1. Scope of Work
1.1 Purpose
The Purpose of this Method Statement is to define the work procedure for
testing & commissioning of Variable Air Volume (VAV) system with Air
Handling Unit (AHU)
1.3 Responsibilities
1.3.2 Check that the works are carried out according to the technical and
engineering specifications
1.3.3 To test together with the Mechanical T & C team to ensure the testing
are in line with Mechanical requirements.
Thermometer
Vane Anemometer
Project: JEWEL
Document: Method Statement for Testing & Commissioning of Variable Air Volume (VAV)
Document No:
Service: ACMV Installation
Multi Meter
Programmable laptop
1.6 Preparation
1.6.1 Ensure the VAV controller and motorized damper actuator is mounted
with wiring completed.
1.6.3 Ensure the determined reading value is entered on the label of the
VAV box and downloaded into the VAV controller.
1.6.4 To check the AHU LMCP wiring termination is correct and tested.
A) Visual Inspection
1.7.2 Ensure the VAV’s are correct Model No., Serial No.
1.7.3 Ensure the VAV’s are the correct model and box number to be fixed
according to the updated floor plan.
B. Electrical Check
1.7.6 Ensure that the correct supply voltage is available to operate a VAV
(24 Volts AC) and that the correct polarity is adhered to when
connected.
1.7.7 Ensure that wiring of the local thermostat for the VAV is terminated
correctly and tested.
1.7.8 Ensure that all electrical connections are tight and the wiring is
secured.
1.7.9 Ensure all BMS wire connection is terminated and tested at the DDC
Panel and field devices.
Project: JEWEL
Document: Method Statement for Testing & Commissioning of Variable Air Volume (VAV)
Document No:
Service: ACMV Installation
Project: JEWEL
Document: Method Statement for Testing & Commissioning of Variable Air Volume (VAV)
Document No:
Service: ACMV Installation
C. Control Function Check
1.7.13 Carry out the air balancing based on the design air flow rate required.
b) Adjust Fan to low speed, 20% of VAV box design air flow.
b) Repeat step ‘a’ for a speed of fan, 100% of VAV box design
airflow.
1.7.15 Adjust temperature set point to a value and notice the VAV boxes
modulate to reach the set point under PI control. Record the
temperature, flow and damper position at stable state. Also record the
temperatures, static pressures and fan speed of the AHU.
1.8.1 Pay attention when working at height, look out for any person passing
or working below.
1.8.3 Always use personal protective equipment (PPE) for personal safety
and protection. (Safety helmet, safety shoes and Safety belt / Safety
Harness).
Project: JEWEL
Document: Method Statement for Testing & Commissioning of Variable Air Volume (VAV)
Document No:
Service: ACMV Installation
1.9 Housekeeping
1.9.1 Ensure the work place will be kept clean and tidy
1.9.2 Daily housekeeping and disposal of waste will be carried out.