Preliminary Design Report Appendix K Drainage Design Basis Document
Preliminary Design Report Appendix K Drainage Design Basis Document
Preliminary Design Report Appendix K Drainage Design Basis Document
Drainage Design
Basis Document
NTA
BusConnects Core Bus Corridor
Drainage Design Basis
Arup
50 Ringsend Road
Dublin 4
D04 T6X0
Ireland
www.arup.com
NTA BusConnects Core Bus Corridor
Drainage Design Basis
Contents
Page
1 Introduction 1
1.1 Background and Overview of the Project 1
1.2 General principles of drainage design 1
1.3 Method of design 3
Appendices
Appendix A
SuDS Eligibility
Appendix B
Bus Connects – Road run-off collection gullies
1 Introduction
Figure 3: Typical Cross section. Kerb between the Bus lane/carriageway and the cycle
track.
Variable Value
Region Scotland/Ireland
Return Period Drainage Network: 1 in 1 no surcharge,
(GDSDS Volume 2, Section 6.2 and Drainage Drainage System: 1 in 100 no flooding in
Requirements for Planning Applications) greenfield areas only,
Drainage System: 1 in 30 years no flooding
for extending urban areas
M5-60 16.3
(Met Eireann. Return Period Rainfall Depths
for sliding Durations. Irish Grid: Easting
315887, Northing: 234669. Values derived
from a Depth Duration Frequency Model)
Ratio R 0.279
(Met Eireann. Return Period Rainfall Depths
for sliding Durations. Irish Grid: Easting
315887, Northing: 234669. Values derived
from a Depth Duration Frequency Model)
Minimum Global Time of Entry 4 minutes
(Recommendation for Site Development
Works for Housing Areas)
Max. Rainfall 50 mm/hr
(GDSDS Volume 2 Table 6.4 Surface Water
Design Criteria)
Max. Time of Concentration 30 minutes
(Wallingford Procedure States the Modified
Rational Method has only been tested for time
of concentration not greater than 30 minutes)
Climate Change 20%
Variable Value
(Dublin City Council Development Plan 2016-
2022 and Drainage Requirements for Planning
Applications)
Table 4 above states minimum pipe sizes, minimum depth of cover, minimum
velocity and roughness coefficient.
The List below applies to all the Local Authorities apart from Dublin City Council
who do not approve the use of uPVC pipes in the public area.
• Concrete: Concrete sewer pipes with spigot and socket joints and rubber rings
fittings to comply with IS EN 1916 and IS 6 2004 or equivalent standard.
Class M or class H. 11.3.2.
• Clayware: Vitrified clay pipes and fittings must comply with the requirements
of I.S./EN 295-1/2/3:1992 or equivalent standard. Class 160 or 200. 11.3.3.
• uPVC: Unplasticised P.V.C. pipes must comply with the "Provisional
Specification for Soil Pipes, Drains, Sewers and Fittings made of unplasticised
P.V.C." issued by the Department of the Environment. B.S. 8005: Part 1
Sewerage or equivalent; B.S. 8010: Part 2 - Pipelines on land or equivalent:
design, construction and installation; B.S. 5955: Part 6 Code of Practice for
the Installation of unplasticised P.V.C. Pipework for Gravity Drains and
Sewers or equivalent EN1401 Unplasticised P.V.C. sewer pipe specification
B.S.4514 Unplasticised P.V.C. soil pipe specification Regulations 11.3.4.
• Other: The use of alternative pipe types requires the prior express written
approval of the relevant Local Authority.
• Pipe material should not change between manholes.
• The installation of sewers by pipejacking/drilling should have the prior written
approval of the relevant Local Authority.
• The Developer must obtain written permission from the relevant Local
Authority when pipes are to be laid in landfill, contaminated sites or on poor
ground.
Fully New Paved Catchment Discharge rates throttled to 2l/s/ha with minimum flow of 2l/s
Areas
Fully newly Paved (existing Attenuation/SuDS measures sized to contain the 1 in 100-year
greenfield) Areas storm with a 20% allowance for future climate change
Exceptions:
• Where attenuation measures are proposed in the floodplain, they shall be sized to contain
the 1 in 100-year storm plus climate change
• Above ground retention of water might be designed to the 1 in 100-year storm plus
climate change in situations where the flooding of existing properties might be
compromised.
The drainage system design must manage on site the quality of runoff to prevent
pollution in receiving surface waters and groundwaters. The type of SuDS is
chosen to achieve the water quality targets.
In areas where the catchment remains unchanged which implies that no additional
impermeable areas are proposed, the design will consist of relocating the gullies to
a suitable location. This location will be based on the water pathway that will
depend on highway alignment and tie-in requirements. A relevant number of
gullies will be located either at the kerb line between the cycle-track and the bus
lane, or at the kerb line between the footpath and the cycle track. Further, the
spacing of existing gullies will be reviewed to ensure that they are collecting the
appropriate run off area.
When schemes run completely through greenfield sites and thus they are not part
of an existing network, they will be considered a new development and GDSDS
Volume 2 and the Drainage Requirements for Planning Applications will be
adhered to.
2.9 Gullies
In accordance with Greater Dublin Regional Code of Practice for Drainage Works
Section 14, the following criteria will be adhered to:
• Gullies, gratings and frames shall conform to EN 124, Class D400 or
equivalent. Gullies shall be provided for every 200m2 of paved area at a
minimum, except for low points which may require additional gullies (SuDS
design may eliminate the need for gullies in various locations). (GDRCoP
Section 14.1)
• Connections from gullies discharging to a combined sewer shall be sealed and
from gullies discharging to surface water sewers can be unsealed.
• Interconnection between gullies shall not be permitted. Gully connections
shall need exceed 10m in length and shall connect to sewers in the direction of
the flow. An additional manhole shall be provided on gullies where the length
of the connection pipework is greater than 30m. If gullies are connected to
manholes, they shall connect at the benching level or a maximum of 500mm
above the invert of the main pipe (GDRCoP Sectioin 14.7
The aim of this document is to provide a list of Sustainable Drainage Systems (SuDS) options,
as designing drainage solutions for the Core Bus Corridors (CBC) project. This document is
an appendix of the Drainage Design Criteria. This document has been developed by TYPSA,
Green Blue Management (GBM) and JACOBS.
requirements are clearly summarised and, particularly, Sustainable Drainage Systems (SuDS)
are required in new developments.
Additional references that have been considered are:
• The Dublin City Development Plan 2016-2022. This Plan includes among its objectives
the promotion of more natural drainage solutions in line with the SuDS principles.
• Relevant Local Area Plans for all the Dublin Local Authorities
• The “Design Manual for Urban Roads and Streets” (https://www.dmurs.ie/).
Finally, it is important to remark that the use of SuDS techniques in urban environments is
also one of the key points of the EU policy on Natural Water Retention Measures (NWRM).
2 PRIORITY LEVEL
In addition to local design guidance including the Greater Dublin Strategic Drainage Study and
Greater Dublin Regional Code of Practice for Drainage Works, the CIRIA SuDS Manual
provides a useful reference for the design of SuDS. The CIRIA SuDS Manual notes that the
components of a SuDS scheme should not be thought of in isolation and but as an
interconnected system to intercept and manage runoff before it is discharged. The Manual
promotes the concept of the SuDS Management Train, as a sequence of components, to
collectively manage runoff. A schematic of the SuDS Management Train is provided in Table
1.
Table 1 – The SuDS Management Train. Source: produced by Jacobs from CIRIA SuDS Manual 2015
The CIRIA SuDS Manual recommends that when considering SuDS solutions, the preferred
approach should be to manage runoff using Source scale solutions where reasonably
practicable. Where Source type solutions cannot fully address an increase in runoff from a
development, residual flows are discharged to be managed at the Site and then Regional
scales.
During Jacobs’s recent consultation on the MetroLink drainage design, a key point raised by
external Stakeholders was to demonstrate that a SuDS hierarchy had been fully considered
in developing the drainage design. This meant that Source and then Site scale solutions had
to be fully investigated and shown to be unsuitable before Regional solutions could be
considered. Similarly, where a Source or Site scale solution could partially mitigate an
increase in runoff this should be progressed to reduce the size of any Regional scale solutions.
Whilst it was recognised that many Source or Site scale solutions might not be suitable to
linear infrastructure projects in a constrained urban environment, full documentation of the
decision-making process was required to demonstrate compliance with best practice. At a
high level, this document is intended to provide a framework for this process, which can be
developed for each CBC.
During this process the limitations of the CBC will constrain the final solution for each individual
case. Two main constraints have already been identified: available space above and below
the ground and low ground infiltration capacity in certain areas. SuDS can not only be effective
solving surface runoff but also attenuating surface flows, while at the same time improving
water quality and possibly the environment. Throughout the design when selecting the best
solution this will be taken into consideration as well as maintenance aspects of each SuDS.
Well-designed SuDS are rarely used for a single function. For that, it is noted that SuDS can
be designed with different functions: water conservation and re-use (collection and re-use of
surface water), infiltration (encourage stormwater to soak into the ground),
detention/attenuation (temporary storage of runoff and slow down flow), retention (permanent
storage of runoff), filtration (runoff passes through a filter layer to remove pollutants) and
conveyance of runoff.
During the planning stage, ground permeability rate will be assumed to be negligible.
Therefore, SuDS will be designed to promote detention rather than infiltration to the ground.
This is likely to mean that we ‘over-design’ our SuDS measures by allowing for additional
storage that might actually be required. It is important to remark that some SuDS promote the
filtration through porous layers (filter media or permeable pavements) and, for this reason,
water quality can be improved where possible. Refer to the Drainage Design Basis main
document for further details.
3 SUDS PROPOSALS
3.1 Introduction
This chapter explains a catalogue of SuDS proposals which fit in our Routes. It is noted that
appropriate SuDS techniques must be applied depending on the available space and pollution
source. Where reasonably practicable for additional catchment areas, SuDS elements, such
as bio-swales or tree-pits will be implemented in order to improve the water quality. By running
through porous layers, a level of treatment (and attenuation) will be provided to the flow before
discharging into the existing network.
Additionally, physical constraints will be taken into account, such as the ground’s low
permeability. The following descriptions show a standard solution and, in the next design
steps, each intervention should be defined in detail.
Figure 1. Proposal type 1: Filter drain schematic. Source: CIRIA SuDS Manual 2015 (chapter 16, figure 16.2)
Figure 3. Type 2: Bioretention system. Source: CIRIA SuDS Manual 2015 (chapter 18, figure 18.1)
Figure 4 Example of previously proposed public realm designs for Dublin using SuDS. Source: DCC
Figure 5 Example of previously proposed public realm designs for Dublin using SuDS. Source: DCC
Figure 6. Type 3: Permeable pavement systems types (partial infiltration). Source: CIRIA SuDS Manual 2015
(chapter 20, figure 20.13)
Our approach to select appropriate SuDS drainage solutions on the BusConnects project
recognises wider scheme constraints, principally land availability, to ensure proposed
measures are proportionate and will not unduly impact on sensitive private lands. We have
followed a 5-stepped approach with Step 1 being the most preferable option and Step 5 being
the least and option of last resort.
The SuDS measures are selected to ensure no net increase in runoff and to maximise the
potential for runoff quality improvements. On this basis, ‘Source’ type measures (see Section
2) are preferred as they provide early interception and the greatest potential to slow runoff
flows, removing sediments and other pollutants. Oversized pipes or attenuation tanks are
used only as the option of last resort where all other measures have been found to be
impractical. Where oversized pipes or attenuation tanks are required they should, where
practicable, being implemented in combination with either Source or Site type attenuation
measures.
Can the redline boundary be extended into low impact Yes – stop, preferred approach,
lands e.g. public green space to accommodate a use in combination with Step 1 if
2 appropriate
Raingarden, Filter Drain, Swale/Bioretention area, Tree
Pit or other Source Control type SuDS solution? No – move to Step 3
Yes – stop, preferred approach,
Can a Site Control measure (e.g. Dry Detention Basin) seek to maximise source control
3 be implemented in addition to Source Control within the measures and minimise size of
redline boundary? Site Control Measures
No - move to step 4
Can the redline boundary be extended into low impact Yes – stop, preferred approach,
lands e.g. public green space to accommodate a Site seek to maximise source control
Control measure (e.g. Dry Detention Basin) measures and minimise size of
4
supplemented, where possible by a Raingarden, Filter Site Control Measures
Drain, Swale/Bioretention area, Tree Pit or other Source
Control type SuDS solution? No - move to step 5
Figure 7. Tolerance to soil salt of common tree species. Source: Forest Research (2011).
The design criteria to allow runoff from the road into the SuDS is preferred to maximize both
quality and space requirements, being also a more cost-effective approach. This criterion
implies that salty water will be collected by the SuDS and; for this reason, the selection of
vegetation species shall be done attending to the salt tolerance.
Therefore, the following SuDS techniques can be applied:
• Bioretention areas located along the routes, updating the existing green stripes. If
runoff of the road is collected, the filter medium must satisfy the conditions below:
1. The permeability should be between 100 and 300 mm/h.
2. 1.00 m depth is compulsory.
It is noted that bioretention areas will contain ground cover plants; and trees are not
required in terms of quality requirements. Trees will be considered only due to
landscape purposes and avoiding in this case collecting runoff from the road.
• Permeable pavements in car parks.
Regarding the location of the SuDS element, some key aspects shall be also taken into
account:
1. Existing trees and streetlights shall be retained. For this reason, spaces clear from
utilities and veteran trees inside the existing green stripes are preferable.
2. If there is not enough available space there where additional impermeable areas are
located, the existing green stripes upstream of the location where additional runoff is
generated shall be used. Thus, it can be guaranteed that the drainage system will have
capacity to convey the resultant flow.
3. In order to optimize the construction, those green stripes which require some updating
(because of implementing the Bus Connects Corridors) shall be prioritized.
Some examples of application are shown in the figures below:
Figure 8. Example of implementation of SuDS elements at the side of roads. Source: CIRIA
SuDS Manual 2015 (chapter 9, figures 9.12 and 9.14).
Figure 9. Example of bioretention area collecting road runoff. Source: Artful Rainwater Design: Creative
Ways to Manage Stormwater (2015).
Our reference
1 Overview
This technical note reviews the feasibility and efficiency of using other types of gully gratings/inlets to
accommodate surface water run-off along the new BusConnects Core Bus Corridors, while re-using the
existing drainage infrastructure.
Gullies are the primary collection system where kerbs are present to drain the carriageway and hard surfaces
around the city. The selection of the most suitable type of gully grating is being sought to increase safety on
cycleways and increase the ride quality along bus lanes.
1.1 General
Most routes along the Dublin BusConnects Core Bus Corridors are along National Roads. Therefore, this
document has been prepared with reference to the following NRA Documents and requirements:
Volume 4 Section 2 Part 3 NRA HD 33/15 Drainage Systems for National Roads
Volume 4 Section 2 Part 3 NRA HD 102/15 Spacing of Road Gullies
The design procedure used for the determination of the allowable spacing for the road gullies/ kerb inlets is
that as describe in Volume 4 Section 2 Part 3 NRA HD 102/15 Spacing of Road Gullies (referred herein as the
Standard). Four different stormwater collection systems are considered for comparison within this document:
2. Gully Collection System #2: 0.5m Wide Kerb Inlet Gully (See Figure 2)
This option considers the use of a 0.5m wide kerb inlet gully, allowing for a total carriageway surcharge flow
width of 0.5m from the kerb. Depending on site specific conditions (kerb profile), the use of a standard or non-
standard unit will be required.
3. Gully Collection System #3: Proprietary Split Grating and Kerb Gully Unit (See Figure 3)
This option considers the use of a standard split grating and kerb gully unit which would fit the finished kerb
cross section. This option allows for a total carriageway surcharge flow width of 0.5m from the kerb.
Figure 1: Gully Collection System #1: Typical In-Situ and Blockwork Gullies
Figure 4 shows a typical section, and plan, of the gully pot and a non-standard kerb gully unit. The non-standard
unit would be required for this system as the proposed geometry of the kerb line between the bus lane and the
cycleway such that a side inlet gully would not fit into the proposed profile.
Figure 3: Site condition allowing for use of standard kerb inlet gully unit
Figure 4: Gully Collection System #2: Non-standard 0.5m Wide Kerb Inlet
Mott MacDonald/ AECOM 4
Figure 6 and Figure 7 provide a street view of the typical installation, and the hinged opening respectively, of
this type of unit.
Figure 5: Gully Collection System #3: Proprietary Split Grating and Kerb Gully Unit
The total collection area (grating and side inlet) of this unit is 650cm2.
The maximum spacing of this split grating and kerb collection system was determined from first principles
using the formulas within Sections 5.12, 5.13, 5.14, 5.15, and 5.17 of the Standard.
The maximum spacing has been determined by calculating the specific G Value for the combined unit based
on assumptions of the Ag and P values (it should be noted that relatively large variations in these values have
minimal impact on the overall maximum spacing). The collection efficiency of the side inlet and the gully grating
were calculated independently, and the value of the more efficient component was used as the design
efficiency to determine the maximum spacing.
Figure 6: Typical Installation of Split Grating and Kerb Figure 7: Typical Hinged Opening
Gully Unit of Split Grating and Kerb Gully Unit
Mott MacDonald/ AECOM 5
Figure 8: Gully Collection System #4: Typical Narrow Profile Gully Unit
The maintenance factor applied for the various options in considered to be 1.0 (well-maintained urban roads).
The design catchment width will ultimately be determined by the collective drainage design for the footpath,
cycleway, and carriageway. Depending on site specific conditions along the various corridors (e.g. longitudinal
gradient, crossfall etc.) it may be necessary to utilise a dual collection unit with one unit collecting drainage
from the cycleway/footpath and one unit collecting the carriageway drainage.
Therefore, the design catchment width may vary to include the footpath, cycleway, and carriageway in some
areas, and the carriageway only in other areas. As a result, this document considers the required spacing of
the drainage units, for the above-mentioned options, for a catchment width of 10.5m (footpath, cycleway &
carriageway) and 6.5m (carriageway only).
Gully tops shall meet the requirements of EN124 load classifications; the appropriate class of a manhole top
or a gully top to be used depends upon the place of installation. The minimum class recommended for use in
each group is shown in brackets.
— Group 3 (at least class C 250): Pedestrian areas and comparable areas, car parks or car parking decks.
For gully tops, installed in the area of kerbside channels of roads (Figure 10) which, when measured from the
kerb edge, extends a maximum of 0.5 m into the carriageway and a maximum of 0.2 m into the pedestrian
area.
— Group 4 (at least class D 400): Carriageways of roads (including pedestrian streets), hard shoulders (Figure
11) and parking areas, for all types of road vehicles
Mott MacDonald/ AECOM 7
Figure 10: Typical highway cross- section showing the location of the groups
Figure 11: Typical detail of a hard shoulder showing the location of the groups
Mott MacDonald/ AECOM 8
2 Comparison of Options
The maximum spacing of gullies, non-standard kerb inlets, split grating and kerb units for the various road
gradients and crossfalls is shown in Table 1. A comparison of the spacings for the carriageway, footpath and
cycleway catchment and the carriageway catchment only, is also shown.
For a typical road crossfall of 2.5% the efficiency of a narrow gully appears to be similar to a typical gully.
Mott MacDonald/ AECOM 12
Typical gully units, the split grating and kerb units and narrow profile gullies have similar discharge capacities
across the various gradients and crossfalls, with the narrow profile gullies proving to be slightly more efficient.
The split grating and kerb unit does not meet Dublin City Council drainage maintenance requirements and is
therefore not recommended.
The narrow profile gullies reduce risks associated with gully gratings being laid within the carriageway outside
the wheel running track of buses and will improve ride quality.
Correct construction of the gully pot blockwork and foundation to the appropriate standard, should mitigate
against the risk of settlement of gully pots.
Based on review of the existing drainage system, discussion with local authorities about the following surface
water collection strategy is being proposed to complement the narrow profile gully.
In the interest of Water Quality all proposed gullies shall contain a sump that will trap debris & prevent
siltation, to enter the drainage networks.
Where existing gullies are present a narrow profile gully as shown in Appendix A should be retrofitted
wherever practicable.
Where existing combined gullies are in the carriageway, single units shall be connected using
separation chambers and rodding facility as detailed in Appendix B.
Refer to Table 2 for pros and cons of the use of a typical gully, kerb inlet gully, split grating and kerb gully and
narrow profile gullies.
Mott MacDonald/ AECOM 1
Footpath / Cycleway
Kerb
600
1050mmØ precast concrete chamber
1050mmØ precast 150mm Ø concrete pipe
concrete chamber not less than 1 in 100 fall
215mm 21N Concrete Blocks to
Heavy duty load class IS 20 with Designation 1 Mortar. 1
D400 cast iron cover No. Coat 10mm Plaster Internally
1050
1400
Connect to existing
Stormwater/ Sewer Network
2 3
Proteus has been deigned to offer an alternative solution in situations where regular replacement
of traditional gratings occurs due to the units being directly in the wheel line, Proteus works by
maintaining water absorbing capability at the kerb face whilst placing the portion of the unit usually
in the wheel line below the road surface thereby making less susceptible to premature failure.
Proteus is manufactured in our UK foundry in Leicestershire to the highest safety, quality and
manufacturing standards.
Safety Water Clearing Efficiency
We have developed a solution in Proteus that offers safe The ability of a grating to effectively remove surface
and predictable grating operation. The grating section water is most important along the kerb line where
is hinged and opens to 110° ensuring the opening 75% of water flows in typical rainfall conditions. Proteus
and closing sequence is safe, simple and predictable, has been designed to provide more than 2x the water
reducing risk of injury. At 300mm wide the grating is clearing area along the kerb line when compared to
designed to effectively remove storm water from the a standard 450 x 450 mm grating.
surface of the road whilst at the same time being out
Proteus has a Type R designation in accordance with
of the wheel track of all vehicles including bicycles.
Appendix A. Table A.2 Determination of grating type
of Highways England Design Manual for Roads and
Bridges CD 526 Spacing of road gullies.
Kerb line
50
90
1
UK IPO (Intellectual Property Office) Grant Number GB2580253
Compatibility
The longevity of any ironwork asset is directly linked to its alignment and compatibility with the structure below.
It is vital that the dimensions of the frame match those of the opening of the chamber in ensuring the frame is
fully supported. Through its unique design Proteus has a large footprint specifically designed to be compatible
with any standard 450Ø gully pot making it an ideal replacement for any existing gully installation.
Watershed 450x450 mm
Ironmaster®
Infill mortar
Ironmaster®
bedding mortar
visit: www.pamline.co.uk
The information given in this literature is,
to the best of our knowledge, correct at
the time of going to print. However, Saint-
Gobain PAM UK is constantly looking at
ways of improving its products and
services and therefore reserves the right
to change, without prior notice, any of
the data contained in this publication.
Any orders placed will be subject to our
Standard Conditions of Sale, available
on request.
Findings
Excellence in everything we do
The Solution:
STUDY and Rhino Asphalt Solutions Ltd for use in the strategic
road network, Wirral Council recognised the
advantages of Proteus when selecting
it as their preferred solution.
”
Ironmaster Installation System and its compatibility with we are confident in less future failures, and
the existing drainage network, Proteus provides a solution have the reassurance of a 5 year guarantee.
that improves cyclist safety and offers long term
performance reducing whole life costs for Wirral Council. Phil Miner Wirral Council
Proteus is just one of several innovative solutions offered by Saint-Gobain PAM UK.
For further information and advice on Proteus or any other product or service
offered by Saint-Gobain PAM UK please contact our team on
CASE STUDY REF: SGPUK004
0115 989 8903 or visit www.pamline.co.uk
National Transport Authority
Dún Scéine
Harcourt Lane
Dublin 2
D02 WT20