Ms-Water Balancing
Ms-Water Balancing
Ms-Water Balancing
No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 1 of 12
INDEX
1. Introduction 3
2. Prerequisities to procedure 4
3. Design parameters 5
4. Reference documents 5
7. Documentation 8
8. Demonstration procedures 8
9. Instrumentation 9
10. Safety 10
11. Attachments 11
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 3 of 12
1. INTRODUCTION
This method statement defines the step by step procedures and implementation of the
correct processes for the Measurement of CHW Flow through the guidelines contained herein
so as to ensure the work is executed in strict compliance with the project requirements,
international standards and local standards. It also ensures to serve the intended function to a
satisfactory level, QAQC control activities are conducted in a systematic manner. Safe
working practices are detailed and will be implemented throughout the execution of the work
activity.
1.1 The following test procedure has been prepared as a guideline for the proportional
balancing of all chilled water for this project.
1.2 The objective of this procedure is to verify that the correct water flow rate is available
at each unit and branch and the overall water flow rate is correct.
1.3 This procedure shall be adopted for all chilled water pipework serving all equipment
including the following:
• Chiller System
• Fan Coil Units
• AHU
• Primary & Secondary Pumps
• Heat Exchangers
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 4 of 12
2. PREREQUISITES TO PROCEDURE
2.1 Access / Egress
2.1.1 Safe access and egress at all times to the location of the system , the areas the
system serves and above ceilings as required is to be provided by the Main
Contractor.
2.2.1 Commissioning Manager; will have the overall responsibility for the execution of
the Testing and Commissioning activities, quality and safety as per the
specification and standards. The Commissioning Manager will maintain the
planning progress and coordination works with the Project Manager or his
nominated representative.
2.2.2 Commissioning Engineer; will be responsible for the day to day activities on site,
for the test report and design information approval and the onsite testing and
balancing.
2.2.3 TAB technician; will be responsible for the day to day systems balancing at site
as instructed by the Commissioning Engineer.
2.3 Requirements
2.3.3 The system pipe work to have been cleaned internally by the MEP Contract
HSE Safety Regulations and site specific safety requirements must be adhered to at all
times during the Testing and Commissioning of the system. The following shall also apply:
a. Suitable warning signs shall be visible to alert personnel of the ongoing work and any
hazards related to it.
b. All personnel carrying out the work have read and understood the method statement
and risk assessment.
c. PPE to be worn at all times.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 5 of 12
3. DESIGN PERAMETERS
The commissioning engineer shall balance the system to the requirements and
tolerances as specified in appendix WA1, section WA1.3 and table WA1.2 (tolerances
for regulation in chilled water systems) of C.I.B.S.E. commissioning code “W”.
3.2.1 Design water flow rates shall be taken from the approved installation drawings.
4. REFERENCE DOCUMENTS
5. PRE-COMMISSIONING/PRE-START CHECK
Carry out the following prior to starting any testing and record the results:
The main objective here is to minimize the risks of injury and damage to personnel and
equipment.
The following checks will be made on the CHW pumps every start:
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 6 of 12
5.2 Pre-Commissioning
A. Ensure all pipe work is system has been thoroughly vented of air at all coils and
high points of the system.
B. Identify all the branch commissioning valves that do not serve individual items
of equipment, and confirm designed flow rate.
C. Produce a commissioning valve schedule showing valves, type, size and
pressure drop at the designed flow rates.
D. Ensure all equipment is on standby and shall not have any contribution that
may effect to the overall flow rates.
E. Confirm that all manual valves are fully open or bypass valves set to fully
closed and that control valves have been set at 100% open thru BMS.
F. Confirm access is available to all commissioning valve test points, and they
have not been insulated over.
6. Commissioning/Test Procedures:
𝑲𝒗𝒔 √∆𝑷
𝑸=
𝟑𝟔
Where, Q = Flow rate (L/s)
P = Differential pressure at test ports (Kpa)
Kvs = Flow Coefficient provided by supplier (m3/hr)
C. P of each DRV at FCUs/AHUs/branches will be measured and adjusted to
obtain the proper flow marked on drawings and equipment schedules.
D. Finally reading of P, the calculated flow rate and DRV setting will be recorded
on the test sheet.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 7 of 12
A. Verify that all manual valves are open or preset as required, and all temperature
control (automatic) valves are in a normal or desired position.
B. Verify that all automatically controlled devices in the piping or duct systems will
not adversely affect the balancing procedures.
Once all pre-commissioning activities are completed, the following procedure will
A. Verify that all balancing, control, and isolation valves are wide open.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 8 of 12
G. The balancing valve serving the branch at the lowest percentage of design flow
H. Adjust the balancing valve serving the branch with the next (second) lowest
percentage of design until both branches are the same percentage of design
and in balance.
I. Adjust the balancing valve serving the branch with the next (third) lowest
percentage of design until all three branches are at the same percentage of
J. Continue this procedure until all remaining branches have been adjusted to be
K. If necessary, adjust the pump volume to set all branches at design flow, ±10%.
L. Perform the proportioning techniques specified in above steps (a) through (i) for
A. Test Sheets will be written up and all figures will be made available the Client’s
C. Any part of the Dossier shall be made available to the Consultant for witness.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 9 of 12
7. Acceptance Criteria:
The criteria for the acceptance of equipment to be tested and commissioned is as follows:
8. DOCUMENTATION
B. Supporting Documentation
The following supporting documents will be issued along with the testing and
commissioning report:
• Valid calibration certificated for the instruments used for the testing and
commissioning of the system.
9. DEMONSTRATION PROCEDURES
The commissioning engineer will ensure that the following works are carried out:
A. The final tested and balanced results are demonstrated to the accepting authority on
a random spot check basis, and that repeatability of readings is proven within the
accepted tolerance.
B. Submittal of all records of data obtained during testing, adjusting and balancing in
accordance with, and on, the approved forms.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 10 of 12
10. INSTRUMENTATION
The following test instruments will be used for the commissioning and testing activities. These will
be selected as having the maximum field measuring accuracy and being the best suited to
the function being measured and will be applied as recommended by the manufacturer.
B. Performance Testing
C. Electrical
• Clip-on ammeter
• Digital multi meter
D. Calibration
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 11 of 12
11. SAFETY
Health and Safety procedures by contractor will be implemented for this job. The responsible
safety officer as per procedure will conduct a routine safety inspection.
In order to ensure safe conditions during testing the following rules have to be followed:
• Persons engaged with inspection and testing have to be skilled and have
received proper and adequate training related to procedures and test
equipment utilized for the particular testing activity.
• Test instruments and test leads should be maintained in a safe condition and the
test methods not to create danger either for the operator or for other persons or
livestock.
• Where tests are required to circuits which are live for amp readings then the
tightness of the cable terminations will be checked without power prior to live
amp readings
• When readings are being taken for amperage and running speeds a support
engineer will be in attendance for safety reasons.
• Safety lights will be used in case of power failure ensuring the good illumination
of the working area to aid evacuation if necessary.
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III
PROJECT : SOCIO PARK HEIGHTS III Doc. No :
CLIENT : EMAAR PROPERTIES PJSC Rev. No : 0
CONSULTANT : HIDI RAE CONSULTING ENGINEERS INC Date : 13 NOV 22
CONTRACTOR : DUBCO CONSTRUCTION LLC Page No : Page 12 of 12
C. Emergency Arrangements
• Fire Precautions: No significant fire risks associated with this activity, but general
fire precaution measures will be taken as per Main Contractor instructions.
12. ATTACHMENTS
TEST FORMATS
SERVE POINT ENERGY TECHNICAL SERVICES LLC, PO Box 13334 , Dubai UAE
.
PROJECT : SOCIO PARK HEIGHTS III