Project Name: LPS01 - 2B+G+6 RESIDENTIAL BUILDINGS

Document Title Inspection and Test Plan for Point Wiring Date 10-OCT-22

Document No LPS-01-HTI-ITP-ELE-005 Rev. No. 0

INSPECTION AND TEST PLAN


FOR
POINT WIRING

Project : LPS-01 - 2B+G+6 RESIDENTIAL BUILDINGS

Employer : ALI HAMAD K ALTHANI

Project Design & Construction


Supervision Service Consultant: Qatar Design Consortium
Neo-Spectrum
Main Contractor : HBK Contracting Company W.L.L.

Revision History

Issued for
LPS-01-HTI-ITP-EL-005 0 Review and
Approval
Rev. Purpose of Rev. by Appr. By Project
Doc. no. no. Date Submission Prep. By QA/QC Manager Manager

23 |27
Project Name: LPS01 - 2B+G+6 RESIDENTIAL BUILDINGS

Document Title Inspection and Test Plan for Point Wiring Date
10-OCT-22
Document No LPS-01-HTI-ITP-EL-005 Rev. No. 0

Legend: H=Hold Point, WIR to be issued and work shall not proceed without acceptance from the responsible party; W=Witness Point- WIR to be issued and work may proceed if the
responsible party does not attend; S=random surveillance, no signature or IRW required; R=“Record/ Document Review”(submitted separately as necessary);TRR=Test Report Review
Checks Intervention Points Verification
Documents
Control Documents Acceptance Criteria/

Contract
Contract

3rd Party
# Works Checking Vol. Clause Tolerances (if applicable) Responsible Required

QDC/
Sub-
Activity to be Job Function Frequency
Performed
1.0 Preliminary Activities of Documents & Approval
1.1 Project QCS-2014 & - Permit should be signed from Site Engineer / Initial H H W N/A Signed/
Permits Project
Engineer/ all Safety Departments Safety Engineer Approved
Safety Specification Permits
Engineer
1.2 Project QCS-2014 & QCS, - All materials shall be Site Engineer Prior Material H H W N/A Approved later
Approval of Project Section 21 Purchase and
Engineer/ QC submitted for approval in Material
Material Specification Part 07 Delivery.
Engineer accordance with the Submittals
Submittal (Cable
specifications and tender
wiring)
drawings.
- Applicable sub-sections of
Section 21 Part 06 of QCS
2010 shall be applied to all
Power Wiring and Cables
1.3 Project QCS-2014 & - As per Document latest Initial H H W N/A Shop Drawings
Shop Drawings Project
Engineer revision Approval status from Site Engineer Submittal
Approval Specification Engineer Documents

1.4 Project QCS-2014 & - As per Document latest Project Initial H H W N/A Approved
Method Project
Engineer/ QC revision Approval status from Engineer/ QC Latest Method

24 | 2 7
Engineer Specification Engineer Engineer Statement
Statement
Submittal
2.0 Pre-Installation Activities
2.1 Delivery Notes The QC will Section Visual Inspection/ Delivery Store-in- Upon Material H H W N/A Material
Material
& Batch check the 26 storage and handling as per Charge / Delivery Inspection
Delivery
Certificates material Manufacturer’s Instructions QC Engineer Request (MIR)
Inspection
according to
project
specification
3.0 Installation and Inspection Activities
3.1 As per QCS-2014 & QCS 2010 Visual Inspection / Approved Project After Marking H H W N/A WIR shall be
Marking and Project Section 21
Approved QA/QC Checklist Engineer /QA- raised.
Installation of Specification Part 6,
method QC Subcontractor
Cable wiring Approved Shop
statement and Drawing Inspection
Horizontal/Verti
approved shop
cal
drawing
Inspection
Checklist
3.2 Project QCS-2014 & - Visual Inspection / Approved Project After Installation H H W N/A Approved
Point wiring specification / Project QA/QC Checklist Engineer /QA- Method
cable wiring Approved shop Specification QC statement &
drawing / QCS QCS 2010
Installation Section 21 Part
Inspection
2014
6, Approved Request
requirement /
Shop Drawing
Manufacturer
installation
recommendation
3.3 Project As per Visual Inspection / Approved Project At times clogged / H H W N/A Approved
Repair works for specification / Approved damaged conduit
by QA/QC requirement Engineer /QA- Method
clogged / Approved shop method run is fount.
QC statement &
damaged Cable drawing / QCS statement
Inspection
wire (if any) 2014 and approved
Request
requirement / shop drawing
Manufacturer Inspection
installation Report
recommendation

25 | 2 7
Appendix 2
10.3. Checklist for POINT WIRING

26 | 2 7
Project Name: LPS01 - 2B+G+6 RESIDENTIAL BUILDINGS

Document Title Checklist for Point Wiring Date 10-OCT-22

Document No LPS-01-HTI-ITP-EL-005 Rev. No. 0


Location/Area MST Ref. ITP Ref. WIR Ref. Date

LPS-01-HTI-MST-EL-005 LPS-01-HTI-ITP-EL-005
Confirm Y/N Inspected By
S. No Activities/Items to be inspected (Tick Mark) (Tick Mark) Remarks
Yes No Site Engineer&/ QC Inspector Others
Sub Cont.
The Make and quality of the material used for
1. wiring are as per approved submittal &
specification.
Size of the wires used is as per approved
2. drawing.
Color coding for the wiring works is as per
3.
approved drawing.

Any visible damage to Insulation of the wiring


4.
works prevalent.
Proper identification/ferrules are provided in
5.
the circuit wires
Wires/ cables are properly protected in
6. switch/ power sockets and at
Distribution Boards at the end.
Wires are properly connected with switch &
7.
sockets with proper lugs.
Insulation resistance test carried out as per
8. the
specifications & test report attached.
Electrical continuity test carried out as per the
9.
specifications& test report attached.
Check whether the cable is fixed properly to
10
the tray
11 Check for any damages or defects
Check whether the incoming and outgoing
12 cables are
labelled as required
GI/PVC conduits provided for cables are
13
passing through the walls or floors.
Comments and Discrepancies (If any)
1

HexaTech Site Engineer HBK Inspector CSC (QDC) NEO/Others


Name Name Name Name

Position Position Position Position

Signature Signature Signature Signature

27 | 2 7