QER Analysis - A Review of The CO2 Pipeline Infrastructure in The U.S - 0
QER Analysis - A Review of The CO2 Pipeline Infrastructure in The U.S - 0
QER Analysis - A Review of The CO2 Pipeline Infrastructure in The U.S - 0
Technology Laboratory
OFFICE OF FOSSIL ENERGY
Disclaimer
This report was prepared as an account of work sponsored by an agency of the United States
Government. Neither the United States Government nor any agency thereof, nor any of their
employees, makes any warranty, express or implied, or assumes any legal liability or
responsibility for the accuracy, completeness, or usefulness of any information, apparatus,
product, or process disclosed, or represents that its use would not infringe privately owned rights.
Reference therein to any specific commercial product, process, or service by trade name,
trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement,
recommendation, or favoring by the United States Government or any agency thereof. The views
and opinions of authors expressed therein do not necessarily state or reflect those of the United
States Government or any agency thereof.
-
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Author List:
Matthew Wallace
Advanced Resources International
Robert Wallace
Booz Allen Hamilton
This report was prepared by Energy Sector Planning and Analysis (ESPA) for the United States
Department of Energy (DOE) Office of Energy Policy and Systems Analysis (EPSA) and the
National Energy Technology Laboratory (NETL). This work was completed under DOE NETL
Contract Number DE-FE0004001. This work was performed under ESPA Task 200.01.03.
All images in this report are property of NETL unless otherwise noted.
The authors wish to acknowledge the excellent guidance, contributions, and cooperation of the
NETL and EPSA staff, particularly:
Judi Greenwald, EPSA Deputy Director for Climate Environment and Efficiency
Table of Contents
1 Executive Summary ......................................................................................................................1
2 Introduction ...................................................................................................................................2
3 Current CO2 Pipeline Infrastructure..............................................................................................3
3.1 Overview ..............................................................................................................................3
3.2 Permian Basin ......................................................................................................................4
3.3 Gulf Coast ............................................................................................................................7
3.4 Rocky Mountains .................................................................................................................8
3.5 Mid-Continent ....................................................................................................................10
3.6 Other U.S. CO2 Pipeline Networks ....................................................................................12
4 Potential CO2 Pipeline Network Expansion ...............................................................................12
4.1 Projections Based on Industry Announcements ................................................................12
4.1.1 Wyoming Pipeline Development and Greencore Pipeline Extension ......................12
4.1.2 Green Pipeline Laterals .............................................................................................13
4.1.3 Potential Additional CO2 Supplies from Natural Sources ........................................15
4.1.4 Additional CO2 from Industrial Sources ...................................................................16
4.2 Projections using the EIA NEMS analysis ........................................................................17
4.2.1 CO2 Price and CO2 Emissions Results......................................................................18
4.2.2 CO2 Pipeline Expansion Results ...............................................................................19
4.2.3 Rates of Projected Pipeline Construction .................................................................30
5 Permitting, Regulations, and Policies .........................................................................................31
5.1 Overview ............................................................................................................................31
5.2 Federal Regulation .............................................................................................................31
5.2.1 General Oversight .....................................................................................................31
5.2.2 Safety Oversight........................................................................................................32
5.3 Pipeline Siting and Eminent Domain .................................................................................32
5.3.1 Texas/New Mexico ...................................................................................................32
5.3.2 Mississippi ................................................................................................................32
5.3.3 Other States ...............................................................................................................33
5.4 Other State Policies ............................................................................................................33
6 Conclusions .................................................................................................................................33
7 Topics for Further Study .............................................................................................................34
7.1 Development of Oversight Authority ................................................................................34
8 Bibliography ...............................................................................................................................35
Appendix ........................................................................................................................................37
i
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibits
Exhibit 1 Geographic areas with large-scale CO2 pipeline systems operating currently in the U.S.
................................................................................................................................................. 3
Exhibit 2 Current CO2-EOR operations and infrastructure ............................................................ 4
Exhibit 3 Permian Basin CO2 pipeline infrastructure ..................................................................... 5
Exhibit 4 Permian Basin CO2 transportation pipelines ................................................................... 6
Exhibit 5 Gulf Coast CO2 pipeline infrastructure ........................................................................... 7
Exhibit 6 Gulf Coast CO2 transportation pipelines ......................................................................... 8
Exhibit 7 Rocky Mountain CO2 pipeline infrastructure ................................................................. 9
Exhibit 8 Rocky Mountain CO2 transportation pipelines ............................................................. 10
Exhibit 9 Mid-Continent CO2 pipeline infrastructure ................................................................... 11
Exhibit 10 Mid-Continent CO2 transportation pipelines .............................................................. 11
Exhibit 11 Other CO2 transportation pipelines in the U.S. ........................................................... 12
Exhibit 12 Denbury’s Wyoming CO2 pipeline developments ...................................................... 13
Exhibit 13 Planned Webster CO2 lateral pipeline ......................................................................... 14
Exhibit 14 Planned Conroe CO2 lateral pipeline .......................................................................... 14
Exhibit 15 Planned Lobos CO2 pipeline in New Mexico ............................................................. 15
Exhibit 16 Planned CO2 transportation pipelines ......................................................................... 16
Exhibit 17 CO2 Price under the Cap40 and CP 25 scenarios ........................................................ 18
Exhibit 18 CO2 Emission reductions for all sectors under the Cap40 and CP 25 scenarios......... 19
Exhibit 19 CO2 pipeline schematic ............................................................................................... 19
Exhibit 20 CO2 transportation by market segment (2040)............................................................ 20
Exhibit 21 CO2 transportation by miles as a function of pipeline diameter (2040) ...................... 21
Exhibit 22 Inter- and Intrastate pipeline segments (2040) ............................................................ 23
Exhibit 23 Transportation Costs for the Cap40 case .................................................................... 24
Exhibit 24 Transportation costs for the CP25 case ....................................................................... 24
Exhibit 25 Transportation cost as a function of CO2 throughput.................................................. 25
Exhibit 26 Oil produced by source for all three cases* ................................................................ 26
Exhibit 27 Oil Production by EOR in the Cap40 case .................................................................. 27
Exhibit 28 Oil Production by EOR in the CP25 case ................................................................... 28
Exhibit 29 Power plant pipeline build-out by 2040 for the Cap40 case ....................................... 29
Exhibit 30 Power plant pipeline build-out by 2040 for the CP25 case ......................................... 29
Exhibit 31 Power plant pipeline build-out by 2030 in the $25/tonne CO2, low carbon scenario . 30
Exhibit 32 Comprehensive List of U.S. CO2 Pipelines ................................................................ 37
Exhibit 33 State-Level Inter- and Intrastate Pipeline Segments for the Cap40 Case ................... 39
Exhibit 34 State-Level Inter- and Intrastate Pipeline Segments for CP25 Case ........................... 40
Exhibit 35 Cumulative CO2 Pipelines Construction ..................................................................... 41
Exhibit 36 Total Mass of anthropogenic CO2 Sequestered .......................................................... 41
Exhibit 37 Sequestered Anthropogenic CO2 Captured at Industrial vs. Power Sector Sources ... 42
Exhibit 38 Electric Capacity with Carbon Sequestration ............................................................. 42
Exhibit 39 U.S. Oil Production (MMBbls/day) Associated with CO2-EOR, in 2015, 2030, and
2040 (table) ........................................................................................................................... 42
Exhibit 40 U.S. oil production (MMBbls/day) associated with CO2-EOR, in 2015, 2030, and
2040 (graph) .......................................................................................................................... 43
ii
A Review of the CO 2 Pipeline Infrastructure in the U.S.
iii
A Review of the CO 2 Pipeline Infrastructure in the U.S.
iv
A Review of the CO 2 Pipeline Infrastructure in the U.S.
1 Executive Summary
Spanning across more than a dozen U.S. states and into Saskatchewan, Canada, a safe and
regionally extensive network of carbon dioxide (CO2) pipelines has been constructed over the
past four decades. Consisting of 50 individual CO2 pipelines and with a combined length over
4,500 miles, these CO2 transportation pipelines represent an essential building block for linking
the capture of CO2 from electric power plants and other industrial sources with its productive use
in oilfields and its safe storage in saline formations. Expanding this system could help to enable
fossil-fired power generation in a carbon constrained environment and increase energy security
by enhancing domestic oil production.
The vast majority of the CO2 pipeline system is dedicated to enhanced oil recovery (CO2-EOR),
connecting natural and industrial sources of CO2 with EOR projects in oil fields. Roughly 80
percent of CO2 traveling through U.S. pipelines is from natural (geologic) sources; however, if
currently planned industrial CO2 capture facilities and new pipelines are built, by 2020 the
portion of CO2 from industrial-sources could be nearly equal to that from natural sources. In
terms of future potential, it is estimated that up to 4 million barrels per day of oil could
potentially be produced in the U.S. with CO2-EOR and that 85% of this would be reliant on
industrial CO2; contributing to significantly fewer oil imports and annual emissions reductions of
400 MMTCO2, by 2030.
Just over 4 percent of total U.S. crude oil production is currently produced through EOR, though
this is projected to increase to 7 percent by 2030, and a national carbon policy could significantly
change the outlook, creating incentives for electric power plants and other industrial facilities to
reduce CO2 emissions through carbon capture technologies and improving the economics for oil
production through EOR. In a low-carbon case, construction through 2030 would more than
triple the size of current U.S. CO2 pipeline infrastructure, through an average annual build-rate of
nearly 1,000 miles per year.
The regulation of CO2 pipelines is currently a joint responsibility of federal and state
governments. The U.S. Department of Transportation’s Pipeline and Hazardous Materials Safety
Administration, is responsible for overseeing the safe construction and operation of CO2
pipelines, which includes technical design specifications and integrity management
requirements. The development of a national CO2 pipeline network capable of meeting U.S.
GHG emission goals may require a more concerted federal policy, involving closer cooperation
among federal, state, and local governments. Federal policy initiatives should build on state
experiences, including lessons learned from the effectives of different regulatory structures,
incentives, and processes that foster interagency coordination and regular stakeholder
engagement.
1
A Review of the CO 2 Pipeline Infrastructure in the U.S.
2 Introduction
A safe, reliable, regionally extensive network of carbon dioxide (CO2) transportation pipelines is
already in place across more than a dozen United States (U.S.) states and into Saskatchewan,
Canada. This system could increasingly become an essential building block for linking the
capture of CO2 from industrial power plants with its productive use in oilfields (with CO2
enhanced oil recovery [CO2-EOR]) and its safe storage in saline formations. The current CO2
pipeline system consists of 50 individual CO2 pipelines with a combined length of 4,500 miles.
The bulk of the existing large-volume CO2 pipelines connect natural sources of CO2 (e.g., Bravo
Dome, New Mexico) with long-running CO2-EOR projects in large oil fields (e.g., Wasson, West
Texas). However, smaller volume pipelines also exist that connect point sources of industrial
CO2 (e.g., Coffeyville Chemical Plant, Kansas) with newer CO2-EOR projects in oil fields (e.g.,
North Burbank, Oklahoma).
Today’s CO2 pipeline system had its beginnings in the 1970s, built for delivering CO2 for CO2-
EOR to oil fields in the Permian Basin of West Texas and eastern New Mexico. With the recent
completion of two long-distance CO2 pipelines – the Green Pipeline in Louisiana and Texas
(2010), and the Greencore Pipeline in Wyoming and Montana (2012) – a much more
geographically diverse CO2 pipeline system is in place. A variety of shorter and smaller volume
laterals are being constructed to link these two large-scale CO2 pipelines to surrounding oil fields
that are amenable to CO2-EOR.
The vast majority of the CO2 pipeline system is dedicated to CO2-EOR, with a small fraction
used for other industrial uses, such as delivering CO2 to the beverage industry. Of the 3.53
billion cubic feet (Bcf) per day (68 million metric tons per year [MMT]) of CO2 transported, 2.78
Bcf per day (54 MMT per year) is from natural sources, and the remaining 0.74 Bcf per day (14
MMT per year) is from industrial sources, including gas processing plants. With new industrial
CO2 capture facilities coming on line (e.g., Air Products PCS Nitrogen plant in southern
Louisiana, Southern Company’s integrated gasification combined cycle (IGCC) plant in Kemper
County, Mississippi, etc.) – including over 600 miles of new pipeline – the volume of industrial
CO2 capture and transportation is expected to increase by over 2.5 times the current supply by
the year 2020.1
The regulation of CO2 pipelines is currently a joint responsibility of federal and state
governments. The federal government regulates only CO2 safety standards. State governments
are largely responsible for the oversight of CO2 transportation pipeline development and
operation. Some states, such as Wyoming and its Pipeline Authority, have begun to plan for and
establish corridors for future CO2 pipelines. However, the development of a national CO2
pipeline network capable of meeting proposed CO2 emission goals may require a more organized
approach and much closer cooperation among federal, state, and local governments than is
currently in place.
1
This is based on a comparison between 0.74 Bcf per day currently and 1.36 Bcf per day planned to begin construction by 2020 (Exhibit 16).
2
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibit 1 Geographic areas with large-scale CO2 pipeline systems operating currently in the U.S.
2
This is based on a comparison between the 2.78 Bcf per day currently drawn from natural CO2 reservoirs and the total of 2.1 Bcf per day
expected from industrial sources by 2020.
3
A Review of the CO 2 Pipeline Infrastructure in the U.S.
4
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Three other important CO2 pipelines round out the large-scale pipeline system of the Permian
Basin:
The Canyon Reef Carrier CO2 pipeline, the initial large-scale CO2 pipeline, links the CO2
captured from the gas processing plants in the Val Verde Basin (West Texas) with the
pioneering Scurry Area Canyon Reef Operators Committee (SACROC) CO2-EOR
project, 170 miles to the northeast.
The Centerline and Central Basin CO2 pipelines deliver natural CO2 from the Denver
City CO2 hub to the oil fields in West Texas and New Mexico.
Exhibit 4 lists the CO2 transportation pipelines installed in the Permian Basin region.
5
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Estimated
Length Diameter Flow
Scale Pipeline Operator Location
(mi) (in) Capacity
(MMcfd)
6
A Review of the CO 2 Pipeline Infrastructure in the U.S.
(1) Potential, proved, and produced-to-date tertiary reserves estimated as of 12/31/13 based on a
range of recovery factors. Proved reserves based on year-end 12/31/13 U.S. Securities and
Exchange Commission reporting.
Source: Denbury Onshore LLC (1)
7
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Estimated
Length Diameter Flow
Scale Pipeline Operator Location
(mi) (in) Capacity
(MMcfd)
Denbury
Green Line LA, TX 314 24 930
Resources
Large-Scale Denbury
Delta MS, LA 108 24 590
Trunk-lines Resources
Northeast Jackson Denbury
MS, LA 183 20 360
Dome (NEJD) Resources
Denbury
Free State MS 85 20 360
Distribution Resources
Line Denbury
Sonat MS 50 18 170
Resources
8
A Review of the CO 2 Pipeline Infrastructure in the U.S.
9
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Shute
Creek/Wyoming ExxonMobil WY 142 30-20 1,220-220
Large-Scale CO2
Trunk-lines
Denbury
Greencore WY, MT 230 22 720
Resources
Powder River
Anadarko WY 125 16 220
Basin CO2
Raven Ridge Chevron WY, CO 160 16 220
Smaller Kinder
Scale McElmo Creek CO, UT 40 8 80
Morgan
Distribution
Systems Monell Anadarko WY 33 8 80
Lost
Merit WY 30 16 43
Soldier/Wertz
Beaver Creek Devon WY 53 8 30
3.5 Mid-Continent
The Mid-Continent CO2 pipeline system (Exhibit 9) is mainly a set of fragmented source-to-field
pipelines supplying captured CO2 from industrial sources to individual CO2-EOR operations.
Chaparral owns and operates the majority of these smaller pipelines while Anadarko controls the
Enid-Purdy pipeline in Central Oklahoma. A small amount of natural CO2 from Bravo Dome is
delivered to the Postle CO2-EOR operation via the TransPetco Pipeline. These CO2 pipelines are
listed in Exhibit 10.
10
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Estimated
Length Diameter Flow
Scale Pipeline Operator Location
(mi) (in) Capacity
(MMcfd)
Chaparral
Coffeyville- Burbank KS, OK 68 8 80
Energy
Enid-Purdy
Anadarko OK 117 8 80
Small Scale (Central Oklahoma)
Distribution TransPetco TransPetco TX, OK 110 8 80
Systems Chaparral
TexOk OK 95 6 70
Energy
Chaparral
Borger TX, OK 86 4 50
Energy
11
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Estimated
Length Diameter Flow
Region Pipeline Operator Location
(mi) (in) Capacity
(MMcfd)
Dakota Gasification
Other Dakota Gasification ND, SK 204 14 130
(Souris Valley)
Other White Frost Core Energy, LLC MI 11 6 70
12
A Review of the CO 2 Pipeline Infrastructure in the U.S.
13
A Review of the CO 2 Pipeline Infrastructure in the U.S.
14
A Review of the CO 2 Pipeline Infrastructure in the U.S.
3
http://www.kindermorgan.com/business/CO2/lobospipeline/default.cfm
4
http://www.blm.gov/nm/st/en/prog/more/lands_realty/lobos_co2_pipeline.html
15
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Illinois Industrial
CCS Decatur, Il 2015 1 50
Carbon Capture
Thompson,
Petra Nova CO2-EOR 2016 82 70
TX
Point
Sargas Texas CO2-EOR 2017 50 40
Comfort, TX
Lake Charles Calcasieu
CO2-EOR 2018 12 200
Co-Generation Parish, LA
Medicine Bow Medicine
CO2-EOR 2018 TBD 130
CTL Bow, WY
South Heart,
Quintana Syngas CO2-EOR 2018 TBD 108
SD
5
http://www.globalccsinstitute.com/projects/large-scale-ccs-projects#overview
16
A Review of the CO 2 Pipeline Infrastructure in the U.S.
17
A Review of the CO 2 Pipeline Infrastructure in the U.S.
indefinitely and an economy-wide CO2 emissions cap was imposed, reducing emissions by 40
percent from 2005 by 2030 and a total of 80 percent from 2005 levels by 2050. Finally, nuclear
at risk retirements that were stated in the Reference case were removed from this case. (7)
AEO2014 Early Release Case with a carbon price of $25/tonne (CP25)
The CP25 case assumes a $25/tonne price on CO2 emissions. The price on is economy wide,
begins in 2015, and increases by 5 percent annually through 2040. This pathway matches the
EIA’s AEO2014 $25 Carbon Price side case. (8) This illustrative national carbon policy is not
intended to represent any actual or proposed policy, but instead is used as a means to understand
the extent to which a climate policy would drive growth in CO2-EOR demand, and consequently
in CO2 pipeline infrastructure. Currently, just over 4 percent of total U.S. crude oil production is
currently produced through EOR, though this is projected to increase to 7 percent by 2030. (5)
4.2.1 CO2 Price and CO2 Emissions Results
The price of CO2 in the CP25 case, as stated above, begins at $25/tonne in 2015 and increases to
$52/tonne in 2030, and nearly $85/tonne by 2040, as seen in Exhibit 17. The Cap40 CO2 price
begins at $0/tonne and does not increase until the 2021 time frame. The price then increases at an
exponential rate, reaching $38/tonne by 2030 and nearly $200/tonne by 2036, where it remains
for the rest of the model time horizon.
Carbon Price
250
200
Carbon Price $/tonne
150
Cap40
100 CP25
50
0
2015 2020 2025 2030 2035 2040
As the price per tonne of CO2 increases, the amounts of CO2 emissions decrease in each case.
Exhibit 18 shows that the Cap40 reduces CO2 emissions at a greater rate than the CP25 case, and
by 2040, reduces CO2 emissions by nearly 1 billion more tonnes cumulatively than the CP25
case and almost 3 billion more tonnes than the Reference case.
18
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibit 18 CO2 Emission reductions for all sectors under the Cap40 and CP 25 scenarios
6,000
Million Metric Tonnes CO2
5,000
4,000 Cap40
3,000 CP25
BAU
2,000
1,000
-
2010 2015 2020 2025 2030 2035 2040
In the CP25 case, by 2030, EP-NEMS projects over 11,000 miles of new CO2 pipelines (Exhibit
35), primarily from electric power plants to EOR projects and saline storage sites. By 2030,
19
A Review of the CO 2 Pipeline Infrastructure in the U.S.
there are 56 new pipeline segments in use to transport captured CO2 from its source to a terminal
sink (EOR or Saline Storage). Under this scenario, regional oil production from EOR occurs
predominantly in the Southwest; however, production also significantly increases in the
Midcontinent, West Coast and Gulf Coast regions.
In terms of sources for the CO2, by 2030, the CP25 case projects a tripling of CO2 capture in the
U.S., with over 99 percent of this coming from the power sector (Exhibit 37). Under this
scenario, an 11 percent reduction in CO2 emissions (94 MMT CO2) from the U.S. power sector
(Exhibit 36) would come through the application of carbon capture technologies to over 32 GW
of generation capacity (Exhibit 38)6.
In terms of sinks for the CO2, oil production from CO2-EOR is projected to increase to over 10
percent of total U.S. production by 2030 (Exhibit 39). This would account for nearly 95 percent
of CO2 sequestration, with the balance being stored in underground saline formations.
In the CP25 case, direct pipelines make up 48 percent of the total pipeline miles and 23 percent
of the tonne-miles transported. This is significantly less than the 79 percent of total miles
dedicated to direct pipelines in the Cap40 case. Additionally, there is about 5,000 miles more of
pipeline in the CP25 than in the Cap40 case; nearly all of that difference comes from an increase
in the use of shared trunk-lines. While the CP25 results in fewer GWs of power plant capacity
with capture (about 71 GW vs. 79 GW in the Cap40 case), they are distributed over a greater
number of plants, thus increasing the total pipeline mileage in the CP25 case (Exhibit 20).
Cap40 Results
Pipe Type Total Miles % Average Miles Million Tons CO2 %
Total 15,194 100 205 468,906 100
Direct 11,977 79 244 269,674 58
Feeder 2,458 16 123 65,309 14
Trunk-lines 760 5 152 133,923 29
Interregional 7,448 49 219 221,823 47
Intraregional 8,411 55 210 247,083 53
CP25 Results
Pipe Type Total Miles % Average Miles Million Tons CO2 %
Total 21,496 100 197 841,086 100
Direct 10,355 48 280 194,038 23
Feeder 5,475 25 112 125,794 15
Trunk-lines 5,666 26 246 521,254 62
Interregional 11,478 53 239 370,276 44
Intraregional 10,018 47 164 470,810 56
6
Of this 32 GW, 5.9 GW is coal-fired and 26.5 GW is gas-fired.
20
A Review of the CO 2 Pipeline Infrastructure in the U.S.
In the Cap40 case, 12-inch pipes are used exclusively in direct connections; however, 85 percent
of them crossed state lines. 60 percent of the 16-inch pipeline miles are associated with direct
connections, with 45 percent of them being interstate pipelines. All of the pipes greater than 16
inches were used as either feeders into trunk-lines or as trunk-lines, 27 percent of which were
interstate lines (Exhibit 21).
In the CP25 case, 12-inch pipes make up almost 90 percent of all the direct pipelines, with the
balance carried by 16-inch pipelines. As in the Cap40 case, in the CP25 case, 12-inch pipes are
used exclusively in direct connections and a large majority (78 percent in this case) cross state
lines. The larger plants (those with emissions >3.25 MMT/yr – approximately equivalent to the
emissions of a 500 MW coal plant) fed into trunk-lines while most of the smaller plants used
direct pipelines.
Cap40
Pipeline Miles
Pipeline Diameter (in)
Pipe Type
12 16 20 24 36
Total 8,623 5,632 192 582 165
Direct 8,623 3,354 - - -
Feeder - 2,171 192 94 -
Trunk-lines - 107 - 488 165
Interregional 3,866 3,488 - 94 -
Intraregional 4,758 2,145 192 488 165
MMT-Miles 135,434 185,295 13,101 97,877 43,199
% of Total 29 40 3 20 9
CP25
Pipeline Miles
Pipeline Diameter (in)
Pipe Type
12 16 20 24 36
Total 9,251 6,706 158 4,370 1,011
Direct 9,251 1,104 - - -
Feeder - 5,317 158 - -
Trunk-lines - 285 - 4,370 1,011
Interregional 6,693 2,014 - 2,006 765
Intraregional 2,558 4,692 158 2,365 246
MMT-Miles 147,141 186,374 4,840 322,990 179,740
% of Total 17 22 1 38 21
Total CO2 pipeline development costs depend on a number of variables, including length,
pipeline diameter, terrain, and other regional variations. However, total cost for a CO2 pipeline
project in a given region can be determined by examining a similar project in the Permian Basin.
21
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Similar to oil field infrastructure development, capital costs for CO2 pipelines are lowest in the
Permian Basin. For example, the 214 mile, 16-inch Lobos pipeline is expected to cost
approximately $300 million. Other announced CO2 pipelines in the Gulf Coast and Rocky
Mountain regions are expected to cost between 25 percent and 33 percent more per inch-mile
than the Lobos pipeline. These additional costs are likely due to harsher terrain, navigation
through denser populations, and less competition among developers capable of undertaking such
technically-demanding work.
Based on recent announcements7, industry is on the brink of capturing significant volumes of
CO2 from industrial sources, including the 740 million cubic feet per day of industrial CO2
utilized for CO2-EOR. Using industrial data and published reports, the volume of CO2 supplies
from industrial facilities could reach 3,060 million cubic feet per day by the end of the decade,
an increase of over four times the current CO2 capture and transportation volume from industrial
sources.
Exhibit 22 shows that the average cost per mile of pipeline is $562,000 in the CP25 case, which
is about 40 percent higher than in the Cap40 case. This difference is largely attributed to the
greater use of larger diameter trunk-lines in the CP25 case. A trunk-line is built when it is more
economical (on a $/tonne basis) for more than one source to share a pipeline than build a
dedicated (direct) pipeline. Because the trunk-line carries the combined volume of two or more
sources, a larger diameter pipeline is required. The larger the diameter of a pipeline, the greater
the cost per mile, although the cost per tonne of CO2 carried may be less than a smaller pipeline
(depending upon utilization). Exhibit 33 and Exhibit 34 in the Appendix provide state-level
detail for inter- and intra-state pipeline segments.
7
http://www.globalccsinstitute.com/projects/large-scale-ccs-projects#overview
22
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Cap40
Interstate Intrastate
Units Total/Average
Pipelines Pipelines
Number of Links 37 37 74
Direct 30 19 49
Feeder 6 14 20
Trunk-lines 1 4 5
Average
mi 278 133 243
Distance
Average Cost MM$ 119 49 105
Total Miles mi 10,278 4,916 15,194
Total CO2 MMT 1,059 1,181 2,240
Total Tonne- MMT-
10,880,053 5,803,705 16,683,758
miles mi
Average Cost/mi ($1000) 362 203 330
CP25
Interstate Intrastate
Units Total/Average
Pipelines Pipelines
Number of Links 60 49 109
Direct 24 13 37
Feeder 20 29 49
Trunk-lines 16 7 23
Average
mi 251 132 244
Distance
Average Cost MM$ 199 73 173
Total Miles mi 15,036 6,460 21,496
Total CO2 MMT 1,960 2,380 4,340
Total Tonne- MMT-
29,477,059 15,378,094 44,855,153
miles mi
Average Cost/mi ($1000) 624 323 562
Transportation costs are calculated as the cost to transfer one tonne of CO2 from its origin
(capture point) to its terminus. There are only two path options: direct (a dedicated pipeline from
origin to terminus) and shared (where several sources of CO2 are collected at a transshipment
point and then transported via a trunk-line to the terminus).
In the Cap40 case, for both direct and shared pipelines, the majority of the costs are below
$8/tonne (Exhibit 23). While the distribution of costs is much greater for the direct pipelines
versus shared, the median cost of transport is similar between the two: $7.92 for direct pipelines
and $8.46 for shared.
23
A Review of the CO 2 Pipeline Infrastructure in the U.S.
10 10
8 8
frequency
frequency
6 6
4 4
2 2
0 0
2 4 6 8 10 12 15 20 25 30 40 50 More 2 4 6 8 10 12 15 20 25 30 40 50 More
$/tonne $/tonne
Unlike the Cap40 case, which saw similar costs per tonne between the direct and the shared
pipelines, there is a greater difference between the pipeline types in the CP25 case with the
median cost of a direct pipeline at $6.38/tonne and that of a shared pipeline being $20.75/tonne
(Exhibit 24).
frequency
10 10
8 8
6 6
4 4
2 2
0 0
2 4 6 8 10 12 15 20 25 30 40 50 More 2 4 6 8 10 12 15 20 25 30 40 50 More
$/tonne $/tonne
Pipeline transportation costs are heavily reliant on the volume of product moved through them.
Exhibit 25 shows that as the amount of CO2 that is transported increases, there is a notable
decrease in costs per MMT of CO2 delivered due to economies of scale.
24
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Despite more miles of pipeline being built in the CP25 case, less CO2 is captured compared to
the Cap40 case. This ultimately results in less oil produced from EOR. Exhibit 26 shows that in
2040, there are 1.3 MMBbls/day of oil produced under the CP25 case, while 1.5 MMBbls/day is
produced in the Cap40 case. For each case, this represents over 16 percent of total oil production
in 2040, with the majority of the CO2 captured for EOR production coming from power plants,
while the amount of naturally sourced CO2 decreases in the Cap40 case and remains nearly
constant from 2015 - 2040 in the CP25 case. By comparison, the Reference case sees a very
small increase in CO2 production from power plants over the modeled period.
25
A Review of the CO 2 Pipeline Infrastructure in the U.S.
1.0
0.8
0.6
0.4
0.2
-
Cap40
Cap40
Cap40
Cap40
Cap40
Cap40
Ref
CP25
Ref
CP25
Ref
CP25
Ref
CP25
Ref
CP25
Ref
CP25
2015 2020 2025 2030 2035 2040
Power Plants Natural Ethanol
Refineries, Hydrogen Natural Gas Processing Ammonia
Regional oil production from EOR in the Cap40 case is dominated by the Southwest, where
nearly half of the EOR oil production is derived. The Midcontinent and Gulf Coast regions also
significantly increase production. There is a small increase in production on the West Coast,
while the Rocky Mountain region remains steady through the 2040 period (Exhibit 27).
26
A Review of the CO 2 Pipeline Infrastructure in the U.S.
1.40
1.20
1.00
MMBbls/day
0.80
0.60
0.40
0.20
0.00
The regional distribution of CO2 is similar in the CP25 when compared to the Cap40 case, as
Exhibit 28 shows, with the Southwest playing the most significant role (followed by the Midwest
and the West Coast)
27
A Review of the CO 2 Pipeline Infrastructure in the U.S.
1.20
1.00
MMBbls/day
0.80
0.60
0.40
0.20
0.00
In the Cap40 case, by 2040, there are 73 new pipeline segments in use for CO2 capture, transport,
utilization, and storage (CTUS) from its source to a terminal sink (EOR or Saline Storage). The
greatest activity occurs in Texas, where EOR activity in the Permian basin attracts CO2. Trunk-
lines are typically employed where there are a relatively high concentration of sources, such as
Texas, Mississippi, and Louisiana (Exhibit 29).
28
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibit 29 Power plant pipeline build-out by 2040 for the Cap40 case
In the CP25 case (Exhibit 30), by 2040, there are 107 new pipeline segments in use to transport
captured CO2 from its source to a terminal sink (EOR or Saline Storage). As in the Cap40 case,
the greatest activity occurs in Texas, where EOR activity in the Permian basin attracts CO2, and
trunk-lines are typically employed where there are a relatively high concentration of sources,
such as Texas, Mississippi, and Louisiana.
Exhibit 30 Power plant pipeline build-out by 2040 for the CP25 case
29
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibit 31 Power plant pipeline build-out by 2030 in the $25/tonne CO2, low carbon scenario
8
New industrial CO2 capture facilities coming on line (e.g., Air Products PCS Nitrogen plant in southern Louisiana, Southern Company’s
integrated gasification combined cycle (IGCC) plant in Kemper County, Mississippi, etc.)
9
This total includes ICF estimates of all new pipelines greater than 8 inches in diameter. If smaller diameter pipelines (e.g., gathering lines) are
included, the estimated miles of new natural gas and petroleum product pipelines is nearly an order of magnitude greater.
30
A Review of the CO 2 Pipeline Infrastructure in the U.S.
10
“Currently, the Bureau of Land Management regulates CO2 pipelines under the Mineral Leasing Act as a commodity shipped by a common
carrier. See: 30 U.S.C. § 185(r).”
31
A Review of the CO 2 Pipeline Infrastructure in the U.S.
“other than water, oil, or gas.” (15) The STB has yet to be asked to hear a case involving the
transportation of CO2, so its oversight status remains unaddressed following the GAO decision.
(15)
5.2.2 Safety Oversight
CO2 transportation pipelines are subject to federal safety regulations that are administered by the
U.S. DOT’s Pipeline and Hazardous Materials Safety Administration (PHMSA). PHMSA
directly oversees pipeline safety for all interstate lines, while intrastate pipelines are subject to
state agency oversight (as long as the standards are at least as stringent as the federal rules). (13)
The major risks of a CO2 pipeline incident are prolonged exposure to high CO2 concentrations.
However, of nearly 2,000 hazardous liquid and CO2 transport pipeline accidental release
incidents reported between 2010 and the March, 2015, a total of 21 incidents occurred for CO2
transport pipelines, none of which resulted in either fatality or injury. (16)
While CO2 is not considered a hazardous material by DOT, CO2 transportation pipelines are
regulated under 49 CFR Part 195, Transportation of Hazardous Liquids by Pipeline. This
distinction is made due to the nature of the transportation pipelines, which carry the highly
pressurized CO2 in a liquid phase similar to other hazardous material transportation pipelines.
Smaller CO2 distribution lines, which transport the CO2 from the trunk-line to individual wells,
are generally not subject to these PHMSA safety standards.
32
A Review of the CO 2 Pipeline Infrastructure in the U.S.
6 Conclusions
The bulk of the existing large-volume CO2 pipelines connect natural sources of CO2 with CO2-
EOR projects in large oil fields. In the coming 5 to 10 years, the completion of several planned
projects could deliver a five-fold increase in the capture of CO2 by industrial facilities, up to
levels that could exceed the scale of CO2 production from natural sources. This is expected to be
accompanied by a 12 percent increase in the total miles of CO2 pipeline infrastructure over the
period. While these new pipeline projects are primarily for the CO2-EOR industry, they will
provide valuable infrastructure for additional utilization of CO2 as well as potential future
transportation and storage of CO2 in saline formations.
However, under a U.S. climate policy case (i.e., $25/ton CO2), by 2030 the scale of U.S. CO2
pipeline infrastructure is projected to triple to enable the delivery of carbon captured by the U.S.
power sector to oil fields for CO2-EOR, and to a lesser extent, for storage in underground saline
formations. While this scenario would involve an unprecedented scale-up of CO2 pipeline
infrastructure, the pace would be comparable to that projected for pipeline construction in other
sectors (in which many of the same companies operate).
The development of a national CO2 pipeline network capable of meeting the Administration’s
greenhouse gas (GHG) emission goals may require a more concerted federal policy, involving
much closer cooperation among federal, state, and local governments than is currently in place.
In the low-carbon cases, several states that are projected to site new CO2 pipeline infrastructure
by 2030 do not yet have policies in place for permitting and operations. More can be learned
from Texas’ experience, as well as recent state policies like the WPA, under which early
planning, interagency coordination, and stakeholder engagement efforts are key government
actions for enabling CO2 pipeline project development and construction.
33
A Review of the CO 2 Pipeline Infrastructure in the U.S.
34
A Review of the CO 2 Pipeline Infrastructure in the U.S.
8 Bibliography
1. Denbury Onshore LLC. Denbury 2013 Annual Report Growth & Income. Denbury. [Online]
2013. http://www.denbury.com/files/doc_financials/2013/Denbury_Final_040814.pdf.
2. Murrell, Glen. Wyoming CO2 Status and Developments, from the 6th Annual Wyoming
CO2 Conference. University of Wyoming. [Online] July 11, 2013.
http://www.uwyo.edu/eori/conferences/CO2/2013%20presentations/murrell.pdf.
3. Dakota Gasification Company. CO2 Capture and Storage: The greatest CO2 story ever told.
Dakota Gasification Company. [Online] 2015.
http://www.dakotagas.com/CO2_Capture_and_Storage/.
4. National Energy Technology Laboratory (NETL). Michigan Basin, MRCSP, Otsego CO.
Geologic Field Test Site. NETL. [Online] December 12-13, 2007.
https://www.netl.doe.gov/publications/proceedings/07/rcsp/pdfs/Gupta_michbasinbrief_2007.pdf
.
5. Energy Information Administration (EIA). Oil and Gas Supply, Reference Case from
AEO2014. EIA. [Online] 2014.
6. Denbury Onshore LLC. Value Driven: Analyst Day Presentation. Denbury. [Online] Nov
2013. http://www.denbury.com/files/2014-02%20UPLOADS/2013-
11%20Analyst%20Day%20FINAL%20FULL%20SLIDE%20PRINT%20VERSION_v001_n45
0ml.pdf.
10. Global CCS Institute. The Global Status of CCS 2013. s.l. : Global CCS Institute, 2013.
Section 6.4, page 114.
35
A Review of the CO 2 Pipeline Infrastructure in the U.S.
11. Falwell, Patrick. State Policy Actions to Overcome Barriers to Carbon Capture and
Sequestration and Enhanced Oil Recovery. Center for Climate and Energy Solutions. [Online]
September 2013. http://www.c2es.org/docUploads/CCS_EOR_Whitepaper_0.pdf.
12. Energy.gov. Energy.gov. Natural Gas Act, Chapter 15B §717(b). [Online]
http://energy.gov/sites/prod/files/2013/04/f0/2011usc15.pdf.
13. Southern States Energy Board. A Policy, Legal, and Regulatory Evaluation of the
Feasibility of a National Pipeline Infrastructure for the Transport and Storage of Carbon Dioxide.
Part 3.I.B.1.a. Southern States Energy Board. [Online] December 10, 2010.
15. Nordhaus, Robert R, and Pitlick, Emily. Carbon Dioxide Pipeline Regulation. Energy Law
Journal. Energy Law Journal. [Online] Vol. 30:85, 2009.
http://felj.org/sites/default/files/docs/elj301/85_-_nordhaus_and_pitlick.pdf.
16. PHMSA. Hazardous Liquid Accident Data – 2010 to Present (zip). PHSMA Online Portal -
Distribution, Transmission & Gathering, LNG, and Liquid Accident and Incident Data. [Online]
2015.
17. Folger, P., and Parfomak, Paul W. Carbon Dioxide (CO2) Pipelines for Carbon
Sequestration: Emerging Policy Issues. s.l. : CRS Report for Congress, 2017.
36
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Appendix
Exhibit 32 Comprehensive List of U.S. CO2 Pipelines
Estimated
Length Diameter Flow
Scale Pipeline Operator Location
(mi) (in) Capacity
(MMcfd)
Bravo Oxy Permian NM, TX 218 20 380
Canyon Reef
Kinder Morgan TX 139 16 220
Carriers
Centerline Kinder Morgan TX 113 16 220
Central Basin Kinder Morgan TX 143 16 220
Cortez Kinder Morgan TX 502 30 1,300
Large-Scale Delta Denbury Resources MS, LA 108 24 590
Trunk-lines
Green Line Denbury Resources LA, TX 314 24 930
Greencore Denbury Resources WY, MT 230 22 720
Northeast Jackson
Denbury Resources MS, LA 183 20 360
Dome (NEJD)
Sheep Mtn Oxy Permian TX 408 24 590
Shute
ExxonMobil WY 30 30-20 1,220-220
Creek/Wyoming CO2
Adair Apache TX 15 4 50
Anadarko Powder
Anadarko WY 125 16 220
River Basin CO2 PL
Anton Irish Oxy Permian TX 40 8 80
Beaver Creek Devon WY 53 8 30
Borger Chaparral Energy TX, OK 86 4 50
Coffeyville- Burbank Chaparral Energy KS, OK 68 8 80
Comanche Creek Oxy Permian TX 120 6 70
Smaller Scale
Distribution Cordona Lake XTO TX 7 6 70
Systems Dakota Gasification
Dakota Gasification ND, SK 204 14 130
(Souris Valley)
Dollarhide Chevron TX 23 8 80
El Mar Kinder Morgan TX 35 6 70
Enid-Purdy (Central
Anadarko OK 117 8 80
Oklahoma)
Este I - to Welch, TX ExxonMobil, et al. TX 40 14 180
Este II - to Salt Crk
Oxy Permian TX 45 12 130
Field
37
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Estimated
Length Diameter Flow
Scale Pipeline Operator Location
(mi) (in) Capacity
(MMcfd)
Ford Kinder Morgan TX 12 4 50
Free State Denbury Resources MS 85 20 360
Llano Trinity CO2 NM 53 12 80
Lost Soldier/Wertz Merit WY 30 16 40
Mabee Lateral Chevron TX 18 10 110
McElmo Creek Kinder Morgan CO, UT 40 8 80
Means ExxonMobil TX 35 12 130
Monell Anadarko WY 33 8 80
North Cowden Oxy Permian TX 8 8 80
North Ward Estes Whiting TX 26 12 130
Pecos County Kinder Morgan TX 26 8 80
Pikes Peak Oxy Permian TX 40 8 80
Raven Ridge Chevron WY, CO 160 16 220
Rosebud Hess NM 50* 12 100*
Slaughter Oxy Permian TX 35 12 130
Sonat Denbury Resources MS 50 18 170
TexOk Chaparral Energy OK 95 6 70
TransPetco TransPetco TX, OK 110 8 80
Val Verde Oxy Permian TX 83 10 110
W. Texas Trinity CO2 TX, NM 60 12 80
Wellman Trinity CO2 TX 25 6 70
White Frost Core Energy, LLC MI 11 6 70
Wyoming CO2 ExxonMobil WY 112 20 220
Total U.S. CO2 Pipeline Length 4,513 - -
*Estimate
38
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibit 33 State-Level Inter- and Intrastate Pipeline Segments for the Cap40 Case
Links
Averge
Distance
Total Transship- per Link Cost Total Total Total tonne- Cost/mile
Start Terminus Links Direct Feeder ment (Miles) ($mm) Miles MMT miles ($k/mile)
AL MS 1 1 - - 173.13 61.14 173.13 17.03 2,948.06 353.13
AR MS 1 1 - - 165.95 58.64 165.95 3.24 537.46 353.38
AZ CA 2 2 - - 394.77 361.05 789.55 88.50 69,871.66 457.28
AZ TX 2 2 - - 467.07 326.49 934.14 53.25 49,746.93 349.51
CO WY 1 1 - - 378.40 132.44 378.40 35.86 13,568.64 350.01
FL MS 1 1 - - 232.68 127.34 232.68 45.24 10,526.83 547.26
FL FL 4 4 - - 98.39 140.69 393.54 20.77 8,172.34 357.51
IA MI 1 1 - - 407.64 222.33 407.64 29.87 12,177.48 545.40
IA KS 2 - 2 - 165.06 218.46 330.12 74.92 24,731.64 661.75
ID WY 3 3 - - 402.54 422.48 1,207.61 59.71 72,104.64 349.85
IL MI 1 1 - - 325.33 114.01 325.33 11.06 3,598.40 350.44
IL IL 1 1 - - 85.10 30.56 85.10 7.05 599.53 359.09
IN IL 3 3 - - 190.70 244.22 572.10 27.95 15,992.99 426.88
KS OK 1 - - 1 204.20 216.19 204.20 206.31 42,127.37 1,058.73
LA MS 3 3 - - 150.62 159.96 451.87 111.66 50,455.90 353.99
MO KS 1 - 1 - 34.09 27.55 34.09 76.26 2,599.55 808.28
MO OK 1 - 1 - 142.62 78.44 142.62 30.23 4,310.80 550.00
MS MS 5 2 2 1 64.01 178.82 320.07 182.60 58,443.81 558.69
MT WY 1 1 - - 373.16 130.62 373.16 0.27 99.63 350.04
NE OK 2 2 - - 354.93 320.46 709.86 16.65 11,820.78 451.45
NE KS 2 - 2 - 164.27 180.40 328.55 55.14 18,114.94 549.07
NM TX 2 2 - - 330.47 231.59 660.95 15.57 10,290.55 350.39
NV CA 1 1 - - 311.09 109.06 311.09 12.66 3,938.62 350.58
OK OK 1 - - 1 81.55 45.28 81.55 30.23 2,464.87 555.30
SD ND 1 1 - - 318.44 111.61 318.44 5.88 1,872.02 350.50
TX TX 21 7 12 2 168.38 2,336.15 3,535.99 908.91 3,213,881.46 660.68
UT CA 1 1 - - 487.69 170.41 487.69 24.24 11,819.45 349.41
UT WY 1 1 - - 305.59 107.15 305.59 12.27 3,748.28 350.63
WY ND 2 2 - - 216.68 197.14 433.35 44.82 19,422.80 454.91
WY WY 5 5 - - 100.01 178.70 500.06 30.96 15,481.45 357.35
39
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibit 34 State-Level Inter- and Intrastate Pipeline Segments for CP25 Case
Links
Avg. Total tonne- Avg. Cost
Terminal Number Distance Avg. Cost Total Total CO2 miles ($000)/
Start Terminus Region of Links Direct Feeder Trunk (miles) ($mm) Miles (MMT) (MMT-mi) Mile
Inter-state Pipelines 60 24 20 16 251 199 15,036 1,960 29,477,059 624
AL MS OGSM2 1 0 0 1 182 100 182 2 449 548
AR MS OGSM2 1 0 0 1 254 269 254 135 34,246 1,058
AR OK OGSM3 1 0 0 1 236 250 236 63 14,902 1,058
AZ CA OGSM6 2 2 0 0 395 138 790 60 47,634 175
AZ CO OGSM5 1 0 0 1 207 219 207 93 19,225 1,059
AZ NM OGSM5 1 0 1 0 95 52 95 11 1,070 554
AZ TX OGSM4 3 3 0 0 314 132 943 38 36,190 140
CO NM OGSM5 1 0 0 1 295 312 295 207 60,963 1,057
CO WY OGSM5 1 1 0 0 378 206 378 91 34,539 546
FL MS OGSM2 2 2 0 0 363 127 726 16 11,919 175
IA KS OGSM3 2 0 2 0 165 109 330 35 11,443 331
ID CA OGSM6 1 1 0 0 503 176 503 8 4,016 349
ID ND OGSM7 1 1 0 0 205 72 205 19 3,899 352
ID WY OGSM5 2 2 0 0 355 124 710 34 24,358 175
IN KY OGSM1 1 0 1 0 183 101 183 2 330 548
KS OK OGSM3 1 0 0 1 204 216 204 60 12,286 1,059
KY TN OGSM1 1 0 0 1 314 332 314 20 6,268 1,057
MI IL OGSM1 1 1 0 0 85 31 85 1 115 359
MN ND OGSM7 1 1 0 0 474 166 474 1 498 349
MO KS OGSM3 1 0 1 0 196 108 196 26 5,007 548
NC AL OGSM2 1 0 0 1 431 455 431 2 1,063 1,056
NM OK OGSM3 1 0 0 1 413 877 413 177 73,240 2,122
NM TX OGSM4 1 0 0 1 352 746 352 41 14,388 2,122
NV CA OGSM6 1 1 0 0 311 109 311 14 4,297 351
NV ND OGSM7 2 2 0 0 492 172 984 7 6,894 175
NV UT OGSM5 1 0 1 0 178 98 178 10 1,816 549
NY PA OGSM1 1 0 1 0 207 113 207 10 2,077 548
OH KY OGSM1 1 0 0 1 246 260 246 16 3,961 1,058
OK TX OGSM4 1 0 0 1 274 289 274 92 25,292 1,057
PA OH OGSM1 2 0 1 1 234 212 468 15 6,944 452
SD WY OGSM5 1 1 0 0 472 165 472 0 63 349
TN KY OGSM1 1 0 1 0 50 28 50 2 104 563
TN MS OGSM2 1 0 0 1 316 334 316 20 6,315 1,057
TX AR OGSM3 5 0 5 0 81 45 405 130 52,538 111
TX MS OGSM2 4 2 1 1 200 142 800 238 190,700 177
TX OK OGSM3 5 1 4 0 60 33 299 107 32,151 111
UT CA OGSM6 1 1 0 0 488 170 488 25.88 12,620 349
UT CO OGSM5 2 0 1 1 167 149 334 114 38,031 448
UT WY OGSM5 2 2 0 0 349 122 697 15 10,143 175
Intrastate Pipelines 49 13 29 7 132 73 6,460 2,380 15,378,094 323
AR AR OGSM3 1 0 1 0 115 63 115 68 7,786 552
AZ AZ OGSM5 5 0 5 0 143 78 713 93 66,114 110
FL FL OGSM2 1 1 0 0 71 26 71 1 90 361
MI MI OGSM1 2 2 0 0 207 105 413 24 10,107 253
MS MS OGSM2 5 3 1 1 81 37 405 406 164,507 90
NC NC OGSM1 1 0 1 0 223 122 223 2 550 547
OH OH OGSM1 1 0 1 0 70 39 70 1 89 557
OK OK OGSM3 2 0 0 2 92 115 184 253 46,581 625
TX TX OGSM2 26 7 15 4 146 92 3,806 1,449 5,512,993 24
UT UT OGSM5 5 0 5 0 92 51 460 83 38,098 111
40
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Power Sector
2015 2030 2040
CO2
Million metric
Ref Cap40 CP25 Ref Cap40 CP25 Ref Cap40 CP25
tonnes
Sequestered
3.48 2.89 3.48 6 92 94 6 229 171
Power CO2
Non
Sequestered 2,075 2,036 1,797 2172 788 743 2193 1 190
Power CO2
Total Power
2,078 2,039 1,801 2178 880 837 2199 230 361
CO2 Emissions
Percent
Sequestered 0.2% 0.1% 0.2% 0.3% 10.4% 11.2% 0.3% 99.6% 47.4%
CO2
41
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibit 37 Sequestered Anthropogenic CO2 Captured at Industrial vs. Power Sector Sources
Sequestered
Anthropogenic 2015 2030 2040
CO2
Million metric
Ref Cap40 CP25 Ref Cap40 CP25 Ref Cap40 CP25
tonnes
Industrial 0.4 0.7 0.4 31.6 0.1 0.1 46.7 8.2 1.0
Power Sector 3.5 2.9 3.5 6.3 91.9 94.0 6.2 228.6 170.7
Total 3.8 3.6 3.8 37.9 92.0 94.1 52.9 236.8 171.7
Percent Power
90.6%11 80.5% 90.6% 16.7% 99.9% 99.9% 11.8% 96.5% 99.4%
Sector CO2
Exhibit 39 U.S. Oil Production (MMBbls/day) Associated with CO2-EOR, in 2015, 2030, and 2040
(table)
11
The reference model assumes a demo plant is currently in operation, and the CO2 is from that plant.
42
A Review of the CO 2 Pipeline Infrastructure in the U.S.
Exhibit 40 U.S. oil production (MMBbls/day) associated with CO2-EOR, in 2015, 2030, and 2040
(graph)
8.00
MMBbls/day
6.00
EOR
4.00 Alaska
Other Lower 48
2.00
0.00
Ref Cap40 CP25 Ref Cap40 CP25 Ref Cap40 CP25
2015 2030 2040
43
Anthony Zammerilli Bob Wallace
anthony.zammerilli@netl.doe.gov wallace_robert@bah.com
www.netl.doe.gov
Pittsburgh, PA • Morgantown, WV • Albany, OR • Sugar Land, TX • Anchorage, AK
(800) 553-7681