10 - GEST 73 25 Edition 13 - Transfer of Dry Chlorine by Piping Systems
10 - GEST 73 25 Edition 13 - Transfer of Dry Chlorine by Piping Systems
10 - GEST 73 25 Edition 13 - Transfer of Dry Chlorine by Piping Systems
Systems
GEST 73/25
13th Edition
April 2023
Euro Chlor
Euro Chlor is the European Federation which represents the producers of chlorine
and its primary derivatives.
Euro Chlor is working to:
• Improve awareness and understanding of the contribution that chlorine
chemistry has made to the thousands of products, which have improved our
health, nutrition, standard of living and quality of life;
• Maintain open and timely dialogue with regulators, politicians, scientists,
the media and other interested stakeholders in the debate on chlorine;
• Ensure our industry contributes actively to any public, regulatory or
scientific debate and provides balanced and objective science-based
information to help answer questions about chlorine and its derivatives;
• Promote the best safety, health and environmental practices in the
manufacture, handling and use of chlor-alkali products in order to assist
our members in achieving continuous improvements (Responsible Care).
***********
This document has been produced by the members of Euro Chlor and should not be reproduced in
whole or in part without the prior written consent of Euro Chlor.
It is intended to give only guidelines and recommendations. The information is provided in good faith
and was based on the best information available at the time of publication. The information is to be
relied upon at the user’s own risk. Euro Chlor and its members make no guarantee and assume no
liability whatsoever for the use and the interpretation of or the reliance on any of the information
provided.
This document was originally prepared in English by our technical experts. For our members’
convenience, it may have been translated into other EU languages by translators / Euro Chlor
members. Although every effort was made to ensure that the translations were accurate, Euro Chlor
shall not be liable for any losses of accuracy or information due to the translation process.
Prior to 1990, Euro Chlor’s technical activities took place under the name BITC (Bureau International
Technique du Chlore). References to BITC documents may be assumed to be to Euro Chlor
documents.
TABLE OF CONTENTS
SUMMARY OF THE MAIN MODIFICATIONS ............................................................ 5
1 INTRODUCTION................................................................................................... 5
2 SCOPE AND DEFINITIONS ................................................................................. 5
3 GENERAL STATEMENTS ................................................................................... 6
3.1 LIQUID PHASE ...................................................................................... 6
3.2 GASEOUS PHASE ................................................................................ 6
4 BASIC DESIGN AND INSTALLATION ................................................................ 7
5 DESIGN AND CONSTRUCTION .......................................................................... 8
5.1 DOUBLE WALL PIPING SYSTEM ......................................................... 8
5.2 BRANCHES AND ANCILLARY EQUIPMENT ....................................... 9
5.3 END CONNECTION AND END OF PIPE VALVES ............................... 9
5.4 INTERMEDIATE ISOLATION VALVES ................................................. 9
5.5 FLANGES, NUTS AND BOLTS ........................................................... 10
5.6 APPLIED LOAD AND STRESSES ...................................................... 10
5.7 DESIGN PRESSURE........................................................................... 11
5.8 DESIGN TEMPERATURE ................................................................... 11
5.9 FLUID VELOCITIES ............................................................................ 11
5.10 PIPE AND BRANCHES DIAMETER .................................................... 12
5.11 CORROSION ALLOWANCE AND PROTECTION .............................. 12
5.12 RADIUS OF CURVATURE .................................................................. 12
5.13 THERMAL INSULATION ..................................................................... 13
5.14 HEAT TRACING OF CHLORINE GAS PIPING SYSTEM.................... 13
5.15 EMPTYING, VENTING AND PURGING .............................................. 14
5.16 TRANSFER EQUIPMENT ................................................................... 15
5.17 PROTECTION AGAINST OVERPRESSURE AND THERMAL
EXPANSION ........................................................................................ 15
5.18 MONITORING THE PIPING SYSTEM CONDITIONS ......................... 16
5.19 MATERIALS OF CONSTRUCTION ..................................................... 17
5.20 SUPPORTS ......................................................................................... 18
5.21 PIPE INSPECTION AND TESTING ..................................................... 19
6 OPERATION ....................................................................................................... 19
6.1 CLEANING AND DRYING BEFORE PUTTING INTO SERVICE ......... 19
6.2 LEAK TESTING ................................................................................... 19
6.3 COMMISSIONING AND TESTING BEFORE PUTTING INTO SERVICE
............................................................................................................. 20
6.4 PUTTING THE PIPING SYSTEM INTO SERVICE .............................. 20
6.5 RUNNING A CHLORINE PIPING SYSTEM......................................... 20
6.6 PERIODICAL INSPECTION AND TESTING OF LONG DISTANCE
PIPING SYSTEM ................................................................................. 20
6.7 MANAGEMENT OF CHANGES ........................................................... 21
6.8 TAKING THE PIPING SYSTEM OUT OF SERVICE ........................... 21
6.9 INTERVENTION IN CASE OF INGRESS OF MOISTURE .................. 22
6.10 INTERVENTION IN THE EVENT OF FAILURE OF THE HEAT
TRACING (FOR GAS PIPING SYSTEM)............................................. 22
6.11 EMERGENCY PROCEDURES AND TRAINING ................................. 22
7 REFERENCES.................................................................................................... 23
1 INTRODUCTION
In Europe and other industrialized regions there are many years’ experiences in
operation of piping systems for dry gaseous and liquid chlorine. Design and
maintenance to operate safely those piping systems are well understood. Basic
principles in terms of design, operation and maintenance are summarized in this
recommendation.
Various considerations and basic principles of design and construction are outlined
and should be followed when designing this type of system.
Experience has shown that each installation requires individual consideration.
Accordingly, this document must only be taken as a guide; it is not a comprehensive
design code and in no way should it interfere with competent engineering
judgement. It is recommended, however, that any proposed deviations are discussed
with an experienced chlorine producer.
3 GENERAL STATEMENTS
Chlorine can be transferred safely by piping systems either in the gas or liquid
phase, provided the appropriate design and operating conditions are satisfied,
avoiding two phase flow, which is a source of corrosion by erosion. All precautions
should be taken such that:
• inpiping systems designed to transport only liquid chlorine, vaporisation
cannot occur,
• in piping systems designed for the transfer of only chlorine gas, nothing
should lead to the formation of liquid.
In each case, specific precautions are required. These are described for both states
within this recommendation.
Remark: in some exceptional circumstances, gaseous chlorine piping systems have
been designed to allow some partial liquefaction; in this case the construction and
the operation procedures have to take all necessary precautions to cope with the
phenomena, after a specific risk assessment.
This very specific case is not further considered in this recommendation.
3.1 LIQUID PHASE
The design and operation of liquid phase piping system must consider at least the
following issues:
• The maximum transfer pressure which is technically achievable.
• The temperature and pressure of the chlorine at the inlet and exit of the
piping system to ensure continuity of the liquid phase.
• The minimum temperature which can occur when depressurizing and purging
the piping system for maintenance or emergency emptying.
• The potential pressure increases by thermal expansion of trapped chlorine
and the protection measures.
• A maximum linear velocity.
• The total pressure drop.
• The safety protection against surge (liquid hammer).
• The quantity of chlorine contained in the piping system which may conflict
with individual and societal risk contours.
• The surrounding of the piping system that could affect its integrity (high
temperature, mechanical damage …).
The above will limit the length and throughput of a particular piping system, as
pumping stations outside the premises of a chlorine-producing or consuming factory
are not recommended. In Europe, there are many years’ experience of liquid phase
piping systems over several km and pressure up to 30-40 bara.
3.2 GASEOUS PHASE
The design and operation of gas phase piping systems must consider at least the
following issues:
• The maximum inlet pressure technically achievable.
• The risk of liquefaction associated with either the operating pressure or a fall
in temperature.
• The maximum temperature of the heat tracing system in all circumstances,
particularly in the event of zero flow.
sheets or warning tapes, concrete slabs marked "buried piping system" etc., as
commonly used with gas and electricity utilities).
Dividing a liquid chlorine piping system into smaller segments with automatic
isolation valves, to improve safety, is not recommended (see paragraph 5.4 below).
For gaseous chlorine, the need/number of automatic or remotely controlled
isolation valves along the piping system is defined by the safety study.
In both cases, such valves and flanges represent a weak point in the construction of
the piping system, adding a supplementary risk (e.g., flange leak). Liquid chlorine,
if trapped between two closed valves might cause a pressure increase due to
possible thermal expansion. This would require installing special protection/relief
with connection to an absorption system for each section. Therefore, it is
recommended to avoid such isolation valves, especially outside the confines of
industrial premises.
The inlet and outlet of the piping system should be equipped with isolation valves
(see 5.3). Degassing capabilities to a chlorine absorption facility and/or a
dump/escape tank to catch liquid chlorine is considered necessary for an adequate
response in case of emergency.
than the outer wall while in service, although the temperatures become the
same while the piping system is not in service. This effect can be more severe
when liquid chlorine is cooling down due to depressurisation/partial
vaporisation.
• Inspection requirements have to be considered at the initial design of the
piping system.
• As this outer wall is basically installed to monitor possible small leaks of the
chlorine piping system, it can be at a lower pressure rating (for example PN
10).
• The space inside the double wall should be monitored, e.g., by a permanent
flow of dry air or nitrogen with a chlorine detector at the outlet of the
flushing gas with alarm; alternatively, the space can be kept under dry air or
inert gas with high/low pressure alarm.
• Branches are very difficult to build on a chlorine pipe with a double wall.
5.2 Branches and Ancillary Equipment
The number of branches should be strictly limited to the minimum necessary as they
increase the risk of leak and, are difficult to insulate allowing a location for possible
corrosion to initiate. Their location in parts of the main piping system which are
below ground should be avoided. If this cannot be avoided, they should be placed in
inspection chambers accessible to personnel wearing protective clothing.
Vent and drains should only be located inside the supplier’s or the customer’s site.
Large diameter branches should be fitted with guide bars if the piping system is to
be "pigged".
5.3 End Connection and End of Pipe Valves
Isolation valves should be provided at the end of the piping system; the safety study
should demonstrate if they need to be remotely operable, depending on their
location and the quantity of chlorine contained in the piping system. Consideration
should be given to automatically close these valves in the case of upset at any point
in the system (for example following an abnormal drop in pressure). In the case of
liquid chlorine, the pipe must withstand the liquid hammer generated by closing the
valves; the speed of closure of these valves can be adapted to reduce this effect.
The valves may be installed to permit in-service functionality testing.
The material of the valves should be compatible with that of the pipe. They should
conform to recommendations of Euro Chlor. Refer to the following documents for
further information:
• GEST 17/492 - Specifications and Approval Procedure for Valves to be Used
in Liquid Chlorine or Dry Chlorine Gas.
Valve operation should be guaranteed at the piping system design temperature
(minus 40°C for liquid chlorine).
If the piping system is to be cleaned or inspected with a "pig", the valves should be
of the full-bore type to permit passage.
5.4 Intermediate Isolation Valves
Intermediate isolation valves, if any are required to separate the pipe in different
sections (not recommended for liquid chlorine because of the risk resulting from
additional flanges, and thermal expansion for trapped liquid), should be remotely
operated type, applying the same considerations as for the end-of-pipe valves.
As for the end-of-pipe valves, all such valves should be carefully chosen and should
be located and protected to prevent unauthorised access.
Consideration has to be given to the sequence of closure of the valves.
5.5 Flanges, Nuts and Bolts
Threaded connections for piping system and instrument connections to the piping
system are not recommended.
The pipes should preferably be welded all along their length with only flanges at the
beginning and the end. Where flanges are needed, they will preferably be of tongue
and groove type or flat flanges with blow-out-proof gaskets in the case of liquid
chlorine.
Note: Tongue and groove joints offer a greater potential integrity, but increased
difficulty when assembling or dismantling the joint.
It is recommended that weld neck flanges are used for all pipe sizes.
It has to be taken into consideration that flanges/gaskets may interfere with the
continuity of the cathodic protection.
Bolts and nuts should conform to Unified inch or ISO metric standards and
recognised national standard and be suitable for the selected temperature
conditions. See GEST 88/134 – Stud Bolts, Hexagon Head Bolts and Nuts for
Liquid Chlorine.
The design temperature of nuts and bolts should be in line with the pipe
requirements (e.g., minus 40°C for liquid chlorine).
5.6 Applied Load and Stresses
The following factors should be taken into account when considering the loads and
stresses applied to piping systems:
• Internal and external pressure
• Thermal expansion and contraction
• Weight of pipe and associated equipment
• Weight of the chlorine in the piping system in case of liquid chlorine (the
density of liquid chlorine is approximately 1500 kg/m³)
• Weight of insulation, including the possible accidental ingress of any moisture
when the vapour seal fails.
• Reaction from lines discharging to lower pressure systems.
• In case of liquid chlorine, effect of surge or “water hammer”
• Wind loads.
• Seismic effects
• Snow and ice (particularly where there is the possibility of ice forming on
unlagged lines)
• Forces arising from valve operation.
• People standing on the piping system.
The dynamic forces arising from two phase flow should be considered in case of
filling/emptying a liquid chlorine piping system.
The basis for any calculation on expansion and contraction in the system should be
the maximum and minimum temperatures arising from:
• Normal operation
• Start-up and shut-down, including abnormal conditions arising from
maintenance and commissioning activities.
• Predictable transient conditions, e.g., de-icing and cases where the piping
system can operate alternately above and below ambient temperature.
5.7 Design Pressure
For liquid chlorine, the complete piping system, including flanges and all
components, shall be designed for the maximum possible operating pressure equal
to the vapour pressure of chlorine at the maximum operating temperature chosen,
plus a safety margin determined by factors such as the magnitude of possible surge
effects, the pressure drop, the piping system layout (static height), the delivery
pressure of the pumping/compression system -including at start-up-, the maximum
pressure in the feed tank, etc. (For protections against thermal expansion and
surge, see 7.6). The minimum design pressure to be used is 25 barg, a design
pressure below 25 barg can only be accepted where the service conditions are fully
known and documented.
For gaseous chlorine, the complete piping system shall be designed for the
maximum operating pressure.
In situations where a vacuum may be applied to dry out the system, the pipework
will be subject to external pressure and must be designed accordingly.
5.8 Design Temperature
The complete system should be designed for the maximum temperature capable of
being attained and for the lowest temperature that can occur.
For liquid chlorine, the minimum design temperature should be minus 40°C or
lower).
5.9 Fluid Velocities
Liquid Chlorine Piping System
The velocity of liquid chlorine in the piping system should be limited to avoid
destruction of the protective film of ferric chloride by erosion in carbon steel pipes,
taking into consideration the higher local velocities due to the presence of valves,
orifice plates, bends and other pipework features. Test by the AkzoNobel Corrosion
Department have not indicated any erosion from liquid chlorine at velocities up to 7
m/sec. For practical reasons such as pressure drop, pressure surge (liquid hammer,
avoiding turbulence in bends, after valves etc. and to create a safety margin the
velocity is normally limited to approx. 2 - 3 m/s.
The prevention of flashing at any point is essential to avoid high two-phase
velocities which can cause serious erosion.
Gaseous Chlorine Piping System
Practical experience from some of our members has shown that gas velocities up to
20 m/s are acceptable without deterioration, provided there is no liquid droplets
entrainment.
where D is the diameter of the nominal pipe size in DN or NPS. If pigs have to be
used, the use of a larger radius of curvature of 2.5*D (corresponding to type 5D) can
be considered.
5.13 Thermal Insulation
The benefit of insulation should always be considered against increased risk of
undetected external corrosion of the pipe.
When a chlorine piping system is to be insulated, greater safety is obtained by
designing the supports, external protection and insulation together as an integrated
system.
Particular precautions need to be taken to avoid any entrapment of moisture during
the installation of the thermal insulation; the work should be performed during dry
weather.
Liquid Chlorine Piping System
For a single wall liquid chlorine piping system above-ground, thermal insulation can
be employed, if necessary, to avoid external water condensation, frosting, potential
fire radiation or heating by sun radiation which could lead to evaporation and two
phases flow. Special attention should be paid to avoid water ingress in the insulation
which could lead to corrosion which is difficult to detect. It is advised to properly
prepare and paint or coat the bare steel pipe before applying the thermal insulation
to prevent corrosion under insulation (CUI).
In the case of a buried piping system, external thermal insulation is usually not
necessary.
For buried piping systems it could be advisable to heat the liquid chlorine just above
the normal temperature of the surrounding soil to avoid heating-up and pressure
increase when there is no chlorine flow.
Gaseous Chlorine Piping System
For gaseous chlorine, thermal insulation is usually not necessary, but can be used
(with or without heat tracing) to avoid the risk of condensation due to
pressure/temperature conditions.
Other means to avoid accidental liquefaction in the pipe may be low operating
pressures, adequate chlorine delivery temperatures and permanent gas circulation.
It should be noted that, in the event of a prolonged shut down or very small delivery
rate, thermal insulation without heat tracing might not be sufficiently effective to
prevent chlorine liquefaction (depending on the chlorine pressure).
Thermal insulation can also be required to protect personnel from high temperature
pipework.
5.14 Heat Tracing of Chlorine Gas Piping System
According to operating pressures, the length of the piping system and other ambient
conditions, heat tracing and thermal insulation can be used to avoid liquefaction of
the gaseous chlorine. All precautions must then be taken to ensure the permanent
availability of the heating system as long as the pipe is in operation and to avoid any
localised overheating to prevent local corrosion or chlorine/iron fire. Such
overheating can be prevented by applying a heating medium with limited
temperature (e.g., hot water supplied from a vessel at atmospheric pressure) or by
suitable calculation of the heat density, so that at any point the metal temperature
should never exceed 120°C, considering the worst possible climatic conditions.
If an electrical heating system is used, it should be equipped with self-limiting/self-
regulating heat tracing cables which shall be attached to, but insulated from, the
chlorine pipes to avoid localised hot spots. The elements should be armoured and
externally protected against corrosion and the ingress of moisture. The heating
power should be calculated as a function of the thermal losses and not as a function
of the heat input required to re-vaporise any chlorine which may have condensed in
the pipework. An independent high temperature safety system will be foreseen;
several temperature sensors could be used along the piping system for alarm.
Heating using the electrical resistance of the pipe itself should not be used.
Heat tracing with a transfer fluid (steam or hot water for example), using tubing
attached to, but insulated from the chlorine piping system can also be used as an
alternative. Steam pressure must be low enough (< 2 bara) and the steam must be
saturated (de-superheating system required if necessary) to ensure that
temperature does not exceed 120°C.
If steam heat tracing is applied, all connections which are not welded should be
outside the insulation to prevent water leaks inside the insulation with risk of pipe
corrosion.
5.15 Emptying, Venting and Purging
Emptying and Venting:
• It is essential that the piping system can be rapidly depressurised.
• To empty a liquid phase piping system, vessels large enough to receive the
entire contents of the piping system should be provided as a minimum at the
producer's side but preferably at both ends for long piping system. If possible,
the piping system will be emptied by gravity. It is also possible to empty the
piping system by gas pressure or using a "pig". The pipe will then be vented.
• The design must be such that chlorine gas can be vented into a suitable
installation (absorption unit or compression and liquefaction plant of
adequate capacity). In the case of liquid chlorine, it should be noted that this
venting will take place at low temperature. All equipment associated with
the operation, therefore, should be suitable for the actual temperatures
which will arise.
Purging:
• Inert dry gas (dew point less than minus 40°C at 1 bara) of adequate quantity
and pressure should be permanently available. All precautions will be taken
to avoid contamination by oils, grease or other contaminants that could react
with chlorine.
• The system will be designed to avoid back flow from chlorine to the dry gas
network; this can be realised by dedicated purging system, if its pressure is at
least 2 bar higher than the maximum piping system pressure, or a backflow
protection.
• Purged gas should be passed through a suitable absorption installation to
remove chlorine, before being vented to atmosphere.
o The ability to reliably detect failure of the heating system (in any case the
temperature may not exceed 120°C).
Drawings of acceptable methods of relieving excess pressure are shown in
Appendices 1A, 1B, 1C and 1D.
The volume of the expansion chamber can be calculated on the basis of the volume
increase of the chlorine (in the piping system) due to a temperature increase from
the minimum possible operating temperature to the maximum design temperature
plus a 10% safety margin; alternatively, a good practice is to give this chamber a
volume of 20% of the piping system section to be protected.
Overpressure of the Gaseous Chlorine
Under most circumstances it is unlikely that gaseous chlorine pipe work will require
a pressure relief system to guard against effects of excess pressure (see GEST
87/133 – Overpressure Relief of Chlorine Installations).
If the compressor is capable of overpressuring the piping system, a pressure
interlock or a relief device must be installed. The pressure relief should be located
directly at the outlet of the compressor. These relief devices (bursting discs, relief
valves or a combination of both) should always be connected to an absorption
system or a point of use in the liquefaction (see GEST 87/133 – Overpressure
Relief of Chlorine Installations).
Protection against Surge for Liquid Chlorine
When the velocity of a fluid in a line is suddenly changed, pressure waves occur due
to the change in momentum. When the amplitude of these pressure waves becomes,
critical this is referred to as “Water Hammer” (or Joukowski effect). There can be
pressure increases as well as negative pressures. The usual initiating event for this
condition is the rapid closure of a valve.
More information on this can be found at the following website:
https://publicwiki.deltares.nl/display/WANDA/Fluid+transient+fundamentals.
A calculation of the maximum pressure reached in these cases will be made together
with the chlorine customer. The system should withstand this maximum pressure
and, if necessary, the valve closure (depending on the characteristic of the valve)
time can be increased to reduce the severity of the surge. Additionally, appropriate
surge protections can be installed at least at one end of the piping system (bursting
disc with exhaust in safety storage connected to chlorine absorption, sealed pots
with inert or chlorine gas …); alternatively, the pipe and accessories can be
designed to withstand this maximum pressure.
A surge wave in a pipe will also generate out-of-balance forces at anchors or other
restraints, and these must be designed for the maximum load. It must be noted that
these are dynamic loads and so an appropriate dynamic load factor should be
applied.
All changes in the chlorine piping system should be agreed between supplier and
customer.
5.18 Monitoring the Piping System Conditions
All precautions should be taken to avoid maloperation by means such as locks, logic
systems, interlocks etc. It should be possible to stop automatically the transfer of
chlorine into the piping system in the event of abnormal conditions such as pressure,
temperature and flow.
All long-distance piping system outside a single operational facility should include as
a minimum the following monitoring equipment at least at the inlet of the piping
system:
• Measurement and recording of the pressure and temperature.
• Maximum and minimum pressure (and temperature for chlorine gas) alarms.
If the piping system is completely or partly double walled, a leak detector should be
installed (e.g., pressure alarm or chlorine detector on the purge gas of the double
wall).
Permanent connections by telephone and/or computer connection should be
provided between the two ends of the piping system.
5.19 Materials of Construction
All the materials used have to be compatible with chlorine in the design conditions
(See “GEST 79/82 - Materials of Construction for Use in Contact with Chlorine”).
The materials and equipment should be obtained from approved suppliers with a
documented quality insurance procedure.
Piping System
The steel chosen for the construction of the piping system should be of a certified
quality, fine grain steel and readily weldable.
For liquid chlorine, it will have a satisfactory impact strength, according to the
standards being used, at minus 40°C after welding.
The metal used in branches and other pieces welded to the pipe (see 5.2) should be
of a quality compatible with the base metal chosen for the pipe itself. It is advisable
to choose a quality of steel which avoids the need for stress relief after welding.
Seamless pipe is preferred. Where welded pipe is chosen, the full length of the weld
seam of every tube should be inspected by ultrasonic or electromagnetic methods or
should be 100% X-rayed.
Flanges, Nuts and Bolts
The metal used for flanges, nuts and bolts should possess the same characteristics as
that of the piping system.
Gaskets
The gasket used should be made in a material with positive experience on chlorine
(see “GEST 94/216 - Gaskets selection for the use in Liquid Chlorine and Dry or
Wet Chlorine Gas Service” for further information).
The mounting of the gaskets should be performed by well-trained people; only new
gaskets should be used.
The stress relaxation resistance of some gaskets decreases with increasing thickness.
It is therefore recommended that gaskets be fitted inside the bolt circle and should
have thickness compatible with the flange rating.
Where spirally wound gaskets using metal windings and a chlorine compatible filler
material are used, care should be taken to ensure that the flange faces are
machined to the joint manufacturer’s recommended standard and that the mating
flanges are similar, i.e., of the same material and surface finish.
Under no circumstances should gasket contact surfaces be machined in a manner
that leaves tool marks extending radially across the seating surface.
No grease which is not compatible with chlorine may be used and torque
calculations should be done with the friction coefficient of the chlorine compatible
grease.
Jointing compounds are not recommended, and paste should not be used with spiral
wound, or PTFE gaskets under any circumstances. However, when paste is used for
flanged joints which have to be broken and remade frequently for process or
maintenance reasons, care should be taken to ensure that the paste is:
• Compatible with chlorine
• Compatible with the gasket material
• Used sparingly and is not forced into the bore of the pipe.
• Spread evenly over the joint surface.
Thermal Insulation
If the installation of thermal insulation is necessary, the materials to be applied
should meet the following criteria:
• Chemically inert to chlorine
• Not flammable or combustible, or at least auto-extinguishing
For cold liquid chlorine, there is no predominant insulation material, but the
following are satisfactorily used:
• Foam glass
• Mineral wool
Other materials are sometimes used please check the reactivity of the materials
with chlorine.
Except for insulation material with closed cells, vapour barriers must be utilised to
prevent the accumulation of moisture on the insulation of any insulated pipe that
operates at temperatures below ambient temperature.
For the cladding used to protect externally the insulation layer and to prevent as far
as possible ingress of water, several materials can be used, according to the local
environment (aluminium, stainless steel, coated carbon steel, plastic, resin, fibre
reinforced resin …). A sufficient spacing should be foreseen between cladding and
the liquid barrier to avoid damaging this one.
For double wall piping system, no insulation will be installed in the inner space.
5.20 Supports
The supports of the piping system should permit the thermal expansion/contraction
of the piping system due to any likely variations in temperature, taking into account
the maximum and minimum achievable temperatures. They should also deal with
any possible earth movement. For above ground piping system, it is preferable to
use large radius expansion loops.
Expansion bellows should not be used because they may be weak points in the
construction, unless a detailed study proves adequacy. For straight lines, where free
expansion cannot take place, account must be taken of the longitudinal stresses
which will result from the maximum variation in temperature.
The support system should be designed to avoid any ingress of moisture under the
thermal insulation, where fitted.
6 OPERATION
6.1 Cleaning and Drying before Putting into Service
Before putting the piping system into service, all equipment should be degreased,
cleaned and dried according to the GEST 80/84 - Code of Good Practice for the
Commissioning of Installations for Dry Chlorine Gas and Liquid.
6.2 Leak Testing
The dried piping system should then be tested for possible leaks.
The recommended procedures are described in the GEST 80/84 - Code of Good
Practice for the Commissioning of Installations for Dry Chlorine Gas and Liquid.
All personnel, including those of the public authorities who could be asked to assist
in the event of an emergency, should be specifically instructed in the means of
dealing with leakages of chlorine or the effects of chlorine-iron fire. Periodic
exercises and re-training shall be organised to ensure maintaining sufficient
knowledge and skills.
Whenever possible, common routing of the piping system with electric cables or
flammable fluids should be avoided.
Self-contained breathing equipment and protective clothing suitable for dealing with
a chlorine leak should be available in lockers located at least near to the ends of the
piping system and accessible at any time in case of emergency.
A means of indicating the wind direction should be installed to inform the operators
of the direction of gaseous dispersion that might occur in the event of a leak. The
persons involved in a chlorine leak should escape perpendicularly to the wind
direction.
7 REFERENCES
GEST 73/17 - Storage of Liquid Chlorine
GEST 76/55 - Maximum Levels of Nitrogen Trichloride in Liquid Chlorine
GEST 78/73 - Design Principles and Operational Procedures for Loading/Off
Loading Liquid Chlorine Road and Rail Tankers and ISO-Containers
GEST 79/82 - Materials of Construction for Use in Contact with Chlorine
GEST 80/84 - Code of Good Practice for the Commissioning of Installations for
Dry Chlorine Gas and Liquid
GEST 87/133 – Overpressure Relief of Chlorine Installations
GEST 94/216 – Gaskets Selection for the Use in Liquid Chlorine and Dry or Wet
Chlorine Gas Service
GEST 10/362 – Corrosion Behaviour of Carbon Steel in Wet and Dry Chlorine
GEST 17/492 - Specifications and Approval Procedure for Valves to be used in
Liquid Chlorine or Dry Chlorine Gas.
TIAS
+/-
isolation
expansion tank
self-regulating electrical heating
gaseous sheet
space
liquid
Cl2 - pipeline
Clamping collar
Pipe supports
Pipe
Slides
Euro Chlor
Rue Belliard 40
Box 15
B-1040 Brussels
Belgium
Email: eurochlor@cefic.be
Internet: http://www.eurochlor.org