Ares(2015)6063816 - 30/12/2015
Funded by the Horizon 2020 Framework Programme of the
European Union
PLAN
ECSITE
DECEMBER 2015
1. INTRODUCTION ................................................................................................ 3
technology shifts in health and medicine. Its aim is to raise awareness and communicate
Sparks will organise an interactive touring exhibition and 230 innovative participatory
activities such as science cafés, pop-up science shops, incubation activities and
scenario workshops. Creative disruptions —in the form of artistic inputs and
questioning— will help it to engage more stakeholders. The European dimension of the
experienced science communicators that will adapt the exhibition and activities to their
relation to health. This is a highly relevant research topic which is able to motivate
3
2. PURPOSE OF THE RISK AND CONTINGENCY
MANAGEMENT PLAN (R&CMP)
The large-scale project nature of the Sparks project, involving 29 different countries and
aiming to have an impact across Europe, requires having a careful risks and
project implementation. Ecsite is in charge of designing and implementing the risk plan
and reporting risks. This R&CMP defines how risks associated with the Sparks Project
are identified, analysed, and managed. Developing an effective R&CMP can help keep
small issues from developing into emergencies and will help us deal with adverse
situations when they arise as well as solve them before they arise.
There are many approaches to project risk management planning, but essentially the
risk management plan identifies the risks that can be defined at any stage of the project
life cycle. The R&CMP evaluates identified risks and outlines mitigation and
throughout the life cycle of the project, as the project increases in complexity and risks
The intended audience of this document is the Sparks Steering Committee and the
4
3. RISK AND CONTINGENCY MANAGEMENT
PROCEDURE
Risk management takes a project throughout the phases of risk identification, risk
assessment and risk resolution. With the advancement in project management studies
and techniques, risk management has taken the main place in the project life cycle; in
Ecsite working with the partners will ensure that risks are actively identified, analysed,
and managed throughout the life of the project. We are identifying risks as early as
possible in the project so as to minimize their impact. The steps for accomplishing this
Risk identification involves the project team, appropriate stakeholders, and includes an
5
plan including the project scope. Careful attention is given to the project deliverables,
We need to understand how Risk Management works. Risk is the effect (positive or
negative in nature, but we will consider in this plan as a negative one) of an event or
series of events that take place in one or several locations. It is computed from the
probability of the event becoming an issue and the impact it would have (Risk =
including:
And we are answering also the questions regarding mitigation: How can you reduce the
Probability (and by how much)? And Contingency: How can you reduce the Impact (and
by how much)?
For Sparks Project the main risks are associated with the exhibition, and all its diverse
stages and components. The exhibition is the main way the scientific contents are going
look at the possible risks and their probability, in order to have a fast reaction capacity.
6
Another big area were risks are present is the communication flow among partners. The
agreements procedures.
All risks identified have been assessed to identify the range of possible project
outcomes. An index number will be used to determine which risks are the top risks to
how much will that affect the project - was identified and assessed by the project
coordinator, with input from the project partners using the following approach:
Probability
Note: If the probability or the impact of an event occurring is zero, then we removed it from
Impact
High – Risk that has the potential to greatly impact project cost, project schedule or
performance
7
Medium – Risk that has the potential to slightly impact project cost, project schedule or
performance
Low – Risk that has relatively little impact on cost, schedule or performance
After we identify the above, the result will be what’s called exposure, by multiplying
the level of probability and impact. This is the amount of risk you simply can’t avoid.
Exposure may also be referred to as Threat, Liability or Severity. Exposure greater than
0,5 will be carefully attended and between 0,3 and 0,5 will be constantly tracked.
Each major risk will be tracked by Ecsite and the Steering Committee to ensure that the
risk will not turn into an issue. Important actions of a response planning are to have
probability that a risk will materialise. We will only do this for High and Medium
For each risk that will be mitigated, the Project Coordinator will identify ways to prevent
the risk from occurring or reduce its impact or probability of occurring. This may
include prototyping, adding tasks to the project schedule, adding resources, etc.
For each major risk that is to be mitigated or that is accepted, a course of action will be
outlined for the event that the risk does materialise in order to minimise its impact.
8
3.4 RISK MONITORING, CONTROLLING, AND REPORTING
The level of risk on a project will be tracked, monitored and reported throughout the
project lifecycle. Any project change request will be analysed for their possible impact
to the project risks. Also we will consider important changes to risk status, in order to
9
4.RISK AND CONTINGENCY MATRIX FOR SPARKS
The initial risks have already been identified and classified in the following Risk
Management Matrixes.
Matrix 1 shows the risks for the entire project, labelling each risk with a GR, meaning
General Risk. Matrix 2 shows the risks related to the exhibition and its risks are
labelled as ER, meaning Exhibition Risks. We are using a specific risk matrix for the
exhibition development, according to the regular risk control procedures in use at the
Science Museum London. The risk assessment follows the same procedures described
Matrix 1
GR2
GR3
10
The management structure and the
regular meetings on work progress with
all relevant partners means the schedule
will be monitored tightly and costs will Rescheduling and reallocation will
Schedule and
All WPs 0.6 0.7 0.42 be managed by careful planning at the always be consulted with the EU
cost limitations
project level. This means the schedule Project Manager.
Unexpected delays or will be monitored tightly and costs will
events that could slow be managed by careful planning at the
down the correct project level.
GR4 workflow
GR5
Cultural
differences may Misunderstanding of
The adaptation of the activities to the Major changes or adaptations will be
require the fundamental goals
WP3 0.7 0.2 0.14 local contexts is foreseen by local done in coordination with the WP2
adaptation of of the project and its
organisers of the project Leader
the public exhibition
activities
GR6
Local partners
Disconnection
fail to identify A tailored accompaniment will be given A bank of examples will be developed
between the RRI local
RRI practices as to the local organizers by conecting by Science Museum London to provide
WP2 component that is 0.5 0.4 0.2
local examples them with the local Hubs from RRI Tools content in case local partners do not
meant to be tackled
of the project. identify relevant examples.
with the project.
exhibition
GR9
11
Ask for support to local experts in
Low Specific communication campaigns,
gender, through the Hypatia project
participation in including actions targeted to women.
Unsuccessful local hubs and contact prominent speakers
the activities, WP2, Selection of topics locally relevant
exhibitions and non- 0.3 0.7 0.21 that could bring the attention of more
and in WP3 (selected by local partnerships) and also
gender inclusive public. Review and redesign the
particular of more suitable to attract women. Use of
communication strategy to address this
women material by the Twist project.
problem.
GR10
Low
Difficulties to asses the
participation in Each activity will have at least one Review the evaluation strategy and
event's impact and to
the survey for WP4 0.5 0.5 0.25 person partially dedicated to encourage involve more local staff to encourage
report accurately
feedback the public to participate to the survey the public to answer the survey.
about them
collection
GR11
The high
number of
A tailored management plan and enough
organisations The communication The Steering committee will decide
resources will be dedicated to the
participating in and results about new management measure that
WP6 0.6 0.5 0.3 management team. A work plan
the project achievement is could include allocating more hours to
reviewed every 6 months will ensure
complicates the hindered. some members.
that the project runs smoothly.
management
process
GR12
12
MATRIX 2
Collaborative
planning with
each Museum and
Touring exhibiton host, Rescheduling as
Touring timing schedule has to based in their soon as the delay is
ER1 fails All be readjust 0.5 1 0.5 own contexts known to happen
Careful planning
of the design and
its costs will
diminish this risk.
Unexpected As soon as Study the
overspend on one Other something possibility of
element(s) of deliverables appears to be out financial
exhibition are of plan, talk to the reallocation of
ER2 delivery WP2 compromised 0.4 0.8 0.32 coordination. resources
Study the
Unexpected build Funding Detailed planning possibility of
complications scheme for the and constant financial
generating extra exhibition is reviewing of the reallocation of
ER3 cost WP2 not respected
Schedule 0.4 0.8 0.32 design's budget resources
slippage,
excessive
strain on
remaining staff,
handover to
new staff pulled Fast reaction to find
from another Consider detail a replacement
Key staff leave / project has planning of among people with
contracts not WP2, implications available human exhibition
ER4 renewed WP6 elsewhere 0.3 0.5 0.15 resources experience
Other
departments and
external
contractors not
given enough The quality of
notice and time to the exhibition The schedule and
deliver resulting parts are not working plan is Reorganise the
in compromised meeting the shared with the duties in order to
quality of expected team involved in stay the least out of
ER5 deliverables WP2 requirements 0.2 0.5 0.1 every stage the schedule.
13
Content is
inaccurate or
misrepresents The institute in
science and charge of the
scientists Inaccurate inception report
representation and creating this New consultation
of the current framework is with experts to
state of considering rewrite the
WP1. scientific cutting edge and sections that have
ER6 WP2 advance 0.2 0.6 0.12 updated sources problems
Content
disengages
audience as is just
another shade of Lack of
grey - science is engagement
TOO uncertain and
and can understanding The AIGHD New consultation
contribute of the links institute is a with experts to
nothing to my life between world lead rewrite the
meaningfully WP2, science and institute in global sections that have
ER7 today WP3 health 0.2 0.6 0.12 health problems
Content speaks to
a single gender
Gender
The exhibition inclusivity is an Consultation to
is not including horizontal gender experts and
diversity of approach that will link to the Hypatia
WP2, publics and be consider by Hub will be a
ER8 WP3 interests 0.2 0.6 0.12 the task leaders bonus
Objects dull and
generic
The exhibitions
is not visually Science Museum
appealing to London is leader
the public, in developing The design will be
turning the engaging and reviewed in order
experience into innovative to make the
ER9 WP2 a boring one 0.2 0.7 0.14 exhibitios necessary changes.
Artists
interventions not
produced to high
standard
Ars electronica is
a cutting edge
organization,
world leader in
the union of arts
and digital
worlds. They will Reviews will be
The high be in charge of done and the
quality art the selection of necessary changes
component at the best artists will be made to
the exhibition and coaching the meet the quality
ER10 WP2 is missing 0.2 0.8 0.16 best works of arts standards.
Exhibition
receives poor
media coverage
and promotion
despite having Exhibition is
great hook and WP3, unnoticed by
ER11 content WP5 the public 0.5 0.5 0.25
14
Visitors
upset/distressed
by insensitive
treatment of Visitors don't Careful selection Actions will be
sensitive topics feel connected and reflection on done to change the
with the the topics and messages or the
exhibition and detailed design way they are
have a bad on the way they communicate so
impression are showcased visitor enjoy and
ER12 WP2 about it 0.2 0.8 0.16 will be given engage
On time press
releases and Review of the
invitations communication
Poor public delivery to local strategy and
assistance to the WP3, Low public media and key changes made
ER13 launching WP5 assistance 0.2 0.6 0.12 persons when necessary
Local organisers
who don’t have
experience with
exhibition hosting Close
might struggle Poor accompaniment Reschedule the
with install/de- organisation of to each partner personal support
install/finding the exhibition from the Science for the partners
appropriate WP2, setting and Museum and the that are struggling
venues
ER14 WP3 running 0.5 0.8 0.4 Touring expert with the exhibition
15
APPENDIX A: KEY TERMS
The following table provides definitions for terms relevant to the Risk Management Plan.
Term Definition
risk.
Exposure It’s an index that indicates how important the risk for your
Issue When a risk occurs and the event turns into a problem,
then it is an issue.
16
17