ABB Installation and Maintenance
ABB Installation and Maintenance
ABB Installation and Maintenance
Project: Cartagena
Project no.: L 002331
Original issue
NOTICE
The information in this document is subject to change without notice and should not be construed as a commitment by ABB AB,
Machines. ABB AB, Machines assumes no responsibility for any errors that may appear in this document.
In no event shall ABB be liable for direct, indirect, special, incidental or consequential damages of any kind arising from the use
of this document, nor shall ABB be liable for incidential or consequential damages arising from the use of any software or
hardware described in this document.
This document and parts thereof must not be reproduced or copied without ABB AB, Machines’s written permission, and the
contents thereof must not be imparted to a third party nor be used for any unauthorized purpose.
Chapter 1 - Introduction
1.1 General information.................................................................................................... 7
1.1.1 Contact information ................................................................................... 7
1.2 Safety .......................................................................................................................... 7
1.2.1 General....................................................................................................... 7
1.2.2 Emergency precaution ............................................................................... 8
1.2.3 Safety symbols........................................................................................... 9
1.2.3.1 Safety symbols in the manual .............................................9
1.2.3.2 Safety symbols on the generator .........................................9
1.3 Site conditions........................................................................................................... 10
1.4 Prerequisites.............................................................................................................. 10
1.5 Contraindications ...................................................................................................... 11
1.6 Control panel (not ABB scope of supply) ................................................................ 11
1.7 Manual system and related documents ..................................................................... 12
Chapter 3 - Alignment
3.1 Preparations for generator installation...................................................................... 27
3.2 Rough levelling of generator after erection .............................................................. 28
3.2.1 Rough alignment...................................................................................... 28
Skeleton No. 3BSM005469, Rev. - EN -
Chapter 5 - Commissioning
5.1 Check of mechanical installation.............................................................................. 38
5.2 Check function of jacking oil system
(the main oil supply need to be switched on) ........................................................... 39
5.3 Check of electrical installation ................................................................................. 40
5.4 Electrical checks ....................................................................................................... 41
5.5 Before the first start attempt ..................................................................................... 46
5.6 The first start attempts .............................................................................................. 46
5.6.1 Start interlocking...................................................................................... 46
5.7 Checks during running of the generator ................................................................... 46
5.7.1 Normal vibration levels ........................................................................... 46
5.7.1.1 Bearing housings ...............................................................47
5.7.1.2 Structural vibrations ..........................................................47
5.7.1.3 Shaft vibrations .................................................................47
5.7.2 Temperature levels................................................................................... 48
5.8 Check list .................................................................................................................. 48
5.8.1 Page 1....................................................................................................... 49
5.8.2 Page 2....................................................................................................... 50
5.8.3 Page 3....................................................................................................... 51
Skeleton No. 3BSM005469, Rev. - EN -
Chapter 6 - Operation
6.1 Start up procedure..................................................................................................... 52
6.2 Continuous supervision............................................................................................. 53
Chapter 7 - Maintenance
7.1 Preventive maintenance ............................................................................................ 56
7.2 Before all maintenance work .................................................................................... 56
7.3 After all maintenance work....................................................................................... 57
7.4 Recommended maintenance program....................................................................... 58
7.4.1 Generator ................................................................................................. 59
7.4.2 Stator........................................................................................................ 60
7.4.3 Stator terminal.......................................................................................... 61
7.4.4 Rotor ........................................................................................................ 62
7.4.5 Bearings ................................................................................................... 64
7.4.6 PMG (Permanent magnetic generator) .................................................... 65
7.4.7 Exciter and Rectifier ............................................................................... 66
7.4.8 Rotor earth brush ..................................................................................... 67
7.4.9 Cooling system ........................................................................................ 68
7.5 Main rotor coil turn insulation (voltage drop test).................................................... 69
7.6 Fault finding.............................................................................................................. 69
7.6.1 Diode fault ............................................................................................... 70
7.6.2 Altering the firing voltage........................................................................ 72
7.6.3 Lubrication............................................................................................... 73
7.6.4 High temperature in bearing .................................................................... 75
7.6.4.1 Trouble shooting 1 ............................................................75
7.6.4.2 Trouble shooting 2 ............................................................76
7.6.4.3 Trouble shooting 3 ............................................................77
7.6.5 High winding and/or air temperature....................................................... 78
7.6.5.1 Trouble shooting ...............................................................78
7.6.6 Water leakage detector............................................................................. 79
7.6.6.1 Trouble shooting ...............................................................79
Chapter 1 Introduction
1.2 Safety
1.2.1 General
The machine is manufactured and intended for use only as described by this manual.
Modification, alteration, or lack of maintenance as described in the manual, may
adversely affect the safety and efficacy of this machine. The manufacturer is not
responsible for malfunctions that comprise machine safety as a result of alteration, use of
non ABB replacements parts, neglect or misuse.
The generator may not be used in such a way as to exceed the values that are described in the
technical specification and the information on the nameplate. If the generator will be used for
anything else please contact ABB.
Replacements parts may vary from those shown in this manual. Should you have questions on
those parts please contact ABB AB, Machines.
Skeleton No. 3BSM005470, EN, Rev. G
The actual appearance of the machine may vary from the illustration in this manual.
Should pre-owned ABB AB equipment be purchased and reconditioned, the equipment should
not be used until testing and analysis demonstrate that the equipment meets the original or
upgraded specifications.
The use of solvents as cleaning agents, the use of lubricants and handling glycol can involve
health and/or safety hazards. The recommended precautions and procedures of the manufacturer
should be followed.
Lifting of equipment/parts must be performed by trained personnel, and with lifting equipment
approved for the load.
Be aware of that the machine sound level is louder than 70dBA, use ear protectors when
entering the machine room during operation.
If part of the jacking oil equipment fails and a person is exposed to a “cutting stream” of oil and
the oil penetrates the skin, it is important to seek medical advice immediately.
The machine operator must follow local requirements for use of personal protective equipment.
If no local requirements, shall the requirements below for maintenance personnel be followed.
Make sure before maintenance work, together with factory electrical responsibility manager,
that the machine is electrical dead, grounded and mechanical blocked. Permit to work system
should be applied.
Maintenance personnel shall wear personal protective equipment such as safety helmet, safety
glasses, flame resistance coverall, gloves, safety shoes and ear protectors.
Use safe ladders and scaffolds, safe step when climbing the machine. A safety harness shall be
used when working on heights, local regulations about working on heights shall be followed.
There are very strong magnetic forces between the PMG rotor and stator. Keep a safe distance
from the PMG stator housing to avoid damage to digital equipment i.e. wrist watch and credit
cards. People with pacemaker shall not be in the vicinity of the PMG, keep a safe distance on
approx 10m.
Be aware that edges, lifting ears etc. might cause a risk of injury depending of the actual
mounting of the machine at site. Parts on the machine causing a potential injury risk are
highlighted with black/yellow tape.
1.4 Prerequisites
1.5 Contraindications
The machine is not designed, sold or intended for any use except as indicated above.
Furthermore, it is not intended to be used outside of the machine specifications or limitations.
The machine must be in good working order. For order specific information refer to the
Technical Specification (included in binder “Users Manual”).
Project: Cartagena
Project number: L 002331
Serial number 8268 483, 8268 484,
8268 485
Users Manual
for the generator
General ABB AB, Machines
AMS Synchronous generator
Technical Specification
Circuit Diagrams
Certificate
Skeleton No. 3BSM005470, EN, Rev. G
Anchoring point
Figure 2-1
Anchor points during transport on lorry. Beware of area that is dotted in accordance with Figure
2-1 on page 14.
Skeleton No. 3BSM005471, EN, Rev. H
Anchor point
Figure 2-2
Anchor points during transport on lorry or by vessel, located on both sides of the crate.
Skeleton No. 3BSM005471, EN, Rev. H
0.86xB
60o
Figure 2-3
2.1.6 Unpacking
Place the generator so that it is out of the way of any other goods handling and on a flat,
Skeleton No. 3BSM005471, EN, Rev. H
vibration-free surface.
Remove top and sides of the wooden crate.
When the crating has been removed a check should be made to see that the generator is not
damaged and that all accessories are included. Tick off the accessories on the packing list which
is enclosed. Report immediately to the supplier if there is any damage, suspected damage or if
accessories are missing.
When lifting the machine, with the cooler top delivered separate, ensure to have accurate angle
on lifting slings, as shown in Figure 2-4 on page 17. (Otherwise there will be risk of damaging
the upper sheet metal housing).
> 60o
Figure 2-4
Skeleton No. 3BSM005471, EN, Rev. H
When lifting the machine, with the cooler top delivered separate, ensure to have accurate angle
on lifting slings, as shown in Figure 2-5. (Otherwise there will be risk of damaging the upper
sheet metal housing).
60o 60o
Figure 2-5
When lifting the cooling top see Figure 2-6 and also the instruction “Mounting of cooler top”
included in the binder “Users Manual”
Skeleton No. 3BSM005471, EN, Rev. H
NOTE: When the cooler needs to be lifted after that the generator has been in operation,
the cooler must be emptied of water before lifting.
Figure 2-6
Skeleton No. 3BSM005471, EN, Rev. H
Figure 2-7 on page 20 shows an example how the main terminal box should be lifted. As an
option a smaller box could be included in the scope of supply, instead of as shown in Figure 2-7
on page 20. Then it will just be supplied with two lifting loops on top.
Not included
Figure 2-7
with a tarpaulin on the top extending at least 1 meter out from the crate to avoid direct rain
on the crate.
• The crate should be kept dry, protected from rain and moisture.
Before commissioning the following items should be carried out:
• Visual external inspection of bearings and entering shaft
• Check insulation resistance in accordance with section 5.4
• Corrosion preventive oil should be filled in the bearings, according to section 3.1 on page
27, once every 12 month. Rotation of the rotor is not required.
Before commissioning the following items should be carried out:
• Visual external inspection of bearings and entering shaft.
• Visual inspection of exciter.
The vertical positioning of the generator is made with hydraulic jacks (optional equipment)
placed as tight as possible to the two footplates in the middle and tight to the two outer
footplates as shown in Figure 2-8 on page 24 and Figure 2-9 on page 25. As alternative if
vertical adjustment screws are included the vertical positioning of the generator is made with
them.
ABB AB, Machines´s delivery includes shims with 1 mm thickness, placed as shown in Figure
2-10 on page 25. Shims needed with other thicknesses are to be provided by the customer.
Bracket plates (optional equipment), with adjusting screws for horizontal positioning of the
generator are placed at its corners, as shown in Figure 2-8 on page 24.
The bracket plate is to be placed against the foundation edge and the bracket is to be tied down
by using an expansion bolt or welding.
Hydraulic jacks
Guiding pin Vertical adjustment parallel connected
only on D-end screws, if included
CL
Guiding pin
only on D-end
Bracket w.
Skeleton No. 3BSM005471, EN, Rev. H
adj. screw
Figure 2-8
Hose
Pump
Hydraulic jack,
recommended NIKE CLF 220-13
Figure 2-9
Footplate in foundation
Figure 2-10
Skeleton No. 3BSM005471, EN, Rev. H
• The transport locking device is screwed into the shaft on the drive end side of the
generator. The transport locking device consists of a beam, two long bolts and a plate
which lock the rotor against axial movements and rotation. See Figure 2-11 on page 26.
• Remove the screws which are screwed into the shaft. Observe the plate between the beam
and the shaft.
• Loosen the beam from the bolts and remove the bolts from the bearing ring. (Save the
locking device for future needs).
Figure 2-11
Skeleton No. 3BSM005471, EN, Rev. H
Chapter 3 Alignment
Introduction
Good planning and preparation result in fast, simple and correct installation. Safe running
conditions with maximum of accessibility are assured.
Figure 3-1.
A simple lever is needed for turning the rotor. While turning the rotor, oil must be continuously
poured into the funnels at both end of the generator.
Skeleton No. 3BSM005472, EN, Rev. G
• When jacking-oil is used, the rotor will be raised and for alignment this must be
considered.
• If the generator is to be erected outdoors, sun and rain protection must be provided to
eliminate measuring errors.
NOTE: When the surroundings are neither heated nor dry, heating equipment must be
provided.
Axially
Lift the generator onto the foundation plates as close to the actual position as possible.
NOTE: The rotor is “NOT” in the magnetic neutral position when the generator is
delivered.
The rotor is in the magnetic neutral position when the dimension B and C is fulfilled, see Figure
3-2 on page 28. Read the correct distance in the Inspection and Test record “Magnetic neutral
position”, included in the binder “Users Manual”.
to D-end
to N-end
Figure 3-2.
Skeleton No. 3BSM005472, EN, Rev. G
NOTE: It is important that the rotor is “IN” the magnetic neutral position when the
generator is in operation.
3.3 Grouting
When the generator has been properly aligned, its base elements are attached to the foundation
by grouting. Use only non-shrinking concrete for grouting to ensure proper adhesion between
the base frame and grouting. Make sure that the grouting fills properly the whole space around
and under the base element. Do not use a vibrator in order to avoid any disturbance in the
alignment.
After the grouting has set (cured), adjust vertically to the final elevation by putting shims
between the base frame and the base element. Check also the other alignments of the generator
and adjust, if necessary.
Non-shrink grout is recommended for the best results. For shaping and grouting, the
manufacturers instructions to be followed.
Skeleton No. 3BSM005472, EN, Rev. G
Figure 3-3.
The tolerances given by the coupling manufacturers must not be used in deciding how accurate
the alignment should be because these tolerances indicate what the coupling can accept.
Excessive tolerances will give rise to vibrations, bearing damage etc. and therefore should
tolerances as narrow as recommended above be aimed at.
Finally check the axial distance between the two coupling halves.
Skeleton No. 3BSM005472, EN, Rev. G
Air to water
If the cooler housing is delivered separately the following action needs to be taken:
1. Remove the transport roof on the generator.
2. Lift the cooler housing over the generator. Connect the hoses for the water leakage
detector to the cooler drain, according to drawing 3BSM 001483-A .
3. Lower the cooler housing until it’s almost resting on the generator (if possible), this will
make it easier to adjust the housing to the generator. After all the bolts have been put in
place lower the housing completely and tighten the bolts.
4. Connect the cooler pipes.
– The cooling water pipes shall be laid so that they do not obstruct service and
maintenance. The water pipes should be designed so that only a short part needs to be
dismantled to allow cooler removal.
– The piping should be designed so that no stress is applied to the cooler flanges.
Before the pipes are connected to the cooler they should be properly cleaned.
– If a cooler element is equipped with an over pressure safety valve, the safety valve
shall be connected via a hose/pipe to a reservoir. This to prevent equipment and
personnel to be exposed to the cooling medium in case of an over pressure in the
cooler.
The return pipes should have an incline of 40-50 mm/m in order to guarantee trouble-free oil
circulation. The oil pipes should be designed so that they do not obstruct service and
maintenance. The pipes should be designed so that no stress is applied to the flanges on the
generator.
Jacking oil
The connection point, required flow and pressure for jacking oil is marked on the outline
drawing.
Jacking oil motor should be protected from overload and the operation supervised for alarm and
trip handling of the main generator.
NOTE: When loosen the plug or the jacking oil connection, be careful not to remove the
bulkhead.
Use two wrenches, one to loose the plug/jacking oil connection and one to hold the
bulkhead in place. If the bulkhead will be moved the jacking oil connection inside
the bearing housing will fall down to the bottom of the bearing housing.
Bulkhead for connection of jacking oil
Hose
Plug
Figure 4-1
For required oil flow and pressure see outline drawing. The oil pipes should be carefully flushed
before they are connected to the generator.
To be able to transport the machine the main terminal box for the high voltage connection is
delivered separately and must be fitted at site.
The terminal should be supported so that no stress is applied to the generator.
1. Remove the protection cover fitted over the generator bushings.
2. Align the main terminal box by shimming so that no stress will be introduced to the
generator bushings when they are connected to the busbars in the main terminal box.
3. The joint between the main terminal box and the generator should be tightened according
to instruction 3BSM 001263R0001, included in the binder “Users manual”.
4. Before the high voltage cables are connected to the main terminal box the insulation
resistance (megged) should be checked. Check both the generator insulation resistance
(stator winding resistance) and the insulation resistance of the main terminal box
according to instruction in Section 5.4. For recommendations how to clean current-
carrying busbars, see instruction 3BSM 001263R0001, included in the binder “Users
manual”.
5. The joint between the main terminal box and the generator should be insulated according
to instruction 3BSM 004941, included in the binder “Users manual”.
6. The main terminal box shall be secured to the foundation after installation and alignment.
Skeleton No. 3BSM005473, EN, Rev. H
Incomming cables/busbars
Figure 4-2
Skeleton No. 3BSM005473, EN, Rev. H
NOTE: Space heaters in exciter and stator should be connected as soon as possible after
unpacking. If the permanent supply is not available a temporary supply should be
connected.
4.2.3 Connection of high voltage cables
The fasteners for connecting the high voltage bus bars shall be arranged as in document 3BSM
001263R0001, tightening torque shall be adapted to the fasteners size.
The high-voltage cables are connected according to the terminal markings. Striping, splicing
and insulation of the high voltage cables should be performed according to the instructions from
the cable manufacturer.
The high voltage cables are connected according to the terminal markings. The stator insulation
resistance should be checked before final connection of the cables.
The main terminal box cable gland arrangement must fulfill the IP-class requirements for the
order.
4.2.4 Earth connection
The earth lead shall be connected either inside or outside the terminal box and to both sides of
the generator frame.
Skeleton No. 3BSM005473, EN, Rev. H
For connection points on the generator see outline drawing (included in binder “Users manual”).
The jacking oil pipes shall be shielded to prevent personnel from being exposed to high pressure
oil in case of a leak in the jacking oil pipes.
Skeleton No. 3BSM005473, EN, Rev. H
3m 3m Safety area
3m
Figure 4-3
Skeleton No. 3BSM005473, EN, Rev. H
Chapter 5 Commissioning
On the commissioning personnel lies a great responsibility for a safe and trouble free operation
of the generator during its lifetime.
Commissioning should only be made by qualified personal.
The following are tests and checks on the generator that are recommended by the manufacturer.
If other tests are to be performed, the manufacturer should be consulted.
Bearing insulation
• “Megging” of bearings should be performed before the generator is coupled to the
turbine. See section 5.4 on page 41.
Other checks
• Open the generator at both ends and check that no loose parts are present inside the
generator. Check that no parts have come loose during transportation and that the air-gap is
free.
• If possible, turn the rotor and make sure that the rotor turns freely and that no abnormal
sound can be heard. See section 3.1 on page 27.
• Check the airgap between the exciter stator and rotor, see the test record “Air gap
measurement” (included in binder “Users manual”).
• Check the air gap between the PMG stator and rotor, see the test record “Air gap
measurement” (included in binder “Users manual”).
NOTE: The lubrication system must be commissioned and running before the rotor is
turned.
• Check the assembly of the main terminal box and cooling system.
• Check pressure and flow for oil and cooling system according to the technical
specification (included in binder “Users manual”).
• If the cooler is not designed for glycol, don’t add glycol into the cooling water. Glycol
decrease cooling capacity.
The jacking oil pump shall be started before the generator is started. The time between starting
of jacking oil pump and generator start must be sufficient to allow for proper pressure build up.
When the high pressure oil (jacking oil) is supplied by other means the time needed for
sufficient pressure build up needs to be checked during commissioning before first start of the
generator. To establish the time needed before start up perform the following procedure:
1. Apply a pressure gauge in the system as close to the bearings as possible.
2. Measure the time from starting of the pump until a stabilized pressure is read on the
pressure gauge (normally the pressure peaks before the rotor is lifted and then stabilizes on
a lower value).
3. Add margin to cover possible longer pressure build up time due to drained pipes if this is a
possible scenario.
Operation modes for the jacking oil system:
Operation modes Normal Lubrication Jacking oil pump
1) Start for rotate the generator On 20 min On X*)
before start before start
2) Speed on generator < 200 rpm On On
3) Speed on generator > 200 rpm On Off
4) At stop of generator, 250 rpm On On
Skeleton No. 3BSM005474, EN, Rev. J
5) After stop of generator 0 rpm Off 20 min after stop On from 250 rpm-0 rpm
Figure 5-2
Insulation resistance is acceptable if the megger value is more than 1 Mohm.
Skeleton No. 3BSM005474, EN, Rev. J
Conversion factor, k
100
50
10
0.5
(0.25)-
0.1
0.05
o
-10 0 10 20 30 40 50 60 70 80 90 100 ( C)
Winding temperature
14 32 50 68 86 104 122 140 158 176 194 212 (oF) when meggering
R = Megger-value at a specific temperature
R40 = Equivalent insulation resistance at 40oC
R40 = k x R Example:
R = 30 M: measured at 20oC
k = 0.25
R40 = 0.25x30=7.5 M:
Recommended minimum insulation resistance at 40oC must exceed the following value
Skeleton No. 3BSM005474, EN, Rev. J
Megging should be performed in the terminal box and from the synchronizing circuit breaker
(when the high voltage cables has been connected).
If the insulation resistance is low when measuring from the synchronizing circuit breaker,
disconnect high voltage cables and perform the megging direct on the terminals in the terminal
box.
A 5000 Volt DC megger should be used. Reading should be made after 1 minute.
NOTE: If 1000V DC megger is used the rectifier has to be short circuit before measuring.
1 2 3 Time (Days)
Figure 5-3
During the drying process it is important that the temperature does not increase too rapidly and
that the final temperature is not too high. The temperature increase may not exceed 5 oC per
hour and the final temperature may not exceed 100 oC. The temperature must be watched
carefully throughout the drying process and the insulation resistance measured at intervals.
When a steady value for the insulation resistance has been achieved, the winding is dry.
• Set the alarm level at 2 times the normal level during operation
• Set the trip level at 4 times the normal level during operation
The alarm and trip levels should in no case be above what is given in the tables below.
Example: The normal vibration level during operation at site is 1.5 mm/s. The alarm level
should then be set at 3 mm/s, and the trip level at 6 mm/s.
Vertical/horizontal Axial
mm/s in/sec micron mills mm/s in/sec micron mills
rms rms p-p p-p rms rms p-p p-p
Testroom
1.8 0.07 32.4 1.3 2.3 0.9 41.4 1.63
(typical)
Alarm 4.5 0.18 81.0 3.2 7.0 0.28 126.0 5.0
Trip 8.0 0.31 144.1 5.7 15.0 0.59 270.1 10.6
Table 5-1: Acceptable vibration levels for bearing housings. The values are valid for all speeds.
(Measured frequency range 10-1000 Hz)
Vertical/horizontal Axial
mm/s in/sec micron mills mm/s in/sec micron mills
rms rms p-p p-p rms rms p-p p-p
Testroom
4.5 0.18 81.0 3.2 4.5 0.18 81.0 3.2
(typical)
Alarm 7.0 0.28 126.0 5.0 11.0 0.43 198.1 7.8
Trip 15.0 0.59 270.1 10.6 20.0 0.79 360.1 14.2
Table 5-2: Acceptable vibration levels for supporting structures. The values are valid for all
speeds. (Measured frequency range 10-1000 Hz)
Vertical/horizontal
mm/s in/sec micron mills
rms rms p-p p-p
Testroom
Skeleton No. 3BSM005474, EN, Rev. J
- - 50.8 2.0
(typical)
Alarm - - 76.2 3.0
Trip - - 101.6 4.0
Table 5-3: Acceptable vibration levels for shaft vibrations. The values are valid for all speeds.
5.8.1 Page 1
Customer: Name and company of responsible commissioning engineer:
Site name:
Serial number:
Order number: Date:
Generator data
Output: kVA Power factor: Voltage: V
Frequency: Hz Speed: r/min Current: A
Excitation: V A Oil quality:
Skeleton No. 3BSM005474, EN, Rev. J
5.8.2 Page 2
Customer: Name and company of responsible commissioning engineer:
Site name:
Serial number:
Order number: Date:
5.8.3 Page 3
Customer: Name and company of responsible commissioning engineer:
Site name:
Serial number:
Order number: Date:
Chapter 6 Operation
Safety precaution
Read and follow the information in the following sections:
• Section 1.2, safety precautions.
• Section 1.4, prerequisites.
Chapter 7 Maintenance
Maintenance
Level 1 (L1) Level 2 (L2) Level 3 (L3) Level 4 (L4)
program
Weight capacity
N/A N/A 2 000 kg *
required
* AMS 1000 - 1120 The required weight to lift the rotor = rotor weight on outline + 2 000 kg.
* AMS 1250 - 1250A The required weight to lift the rotor = rotor weight on outline + 2 600 kg.
Preparation for Open inspection covers. Open inspection covers. Disassembly covers. Open bearings.
inspection Disassembly PMG stator. Removal rotor
Open bearings. and exciter.
Open water coolers. Open water coolers.
Instrument/ Megger, stator. Megger, stator Megger, stator.
Tools Megger, rotor. Megger, rotor Megger, rotor.
Fibre-optic or video Rotor removal equipment.
borescope. Torque wrench.
Oscilloscope/Test Oscilloscope/Test
equipment. equipment.
Parts/ Bearing liners, Acc. to L1 and suggestion Acc. to L2 and suggestion Acc. to L3 and suggestion
Spare parts Brushes, from inspection L1. from inspection L1 and from inspection L1, L2
Air-lock filter (bearing), Silicon tape. L2. and L3.
Control pulse unit, Water cooler. Rotor kit.
Thyristors, Diodes. Rectifier kit.
Other order specific Bearing kit.
parts. Gaskets.
Expected Approx. 1 day. Approx. 2 days. Approx. 5 days. Approx. 10 days.
downtime
Interval 10 20 30 40 50 60 70 80
Hours x 1000
Program L1 L2 L1 L3 L1 L2 L1 L4
Timing of the inspection and overhauls are largely determined by the number of operating hours, the mode of operation and
the number of starts of the generator. Local condition has to be considered.
Skeleton No. 3BSM005477, EN, Rev. H
The maintenance intervals shall be co-ordinated for the generator, in a suitable way.
7.4.1 Generator
Location L1 L2 L3 L4 Activity Approved
General cross-section
AMS machine (actual
design acc. to outline
included in binder
“Users Manual”.)
Inspection covers
on both ND- and
D-end sides.
Skeleton No. 3BSM005477, EN, Rev. H
Figure 7-1.
7.4.2 Stator
Location L1 L2 L3 L4 Activity Approved
Air cover
Stator coils
Bracing rope
Pressure finger
Skeleton No. 3BSM005477, EN, Rev. H
Figure 7-2.
Example of a terminal box for a generator (actual design acc. to outline for terminal box).
See drawing in Users manual XYK 210780-GCR.
Skeleton No. 3BSM005477, EN, Rev. H
7.4.4 Rotor
Location L1 L2 L3 L4 Activity Approved
BY BY
Location L1 L2 L3 L4 Activity
ABB Cust.
4. Pole shoes X X X X 1. Check pole shoes for discoloration.
5. Pole bolts X 1. Inspect by knocking on bolt head.
If pole bolts are loose or corroded, ABB has to be
contacted.
6. Fan X X 1. Inspect fan blades and weldings.
7. Balancing X X 1. Inspect balancing weights and fastening details.
8. Air gap X 1. Check air gap after assembling of machine.
7.4.5 Bearings
Location L1 L2 L3 L4 Activity Approved
Air-lock seals
Shaft seal
Bearing liners
Bearing shell
Skeleton No. 3BSM005477, EN, Rev. H
Figure 7-5.
PMG stator
PMG rotor
Permanent magnets
Skeleton No. 3BSM005477, EN, Rev. H
Figure 7-6.
Exciter stator
Exciter rotor
Rectifier
Figure 7-7.
Shaft
+ +
+ + Brush holder
+ +
+ +
+
Brush
Figure 7-8.
Skeleton No. 3BSM005477, EN, Rev. H
*) If bad efficiency clean the heat exchanger by using brush or chemical rinsing.
Tube
Tube plate
Water box
Gasket
Figure 7-9.
If temperature detectors show normal temperature, usually no additional maintenance to
supervision inspection is required for the cooling system. If the coolers have to be cleaned, find
instruction included in binder “Users Manual”.
If temperature detectors show an abnormal temperature, or close to alarm level, in winding or
cooling air a check of the cooling system has to be made. If the coolers have to be cleaned, find
instructions included in binder “Users Manual”.
To empty the water leakage detector of water, open the ball valve at the bottom of leakage
detector, see drawing included in the binder “User Manual”.
The test is carried out by applying an AC-voltage over the entire field winding and measuring
the current and the voltage drop across the total winding as well as each single coil, see Figure
7-10.
The applied voltage should be 230 V or 400 V 50 Hz / 208 or 480 V 60 Hz depending on the
rated frequency of the machine.
+ 'U1
The voltage over a single coil ('U) should
'U
U
'U
'U4
3
-
Figure 7-10
• Vibration protection.
Supply
Exciter
voltage osc side
Uac
|600:
+
Figure 7-11
• Increase the voltage and check with an oscilloscope the triggering voltage level of the
firing unit and the thyristors as shown in figure 7-12 chart 2 and 3.
• Decrease the voltage to a level under the firing units trigger level, see figure 7-12
chart 1 and measure over each diode separately. A shorted diode will show zero (0)
volt on the oscilloscope.
Skeleton No. 3BSM005477, EN, Rev. H
Ûac
3. Û > Triggering voltage level Ûac > UT
UT
Ûac
Figure 7-12
Skeleton No. 3BSM005477, EN, Rev. H
NOTE: Before altering the firing level, write down the original connections for firing
level, thyristors, etc.
Thyristor B Thyristor A
K K-G K K-G +
150V
225V
300V
450V
600V
750V
900V
1.1kV
1.3kV
1.5kV
x Drawing number
x
Seriel number
Figure 7-13
Skeleton No. 3BSM005477, EN, Rev. H
7.6.3 Lubrication
The generators are provided with sleeve bearings with an almost unlimited service life provided
that the lubrication functions continuously and that the oil is changed at suitable intervals.
Temperature
To enable the bearing temperature to stabilize at a normal level, the correct amount or flow of
oil is required. The normal bearing temperature is 65 - 85 oC.
Oil qualities
Unless otherwise stated on ABB AB, Machines drawing “Outline synchronous generator”
included in the binder “Users Manual”, the bearings are designed for any of the following oil
qualities:
Klüber: Lamora 68
Mobil: D. T. E. 26
Optimol: Ultra 5045
Shell: Tellus Oil 68
Texaco: Rando Oil HD C 68
Check with
Unsuitable oil Change oil
ABB AB,
quality Machines´s quality
recommendation
Damaged shaft
Repair the seals
seals
Repair/replace
Air-lock seal the air-lock seal
out of action and check the
air filters
Oil leaks
Too high oil
flow Correct oil flow
Incorrect
Problem in oil
inclination of
flow return
the return pipe?
Skeleton No. 3BSM005477, EN, Rev. H
Faulty
Faulty sensor
instrument
Replace the
Leaking cooler cooler
8.1 General
The manufacturing process of the machine is carried out in accordance with the Environmental
Management System ISO 14001.
This instruction concerns the disposal and recycling of Large AC-machines. The machines are
designed in a way that it is easy to separate the different components and types of material from
each other, making it easier to recycle.
NOTE: The methods are described in a very general way. All instructions are to be
performed by personnel which is trained and skilled for the procedure.
Dismantling the machine is done by simply separating all the components of the machine. Since
the machine mainly is assembled with screws and nuts, it is rather simple to carry out the
dismantling. When the machine has been dismantled into its different components, the different
components has to be separated and grouped together dependent upon the different types of
material.
• Encapsulation
• Side plates
• Roof
The following components are separated into one group for cast iron:
• Bearing housing
• Bearing spheres.
8.3.7 Aluminium
The following components are separated into one group for aluminium:
• Coil supports of the rotor
• Heat sinks for thyristors and diodes in the exciter.
8.3.8 Copper
Copper is mostly integrated in the actual components and require some effort in order to be
separated. There exist some special tools for making the separation but normally wedges, large
hammers, gas burners and manpower is used.
The following components are separated into one group for copper:
• Stator coils
The copper is integrated in the stator and is glued to the stator by use of an impregnation
resin. Thereafter the copper in the stator is surrounded by several mm of micabased
insulation. The separation of copper from the insulation is done by the method granulation,
which is used by larger recycling companies. The granulation method cuts the copper into
pieces and the copper is then separated from the insulation by a mechanical process. This
can also be done by manpower using hammer and wedges. The amount of copper in the
stator is large.
• Stator connection
The copper is integrated within the stator winding. It may be cut off and separated from its
insulation by granulation or by manpower.
• Rotor coils in the machines rotor
This is clean copper mixed together with layers of insulation. It may be separated from the
rotor by loosening the pole bolts of the rotor body and by removing the coil supports. This
copper is of high quality and value, and the amount is large. The copper from the rotor
coils is to be kept separate from all insulated copper.
• Rotor connections in the machines rotor
This is cable copper that may be separated from the rotor by a gas burner combined with
manpower.
It might come off easier if first heating up the rotor until the epoxy resin within the rotor
shaft is carbonised.
Skeleton No. 3BSM005478, EN, Rev. G
It might come of easier if first heating up the stator until the impregnation resin is
carbonized.
• Rotor coils in the exciter rotor
This is enamelled copper that is glued together by impregnation resin. It may be separated
from the exciter by manpower or using special equipment.
It might come of easier if first heating up the rotor until the impregnation resin is
carbonised.
NOTE: Make sure the power plant is adapted for this kind of fuel and have the proper
types of filter etc. in order to prevent gases and dust to enter the environment.
Skeleton No. 3BSM005478, EN, Rev. G