Influence of Project Planning Practice On Performance of Construction Projects in Kenya

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

http://www.ijssit.

com

INFLUENCE OF PROJECT PLANNING PRACTICE ON PERFORMANCE OF CONSTRUCTION


PROJECTS IN KENYA

1* 2** 3***
Priscah Wabuti Mwanza Gregory Simiyu Namusonge Elizabeth Nambuswa Makokha
cahmpris@gmail.com gsnamusonge@jkuat.ac.ke enambuswa@gmail.com
1,2,3
Jomo Kenyatta University of Agriculture & Technology, Kenya
Abstract: The purpose of the study was to establish the influence of project management practices on
performance of construction projects with a specific objective to determine the influence of planning practice
on performance of construction projects in Kenya. The study adopted a mixed research design which included
descriptive survey, census and correlation. The target population was 1761 respondents with a sample size of
313 respondents comprised of 160 managers of Early Childhood Development Education, 11 managers of
county polytechnics, 133 stall managers and 9 managers of county modern markets. The study is of significance
to policy makers, county governments and academicians. The study found out that project planning practice
and project stakeholders’ practice had a negative significant influence on performance of construction
projects. The study also found out that planning gives direction to the activities to be performed in time and
reduces mistakes. The study therefore recommended that management of the construction projects should have
competent managers to have plans in place to give direction to the activities to be performed on time and
reduce mistakes also utilize the project resources adequately
Keywords: construction projects, project planning, project management practices
I. INTRODUCTION
The community and the stakeholder participation in planning process involve different roles and
responsibilities in the planning (Omolo, 2011). Project planning includes coming up with a plan that entails
specification of resources required and their allocation and determining the project end results, solving critical
issues and time schedule (Ntuala, 2010). To manage a project professionally and successfully, a project
manager will need adequate project management skills. Omidvar, Samad and Alias (2012) state that the
competence elements like technical, behavioural and contextual are essential. They further argue that project
managers’ competency can influence the achievement under construction process.
National Perspective of Project Management Practice and Performance
In Kenya, construction industry is an important sector in the growth of the economy. The Kenya National
Bureau of Statistics (KNBS, 2015) notes that the construction industries contributes to 4.1%, 4.2% and 4.8%
towards Gross Domestic Product (GDP) 2011 – 2014 (Gwayo, Wanyona & Ong’londo, 2015). The importance
of using construction projects is to create socio-economic value through effective public services that produces
an environment that fosters investment and improving the standards of living of the people in any society
(Ofari, 2013, Graham & Englund, 2013).

© Mwanza, Namusonge , Makokha 23


International Journal of Social Sciences and Information Technology
ISSN 2412-0294
Vol V Issue V, July 2020

Gwayo, Masau and Wanyona (2014) assert that the construction projects faces problems such as not being
completed on time, the building defects and over reliance on foreign workers. Many construction projects
majority being road infrastructure faces cost escalation that they may need extra funding and also project
management conflicts. Munamo (2012) asserts that many projects which are from the public sectors are not
completed on time. For instance the rate of completing government projects in Kenya 2010 – 2012 was 37.97%,
47.53%, 33.14% and 21.88%. In place they have building operations and organization documents that are
supposed to give guidelines 35.6% in the average completion rates. According to Mbaluku and Bwisa (2013)
a project is successfully implemented when it is on schedule, budget and when it is able to attain all the goals
set and accepted by the customers and used by him or her for the purpose it is intended. Muchungu (2012)
supports that despite the good quality of training of consultants in the building industry in Kenya, construction
projects do not meet the key performance goals. This can be seen by delay in completion time, cost overrun
and low quality of work hence collapsing of buildings in various parts of the country, customers’
dissatisfaction, while cost of maintenance is high and some buildings are not functional.
Reasons why objectives of a project are not successfully attained are noted by Gwayo, Masau and Wanyoma
(2014) is that they do not depend on the stakeholder’s satisfaction in the project. They further assert that the
construction industry contributes to 4.1%, 4.2% and 4.5% towards the Gross Domestic Product (GDP) between
2011- 2014 (KNBS).
Olembe (2012) and Okumbe (2008) note that there is less training of mangers in schools during the construction
of infrastructural facilities. This could be the causes of many schools having projects that are stalled,
dilapidated structures and poor performance in construction projects. Kibuchi and Muchungu (2012) further
argue that even with the best quality of training of consultants in the Kenyan construction sector do not always
meet their objectives. This is when many projects are delayed to be completed in time. Mukulu, Nteere and
Namusonge (2012) noted that performance measure is important for growth of organizations in achieving
goals.
Scope of the Study
The study focused on construction projects which are located in Kakamega County. This study comprised
Early Childhood Development Education, County polytechnics, County stalls and County modern markets that
are located in the County.
Kakamega County is the second largest county among the forty seven counties in Kenya. The County chosen
was justified by the many construction projects that are being undertaken and it has been used by other counties
as a bench mark.
Statement of the Problem
Project management practice in the construction industry continues to be a great challenge in Kenya. Projects
undertaken are substandard and only the contractors reap heavily from the shoddy work they do and most
people are not pleased with the quality of projects done (Bwisa & Oyalo, 2015). Despite the training of
consultants in the construction industries they do not meet the specified criteria. This construction projects can
collapse due to poor design, use of low quality materials and lack of qualified and incompetent contractors as
noted by previous researchers, Githenya and Ngugi (2014), Gacheru (2015) and Nyagah 2010. This is a
problem because few projects in Kenya are supervised by qualified technicians who end up failing. The
objectives of construction project are not successfully achieved since they do not depend on the customer
satisfaction (Gwayo et al., 2014). According to Kakamega County project implementation report (2013 –

© Mwanza, Namusonge , Makokha 24


International Journal of Social Sciences and Information Technology
ISSN 2412-0294
Vol V Issue V, July 2020

2017), the County has twelve sub counties under which construction projects are located. These markets are
Shianda, Khayega, Harambee, Shirere and Mulwanda are completed and yet some are under construction yet
the plan by County government was to complete these projects within a period of five years. It is noted with
concern that some projects are still under construction. For example, the construction of Bukura market,
Kipkaren and Mumias and Early Childhood Development Education Centres in Bahari Primary and Furale
Primary school are not yet completed and the period stipulated was five years. Namusonge, Kabare and Mutua
(2012) suggest that performance measure is important in assessment of improvement of organisation as well
determining whether or not it is achieving its stated goals. This study therefore sought to examine how project
planning practice influence the performance of construction projects in Kenya.
Study Objectives
The general objective of the study was to establish the influence of project management practices on
performance of construction projects with a specific objective to determine the influence of project planning
practice on performance of construction projects in Kenya.

II. RESEARCH METHODOLOGY


The study adopted a mixed research design. The research design was both qualitative and quantitative. The
research was descriptive and census. Descriptive was to assist the researcher to describe fully all the dependent
variables and independent variables to establish the relationship between the variables. The target population
was 1761 respondents comprised of 925 Early Childhood Development Education managers, 62 County
polytechnics managers, 765 modern stall managers and 9 managers of County modern markets. A sample size
of 313 respondents comprised of 160 managers of Early Childhood Development Education, 11 managers of
County polytechnics, 133 stall managers and 9 managers of county modern markets. The sampling technique
that was used was stratified random sampling. For primary data questionnaires was used as the main data
collection instruments and was in form of a five likert scale with both closed and open ended. Multiple sources
were used to collect secondary data; the respondents filled in the answers in the spaces provided to collect
information required. Pilot study was done using 11 respondents. Reliability was measured using Cronbach’s
Alpha. Validity of the instruments was measured using a team of experts in the field of project management
who are in charge of the area of study. Data was analyzed using qualitative and quantitative methods. Linear
regression model and correlation coefficient was used to determine the relationship between project
management practices and performance of construction projects.

III. RESEARCH FINDINGS AND DISCUSSION

Descriptive Results
The The findings are presented in a five point Likerts scale where SA=strongly agree, A=agree, N=neutral,
D=disagree, SD=strongly disagree and T=total.
Table 1 below contains a summary of data relating to attitude of respondents towards determining the influence
of project planning practice on performance of construction projects in Kenya. For instance, when respondents
were asked whether planning gives direction to the activities to be performed in time and reduces mistakes.
The distribution of findings showed that 46.0 percent of the respondents strongly agreed to the statement that
planning gives direction to the activities to be performed in time and reduces mistakes, 27.0 percent of them

© Mwanza, Namusonge , Makokha 25


International Journal of Social Sciences and Information Technology
ISSN 2412-0294
Vol V Issue V, July 2020

agreed, 1.0 percent of the respondents were neutral, 12.0 percent disagreed while 14.0 percent of them strongly
disagreed. These findings implied that planning gives direction to the activities to be performed in time and
reduces mistakes. The study findings are in agreement with Githenya and Ngugi (2014) who opine that project
planning leads to success of implementation of housing projects in Kenya.
The respondents were also asked whether funding of the project is done on time. The distribution of the
responses indicated that 25.0 percent strongly agreed to the statement, 30.0 percent of them agreed, 6.0 percent
of them were neutral, 33.0 percent of them disagreed while 6.0 percent of them strongly disagreed to the
statement. These findings implied that funding of the project is done on time. The study findings disagree with
the findings by Bwisa and Oyalo (2015) who found that there were delays in funding the CDF projects in
Kenya.
The respondents were also asked whether resources used in the project were adequate. The distribution of the
responses indicated that 24.0 percent strongly agreed to the statement, 28.0 percent of them agreed, and 5.0
percent of them were neutral, 26.0 percent of them disagreed while 17.0 percent of them strongly disagreed to
the statement. These findings implied that resources used in the project are adequate. The results support the
findings of Kariungu (2014) who noted that timely availability of material and work had a significant impact
on early delivery of the construction project.
The respondents were further asked whether project managers have experience and skills in planning the
construction projects. The distribution of the responses indicated that 33.0 percent strongly agreed to the
statement, 25.0 percent of them agreed, 5.0 percent of them were neutral while 20.0 percent and 17.0 percent
of them disagreed strongly and disagreed to the statement respectively. These findings implied that project
managers have experience and skills in planning the construction projects. This finding are corroborated by
Cherono and Morenge (2016) who asserted that planning skills assisted the project team with knowledge and
skills to achieve the project goals.
The respondents were further asked whether planning tools are involved in the project. The distribution of the
responses indicated that 21.0 percent strongly agreed to the statement, 36.0 percent of them agreed, 4.0 percent
of them were neutral, 21.0 percent of them disagreed while 18.0 percent of them strongly disagreed to the
statement respectively. These findings implied that planning tools are involved in the project. Findings
consistent with Kariungu (2014) who found that project planning tools influenced the completion of projects.
The respondents were asked whether the estimated period (long term and short term) by managers in planning
is used in projects. The distribution of the responses indicated that 22.0 percent strongly agreed to the statement,
28.0 percent of them agreed, 4.0 percent of them were neutral, another 27.0 percent of them disagreed while
19.0 of them strongly disagreed to the statement respectively. These findings implied that the estimated period
(long term and short term) by managers in planning is used in projects. The findings concurred with Nzioka
(2017) who suggested that project management planning on time affected the performance of construction
projects.

Table 1: Influence of project planning practice on performance of construction projects in Kenya

© Mwanza, Namusonge , Makokha 26


International Journal of Social Sciences and Information Technology
ISSN 2412-0294
Vol V Issue V, July 2020

Statement on Influence of project SA A N D SD


planning practice on performance of
construction projects in Kenya
1. Planning gives direction to the % 46.0 27.0 1.0 12.0 14.0
activities to be performed in
time and reduces mistakes
2. Funding of the project is done % 25.0 30.0 6.0 33.0 6.0
on time
3. Resources used in the project % 24.0 28.0 5.0 26.0 17.0
are adequate
4. Project managers have % 33.0 25.0 5.0 20.0 17.0
experience and skills in
planning the construction
projects
5. Planning tools are involved in % 21.0 36.0 4.0 21.0 18.0
the project
6. The estimated period (long % 22.0 28.0 4.0 27.0 19.0
term and short term) by
managers in planning is used in
projects

Inferential Analysis
Table 2: inferential analysis
Statement on CorrelationsProject Project Project Project Project Project
matrix planning stakeholders’risk monitoring leadership performance
practice practice practice and practice
evaluation
practice
Pearson
1 .241* .233* .196 .296** .006
Project Correlation
planning Sig. (2-tailed) .016 .020 .052 .003 .009
practice 300
N 300 300 300 300 300

As shown in table 2 above, the p-value for project planning practice was found to be 0.009 which is less than
the significant level of 0.05, (p<0.05). The result indicated that Pearson Correlation coefficient (r-value) of
0.006, which represented an average, positive relationship between project planning practice and performance
of construction projects in Kenya.
Regression Coefficients
A simple linear regression was performed to determine the effect of project planning practice on their
contribution to performance of construction projects in Kenya.

Y= β0 +β1X1 + ε

© Mwanza, Namusonge , Makokha 27


International Journal of Social Sciences and Information Technology
ISSN 2412-0294
Vol V Issue V, July 2020

Y = 0.002+ 0.153X1
Where;
Y=Performance of construction projects in Kenya
β0 = Constant (coefficient of intercept)
X1=Project planning practice
β1= Regression Coefficients
ε - error term
Table 3: Regression Coefficients
Model Unstandardized Coefficients Standardized T Sig.
Coefficients
B Std. Error Beta
(Constant) .002 .091 .019 .000
Project planning practice -.153 .099 -.153 -1.549 .000
a. Dependent Variable: Project performance of construction projects in Kenya
The results indicated that a unit increase in project planning practice leads to 15.3% improvement in the
performance of construction projects in Kenya. According to this model when the project planning practice
value is zero performance of construction project in Kenya will have a score of 0.002. This shows that model
is a good fit that significantly be used to predict the dependent variable representing the performance of
construction project in Kenya.
Hypothesis Testing
The hypothesis to be tested was:
H01: Project planning practice does not have a significant influence on performance of construction projects
in Kenya.
The findings from the table 3 above show that project planning practice (β = -.153) was found to be negatively
related performance of construction projects in Kenya. From t-test analysis, the t -value was found to be -1.549
and the ρ -value 0.000. Statistically, this null hypothesis was accepted because ρ<0.05. Thus, the study rejected
the alternative hypothesis and it concluded that project planning practices does not affect performance of
construction projects in Kenya.

IV. SUMMARY AND CONCLUSION


Project planning is organizing the assembling or putting the required resources such as manpower, time,
material, inputs and money to perform the work in the plan. In this study project planning practice were
measured by planning giving directions to activities to be performed on time to reduce mistakes, funding of
the projects is done on time, adequate use of resources, experience and skills in planning, projects tools and
estimated period. This study sought to determine the influence of project planning practice on performance of
construction project in Kenya. The study found out that planning gives direction to the activities to be
performed on time and reduces mistakes influenced the performance of construction projects. It also

© Mwanza, Namusonge , Makokha 28


International Journal of Social Sciences and Information Technology
ISSN 2412-0294
Vol V Issue V, July 2020

established that resources used in the project are adequate influenced the performance of construction projects
and project managers experience and skills in planning influenced the performance of construction projects.
Likewise planning tools are involved in the project and that estimated period (long term and short term) by
managers in planning used in projects influenced, performance of construction projects.
Moreover, the study found out that there was an average positive relationship between project planning and
performance of construction projects. Therefore, the study found out that project planning influenced the
performance of construction projects.
In conclusion basing on the findings, project planning practices (β = -.153) was found to be negatively related
to performance of construction projects in Kenya. From t-test analysis, the t -value was found to be -1.549 and
the ρ -value 0.000. Statistically, this null hypothesis was accepted because ρ<0.05. Thus, the study rejected the
alternative hypothesis and it concluded that project planning practices does not affect performance of
construction projects in Kenya.

References
Bwisa, H., & Oyalo, N. (2015). Study on factors influencing the completion of Constituency Development Fund
projects in Kangundo constituency. Journal of Management, 2(49), 21 – 36.
Cherono, E. & Moronge, M. (2016). Drivers of performance of textile projects in Kenya. A case of Rivatex
East Africa Limited project. The strategic journal of Business & change management, 3(1), 251-283.
Gacheru, E. N. (2015). An Investigation into National Construction Authority’s. challenges in regulating
building contractors. The case of Mombasa, Unpublished PhD thesis, Juja: Jomo Kenyatta University
of Agriculture & Technology.
Githenya, M. S., & Ngugi, K. (2014). Assessment of the Determinants of Implementation of Housing projects
in Kenya. European Journal of Business Management, 1(11), 230 – 253.
Gwayo, A., Wanyona, G., & Ong’londo, B. C. (2015). An Investigation into the factors that influence project
control process in the implementation of construction projects in Kenya. International Journal of soft
Computing and Engineering, 5(4), 56 – 63.
Gwayo, A.O., Masau, S.M., & Wanyoma, G. (2014). A critical analysis of the causes of project management
failures in Kenya. International Journal of soft computing and Engineering, 10(6), 492-497.
Gwayo, O. S., Masau, M. S. & Oyawa, O. O. (2014). The Role of servant leadership in project management in
Kenya. International Journal of Soft Computing and Engineering, 4(5), 35-36.
Kibuchi, N., & Muchungu, P. (2012). The contribution of human factors in the performance of construction
projects team participants in Nairobi. Retrieved from
http://eropository.uonbi.ac.ke,8080/xm/ui/handle/123456789/6951
Mukulu, E., Nteere, K., & Namusonge, G.S. (2012). Pedagogical Approaches Determining the performance of
Entrepreneurship Education in Kenya Public Universities. International journal of Humanities and
Social Science, 2(13), 1-13.

© Mwanza, Namusonge , Makokha 29


International Journal of Social Sciences and Information Technology
ISSN 2412-0294
Vol V Issue V, July 2020

Namusonge, G. S., & Kanyari, J. W. (2013). Factors that influence the Kenya Youth Entrepreneurs towards
the youth enterprise development fund: a case study of Gatundu South District, Kenya. International
Journal of Education and Research, (5), 1 – 22.
Namusonge, G. S., Kabare, K., & Mutua, S. M. (2012). Role of Human Resource Management practices on
performance of financial cooperatives based in Nairobi County Kenya. International journal of
Humanities and Social Science, 2(22), 289 – 297.
Namusonge, G., Kuria, L. (2017). Influence of employee participation on performance of government
Healthcare institutions in Kenya. Unpublished PhD thesis, Juja: Jomo Kenyatta University of
Agriculture and Technology.
Namusonge, G.S., & Kiage, K.A. (2016). The effect of monitoring, evaluation and risk monitoring of projects
on performance of firms in the telecommunication sector in Kenya. Strategic Journal of Business and
Change Management, 3(4), 1376 – 396.
Namusonge, G.S., Sakwa, M., & Omboto, D. (2017). The influence of corporate leadership on strategy
implementation in Commercial Banks in Kenya. Strategic Journal of Business and Change
Management, 4(3), 60-75.
Ng’ethe, J. M., Iravo, M.E., & Namusonge, G.S. (2012). Determinants of academic staff Retention in public
universities in Kenya: Empirical Review. International Journal of Humanities and social science,
2(13), 205-215.
Ntuala, M. (2010). Factors Influencing Implementation of Constituency Development Funded Projects,
Unpublished PhD dissertation, Master Thesis, Nairobi: University of Nairobi.
Nzioka, C. (2017). Role of project management planning on project success in Kenya: A case of Kenya power
infrastructure development projects. International Journal of Novel Research in Engineering and
Science, 4(1), 36-43.
Ofari, D.F. (2013). Project management practices and critical success factors. A developing country
perspective. International Journal of Business and management, 8(21), 14 – 31.
Okumbe, J.A. (2008). Educational management: Theory and practice, Nairobi: University Press.
Olembe, J.O., Wang, P.E., & Karagu, N.M. (2012). Management of Education, Nairobi: Educational Research
and Publications.
Omidvar, G., Samad, Z., & Alias, A. (2012). Project Management Competency Elements valued by project
managers in construction industry. IRASCST- International Journal of Research in management and
technology, 2(6), 2249-2263.
Omolo, A. (2011). Policy Proposal on citizen participation in devolved governance in Kenya. Nairobi: The
Institute of Social Accountability.

© Mwanza, Namusonge , Makokha 30