Docking System Mechanism Utilized on Orbital Express Program

Scott Christiansen* and Troy Nilson*

Abstract

Autonomous docking operations are a critical aspect of unmanned satellite servicing missions. Tender
spacecraft must be able to approach the client spacecraft, maneuver into position, and then attach to
facilitate the transfer of fuel, power, replacement parts, etc.

The philosophical approach to the docking system design is intimately linked to the overall servicing
mission. The docking system functionality must be compatible with the maneuvering capabilities of both
of the spacecraft involved. This paper describes significant features and functionality of the docking
system that was eventually chosen for the Orbital Express (OE) mission. Key analysis efforts, which
included extensive dynamic modeling, are also described. Zero-g simulation tests were performed to
validate the dynamic analyses.

The docking system was flown and operated on the Orbital Express mission. The system performed as
intended and has contributed to demonstrating the feasibility of autonomous docking and un-docking of
independent spacecraft.

Introduction

Once on orbit, typical spacecraft have limited lives. The harsh environment and lack of access make any
type of external support or maintenance nearly impossible. Anything from simply running out of fuel to
failure of a significant component can end the life of an otherwise useful spacecraft. If some type of
servicing capability were possible, flight operators could potentially get more out of their flight systems.

While limited servicing capability has been available through the Space Transportation System, or
Shuttle, high cost has limited its use to very expensive systems within the Shuttle’s orbital reach, notably
the Hubble Space Telescope. Over the past decade there has been a push to develop the capability of
autonomous servicing of orbiting spacecraft. The intent is to create autonomous, un-manned, tender
spacecraft that might provide services such as spare propellant, or new or replacement parts to already
orbiting client spacecraft.

Several practical needs can be met through autonomous servicing


• Extension of the life of spacecraft due to propellant replenishment
• Replacement of components that are obsolete or have failed
• Capture and move spacecraft to more effective orbit
• Recovery of a spacecraft with a failed deployment by assisting deployment
• Examination of a spacecraft to determine cause of failure

The company began working on a docking mechanism concept and prototype docking system on an Air
Force Research Laboratory (AFRL) Small Business Innovative Research (SBIR) program in 1999. As the
docking mechanism design matured, the Orbital Express program was developing requirements for
docking hardware. These eventually converged and our docking system was chosen for the flight
demonstration.

* SpaceDev, Louisville, Colorado

Proceedings of the 39th Aerospace Mechanisms Symposium, NASA Marshall Space Flight Center, May 7-9, 2008

207
Docking Mechanism Evolution

Initial Prototype Docking Mechanism


Beginning in 1999, SRC undertook a design effort to develop autonomous soft docking. The project
began with a Phase I SBIR grant from AFRL, who provided bounding conditions to the problem that
included an estimated spacecraft size and mass (a cylinder, 50-cm OD x 130-cm L, 50 kg) and a
requirement to dock two small microsat spacecraft and transfer fluid and/or electrical data between them.
Yet, definition of the various needs that might arise when servicing obsolete or exhausted spacecraft had
to be formulated. A key challenge became one of both establishing concept requirements as well as
designing to address those requirements.

Evaluation of existing designs revealed a myriad of related technology. Most available technology related
to extra-vehicular activity (EVA) interfaces, robotic boom end-effector configurations, or impact docking
mechanisms. Much of this technology, by nature, required manned intervention. Most of these systems
were primarily intended for large spacecraft and impact docking applications, and were not well suited for
the more precise requirements of autonomous soft docking and alignment of fluid and electrical
couplings. A critical component in identifying design requirements involved defining the eventual use and
application of the intended mechanical docking system. Further research did not yield any definitive
mission scenarios, but did present general ideas regarding potential applications. Two mission scenarios
were conceived:

Client (on-orbit spacecraft needing service) / microsat (spacecraft servicing the client): A microsat
could be launched on an as-needed basis to directly service an orbiting client. This would provide
very specific refurbishment based on the individual needs of the client. Response time would include
arranging a specific launch for the re-supply microsat.

Various client satellites and a microsat base station (both on-orbit): The client calls on the microsat
base as needed. This could provide faster service, but would be limited to common, more generic
types of refurbishment or repair.

In either of these scenarios, the tender would need to approach the client, match velocity and orientation,
establish initial mechanical contact, pull together to rigidize, establish electrical contact, and finally, the
pair must fly together as a single unit while docked.

Prototype Trade Studies


In parallel with organizing general mission requirements, the design team looked at many different
methods of joining, grappling, and aligning. Four techniques that seemed reasonable with respect to a
plausible flight control approach were traded in more detail:

1. “Harpoon”
2. A telescoping probe
3. Impact docking with a large conical guide
4. “Claw-type” linkages interfacing with a trefoil

The harpoon configuration, in which a probe is launched at a target, latches on, and is reeled back into
guide features, seemed unpredictable and presented complications concerning the alignment of fluid and
electrical couplings. A telescoping probe, where a telescoping pole extends to the mating spacecraft,
engages a target feature, and retracts to join the two, turned into a complicated multi-mechanism
apparatus not well suited for the direction and vision taking form. Impact docking was eliminated as an
option because soft docking seemed safer for the two spacecraft and better suited to precisely align fluid
and electrical couplings and prevent potential damage of components.

After extensive evaluation, SRC selected a three arm grapple design (Figure 1). The design would
consist of two main subassemblies: an active mechanism and a passive structure. The active mechanism
would consist of a motor driven lead screw that would actuate three individual linkages. The linkages
would engage the passive structure, whose geometry would allow it to be constrained by the linkages.
Further retraction of the linkages would seat the passive structure into a three point kinematic mount,

208
establishing a rigid interface. Release of the structure would be achieved by reversing these steps, with
separation velocity provided by the spring loaded kinematic mounts. Construction on the prototype
developed under the Phase I SBIR was completed in the early part of 2000. Figure 2 shows a picture of
the completed design.

Figure 1: SRC grappling concept Figure 2: SRC prototype

Prototype Testing
Beginning in early 2000, SRC began extensive testing on the prototype hardware in order to evaluate its
effectiveness and limitations. The test program included two significant components:
x In-house off-load testing: An off-load fixture was designed and manufactured to assist in
understanding various dynamics of docking as well as to prove system ability to dock and
transfer cryogenic fluids (LN2).
x Micro-gravity flight: A test plan was developed and executed to test the prototype in a micro-
gravity environment.

Counter Balanced Off-load Testing


In order to gain a general understanding of the docking system dynamics, a test was constructed using a
simulated inertia mass and cable/pulley system. Figure 3 shows the system with the prototype mounted
in the lower left hand corner. The passive side was mounted to an adjustable tip/tilt fixture allowing tests
to be performed in various misalignment configurations. Adjustment of the cable attachment point
(universal joint) and offload weights provided an approximation of a zero-g environment. During
development, more than 200 mechanical mate/de-mate cycles were successfully completed.

209
Figure 3: Off-load setup Figure 4: Micro-g flight

Micro-gravity Testing
The second component of testing included a flight on NASA’s modified KC-135 aircraft flown from
Ellington Field near Johnson Spaceflight Center (JSC), Houston (Figure 4). The experiments focused on
the grappling and capture events that could be accomplished within the 25-second micro-g window each
parabola. The experiment was designed to have two separate, free-floating simulators that represent the
relative mass and inertia of a client and a servicing satellite (approximately 2:1, client to servicing). The
active and passive halves of the prototypes were each mounted to their respective mass/inertia simulator.
With JSC crew assistance, the two halves were positioned within capture range. The active docking
mechanism was immediately powered in an attempt to demonstrate “zero” gravity docking. Because of
the limited time in micro-gravity, consecutive phases of the docking sequence were performed throughout
a series of parabolas. Despite these limitations, the micro-gravity tests proved instrumental in
demonstrating the mechanism behavior. The basic functionality of the docking system was demonstrated.
Observations of dynamic behavior during the test led to improvements of the design prior to the next
prototype build.
nd
Development of 2 Prototype and Orbital Express Flight Design

The OE program was intended to develop an industry-wide standard architecture to perform cost effective
autonomous satellite servicing. To demonstrate the technology, OE planned to use two spacecraft: the
client vehicle, referred to as NEXTSat, and the servicing vehicle, referred to as ASTRO. An illustration of
the OE vehicles is shown in Figure 5. The demonstration mission launched both vehicles together and
performed a series of mating and servicing operations on-orbit.

Orbital Express and the Phase II SBIR


A major criterion for autonomous docking success is the reliability of the capture system. SRC already
had developed and tested a functional prototype, and the capture requirements were well suited to the
SRC design. OE was still in the proposal stage and the design of the mechanical docking system (MDS)
[this was the second generation prototype/engineering unit] was proceeding under AFRL funding. It
therefore became necessary to balance the design objectives of OE within the practical limits of the SBIR
scope. At the onset of the MDS design effort, SRC worked closely with Boeing, who was providing much
of the initial insight into the technical requirements.

210
Figure 5: Orbital Express vehicles, conceptual drawings

Significant Changes from Initial Prototype

Mechanism Capture Capability


During the initial prototype design, a clear definition regarding the capture capability envelope did not
exist. In light of the emerging requirements, the prototype capability was not sufficient to meet the
requirements of the OE program. Therefore, the capture capability would need to increase in order to
accommodate the precision of the guidance and navigation controls. The required capture capability
would be achieved from scaling up the design, with minimum impact to the overall mechanism
configuration. In short, the mechanism size and stroke were increased to create a much larger “capture
zone”.

Mechanism Structural Capacity


The initial prototype had also been developed for use with a microsat, and its structural capability was not
suited for large vehicle payloads. Thought was given to refining the load paths in order to handle the
increased strength and stiffness requirements. The drive train also needed to be enhanced in order to
achieve the necessary mated interface stiffness. As a starting point, it was decided that the capacity
would be designed to accommodate the largest operational vehicle payloads encompassed in the scope
of the OE program.

Mechanical Docking System (MDS)


From a functional standpoint, the design that emerged looked very much like a scaled-up version of the
original hardware. The design had nearly doubled with respect to the prototype. However, the design had
not only grown in size, but had matured in complexity to accommodate its enhanced capabilities, both
internally and externally. Figure 6 displays the second generation prototype hardware, officially
designated MDS. The requirements that encompassed the design effort are displayed in Table 1.

MDS Testing

In-house Development Testing


SRC completed in-house testing of the MDS design that contributed additional information for the parallel
effort of the OE flight unit design. In house testing included stiffness characterization, off-load testing, and
mated interface load. All tests performed proved the MDS unit design accomplished the main goals of the
program.

Computer Simulation
Latch arm stiffness measurement was one of the several tasks undertaken on the MDS hardware. The
lateral and radial stiffness of the linkage assemblies had been measured in both the deployed and
captured position. By considering these measured stiffness values together with analysis of dynamic

211
simulation results, higher fidelity results and conclusions were produced. Dynamic Analysis and Design
System (DADS) software was used to model the capture and retraction features of the MDS. The model
included complete mass properties of two satellites, a zero gravity environment, and contacting features
of the MDS.

In excess of 400 cases were simulated to explore performance issues using a uniform distribution of
initial condition parameters. The analysis concluded that the mechanism was always capable of positive
captures given reasonable limits of relative initial test conditions.

Passive Side Active Side

Figure 6: MDS, second generation prototype

Table 1: MDS Phase II Design Requirements

Parameter Value
Axial Capture Distance: 15 cm
Angular Capture Misalignment Tolerance
Pitch/Yaw ±5 degrees
Roll ±5 degrees
Lateral Misalignment Tolerance: ±5 cm
Linear Contact Velocity Tolerance: 3 cm/s
Preload: 11250 N
Capture Time: < 10 s
Capture and Latch Time: < 240 s
Interface Outer Diameter: < 46 cm
Active Side Mass: < 23 kg
Passive Side Mass < 11.5 kg

6 Degree of Freedom (6 DOF) Tests


The main goals of these tests were to correlate/verify the dynamics analysis model and to demonstrate
functionality and performance of the hardware in a flight-like environment. 6-DOF testing was performed
with the test equipment as shown in Figure 7. The test simulated full, relative six degrees of freedom with
the actual hardware in the loop. During testing the active half of the hardware was mounted to a
moveable platform supported by six hydraulic actuators. The passive half was mounted above the active
half at a fixed location with a force/moment sensor in the load path. Software commanded the six legs to

212
start the test at a user-specified set of relative initial conditions between the active and passive halves.
Once the test was started, software simulated the complete relative dynamics of the two vehicles due to
the real contact between the active and passive halves during the capture sequence. The test results
were then compared to the dynamic model simulation predictions. Comparison of the test data confirmed
the model accurately depicted the capture dynamics. The information gained from the MDS tests was
critical to the flight design effort.

Figure 7: 6-DOF testing facilities at MSFC

Docking System Mechanism Description

Following are more detailed descriptions of some of the significant features of the docking mechanism
final design as it was flown on the Orbital Express program.

Figure 8: Docking system major components and schematic layout, as configured for Orbital
Express

213
Orbital Express Capture System (OECS)

The capture system consists of an active side and a passive side. The active side contains the grappling
arms and the drive system; this side would normally be part of the supply spacecraft. The passive side
provides capture features and a sensor to indicate proper engagement of the grappling arms; this side
would normally be a part of the client spacecraft. Figure 8 shows a general schematic of the system
configuration.

Capture Sequence
To understand the OECS unit, a description of its functionality is necessary. Figure 9 displays the typical
steps involved in a capture operation.

1. The linkages of the active mechanism begin in a deployed (open) state. The passive structure is
held in a station keeping envelope within the capture capability of the active mechanism.

2. Upon receipt of command, the motor begins to actuate a ball screw which translates an internal
piston along the length of the active mechanism canister. The piston moves three separate four-bar
linkages that make up the grappling linkages. The linkages then move downward over a roller feature.
The camming action of the roller causes the linkages to constrict, engaging the passive structure. The
wedge shaped architecture of the passive structure guides the tips of the linkages into center grooves.
Capture is achieved as the passive structure is constrained within the bounds of the linkages.

3. As the linkage tips move down along the grooves, they engage a shelf feature, allowing the active
and passive structures to be drawn together. As retraction proceeds, alignment occurs in stages.
Continued motion of the linkages causes the interface plate of the passive structure to contact push-off
rod struts that act as a three point alignment mount on the active mechanism. The alignment features
each consist of a spring loaded pin with conical ends that seat into tapered cups on the passive structure.
These features provide a gross alignment. With further retraction, additional features align the electrical
couplers within their allowable tolerance.

4. At the final stages of retraction, the passive structure becomes fully constrained by a final set of
cup/cone features. Rigidization then occurs as the motor applies the necessary preload to provide the
required interface stiffness.

1 2 3 4

Figure 9: Orbital Express Capture Mechanism Capture Sequence

214
Cone Mount, 3Plcs

Grappling Linkage , 3Plcs


(shown retracted) Top Plate Assembly

Floating Electrical Connectors, 3Plcs

Canister Assembly

Push-off Rod Assembly, 3Plcs

Motor, Gear Train, Brake Assembly

Figure 10: Active mechanism cross-section

Active Mechanism
The Active mechanism is composed of a top plate assembly to which the canister assembly is attached
(Figure 10). Within the canister assembly is a drive train consisting of a motor, ball screw, and
radial/thrust bearings which transfer load into the housing. All three linkages are fixed to a piston, which is
connected to a ball screw via a ball screw nut. The linkages consist of one upper grappling linkage and
two lower linkages which make up a four bar connection. Mounted to the canister is a reaction roller that
guides the linkages through deployment. Alignment occurs via two separate features: push-off rods, and
alignment pins. The three push-off rods are spring loaded features that seat into alignment cups on the
passive end to provide gross alignment. The cone mounts are hard mounted features that also seat into
cup features on the passive side. This geometry provides a statically determinate final position after mate.

Passive Damping
The need for passive damping was identified during simulation and prototype testing. Concerns had been
raised regarding difficulties that could arise during capture; specifically, the passive half impacting the
push-off mount and rebounding. While it was agreed that the passive side would need to be held within a
station keeping envelope during capture, a non-zero relative velocity would likely exist between the two
spacecraft. This could result in slight amounts of contact between the two faces of the active and passive
halves, making it difficult to maintain the passive structure in the required envelope. Also of great concern
was unintentional impact involving even larger than nominal velocity deltas, and the possibility of damage
to the mechanism.

Another motivation to introducing damping involved oscillations occurring during the capture event.
Testing of the prototype in a micro-g environment exhibited a tendency for the passive structure to
oscillate within the constraints of the linkage tips and the push-off mounts. Computer simulations
performed by Boeing confirmed this behavior. In order to address this issue, a spring damper system was
added to the push-off struts on the active mechanism. Figure 11 depicts a cross section view of the push-
off mounts with the spring damper system.

215
D amper R od
Bushing

D am per R od Spring
H igh Stiffness Piston

M ounting Flange

C ompression Piston Spring

H ousing

Adjustable C oulomb D a mper

Figure 11: Push-off rod cross-section

Torque Sensing Mechanism


Running the motor/actuator until proper preload is achieved was accomplished using a torque sensing
mechanism (Figure 12). To apply a preload in the mated position, a specific torque from the motor is
required. The torque sensing mechanism is adjusted to activate limit switches at the set torque needed
for proper preload. Once the limit switches are activated, the motor is commanded to stop. In the stop
mode, the motor/actuator applies a brake holding the preload developed.

Passive Assembly
The passive assembly (Figure 13) is a three wedge shaped trefoil. The faces of each wedge terminate at
a center groove that runs along its length. The passive interface consists of an interface plate that is
mounted to the three trefoils. Part of this geometry includes retention lips, or shelves, which provide the
linkage with a positive feature to grapple. The interface also includes kinematic cup features which help to
align the structure and institute preload. The OE program required a sensor to confirm that capture had
been successfully accomplished (Figure 9, step 2). Light Emitting diodes (LED’s) located on the passive
assembly detect when the active assembly arms are in the captured position (Figure 14)

216
Piston
Limit Switches
Compression Spring

Preload Adjuster
Motor Lever Arms

Bearing

Wave Spring Motor Mount Base


Wave spring retainer
and stop
Ball Screw

Figure 12: Torque sensing mechanism

Proximity Sensor Assembly

G&H Electrical Connector

Mating Cup Feature Housing Segment

Interface Plate

Figure 13: Passive assembly

217
IR LED
3pl

Light beam

Sensor
Electronics
Housing

Photo Transistor
3 pl
Figure 14: Proximity sensor detail

OECS Flight Unit Testing

Acceptance Testing
Based on the experience gained with the two prototypes, SRC developed and performed comprehensive
acceptance test program. In-house testing included many of the same elements that were present in the
prototype and MDS testing: mate and de-mate verification, stiffness characterization, and off-load testing.
In addition, thermal, thermal vacuum, and vibration testing were performed.

Computer Simulation
Dynamic models were updated to include all modifications incorporated after development. Significant
load cases were analyzed to verify that mechanism performance met the Orbital Express requirements.
The same software and methodology were used as for the development unit design effort.

6 DOF Testing
The final phase of qualification and flight testing included 6-DOF testing similar to that which was
performed on the MDS. Although the MDS and OECS mechanism features important for capture and
alignment are almost identical, small changes were made to the design based on the results of 6 DOF
testing of the MDS. Furthermore, the manufacturing fidelity of the OECS qualification components was
flight-identical, unlike the MDS which was of engineering development unit quality. For these two main
reasons, a second 6-DOF test of the qualification unit was performed. The goal was to once again
confirm that the dynamic modeling accurately depicted the dynamics encountered during capture and
alignment.

218
Orbital Express Mission

NEXTSat

Astro

OECS

Figure 15: Astro and NEXTSat mated by OECS during flight


For the Orbital Express mission, the two spacecraft were launched attached together with an adapter
coupling ring. The OECS docking mechanism was engaged in a unique, preloaded condition for launch,
but was not the primary load path for support of launch loads for NEXTSat. After system checkout and
stabilization, the robotic arm was used to attach the two spacecraft together. Prior to free flight
operations, the robotic arm was used as a safety measure to keep the two spacecraft connected while
the adapter coupling ring was released and jettisoned. The first docking operation was performed by
moving the spacecraft with the robotic arm (the two spacecraft were already de-mated and were held
together by the arm) and operating the OECS docking mechanism. This operation was successfully
performed and confirmed that further docking operations could be performed. After proving out a
“captured” docking operation several distinct free flying docking operations were performed. In each case
the separation of the spacecraft, the proximity flying, and the subsequent re-docking were performed
autonomously by the two spacecraft without ground control intervention.

While docked, key refurbishment operations were performed:


x The electrical connections were utilized for direct communication and electrical power transfer
between the spacecraft.
x The fluid connector was engaged and transfer of propellant was successfully performed.
x The robotic arm was utilized to install an electronics box on a mating port on the NEXTSat
spacecraft.

Overall, all mission goals were successfully completed. The two spacecraft have since been
decommissioned.

219
Conclusions

The OECS flight mechanism performed as expected and has supported demonstration of the
effectiveness of the soft docking approach enabled by the design. The blending of technology and vision
yielded a simple and effective concept. Through a series of design trades and system testing, the
application of minimal mechanisms, and the use of common proven technology (i.e. motors, lead screws,
and linkages), a highly functional design resulted. What began, during the primary phase, as a well
developed concept quickly evolved into a commercially viable product.

References

1. Shane Stamm and Pejmun Motaghedi, “Orbital Express Capture System: concept to reality,” SPIE
Conference, May 2004.

2. DARPA website http://www.darpa.mil/orbitalexpress/