Final Report 123
Final Report 123
Final Report 123
CORPORATION (ECWC)
Addis Ababa,
Ethiopia February ,
2023
FINAL INTERNSHIP REPORT WOLLO UNIVERSITY (KIOT)
DECLARATION
From the beginning of the internship period, We have been actively following the job training in the site.
we attempted to ask the labors and the Forman about the work in the site. we honestly announce that it is
our unique work and all source of material used in this internship report have properly approved.
Approval of
supervisor: Approval
of mentor:
ACKNOWLEDGEMENT
First and for most, we thank Almighty God to keeping peace of the environment in which we have
accomplished our internship duration, keeping us safe from beginning to thistime and for his extreme gift.
Secondly, we would like to thank Wollo University (KIOT) for offering this glorious internship
opportunity for us to observe, learn and practice the real life works and challenges in the civil engineering
profession. We would also like to thank our academic advisors for requesting this report and checking in on
his students. We would like to express our sincere appreciation to our internship advisor assign by hosting
company , Engineer Aychilum , for his valuable suggestions, comment and patience during on site work
and to prepare the final internship report document. Wewould like to express our deepest gratitude to the
people who helped us by giving the information. we also would like to express our thanks and appreciation
touniversity industry linkage for approving a hosting company for last 3 months.
Finally, we would like to thank our mentors and everybody in the company for sharing their experience
and answering every single question we ask during our internship period.
EXECUTIVE SUMMARY
It is mandatory for civil engineering students to take part in an internship program. The purpose of the
internship is to introduce students to the actual working environment. Upon the finalization of the practice,
they will be required to submit adraft report to the university. This report to be prepared and presented by
the studentscovers all aspects of the works they have been engaged in through the internship.
Accordingly, this report covers our practice time at ECWC for three months and it gives information on
the activities carried out on the building site. The internship report has four main parts.
Introduction is the first part of our report; we briefly described the background of our internship hosting
company, including the history and objective of the company, its main products and services, the overall
organization etc. The second part of the report briefly explains the overall internship experience we have
gained in our practicalperiods. We started by telling how we got into the company, in which section of the
company we have been working in, the workplace. We also clearly explained the generalworkflow in our
site. We tried to explain work procedures. Next to this, we briefly described the preparation of formwork,
rebar and about concrete casting, including placing of concrete. The challenges we have faced during our
internship period both site challenges and personal challenges are included in this report. The third part of
our report briefly explains about the overall benefits we gained from our internship interms of improving
our practical skills, interpersonal communication skills, team playing skills, leadership skills, upgrading
our theoretical knowledge and work ethics. Finally, the fourth part discusses conclusions and
recommendation.
Table of Contents
DECLARATION..............................................................................................................................................I
ACKNOWLEDGEMENT...............................................................................................................................II
EXECUTIVE SUMMARY............................................................................................................................III
Table of Contents...........................................................................................................................................IV
List of Figures..............................................................................................................................................VI
List of Tables..............................................................................................................................................VII
INTRODUCTION............................................................................................................................................1
CHAPTER ONE..............................................................................................................................................1
1.1. GENERAL INTRODUCTION...........................................................................................................1
1.2. Background of hosting company........................................................................................................1
1.3. Location, vision, mission, and values.................................................................................................2
1.4. Purpose of Establishment....................................................................................................................2
1.5. Organizational structure of the company............................................................................................4
1.6. Product and service.............................................................................................................................5
1.7. Main customer and end users..............................................................................................................6
CHAPTER TWO.............................................................................................................................................7
2. Internship experience and specific work......................................................................................................7
2.1 General and specific objective of the internship......................................................................................7
2.2 Why we selected this company...............................................................................................................7
2.3 Section of the company we have been working in..................................................................................7
2.4 Introduction to the site.............................................................................................................................8
2.5 project workflow......................................................................................................................................9
2.6 Material and methodology used.............................................................................................................11
2.7 Components of a structure.....................................................................................................................12
2.8 The work task We have been executed in my internship period...........................................................13
2.9 Challenges Faced And Measures Taken................................................................................................34
CHAPTER THREE........................................................................................................................................35
3 OVERALL INTERNSHIP BENEFITS......................................................................................................35
3.1. Knowledge gained in improving practical skills...............................................................................35
3.2. Knowledge gained in upgrading theoretical skills............................................................................36
February, 2023 Page IV
FINAL INTERNSHIP REPORT WOLLO UNIVERSITY (KIOT)
3.3. Improvement of Interpersonal communication skills.......................................................................37
3.4. Improvement of team playing skills.................................................................................................38
3.5. Improvement of leadership skills......................................................................................................39
3.6. Understanding about work ethics related ethics...............................................................................40
3.7. Improvement of Entrepreneurship skills...........................................................................................41
CHAPTER FOUR..........................................................................................................................................43
4 Challenges faced on the construction site...................................................................................................43
Introduction....................................................................................................................................................43
4.1 Project delay...........................................................................................................................................43
4.1.1 What causes project delays?............................................................................................................43
4.1.2 Ways to avoid project delays..........................................................................................................44
4.2 Working on a schedule...........................................................................................................................47
CHAPTER FIVE............................................................................................................................................48
5. Conclusion and Recommendation.............................................................................................................48
5.1 Conclusion.............................................................................................................................................48
5.2 Recommendation...................................................................................................................................49
References....................................................................................................................................................51
Appendix......................................................................................................................................................52
List of Figures
List of Tables
CHAPTER ONE
INTRODUCTION
1.1. GENERAL INTRODUCTION
An internship program offered 4th year Civil Engineering students is planned by Wollo
University Kombolcha Institute Of Technology, which forms foundation for the development of
capacity building and competitiveness of industries in the field of engineering and technology.
Moreover, it can give student to develop their 3 years theoretical background to practical one.
This program takes one semester long time starting from March 20/2014 - June 21/2014 E.C
On the regard we were able to take this internship program after we had successfully completed
three years academic study. After this, we applied for our hosting company Ethiopian
construction work corporation (ECWC) which is found in Addis Ababa, and we have been
accepted as they promised by the confirmation paper. The project building consists of 4
basements and G+21administrative building.
Vision
To be one of the best ten East and central Africa construction and manufacturing Companies by
the year 2030G.c
Mission
By using skilled manpower and modern technology, the corporation has the mission to Deliver quality
engineering, construction, and investment work domestically and overseas; to assemble construction
assemble construction equipment and vehicles; as well as to manufacture spare; deliver maintenance
service and to rent construction equipment, machineries warehouse andbuildings.
Values
• Team sprit
• Quality first
• Continuous improvement
• Responsiveness
• Cost effectiveness
• Commitment and accountability
• Workplace and ecological safety
1.4. Purpose of Establishment
• equipment and machinery, and produce construction material and different kinds of pipes
necessary for its activities, and to sell them as may be appropriate.
• To acquire own administration irrigation dams, deep water wells, and as may be
necessary water supply canals constructed and to be constructed by the federal
government budget and collect charges from the beneficiaries of such dams.
• To sell and pledge bond and to negotiate and sing loan agreements with local and
international financial sources in line with the directive issued by the ministry of finance
and economic co-operation and in accordance with policy direction given by ministry of
public enterprises.
• To make studies and forward proposals in line with direction given by the ministry of
public enterprises to get financial, technological, and modern administration inputs
(including attractive investment or to engage in investment) to be competitive in domestic
and overseas works.
• To undertake any other related activities necessary for the attainment of its purpose
• To engage in deep foundation and excavation for specialized electromechanical work,
tunneling ready mix concrete production and pouring, demolishing services, rendering a
concrete and steel structure-based building technology and construction solution related
to prefabricated building and conventional system.
Owners, sectors, government and non- governmental institution are the end users of the company
product; as we see in the above least in the above least used by private sectors and high institution
like different governmental and private residential are the end product used by those sectors. The
reason behind many customers in the company is its clear and unbiased work, their excellent
work; quality time takes for the work
CHAPTER TWO
2. Internship experience and specific work
2.1 General and specific objective of the internship
Specific objective
• It is a big structure.
• Project title- FDRE document authentication and registration head office building
project (4B+G+M+21)
• Project location- Addis Ababa around Mexico square in front of National alcohol
and liquor factory
Workflow is very important for the project management of any site project. A good
project management will maximize efficient resource utilization, development of effective
communication and mechanization for resolving problem.
Our hosting company has simple structure that facilitates the progress of the project ensuring
clear line of communication among the different level of employees. The type of work we have
witnessed on the site has the following form:
Project manager
The project manager, in the broadest sense of the term, is the most important
person for the failure and success of the project. The project manager is
responsible for planning, organizing and controlling the project. In turn, the
project manager receives authority from the management of the organizational to
mobilize the necessary resources to complete the project. The project manager
must be able to exert interpersonal influence in order to lead the project team. He
must possess leadership quality and the ability to handle intricate interpersonal
relationships effective within an organization.
February, 2023 Page 9
FINAL INTERNSHIP REPORT WOLLO UNIVERSITY (KIOT)
Office engineer
The main responsibilities of the office engineers are: -
1. Prepare material lists for the project and ensuring deployment
3. quantity executed.
4. documentation
The above every group of jobs in the chart is done by their procedures.
The project manager doesn’t affect the activities done by either the engineers or
workers, but he gives ideas and controls the activities.
Into the organization chart flow, the resources of the company are systematically
arranged in such a way that activities contribute to the organizations goal as we see
from the above chart each person.
In an organization to separate or distinct task and to ensure these tasks are coordinated
in the way that the company accomplishes its goal, but sometimes we see the
companies’ professions can’t follow the chart.
In other way, as much as we know no one can interfere the others activity.
In addition, the site work can have three main building construction sections. These are
• vibrator
• mobile mixer
• survey instruments
• generator
Methodology
This section discusses the methods used in the collection and analysis of data. It presents and
explain the methodological approach of the report and method of data collection technique of the
study were represented. Some of the followings are
A structure is classified into two broad classes on its loading effect and load transferring
mechanisms as well as its location:
a. Sub structures
b. Super structure
Because of our internship duration time and by chance our site project we are working on super
structure. Because when we started our practice, the project was in the super structure 1 st floor
column, shear wall, and core wall form work was erected, and it has 4 basements below the
ground level. Therefore, the whole internship report is depend on what we have seen.
During our internship practice, the main task was observing the overall building activity on the
site and some office works.
Site work
•Checking the number of reinforcement bar space
•Checking the alignment of the column
•Checking level of form work
Office work
•preparing takeoff sheet
•Explanation of construction material
Scaffolding
Qualities of formwork
It should be water tight.
It should be strong.
It should be reusable.
The surface contact with concrete should be uniform/ smooth and free from
contamination.
It should be according to the size of the member.
Safety: -formworks must be built sufficient strength and factor of safety so they have the capable
of allsupporting load
Ensures quality surface finish and is especially recommended in works where large, exposed
areas of the concrete are to be constructed such as floor slab, faces of retaining, parapet and shear
walls, etc. Releasing agent is used on plywood surface to facilitate the removal of the formwork
and prevent the concrete adhering to the face of the formwork.
Steel panel:
Although steel formwork costs more, it may work out to be economical in the long run due to itslarge
number of reuses
In other word for slender walls where the bending deformation is more shear wall resist the
loads due to cantilever action. This means shear walls are vertical elements of horizontal force
resisting system. Generally lateral force is caused by
• Wind
• Earthquake
Plywood is conventional material used in shear walls but sometimes they use panels.
Frequently building have interior concrete core wall around elevator, staircase and service wells
such walls may be considered as shear walls. The shear walls are also placed as exterior walls
and interior walls of the building. The step of the construction of the shear walls are the same as
column Form works are classified as:
• Wooden
• steel
In the case of shear wall form, working the type of formwork material we used is wooden type
because of large area covering and reused for another part of the structure (reused several
times).
Column
Column form work
One of the structural members that were being casted on the site was column. Column is
primarily constructed to support beams and columns. It transfers loads from beams and columns
to column and finally to the foundation. There are staircase column and the elevation column.
Construction of a column starts by setting out the alignment for the corner columns using rope,
plumb bob and water bubble.
The column formwork is arranged to make sure that the column is perfectly straight, to make
sure of this they use what they call a “Tumby” which is showed in the picture below.
Procedures to construct the column
Reinforcement bars
are placed
A. circular column
B. Rectangular Column
C. Square Column
Circular Column
The resistance to bending or deflection of a circular cross section is higher than a rectangular
cross section with the same area. In addition, the load required to buckle a column with circular
cross section it is the same around its perimeter. However, a beam with a rectangular may bend
first in either of two axes.
Rectangular column
There are very common and easy for construction work the stirrups have small spacing at the
bottom and top of the column because at the top and bottom of the column there is high amount of
interaction of load pressure. Therefore, to prevent structural failures and to increase the resisting
capacity of the column (building) the number of stirrups were provide within high amount with
small spacing.
Beams are constructed primarily to carry the slab and transfer loads from slab to column. Beams
generally carry vertical gravitational forces but can also be used to carry
Horizontal loads (i.e., loads due to an earthquake or wind). The loads carried by a beam are
transferred to supporting columns.
In our site the beam bottom formwork is done by using RHS, CHS and play wood form
work materials.
Slab
service load.
Procedures to construct beam and slab
• Alignment of the beam and slab is kept
• Concrete is poured.
Fig 2.9 formwork release agent, top and bottom slab formwork
Ramp
Although we did not seen how it is constructed our site assistant described as how ramp is
constructed and even shown us a photo of the ramp during construction. Ramp is a sloped
pathway used to provide access to between two vertical levels. It facilitates the movement of
wheelchairs, bicycles, and another wheeled vehicle. Ramps are constructed when several people
vehicle have to be moved from one level to another. They are widely used in public building,
railroad stations, and stadium, hospital, and exhibition halls.
stair
Stairs are set of steps to allow easy pedestrian access from one floor level to another in safety.
Steps arranged in series and placed in an enclosure are called Staircase. Stairs must be strong
enough to carry weight of people, furniture and equipment.
Design of stairs requires a very careful consideration, mainly as they are exposed to high load
congestion. Stairs have a difficult configuration than other structural elements of a building.
However, in design of stairs are considered as a straight frame.
Stairs should be designed properly to provide proper:
• Natural Light
• Ventilation
• Nosing: it is the projecting part of the tread beyond the face of the
riser.
• Flight: is a continuous set of steps b/n floors and/or landing.
Removing formwork
The process of removing formworks from around the concrete is called striping. The workers
must not strip the forms until the concrete has properly set and reaches strength of at least twice
the stress to which the concrete may be subjected at the time of striking. Removing of the forms
must be done carefully so that they do not damage or break the parts. The stripping time differs
for different structural parts
Formworks can be reused, and this reduces or lowers the cost of construction. After the
formworks are removed, the workers clean and store them for future use; Cleaning consists of
pulling nails, scraping or knocking off concrete particles.
Table 2.1 removal period of formwork
• Distribution bar- it is a type of bar which is used to anchor the placed bar on
its position. specially this type of bar is used on slab
• Z bar (kobellite bar)- the bar used to fix the bar on its position mainly used
on slab to separate bottom bar to top bar
It is one of the important terms in the reinforcement. During the placement of steel reinforced
concrete structure, if the required length of single bar may fall short.
To get the desired design length, lapping of two bars side by side is done. Usually, the stock
length of steel bars is limited to 12mm. this is for easy transportation of steel bars to the
construction site. Then, the tension forces are required to be transferred from one bar to other
bar at the location of discontinuity of the bar, so the second bar is kept closely to the first bar
and overlapping is done.
This amount of over lapping between two bars is called lap length. Lapping is usually done
where minimum bending stress is encountered. In my specific project a lap length of 5D for
columns and 4D for shear wall and retaining wall, where D is the diameter of bar were used.
It also includes removing unnecessary (wrong casted) thickness from the structural member.
Stirrup
It is closed loop of reinforcement bar, which has a main function of holding the main
reinforcement bars together in a reinforcement concrete element. Stirrups can come in multiple
shapes according to the design and shape of elements.
The stirrups used are typically made out of steel piece, which is wrapped around top and bottom
bars of the beams (rectangular shape) or columns (rectangular or circular shapes).
Reinforcement work- including cutting, bending, placing in position, tie and spacers.
Reinforcement shall be measured by the net weight of the bars. The length of one full
bar is 12m the so called “Berga”.
It shall be stored in clean condition and is of specified quality. It shall be stored in an off
the ground position to prevent rust by contact with soil, dampness and other
objectionable materials.
Cutting of reinforcement bar is done using saw and hydraulic machinery. The cut
section shall be painted to avoid rust during concrete casting.
The bars shall be accurately placed, and their positions maintained during all operations.
The dimension, length and shape of the reinforcement of bar is according to drawing
and specification.
Bending of reinforcement is done with adequate bending tools. The bending tool that is
using in my site is called” berga” and it is made from reinforcing steel bar.
The size of the bar used in the site with their placement location:
Table: 2.2 The bar used in the site for different structure of the building
Terms in bar
It also needed to prevent the columns and beams from buckling and assist resisting lateral loads
(e.g., earthquake load).
Purpose of stirrups
Spacers are used to maintain uniform thickness of cover to reinforcement in sub structure and
super structures. Another advantage is it helps to protect tearing of concrete by formwork during
removing. They were premade at the site by using plain concrete with its required dimension of
cover to reinforcement. I.e., different size spacers were used for different part of the structure
• Column 50 mm
Spacers were placed between the formwork and reinforcement bars by using metal ties, which related
to the spacer while preparing them. They are remained as the part of structure after the formwork was
removed and gave the cover for the reinforcement.
Advantage of spacer for reinforced concrete structure as per [EBCS 2-1995-7.1.3]
• The spoliation (separation of fragments from the surface of a rock) will not occur
Electrical installation
Electrical installation means the construction or installation of electrical wiring and the permanent
attachment or installation of electrical product in or on any structure that is not itself an electrical
product
Concrete work
Concrete is a composite material made up of inert materials of varying sizes, which are bound
together by a binding medium. Concrete contains coarse aggregate in addition to cement, water,
air and fine aggregate. The cement, water, and air combine to form a paste that binds the
aggregates together. Thus, the strength of concrete is dependent on the strength of the aggregate
matrix bond.
Advantage of concrete
• It doesn’t require complex equipment and special skill. I.e., it is mould able in to
any desired shape.
• It does not deteriorate with time. I.e., it is fire, weather and corrosion resistant.
Disadvantage of concrete
• It is difficult to dismantle.
• It has required formwork.
• It is difficult to supervise after pouring.
Reinforced concrete, also known as RCC (reinforced cement concrete), which incorporates steel
bars in sections of the concrete which are in tension (to supplement the low tensile strengthof
mass concrete and control thermal and shrinkage cracking), for floor slabs, beams, columns and
stairways all these were cast in situ. The high strength to weight ratio of steel, coupled with the
fortunate coincidence of its coefficient of thermal expansion being about the same as concrete,
make it the ideal material for reinforcement.
Grade of concrete
The grade of concrete tat used for our internship company is C50 and C30. A grade C50 concrete
is used for column when placing concrete in harsh condition where aggressive chemicals or high
level of abrasion are present. In addition, grade C30 concrete is used for slab and beam.
Curing
It is important for prevent formation of surface cracks due to rapid loss of water
while the concrete is fresh and weak.
In addition, used to keep the concrete moist and warm enough so that the hydration of cement can
continue.
In our site, we used water-curing mean spreading the water on the structure.
For columns and ramp, plastic sheets were used this method is very
advantageous because once formwork is removed from column the column
is wrapped by a plastic sheet and there is no need to water it manually by
water.
For shear walls and core walls, curing is done manually twice a day for 7
days
Under the office work, it covers all the managing, monitoring, directing and revealing process of
the project work. The application of knowledge, skills, tools and techniques were required to
insure the correct implementation of the work according to the technical specifications and
standards of the company.
The office work consists of-
• verifying the collection of data and confirming the quantity of each work
Column1: used for stating the number of times an item occurs and is called the timising column.
Column 2: is called dimension column as it is used to enter the dimensions of the items of
works. The dimensions are entered in the order indicated below: Length, Width, Height or
thickness.
Column 3: is called squaring column. The stated dimensions in column 2 are multiplied to
determine the quantity of the work either in ml, m2, m3 or in Pcs. or No.
Column 4: is called description column and description of the work item is briefly stated.
A separate sheet (bar schedule) is used to prepare reinforcement quantities. Bar schedule is
used to know the amount of rebar used on the site and to tell the bar bender that the amount of
bar needed in some position of the building and its number.
Ite Positi Dia Sha No No. of Leng Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20
m on m. pe bar th
. of
(mm memb
bar (m)
) er
s
Total length,
m
2 8 7 8 8 8 6
Total weight,kg
Squaring
The dimensions entered in Column 2 are squared or cubed as the case may be, multiplied by the
timising factor, and the result entered in Column 3. This task is called squaring. Another person
should carefully check all squared dimensions before abstracting, and if correct, the item should
be ticked with red. Use two decimal places.
Abstracting
The squared dimensions are transferred to abstract sheets and all similar dimensions are
collected in the same category to obtain the total quantity of dimensions are collected in the same
category to obtain the total quantity of each item. Writing the Final Bill: After the abstract sheets
have been com Tumbi: (Plumb bob)It is used for checking perpendicularity of columns placed
and checked, the final bill of quantity is written.The dimensions are copied from the abstracts
and as each item is transferred, it copied from the abstracts, and as each item is transferred, a
vertical line from the abstract sheets should tick it. Thedescription of each item in the final BOQ
should be short, precise and descriptive as per the specification.
Communication with site staff members because they are so busy at their daily task.
Minor physical injury while observing site activities.
Understand about quantity survey in office work.
Measures taken to overcome challenges encountered
• To understand site language, we tried to ask repeatedly daily laborers
• To get skilled workers and engineers move to another site with them
• Since there were many sites, many workers move from site to sites w/c minimize the
chance to work together with engineer. To solve this, we tried to contact them
personally.
• To see other substructure works move into other sites.
• To know about quantity survey in office work we tried to ask office workers repeatedly
CHAPTER THREE
Considering practical skills, it was necessary for us to get ourself through the different site
operations and activities on the site. Moreover, this was achieved through participating on
activities on the site, by observing and asking question.
Throughout all this, it was necessary to understand the practicalities of working on site and to
know the actual construction process. As a result, we have obtained the following practical skills.
• Allocation of different equipment’s and office in the site for example...Choosing where the
store should be, where the fine aggregates must be placed, how to keep a rebar from rust,
how cement should be stored.
• How to keep the alignment of a column using plumb bob
• Reinforcement overlapping.
Talking about the theoretical skills we upgraded our theoretical skills by working in cooperation
with the site engineers and staff members at the construction site. In addition, we foundthat a lot
of materials and engineering knowledge that we had gained at university was strengthened
through our two-month practical experiences. Subjects such as RCC Design, Soil mechanics,
Foundation Engineering, building construction and Construction of materials provided
invaluable preparation for what we were to learn while working on the construction site.
we gained the following theoretical skills during the internship program.
• Preparation of reinforcement bar schedule
• Preparing quarterly, monthly, and weekly report
• Preparing take off sheet
• Functions of concrete with different types of compressive strength.
• Making Re-bar summary.
• Duties of different parties in the site.
• Curing periods of different structural elements.
This Interpersonal communication is among the most important measures in construction site. If
one did not know how to communicate with workers, it will be difficult whether to employ
workers on its firm or to be employed on others firm and to work with others. Due to this having,
good interpersonal communication is very important. Questioning is among the best alternatives
to gain knowledge. Regarding to this communicating with every staff member is allowable. we
had to ask and work with different people who had different levels of skills and expectations.
When working in a large and complex project, coming across associates that have different
duties and expectations is unavoidable. So, in order to perform any activities, one should
communicate wisely and effectively. Development of effective communications and mechanisms
for resolving conflicts among the various participants will be handy. Even within a single
profession such a civil engineering, there are quite distinct groups of specialties in planning,
design management, construction, and other sub-specialties. Good communication and
coordination among these participants are essential to accomplish the overall goals of the project.
The fundamental challenge is to enhance communications among individuals, groups and
organizations so that obstacles in the way of improving interpersonal relations may be removed.
It was challenging to be liberated enough to ask questions and observe the practical part of the
process. However, after few weeks, the environment was familiar, and we worked hard in
improvingmy communication capability. We believe that going into a new working environment
would not bedifficult after this experience.
In this internship program, we have improved the following interpersonal communication skills:
Shortly speaking all the staff members in my hosting company are so friendly and have respect
to each other. The way of their social interaction is so grate and anybody appreciate them.
Participants in the process of planning, designing, financing, constructing and operating physical
facilities have different perspectives on project management for construction. Specialized
knowledge can be very beneficial, particularly in large and complicated projects, since experts in
various specialties can provide valuable services. However, it is advantageous to understand how
the different parts of the process fit together.
Poor coordination and communication among specialists’ results in loss of:
Every project requires that team member’s work together to achieve a common goal. Project can
involve activities like putting puzzles together or cleaning up or rebuilding a property. Projects
typical involve assigning each team member a specific task that he is responsible for completing,
which helps to develop trust within the team.
There was a great teamwork between the consultants, the company’s engineering, and the
foreman on resolving a problem.
Some of the team playing skill we came across with is put as follows.
• When the office engineer gave us assignment in a group, we were working together sharing
ideas and knowledge
• The other is when we ask question to the office engineer or site engineer, we were moving
as a team
• Establish a good trust within the members of the team.
• Prioritize the risks, based on the likelihood consequences of occurring, and develop a plan
for mitigating and reducing these risks.
• Have a sense of purpose to achieve clear and specific goals.
• Be capable of contributing to the achievements of the goals based on our level of knowledge
and experience.
• Create a cooperative spirit with the team members.
• Be able to openly communicate with our team members for project updates, questions, ideas
and general inputs.
• Give respect for each members
• Generally, having good team playing skill gives a deep spiritual pleasure and creates a
suitable condition to work hard and a good impression on everyone.
Civil engineering project management is the overall planning, organizing, staffing, leading and
controlling of a project from inception to completion and at meeting client’s requirements in
order to reduce a functionally and financially viable project.
Ourselves not being engaged on any project management, we have rather learnt about it through
observations being together with the site engineers when they were checking on the workers and
making sure the project is going well. Since leadership is the process of influencing individuals
or groups to accomplish an organizational goal or mission, it is necessary to influence other for
the best achievement of the firm objectives. we have also learnt by observing the project
managers leading respective teams.
As to our observation, we have gained the following leadership skills:
• If there is a team, there must be a leader, so some of us were taking tasks representing
out- group.
• Collecting ideas of the group and make a conclusion out of it.
• Making sound and timely decisions.
Construction industry is a firm with enormous constructive culture, which encourages members
to work to their full potential, resulting in high level of motivation, satisfaction, teamwork,
service quality and sales growth. Constructive norms are evident in environments where quality
is valued over quantity, creativity is valued over conformity, corporation is believed to lead to
better results than competition, and effectiveness is judged at the system level rather than the
component level. The type of cultural norms is consistent with the objectives behind
empowerment, total quality management, transformational leadership, continuous improvements,
re-engineering and learning organization.
The most valuable things we learned concerning ethics are:
• We have identified the relation between the consultant and the contractor
Ethics is a branch of philosophy that defines morality and determines the meaning and rational
justification of the right way to live, correct values as well as correct ways of treating others. As
workers wear made to specialize in different fields, specific codes of conduct were expected
from each worker. In today’s complex world, Ethical conduct of workers is very important for
developing healthy working environment and increasing productivity. Ethical work conduct
enables workers to posses’ appropriate behaviors in their work and so as to develop proper
relationships with co-workers and it helps them to create good industrial environment. There are
two common types of ethics.
The following are some of the common professional ethical principles, which are applied in the
construction environment:
• Confidentiality
• Punctuality
• Loyalty
• Responsibility
• Impartiality
• Integrity
We have been able to understand that the above-mentioned common professional ethical
principles are qualities that most employers hope their workers will possess and it is when the
above- mentioned conducts are fulfilled that an effective output can be created. Every worker,
including me, had been practicing workplace ethics. Many workers practice them more
conscientiously than they practice others. Unfortunately, some workers are unethical in their
performance of duties. Attimes, they break laws and are prosecutes, but more often they simply
fail to live up to accepted standards of doing the job well.
CHAPTER FOUR
4 Challenges faced on the construction site
Introduction
The construction industry has been living through an exciting phase of its life, growing nonstop and facing
many challenges at the same time. Some of these challenges are relatively new; others are as old as the
industry itself.
There are several different approaches to construction issues, as well. For example, sometimes slow
technology adoption rates are treated as a single big challenge, and sometimes it is treated as a multitude of
different problems – including communication problems, scheduling problems, problems with
documentation, and so on.
Now we’re going to go over some of the problems or challenges we have seen on our site , starting with
project delay. Other issues are going to be mentioned, too.
Remember that it’s far better to under promise and over deliver than to overpromise and under deliver. Good
goals are realistic, clear, and measurable.
Realistic– Can we accomplish this goal with the allotted time and resources available to us?
Clear– Do we know exactly what is being asked of us? Does everyone understand?
Measurable– Are there quantifiable indicators with which we can judge each goal?
Spend some time discussing the goals of the project and, if necessary, clarifying how they’ll be measured.
Your most important resources are the people working with you on the project. Assess the composition of your
team to see if you have enough people to get the project done on schedule and whether all those people
have the necessary project management skills.
If not, you’ll need to update your project plan to factor in how much time and money it will cost to add team
members, provide training, or outsource to cover the gaps.
Don’t neglect the material resources required for your project. Things like office space, computers, printers,
and software are vital, and you can’t take for granted that they’ll be available.
4. Schedule carefully
A project schedule is more than a timetable. It’s a comprehensive document that details the project timeline and
the organizational resources required to complete each task.
with the help of a project scheduling tool. The schedule should be readily available to every member of the
project team.
time
money and/or
Project deliverables.
Establish how long it will take to complete the project with the delay and how much that will cost. Get a
breakdown of what the delay will do to their budget.
Find out what their team is able to deliver by the original due date, staying within budget. Once the team
has established what’s possible, they can update their client and present the new options.
2. Prioritize tasks
With the adjusted plan decided, they need to prioritize tasks. Re-evaluate the original project plan they made and
see what tasks have already been accomplished, which can be eliminated, and which may need to move up or
down their team’s priority list.
4. Communicate
Communicate, communicate, communicate ! Keep the team informed of every delay, change of plans, and altered
client expectations. By using task management in projects, every member of the team should be able to see when
tasks are due and what major deadlines are approaching. Don’t forget to communicate with the clients as well.
They’re surely stressed by the delay (even if they’re to blame for it), and clear, reassuring communication from
the company will help ease minds and preserve business relationships.
With effective project communication, the company can ensure that everyone stays on the same page and
minimize delays due to misunderstandings.
This is one of many problems that modern technology and its advantages are either partially or entirely
solvable. However, this list would not be that long if it wasn’t for another massive problem that the entire
construction industry has been dealing with for a while now.
Conclusion
The construction industry is quite old and has been through a lot. Some of the problems are extremely old;
others have become more prominent in recent years and were not a problem before. In this article, we’ve
tried to go over the most significant construction issues on the market, as well as some of the means of
avoiding or eliminating them.
CHAPTER FIVE
This internship program has been a helpful experience in participating us to the real engineering
works. We have gained a knowledge that we would not acquire if we spent the time in the
university. We could say that we have experienced a number of new things related with our
work during the internship, and it gave us a clue in what section of work should we continue
after the graduation.
We were able to acquire a high level of confidence to deal with problems that a rise in the
construction site. Thus, during these past three months we had been able to see the different
structural parts construction procedure and methodologies applied. In addition to this, we learnt
how to communicate with workers: this intern improves our interpersonal communication skills.
We also were able to understand work ethics related issues such as integrity, transparency,
accountability, diligence etc.…
The various types of tasks that we have been undertaking during these past three months on the
site and the office enhanced our theoretical knowledge, confidence, and practical skills during
the construction process. We also developed knowledge in terms of entrepreneurship that gave
us a direction on how we can create new set of ideas and different things that are helpful in the
production process not only in the construction aspects but also in any form of activities that
have certain product.
Generally, this internship program provides a bridge between the student life and professional
life. So, we conclude that the institution must continue this program in a more supervised and
advanced manner to create a successful, creative, and self-reliant professional which we can
reduce our country’s dependency on foreign skilled manpower on construction work.
5.2 Recommendation
In this three -month internship program, we have experienced so many things about our field. In
this part of our report, we would try to suggest some ideas for our internship hosting company
and our university.
Recommendation for Hosting Company
We have seen some positive and negative sides about the internship hosting company.
Positive side
• They use safety material, such as helmet, safety shoes etc.
• Medical facilities/ first aid is given on the site . We recommend that to keep it up.
Negative side
• We recommend that the project task/ activity to be finished as by schedule
• Store the material at proper place to avoid wastage of material and time
• Organizations and companies hosting the students do not pay much attention to students
as well as the follow up of the academic supervisors. We highly recommended the
universities and concerned bodies to make strict follow up on students by working in
close relationship with hosting organizations
Having an internship offers a list of advantages to the students, as mentioned above, our
academic and career goals, but also our social skills because it is known that we will meet a lot of
for instance it helps us to grow not only practical experience and knowledge related to people
and would deal with accordingly.
Because of this and all the listed advantages above, we recommend our university to keep giving
this great chance for the next student.
References
The Company profile documents which containing organizational structure and brief history.
Appendix
Aggregate: Material such as sand or gravel used with cement and water to make concrete,Mortar,
or plaster
Cast: Object part of a building such as beam, slabs, and columns formed by a mold.
Concrete: …. (Armata)
Fasha: Horizontal or vertical strip in either concrete or plastering to keep the levelhorizontal
as required or the concrete filled in the Riga
Fond: ……… (Bottom soffit) Type of formworks that place side of beam or bottom panel
for beam.
Gindilla: A large eucalyptus tied with wires protruding from the slab, which help us attain
Krabat: Literally means a tie. Pieces of timber tied to the column formworks, which help
Soleta....................(slab)