles High
03 December 2018
Risk Work Requirements
04 May 2020 Added detail to ‘Securing the Isolation’ section based on audit findings.
Energised Connected to a source of electrical supply or subject to hazardous induced or capacitive voltages.
A conductive part of electrical equipment, which can be touched and which is normally not live, but which may
Exposed Conductive Part become live under fault conditions.
A term applied to part or all of an item of electrical equipment when a difference of potential exists between it
Live (energised)
and the mass of earth under normal conditions of operation.
Live access work ‘Live Access’ means the access to electrical equipment while energised and includes fault finding, verification of de-
energised equipment and visual inspections of energised equipment.
Examples of live access are:
• Fault finding live electrical equipment whilst energised
• Testing electrical equipment for isolation
• Commissioning of electrical equipment that has exposed parts
• Taking voltage and current reading of equipment whilst energised
• Adjustment of electrical switchgear and control equipment that exposes live parts
• Thermal scans
• Visual inspections
• Opening of a door to motor control panels
• Installation of electrical equipment, new Installations and field works
Live Work ‘Live work’ means electrical work performed in circumstances in which some, or all, of the electrical installation, or
equipment being the subject of the electrical work, is energised at voltages above Extra Low Voltage. Extra Low
Voltage means “an operating voltage not exceeding 50 V ac or 120 V dc ripple free”.
Live work is not to be performed by any contractor, except in a limited number of circumstances. For further
information and examples of what constitutes live work, refer to ‘Live Work’.
Lock Holder The primary electrical contractor who affixes a lock out item of hardware to an item of plant.
Low Voltage (LV) Voltage exceeding 50 volts ac or 120 volts DC but not exceeding 1000 volts AC or 1500 volts DC.
A person specifically assigned the duty by the electrical worker of observing and warning against unsafe approach
Safety Observer
to equipment and other potential hazards. This is particularly important when working near live exposed high
voltage equipment.