1977 Drakensberg Pumped Storage Scheme
1977 Drakensberg Pumped Storage Scheme
1977 Drakensberg Pumped Storage Scheme
engineering aspects
In Z.T. Bieniawski (Ed) 1977. Exploration for Rock Engineering. Proceedings of the
Symposium on Exploration for Rock Engineering, November 1976.Vol 2, 121-139. A.A.
Balkema: Rotterdam
1977 Bowcock et al. Drakensberg rock engineering
Synopsis
Introduction
1. Engineering description of the works
The principal source of water for Johannesburg and other centres in the Witwatersrand
for both industrial and domestic purposes has traditionally been the westward flowing
Vaal river (Figure 1). However, this source is no longer sufficient to provide an assured
supply to meet the demands of this rapidly growing area. As a result, the Department of
Water Affairs has proceeded with a scheme to abstract water form the upper regions of
the eastward flowing Tugela river and to pump this over the Drakensberg escarpment into
the Vaal catchment.
The first phase of this scheme was completed in 1974 and water is now being pumped
over the excarpment from a pumping station at Jagersrust.
The predicted demand for water from the Vaal catchment would have made it necessary
to duplicate this pumping scheme by 1980. However, as an alternative, studies were
carried out into the possibility of developing a pumped storage station which could be
used both for pumping water into the Vaal for water supply purposes and for storing
electricity. These studies were undertaken jointly by the Department of Water Affairs
and the electricity Supply Commission (Escom) as a result of which it was decided to
proceed with the Drakensberg Pumped Storage Scheme (1).
Escom will use the Drakensberg Scheme primarily to store surplus off-peak energy from
thermal power stations. For water supply purposes the Department will draw water from
the upper reservoir (Direkloof).
2
1977 Bowcock et al. Drakensberg rock engineering
The pumping head will be approximately 500 m, one of the highest in the world for this
type of scheme.
The Scheme, which is now in the early stages of construction, is located approximately 5
kilometers to the north of the existing Jagersrust pump station. The principal engineering
structures include an underground power station to contain four reversible pump-turbines
each driving a 250 MW reversible motor-generator, associated tunnels and shafts, surge
chambers and access tunnels (Figures 2 and 3). These works will be carried out under
contract to Escom. In addition, the Scheme involves the construction of two major
embankment dams at Kilburn and at Driekloof and extensive open excavations. These
excavations and dams are not discussed further in this paper.
An initial study of the rock mechanics aspects of the Scheme was made by the Council
for Scientific and Industrial Research (CSIR). After this study, Escom appointed Gibb
Hawkins and Partners as its consulting engineers for the design and site supervision of
the excavation, stabilization and lining of the underground works. Gibb Hawkins and
Partners in turn appointed Golder Associates of the United Kingdom as their specialist
advisers for the rock engineering aspects of the Scheme.
Two exploratory contracts were awarded by Escom at the beginning of 1975. The first
contract involved excavation of an exploratory adit and an exploratory shaft with
interconnecting headings in the area of the future machine hall. In addition provision was
3
1977 Bowcock et al. Drakensberg rock engineering
made in this contract for excavation of a test enlargement to the full span of the machine
hall and construction of a trial length of concrete lined pressure tunnel. The second
contract was for exploratory drilling both from the surface and from underground.
In August 1975, a preliminary contract was awarded for the excavation of the tailrace
tunnel and main access tunnel (headrace and tailrace refer to the generating mode).
Further contracts will be awarded by Escom for the remainder of the underground work.
This paper describes the rock engineering aspects of the Scheme including investigation,
testing and design phases. Particular emphasis is placed on the power station
excavations. Following a brief summary of geological and groundwater conditions, the
main rock engineering aspects are discussed. At the time of writing (July 1976) the
exploratory works are still in progress and full results are therefore not available.
2.1 Geology
The underground works lie mainly beneath the south facing slopes of the Drakensberg
escarpment between elevation 1730 m at the top of the surge shafts and elevation 1214m
at the invert of the tailrace portal (Figure 2).
The Scheme is sited mainly within rocks of the Beaufort Series of the Karroo System.
Fossil and stratigraphic evidence indicates a continental depositional environment.
Lateral facies variations are common and therefore the boundaries of the lithological untit
are frequently diachronous.
A distinct division of rock types in the vicinity of the Scheme occurs below a prominent
sandstone horizon which outcrops at approximately elevation 1550 m (Figure 2).
Below the marker horizon the rocks are primarily sandstones, siltstones and mudstones
from the Middle and Lower Beaufort series. Siltstones and mudstones from these
horizons vary in colour from greenish or bluish grey to dark grey.
Above the marker the rocks consist mainly of interbedded sandstones, siltstones and
mudstones of the Upper Beaufort Series, the mudstones and siltstones of which have
respectively and distinctive reddish-brown and greyish-green colouration.
In addition to the rock types mentioned above there are also occasional thin carbonaceous
seams predominantly in those rocks below the marker horizon. Carbonaceous seams are
usually thin, poorly developed fossil leaf remains within dark mudstones.
4
1977 Bowcock et al. Drakensberg rock engineering
5
1977 Bowcock et al. Drakensberg rock engineering
Dolerite sills and dykes are also present. The dykes are typically near-vertical, from one
to three metres thick, and often bounded by slickensided, serpentinised shear zones. A
major sill having an upper elevation of 1133 m and over 70 m thick has been found
beneath the proposed machine hall.
The strata within the Site area are essentially horizontal and bedding forms the dominant
structural feature. Bedding plane spacing has been found to vary from less than 5 mm to
up to 500 mm. Frequently cross bedding and other sedimentary structures occur within
the lithological units.
Joint surveys have been carried out both on surface exposures and in underground adits.
The surveys show three statistically significant near-vertical jointing trends striking at
approximately 120º, 160º and 190º. In interpreting the significance of the jointing it
should be remembered that the major axes of the main halls are east-west, the axes of the
tailrace and pressure tunnels are approximately north-south. (All directions in this paper
are with respect to magnetic north, 19º04’ west of grid north).
Faults are usually associated with dolerite dykes although displacements are generally
limited to a few metres.
2.2 Groundwater
Borehole permeability tests carried out over the area of the Scheme show a range of
permeability from 10-6 m/s to 10-9 m/s. In general, the sedimentary units are relatively
impermeable. Permeable fractured zones up to 2 m thick have been found at dyke
margins.
The presence of low permeability mudstone and siltstone seams gives ise in general to a
preferred ground water flow direction parallel to the bedding within the more permeable
units. The dykes and dyke margins modify this general flow pattern by dividing the rock
mass into a series of reservoirs. Significant changes in peizometric head across dykes
have been observed.
6
1977 Bowcock et al. Drakensberg rock engineering
1. General Approach
The scope of the investigation, testing and design processes depends largely upon the
characteristics of the rock mass and the nature of the in-situ stress field. These factors
will determine the degree of stability inherent in the roof, sidewalls and inter-section of
the excavations and the necessary reinforcement to maintain required stability conditions
permanently.
During feasibility studies for a project, only the most general type of geological
information is usually available. At this stage, the potential behaviour characteristics of
the rock mass are identified in very broad, general terms. Precedent and experience from
other similar schemes are principal factors.
Such experience is related to the rock mass and excavation geometry by means of
geomechanical classifications (2 and 3). Geomechanical classifications can be used to
distinguish between different potential failure modes which may range form structurally
controlled roof falls in jointed hard rock masses, to failure of intact rock material under
stress in more homogeneous, weaker rock masses.
The potential behaviour and possible support requirements for the underground
excavations are then estimated.
7
1977 Bowcock et al. Drakensberg rock engineering
8
1977 Bowcock et al. Drakensberg rock engineering
During the exploratory phase the available geological information becomes more detailed
and a final specific design is formulated. At this stage, the mechanical behaviours for the
rock mass is considered in terms of the most dominant characteristics and the
investigation, testing grand design processes are related to these specific parameters.
As previously mentioned, the earliest studies on the rock mechanics aspects of the
Drakensberg project were carried out by the CSIR and were based upon the use of a
geomechanics classification system (2). These studies suggested that stable roof spans
would be limited by the poor quality, horizontally bedded rock mass in which te major
underground excavations would probably be located. Other schemes with similar rock
conditions to Drakensberg were appraised. Table 1 gives the general rock mass
characteristics and machine hall sizes for the Drakensberg, Poantina and Portage
Mountain hydro-electric projects.
Based upon comparisons with the Poatina scheme in Tasmania (4), the use of a
trapezoidal roof arch with a total span limited to 20m was considered. In order to
minimise the effective overall height of the Drakensberg excavation and thus ensure
greater inherent stability of the sidewalls, each of the four pump-turbines was planned to
be located in individual pits separated by adequate rock pillars.
2. The initial design of the roof of the machine hall would be based upon a
trapezoidal section (similar to that used at Poatina). The purpose of this shape is
to limit the roof span in the horizontally bedded sequence by means of haunches.
In order to check the validity of this concept to the rock mass conditions at
Drakensberg and to permit the evolution of a rational roof support system, based
upon the use of tensioned reinforcement and pneumatically applied concrete
(PAC), it was proposed that a machine hall test enlargement should be excavated
during the exploratory phase of the project. This test excavation would be
9
1977 Bowcock et al. Drakensberg rock engineering
Table 1.
carefully excavated in stages, monitored and the results used to ascertain the optimum
roof shape and support system.
This chamber, which would be lined in the same manner as the lower portion of
the penstocks would be fully instrumented and tested to the full hydraulic head of
the Scheme to check the interaction of the lining and the surrounding rock mass
with respect to deformation and leakage.
3. Exploratory Stage
3.1 Introduction
The purpose and scope of the various elements of the exploratory programme were
established initially in terms of the design objectives. Adequate flexibility was built into
each element to allow progressive refinement during the exploratory phase.
1. Geology
2. Groundwater
10
1977 Bowcock et al. Drakensberg rock engineering
These studies together with the machine hall test enlargement and the penstock test
chamber are described in the following section of the paper.
The geological and groundwater conditions have been summarised earliest in this paper.
The broad scope of the investigations are described in the following section for
completeness.
The investigation and testing programmes were carried out to satisfy the following two
main requirements:
For the first requirement, extensive use has been made of simple index tests on core to
supplement geological data. For the second requirement more elaborate tests have been
carried out at a representative scale and at locations relevant to the major works.
Figure 4 shows the locations of boreholes which were drilled primarily during the
exploratory contract to investigate both the general geological conditions over the entire
alignment and the detailed conditions in the vicinity of the major excavations. The rocks
were classified according to argillaceous content as illustrated on Figure 5.
Most of the boreholes were drilled with 54 mm diameter double tube coring equipment.
The core was generally wrapped in aluminium foil and waxed immediately upon
extrusion from the barrel in order to minimise deterioration of due to weathering prior to
testing. Permeability testing was carried out in representative boreholes.
Detailed geological logging was carried out on all core. An example of a typical
geological log is given in Figure 6. An expanded scale of logging was used in the
vicinity of the major cavern roofs.
11
1977 Bowcock et al. Drakensberg rock engineering
12
1977 Bowcock et al. Drakensberg rock engineering
13
1977 Bowcock et al. Drakensberg rock engineering
High quality colour photography of all core prior to testing was carried out in order to
provide a permanent record.
Sample testing
Tests on core samples were carried out for two main purpose:
1. To provide representative ‘intact’ strength and modulus values for the various
rock types.
Small scale sample test results were not used as a basis for design of the major openings.
Early studies of various types of index tests indicated that the Point Load Index for core
loaded diametrically (parallel to bedding) gave the most representative mechanical index
for roof stability conditions.
This test was therefore carried out as a general index test for the entire works and also
incorporated in to a Roof Stability Index for tunnel (limited span) sections. Correlation
with lithology and actual roof conditions in the tunnels allowed three classes of
diametrical point load strength values to be defined (Figure 5).
Uniaxial compression testing of cores with modulus measurements using the mechanical
callipers was carried out on a large number of representative specimens. Results form
such tests were correlated with lithology, inclination of bedding to the core axis and other
parameters. Expected lower values of strength for increase in argillaceous content and at
critical inclinations of the bedding to the core axis were determined. The sample
preparation and testing techniques used were relatively simple and the results should be
considered as ‘index’ values rather than absolute parameters.
14
1977 Bowcock et al. Drakensberg rock engineering
A series of carefully controlled uniaxial compression tests on selected core samples from
the various lithological groups was also carried out to determine laboratory values of
strength, modulus and Poisson’s ratio. Modulus and Poisson’s ratio measurements were
made using strain gauge techniques.
Shear testing of mudstone samples and specific bedding planes and joints was also
carried out.
The objective of the in-situ testing programme was to provide definitive design data for
the major underground openings. The following tests were carried out:
Measurements of in-situ stresses are necessary in order to determine likely stresses and
displacements induced in the rock as a result of excavation. All such measurements were
therefore concentrated in the vicinity of the power station. The objective of the tests was
to provide average stress values in the vicinity of the main halls and in particular ratios of
principal stresses.
It was recognised that stress measurements in the rock mass at Drakensberg would be
difficult owing to the weak nature of the rock and the relatively limited depth below
surface of the excavations. The CSIR triaxial strain cell overcoring method was
considered to be the most suitable. The disturbed nature of the excavation sufaces did not
favour the use of flat jacks (stress relieving slots) and bored raises were not available for
larger scale over-coring methods.
Following an initial test to check equipment operation, a two stage testing programme
was drawn up and carried out by the CSIR. The scope of the second stage was based on
the first stage results.
Only tow measurements out of a possible total of ten yielded correlatable results from the
first stage testing. The other tests were discounted due to flooding, lack of gauge
adhesion or breakage of the overcored section. Preliminary results indicated the minor
principal stress to be vertical and slightly greater than the overburden stress. The ratio of
horizontal to vertical stresses (horizontal stresses about equal) was approximately 2.5:1.
15
1977 Bowcock et al. Drakensberg rock engineering
The second stage of tests has been carried out but results are not yet available.
Rock mass moduli in the vicinity of the power station were determined by Plate Bearing
Tests at representative locations together with Borehole Modulus tests (Goodman Jack)
in a number of boreholes in the roof and walls at the proposed machine hall location.
Plate Bearing Tests were carried out in exploratory headings at locations shown on
Figure 7. The locations corresponded to the roof strata encountered in the machine hall
test enlargement and the proposed machine hall enlargement was excavated prior to a
final decision on the machine hall elevation). The test equipment is shown typically on
Figure 8. A loaded area of 1.00 m2 with a corresponding contact stress of up to 4.5 MPa
was used. The maximum stress was determined following consideration of the stress
changes induced during excavation.
Tests were carried out parallel and normal to the bedding. Rock mass displacements
were measured relative to the loading plate on the loading axis. Three point
extensometers were used at depths up to 6 m. Several loading cycles were carried out
(generally 5) and a short term creep test was carried out at the maximum loading.
A typical test result is shown on Figure 9. The influence of rock relaxation at limited
depths is clearly indicated. Modulus values are corrected to allow for the confining effect
of the heading using results from a three dimensional boundary integral equation method
study (5).
Bore hole modulus tests using a Goodman Jack were carried out in vertical boreholes into
the proposed machine hall roof strata. The boreholes were spaced along the length of
proposed machine hall as illustrated in Figure 7. Tests were carried out on representative
strata identified during detail logging. Other tests were also carried out in the vicinity of
the larger scal Plate Bearing Tests to compare the results obtained from each type of test.
In addition, borehole jacking tests were carried out in horizontal holes in both a
horizontal and vertical sense on selected strata to determine modulus anisotropy.
Plate bearing tests were carried out in a special test adit alongside the penstock test
chamber to determine the rock mass modulus at various points around the chamber. The
tests were carried out on the structure representative of those exposed in the chamber
excavation. All tests were radial to the surface and indicated in Figure 7.
Tests were carried out using a plate area of 0.5 m2 and contact stresses up to 9.0 MPa.
Such stresses are representative of the induced stress (pressure) changes in the penstocks
during operation.
16
1977 Bowcock et al. Drakensberg rock engineering
17
1977 Bowcock et al. Drakensberg rock engineering
18
1977 Bowcock et al. Drakensberg rock engineering
The test normal to the invert of the penstock test chamber was repeated following
grouting of the rock mass. The grouting process was designed to stimulate as closely as
possible the actual grouting technique around the lining of the test chamber
Specific test were carried out on the type of reinforcement proposed that the main halls.
It is intended that resin anchored bolts with adequate or continuous (threadbar) nut
adjustment will be used. Secondary bonding of the free length after completion of final
tensioning will be affected probably using concrete grout.
It is intended that the crane beams in the machine and valve halls will be supported by
stressed rock anchors, each with a working load of 90 tons. Tests will be carried out to
determine the anchorage characteristics of the rock strata in which the anchors will
finally be located. A cement grouting anchorage will be used. During the tests each
anchor will be fully loaded and unloaded several times and in addition short term creep
tests on anchorages of varying length will be carried out.
As currently proposed all excavations will be permanently lined with mesh reinforced
PAC other than where placed concrete lining is required for hydraulic or internal
structure of reasons. The PAC lining will be applied generally in two stages with mesh
reinforcement being placed after the initial PAC application. Apparently PAC as used in
the exploratory contract and preliminary contract works has been evaluated.
PAC spalling has been recorded and the results related to the particular rock
strata/bedding weakness. Only limited trials using mesh reinforcement have been carried
out. The following conclusions involving the use of PAC for the permanent lining of
rock strata such as encountered at Drakensberg are as follows:
4. Adequate peeling back of mesh to the first PAC layer to ensure minimal clearance
is required.
Since the process of PAC application is highly dependent upon the method used, final
trials will be carried out after the main contract award.
19
1977 Bowcock et al. Drakensberg rock engineering
The purpose of the machine hall test enlargement (MHTE) can be summarised as
follows:
1. To confirm that the roof span required for the main halls is feasible.
In order to develop a realistic loading condition for the roof span, the effect of sidewall
excavation was simulated by excavating slots to a depth equal slots to a depth equal to
about half the final sidewall height. The principal stages of excavation are shown on
Figure 11.
The influence of excavation to the full cross-section on the stresses in the roof strata will
be determined by a staged stress analysis using both the results of monitoring from the
actual test excavation and the results from the in-situ stress measurements and rock mass
properties.
The elevation of the MHTE was chosen such that the haunches and roof were positioned
in the weakest possible strata (as determined from the drilling from surface) for the 15 m
range in possible level for the proposed machine hall. This level was only finally
selected in July 1976, based on the required setting for the pump-turbines. The axis of
the MHTE is parallel to the proposed machine hall.
20
1977 Bowcock et al. Drakensberg rock engineering
The length of the MHTE (approximately 1.5 times the span) was chosen to allow for a
central 10 m section which would be relatively unaffected by end constraints.
The excavation sequence for the test enlargement was slightly more complex than that for
the proposed machine hall (5 slices instead of 3) because of the need to install crown
instrumentation prior to significant rock deformation.
1. Rock bolts estimated on the basis of precedent and simple numerical analyses
2. Temporary hydraulic props along the centreline of the enlargement (5 x 100 ton
capacity).
The purpose of the temporary props was to provide a calibrated stiff support along the
centreline as well as a temporary support during excavation. Prior to increasing the span
at a given stage the props were set to a nominal load (10 ton) and the increase in load
with span monitored.
21
1977 Bowcock et al. Drakensberg rock engineering
The load carried by the props was then distributed to the primary reinforcement as an
installed ‘calibrated’ load and the props subsequently unloaded. It was thus possible to
observe potential support requirements under acceptable displacement conditions (as
monitored by the extensometers). Unfortunately, the excavation of Stage 2 (Figure 11)
caused considerable damage to the pillar supporting the props and the stiffness of the
pillar was significantly reduced. Following an evaluation of this condition, additional
load was placed in the primary reinforcement for safety reasons.
3. Piezometric monitoring
The instrumentation was primarily located on three sections; a central section and
sections spaced 5 m either side. Typical layouts are shown on Figure 11.
22
1977 Bowcock et al. Drakensberg rock engineering
A typical plot of displacement versus time/excavation stages is shown on Figure 12. both
closure measurements and precise levelling were an order of magnitude less accurate than
the extensometers.
Stresses monitored during the excavation stages were very sensitive to changes in
excavation geometry and could be usefully correlated with the displacement records
(Figure 12).
Piezometric monitoring in the roof strata indicated relatively high pressure (up to 15 m
head) relatively close to the excavation face. These measurements further indicated the
low transverse permeability of the siltstones. Consideration of likely loadings due to
groundwater pressures on roof strata will be made during the design stage.
Load monitoring in primary reinforcement has yielded few results to date (end Stage 3)
as deformations have been small since the reinforcement was installed (Figure 12).
Significant load increases (of the order of 40 tons) were observed in some support props
during Stage 3 excavation. These load increases occurred where the pillar was relatively
undamaged and were used in assessing Stage 3 primary reinforcement loads. At all
stages of the development a continual evaluation of displacement, stress and load changes
was carried out.
The penstock test chamber has been constructed to check the suitability of concrete as a
lining for the pressure tunnels. The chamber has been located in an area representative of
the weaker rock conditions expected along its alignment. Attention was given in the
choice of site to locating the chamber in strata having a considerable modulus variation
over the height of the chamber.
A principal objective of the test was to determine the relative behaviour of the concrete
lining, grouted rock and surrounding rock mass to demonstrate that an effective transfer
of stress into the rock will occur under acceptable deformations and leakage.
The chamber was concreted in three bays approximately 10 m long having a finished
internal diameter of 5.5 m and a nominal lining thickness of 0.6 m. the three bays are
separated by conventional waterstops. Each end of the chamber is terminated by a
concrete plug.
23
1977 Bowcock et al. Drakensberg rock engineering
2. Radial deformation of the lining, grouted rock and surrounding rock mass
monitored by means of multi-point borehole extensometers which are tied in with
the diametral closure measurement (1)
3. Strains in the lining measured by means of embedded and surface vibrating wire
gauges (radial and tangential strains monitored)
5. Water pressures behind the lining and in the surrounding rock mass monitored by
means of hydraulic piezometers.
Remote read-out of instrumentation under high fluid pressures (up to 7.5 MPa)
necessitated special developments particularly of remote sensing elements. Temperatures
are monitoring at various points in the test zone and invar rods/wires are used for
reference displacement monitoring. Stress cells are designed to allow for compensation
from within he chamber.
As previously discussed a series of plate bearing tests was carried out to determine radial
modulus conditions within the rock mass as well as the effect of grouting.
High pressure grouting behind the chamber lining will be monitored by means of the
installed instrumentation. Particular attention will be paid to uniformly of deformations
and stresses indicating that a complete grout ring has been established. Residual stresses
induced in the lining will be carefully monitored.
The chamber pressurization programme has not yet been finalised. It is intended
however to pressurize in stages and carry out tests at constant pressure as well as under
cyclic conditions.
24
1977 Bowcock et al. Drakensberg rock engineering
25
1977 Bowcock et al. Drakensberg rock engineering
The design process for the excavation and reinforcement requirements of the main
underground works was initially considered during the formulation of the investigation
and testing programme which was consequently arranged to provide relevant parameters
for the design requirements.
As already outlined, considerable attention has been paid to testing rock conditions at a
representative scale. Both the machine hall test enlargement and penstock test chamber
are full scale tests. The information obtained from the investigation and testing stages
will e used primarily to extrapolate observed underground conditions to the overall
station layout using recognised stress analyses techniques and a structural evaluation of
the rock mass. Optimisation of the detailed underground layout and rock reinforcement
with respect to localised geological conditions will then be carried out.
9. Shape and precise elevation of major roof spans taking into account predominant
bedding features, haunch geometry and geology.
26
1977 Bowcock et al. Drakensberg rock engineering
14. Reinforcement of minor galleries and tunnels in the vicinity of the main works
17. Drainage of the rock mass in the vicinity of the penstocks and upstream wall of
the valve hall
1. Two and three dimensional stress and deformation analyses finite element and
boundary integral equations methods)
3. Analysis of structurally controlled failures taking into account rock stresses and
reinforcement loadings (production of detailed reinforcement requirements and
likely rock deformations).
A final design will be evolved form the results of the full scale tests, an evaluation of the
rock mass characteristics and an analysis of the final station layout in terms of the
measured parameters.
The inter-relationship of investigation, testing an analysis and design for the underground
works at Drakensberg is summarised on Table II.
27
1977 Bowcock et al. Drakensberg rock engineering
Conclusions
The particular role of full scale testing has been highlighted. The relevance of testing at
other scales, both in-situ and on a sample scale, has also been discussed in relation to the
final design process.
The current status of the investigation/testing works precludes the reporting of detail
results at this stage. A full evaluation of all data is expected by early in 1977.
Acknowledgements
The authors wish to thank the Electricity Supply Commission for permission to publish
this paper and Gibb Hawkins and Partners and Golder Associates for the material which
has been used in its preparation. They also wish to acknowledge the extensive
contribution of their many colleagues whose work is reported here.
28
1977 Bowcock et al. Drakensberg rock engineering
References
1. Secretary for Water Affairs (1974-1975). Report on the Proposed Second Phase
of the Tugela-Vaal Government Water Project with the Drakensberg Pumped
Storage Scheme Development.
3. Barton, N., Lien, R. and J. Lunde (1974). Analysis of rock mass quality and
support practice in tunnelling and guide for estimating support requirements.
Norwegian Geotechnical Institute Internal Report 54206.
4. Endersbee, L.A. and Hofto, E.O. Civil engineering design and studies in rock
mechanics for Postina underground power, Tasmania. J. Australian Inst. Engrs.,
35, September 1963, 187-206.
5. Hocking, G. Brown, E.T., Watson, J.O. (1976). Three dimensional elastic stress
analysis of underground openings by the boundary integral equation method. 3rd
Symposium on Engineering Applications of Solid Mechanics. Toronto, June
1976.
29