Method Statement For Concreting Works
Method Statement For Concreting Works
Method Statement For Concreting Works
______________________________________________________________
1- INTRODUCTION
2- RELEVANT DOCUMENTS
3- RESPONSIBILITIES
A. DESIGN MIX
6- CONTRUCTION METHOD
A. DESIGN MIX
B. FORMWORK
C. FALSEWORK
D. PRE-POUR INSPECTION
E. FORMWORK REMOVAL
F. REINFORCEMENT
G. PRE-POUR WORKS
H. CONTRUCTION JOINTS
I. FINISHING
J. POST-POUR WORKS
K. SCHEDULE OF WORK
B. EMERGENCY PLANS
Page 1 of 9
PROJECT: TOYOTA HEADQUARTERS PP
THQ-LBL-MDS-005-0 (Concreting Works)
______________________________________________________________
1- INTRODUCTION
The purpose of this document is to point out the various steps to be carried out for the general
features and sequence which this activity shall be performed in accordance with the
specification and as indicated in the approved drawings; to meet the requirements of the
Contract Works.
This work Method Statement has been arranged to give a clear guidance to the people
working at project site and to ascertain the limits and controls for the quality of works.
In this MDS, LBL international shall be identified as the ‘’Main Contractor’’, Archetype as the
‘’Consultant/Engineer’’ and Toyota as the “Client”.
2- RELEVANT DOCUMENTS
3- RESPONSIBILITIES
2.0 The QA/QC Manager (Mr. Eng Sen) shall be responsible in leading and directly
supervising the Quality Assurance and Quality Control of the aforesaid Works.
3.0 Safety Manager (Mr. Ngouv Chanvirak) is tasked to ensure that the major
objectives of the plan will be implemented properly to provide comprehensive
measures that will ensure the protection of life and properties as well as to
provide construction efficiency through selective use of safe work practices and
working conditions.
3.1 A personal to guard site access.
Page 2 of 9
PROJECT: TOYOTA HEADQUARTERS PP
THQ-LBL-MDS-005-0 (Concreting Works)
______________________________________________________________
3.2 Safety Manager has to ensure daily safety work at the beginning of work
shifts such as hot work (cutting & wielding), working at height, working
plate form, and individual HSE…
The structural works shall start, upon obtaining site opening permit. Works to be carried out
shall be in accordance with sequence as mentioned in Chapter 6.
LBL will employ sufficient qualified supervisors in addition to the experienced site workers
and foremen to supervise the structural works.
A. QUALITY ASSURANCE
The Contractor shall notify the Consultant within 24 hours through submittal of Request for
Inspection informing the type, time, date whenever the Contractor wants the Consultant to
inspect the works.
The Contractor has to ensure that works are being done according to the specifications
/approved drawings to achieve best quality.
Page 3 of 9
PROJECT: TOYOTA HEADQUARTERS PP
THQ-LBL-MDS-005-0 (Concreting Works)
______________________________________________________________
Generator: 1set
And other tools etc.
Site manager: 1p
Site engineers: 2p
QC engineer:1p
MEP engineers :2p
Safety manager: 1p
Safety supervisors:3p
Skill workers: 50p to 200p following monthly progress
6- CONTRUCTION METHOD
A. DESIGN MIX
Concrete testing : 3 samples of 3days and 28days age of beam and slab per
floor will be done at third party laboratory (Cast Lab) and the remaining samples will
be done at supplier lab test. Company profile and calibration certificated of Cast Lab
and concrete supplier have been submitted separately.
B. FORMWORK
Page 4 of 9
PROJECT: TOYOTA HEADQUARTERS PP
THQ-LBL-MDS-005-0 (Concreting Works)
______________________________________________________________
Formwork shall be constructed to the exact sizes, shapes, lines and dimensions
shown on the drawings and as required to obtain accurate alignment, location, grades,
level and plumb of the finished structures in accordance with the schedule of the
tolerances.
C. FALSEWORK
Falsework shall be erected to give sufficient support and bracing and allow for
any necessary adjustment for positioning and striking. Wedges, jacks or camber strips
to be provided to facilitate vertical adjustments. After concrete placement operations,
the falsework and formwork shall be inspected to determine abnormal deflection or
any signs of failure.
D. PRE-POUR INSPECTION
E. FORMWORK REMOVAL
F. REINFORCEMENT
The Contractor shall submit mill steel certificate with tensile test by third party
to Engineer for review. The Contractor shall ensure that the reinforcement is stored
correctly to avoid any adverse effects from the environment.
MAR for steel bar: has been submitted separately.
ITP form: to be submitted separately.
Page 5 of 9
PROJECT: TOYOTA HEADQUARTERS PP
THQ-LBL-MDS-005-0 (Concreting Works)
______________________________________________________________
Reinforcement, once cut and bent following approved shop drawing, shall be stored in
the lay down area or on off ground supports and shall only be delivered to the work
area when required. All bars will be tagged as per the bending schedule. All scrapped
or unused reinforcement shall be stored in a central area before being removed from
site. In general, no loose or scrap reinforcement shall be left in / around the work areas.
Concrete spacer blocks or steel chair shall be used to support the bottom layers
of reinforcement and to space reinforcement from edge forms. Mortar spacer may be
used to space reinforcement from edge forms. The spacer block shall be selected to
provide the correct cover to the bottom reinforcement layer.
Where required, steel chairs shall be scheduled and fabricated to support
intermediate and top layers of reinforcement, spacing of chairs will be max 2m.
Reinforcement shall be installed once the blinding, soffit formwork or preparation of
the supporting / adjacent concrete element has been inspected and signed off.
G. PRE-POUR WORKS
The engineer shall be notified 24 hours prior to placing of concrete for inspection of
thoroughly. The surface and reinforcement shall be sprayed with clean water prior to
concrete pouring. While placing concrete, objects such as anchor bolts, reinforcing
bars and other fixtures shall be monitored for movement. ITP list will be submitted
separately.
The concrete slump shall be such that it can be easily placed without
segregation. If the concrete is acceptable, it will continue to be discharged. Slump test
Page 6 of 9
PROJECT: TOYOTA HEADQUARTERS PP
THQ-LBL-MDS-005-0 (Concreting Works)
______________________________________________________________
shall be taken at every load of concrete. The load shall be accepted if the concrete
slump at the point of discharge is within tolerance for the design mix ordered. If the
slump is below tolerance, the load shall be rejected. The concrete is to be agitated
continuously by rotation of the mixer drum during transport to the Site and while waiting
discharge. Concrete shall be discharge from the delivery vehicle within 2 hours after
the time of loading.
H. CONTRUCTION JOINTS
I. FINISHING
When the concrete is poured to level, the surface will be finished generally.
Areas of specialized finishes will be treated separately.
Holes left by the withdrawal of the tie rods shall be filled solidly with non – shrink
mortar (datasheet to be submitted to engineer for review) and finished to match the
surrounding surface. All exposed concrete shall be free from bulges, honeycomb, fins
and other similar surface defects.
Page 7 of 9
PROJECT: TOYOTA HEADQUARTERS PP
THQ-LBL-MDS-005-0 (Concreting Works)
______________________________________________________________
When the concrete has stiffened sufficiently, the surface shall be bowelled by
hand or by machine sufficiently to produce a uniform surface free from screed marks
and to ensure that the surface of the concrete is within tolerance.
J. POST-POUR WORKS
Detail schedule per tasks: columns, wall, beam, slab and ramp will be submitted
separately.
The Safety Manager is tasked with ensuring that the major objectives of the plan will be
implemented properly to provide comprehensive measures that will ensure the protection of
life and properties as well as to provide construction efficiency through selective use of safe
work practices and working conditions.
B. EMERGENCY PLANS
The Contractor will make necessary arrangements with a general hospital near the vicinity of
the site for providing proper and expeditious medical care during the execution of the works.
Safety Personnel shall be assigned to carry our first aid treatment prior to shifting the patient
to hospital if necessary and shall be available at all times within the vicinity of the working
site.
An emergency vehicle equipped with mobile phone will be assigned for carrying the
sick/injured to the hospital. The vehicle driver shall have the same communication to receive
any emergency call relative to Safety matters and shall be available always within the vicinity
of the working site. The SM will immediately report to the Consultant the particulars of any
accident or any unusual or unforeseen occurrences on the site, whether or not they are likely
to affect the progress of works.
Page 8 of 9
PROJECT: TOYOTA HEADQUARTERS PP
THQ-LBL-MDS-005-0 (Concreting Works)
______________________________________________________________
The Safety Officer shall identify the hazard, the people who might be harmed, evaluate the
risks and decide on precautions, in accordance with the safety plan.
In order to evaluate the hazard assessment, the Contractor shall conduct inspections of all
workplaces to determine the need for PPE and help in selecting the proper PPE for each
tasks performed. Each survey will document the workplace surveyed, date of survey, the
identified source of hazards and precautions to be implemented.
The Contractor ensures that the PPE program is implemented in the work area; defective or
damaged equipment are to be immediately replaced; workers must attend required training
sessions and records on hazard assessments are maintained.
The safety program is to be regularly reviewed, evaluated and if necessary, updated
according to site and working conditions.
Page 9 of 9