Plant Power and Water Utility Company for Jubail and Yanbu

Client MARAFIQ
Replacement of seven drum screens in sea water cooling plant 1 and LCP's in sea water cooling Plant
Project
2
Contractor Global Environment Management services LLC. (REVIVA)
PO 7200043000
Week From To
Project One Week Look a Head Plan 24 17-Jun-23 23-Jun-23
Electrical and Instrumentation
Sl.No. Activities From To Status Remarks
SWC - 2
1 Removal of existing field cables for SWC-2 (MOV 2-1 cables) 18-Jun-23 19-Jun-23
2 Laying New cables for SWC-2 from DS 2-1 to DS 2-7 08-Jun-23 25-Jun-23 Ongoing
3 Level sensor calibration (2-3, 2-4, 2-5, 2-6 , 2-7) 17-Jun-23 19-Jun-23
4 Drum Screen level sensor installation for Drum Screen 2-2 to 2-7. 20-Jun-23 21-Jun-23
5 DPS pressure gauge and switch calibration Drum Screen 2-1 21-Jun-23 22-Jun-23
SWC-1
1 LOP Stanchion Installation in SWC-01 (Drum Screen 1-4) 18-Jun-23 19-Jun-23
2 LCP 1-1 alingment 17-Jun-23 18-Jun-23
3 MCC cubical Installation for Drum Screen 1-4. 19-Jun-23 21-Jun-23

Civil Works
SWC-1 From To
1 Rebar and Formwork installation for LOP@ (1-7),PT@(1-1 to 1-7) & Wash water pump area 05-Jun-23 18-Jun-23
4 Concrete Pouring for LOP@(1-7),PT@(1-1 to 1-7) & Wash water pump area 18-Jun-23 19-Jun-23
5 Epoxy removal at left & right chamber (1-4) - - Wating for MFQ approval for epoxy removal drawing
6 Dewatering(Drum screen 1-3) 10-Jun-23 19-Jun-23 Started 10 June Night shift
7 Leak arrest(Drum screen 1-3) 20-Jun-23 22-Jun-23
8 Chipping for anti rotaion lock system for drum scrren -1-2 and 1-3. 19-Jun-23 22-Jun-23
SWC-2 From To
1 Formwork installation for LOP@ (2-1 to 2-7),PT @ Wash water pump area 05-Jun-23 18-Jun-23 Only Inspection balance
2 Formwork installation for LCP @ (2-1) 12-Jun-23 18-Jun-23 Only Inspection balance
3 Rebar installation for LCP @ (2-1) 13-Jun-23 18-Jun-23 Only Inspection balance
4 Concrete pouring for LCP @ (2-1) 18-Jun-23 19-Jun-23
5 Concrete Pouring for LOP@(2-1 to 2-7),PT@Wash water pump area 18-Jun-23 19-Jun-23

Mechanical and Piping Works


SWC -1 From To
1 Installation of rims / Intermediate beams / extremity circle/ gear segmaint (DS 1-4) 16-Jun-23 22-Jun-23
2 Schaffolding for platform dismantling DS 1-3 20-Jun-23 21-Jun-23
3 Dismantling of DS 1-3 platform 22-Jun-23 24-Jun-23