What Is Time Schedule
What Is Time Schedule
What Is Time Schedule
What is the time Schedule? and What are the types of Schedules?
1- Tender schedule:
This is a schedule prepared by the contractor to the client in the very beginning stages of
the project, even before the project is awarded to the contractor.
It is a summary schedule clarifying how the contractor intends to execute the project
(sequence and duration). This schedule does not contain a lot of details and is issued as a
part of the tender documents for future reference.
Once actual values were applied to a baseline schedule it became an updated schedule with
forecast completion dates for each activity that could be earlier than the baseline schedule
which means (Ahead of schedule) or after the baseline schedule dates which means (Behind
the Schedule).
6- Recovery Schedule:
A recovery Schedule is a schedule prepared by the contractor to recover delays in the updated
schedule. From its name, it should recover all the project delays and maintain the contractual
completion date of the project. The contractor should not develop a recovery schedule if the
delays are caused by other parties such as the client, other contractors/subcontractors, and
are not under the contractor's scope of work. Alternatively, the contractor should develop a
revised schedule as explained below.
Sometimes, the client asks the contractor to accelerate the project schedule for a certain duration.
In that case, the contractor might accept to do schedule crashing / fast tracking to fulfill the client's
requirements by working in parallel for some activities and/or working 2 shifts instead of 1 shift. In
that case, the contractor is entitled to acceleration costs.
---------------
Useful links:
---------------
Keep in Touch:
WhatsApp: +201277767728
Email: Info@PlanningEngineer.Net
Twitter: https://twitter.com/PlanningEEst
Instagram: https://www.instagram.com/planningengineerest/
TikTok: https://www.tiktok.com/@planningengineerest
---------------