Proyek -
Lokasi Ponjong
No Pekerjaan Koef Vol Sat Harga Satuan Total Upah Total upah + Bahan
I Pekerjaan Persiapan 1.77%
1 Uitzet + Bowplank Lt.01 120.00 m2 Rp 17,000.00 Rp 2,040,000.00
Kaso\Glgugu 0.007 0.84 m3 Rp 3,800,000.00 Rp 3,192,000.00
Papan 1 120.00 lbr Rp 20,000.00 Rp 2,400,000.00
Paku 0.1 12.00 kg Rp 20,000.00 Rp 240,000.00
Benang 0.1 12.00 roll Rp 3,000.00 Rp 36,000.00
2 Uitzet + Bowplank Lt.02 0.00 m2 Rp 17,000.00 Rp -
Kaso\Glgugu 0.007 0.00 m3 Rp 3,500,000.00 Rp -
Papan 1 0.00 lbr Rp 20,000.00 Rp -
Paku 0.1 0.00 kg Rp 20,000.00 Rp -
Benang 0.1 0.00 roll Rp 3,000,000.00 Rp -
II Pekerjaan Galian & Urug Bawah Pondasi 3.02%
1 Galian Tanah Pondasi Foot Plate 56.00 m3 Rp 65,000.00 Rp 3,640,000.00
2 Galian Tanah Pondasi Stall m3 Rp 50,000.00 Rp -
3 Urug Pasir Bawah Pondasi 4.60 m3 Rp 11,000.00 Rp 50,600.00
Urug Pasir Bawah Pondasi 1 4.60 m3 Rp 250,000.00 Rp 1,150,000.00
4 Urug Tanah Peil Lantai 60.00 m3 Rp 10,000.00 Rp 600,000.00
(Tanah Urug Mendatangkan) 60.00 m3 Rp 90,000.00 Rp 5,400,000.00
2 Beton Kolom Struktur Atas Sloof K.1 (0,3*0,30) 3.60 m3 Rp 885,000.00 Rp 3,186,000.00
pc 8.4 30.24 zak Rp 45,000.00 Rp 1,360,800.00
No Pekerjaan Koef Vol Sat Harga Satuan Total Upah Total upah + Bahan
pasir 0.495 1.78 m3 Rp 250,000.00 Rp 445,500.00
split 0.7 2.52 m3 Rp 290,000.00 Rp 730,800.00
besi d= 12mm 9.151 32.94 ljr Rp 100,000.00 Rp 3,294,360.00
besi d= 8mm 7.765 27.95 ljr Rp 50,000.00 Rp 1,397,700.00
bendrat 2.4 8.64 kg Rp 22,000.00 Rp 190,080.00
kaso 5/7(glugu) 0.1 0.36 m3 Rp 3,500,000.00 Rp 1,260,000.00
papan 30 108.00 lbr Rp 20,000.00 Rp 2,160,000.00
paku 2.36 8.50 kg Rp 20,000.00 Rp 169,920.00
3 Beton Kolom Struktur Atas Sloof K.2 (0,15*0,2) 4.08 m3 Rp 885,000.00 Rp 3,610,800.00
pc 8.4 34.27 zak Rp 45,000.00 Rp 1,542,240.00
pasir 0.495 2.02 m3 Rp 250,000.00 Rp 504,900.00
split 0.7 2.86 m3 Rp 290,000.00 Rp 828,240.00
besi d= 12mm 9.151 37.34 ljr Rp 100,000.00 Rp 3,733,608.00
besi d= 8mm 7.765 31.68 ljr Rp 50,000.00 Rp 1,584,060.00
bendrat 2.4 9.79 kg Rp 22,000.00 Rp 215,424.00
kaso 5/7(glugu) 0.1 0.41 m3 Rp 3,500,000.00 Rp 1,428,000.00
papan 30 122.40 lbr Rp 20,000.00 Rp 2,448,000.00
paku 2.36 9.63 kg Rp 20,000.00 Rp 192,576.00
4 Balok Latei 10/12 33.00 m' Rp 14,000.00 Rp 462,000.00
pc 0.098 3.23 zak Rp 45,000.00 Rp 145,530.00
pasir 0.014 0.46 m3 Rp 250,000.00 Rp 115,500.00
besi d 8 0.348 11.48 ljr Rp 50,000.00 Rp 574,200.00
begel 8/8 0.198 6.53 kg Rp 20,000.00 Rp 130,680.00
bendrat 0.036 1.19 kg Rp 22,000.00 Rp 26,136.00
papan cor 0.33 10.89 lbr Rp 20,000.00 Rp 217,800.00
paku 0.01 0.33 kg Rp 20,000.00 Rp 6,600.00
3 Pipa Air Bersih Main Line 1" 75.00 m' Rp 5,000.00 Rp 375,000.00
Pipa Wavin 1" 0.27 20.25 ljr Rp 37,000.00 Rp 749,250.00
Asesories + Lem 0.25 18.75 ls Rp 25,000.00 Rp 468,750.00