Prepared by
Prepared by
Prepared by
TECHNICAL REPORT
ON
Prepared by
Submitted To
(CHE 505/506)
DECEMBER 2012.
i
OGUNGBENRO Adetola Elijah
Department of Chemical Engineering,
Obafemi Awolowo University, Ile-ife.
December 1, 2012.
LETTER OF TRANSMITTAL
humbly submit for assessment this complete design report on process plant for the
production of 72,000 tons per year of 2-Ethylhexanol from synthesis gas and propylene
feed.
I hereby certify that all information contained therein are based on knowledge
Yours faithfully,
(CHE/2007/083)
ii
EXECUTIVE SUMMARY
A critical approach is attempted in this project work at realizing the design objectives for
a process plant. Design, being an iterative procedure with a route of procession from the
input or feed to the stated objective(s), amidst intervening constraints, requires a careful,
The stated objective in this case is the design of a 72000 tons/year capacity of a 2-
EthylHexanol (2- EH), such as the Acetaldehyde Route and others developed by Shell
Corporation etc, the Oxo Process route utilizing propylene and synthesis gas as feed
components was the given route for this design work. However, important modifications
were implemented to the process description for effective process optimization, such as
processes.
The oxo synthesis began by reacting propylene feed and synthesis gas (CO + H2) in a
input of 198.3275 kmols/hr was made up by three streams; Fresh Feed of 152.9 kmols/hr,
recycle streams from cracking unit of 42.9775 kmols/hr, and stripped propylene from
310.709 kmols/hr of synthesis gas (CO + H2) was supplied together with 218.5415
kmols/hr excess Hydrogen for use in latter processes. The hydroformylation reactor was
iii
at operating temperature and pressure of 130°C and 350 bar. The design temperature and
The main product of the oxo reactor was n- butyraldehyde with molar flow rate of
with a selectivity ratio of 4:1. Alcohols formed from the hydroformylation reaction
included n- butanol (9.0437), and iso butanol of 1.5073 kmols/hr. Other reactions occured
to a small extent yield 136.0750 kg of high molecular weight or heavy end compounds,
A cleaner technology approach to pollution control was adopted for the plant design.
Hence, the need for thorough separation processes and purge streams to remove
extraneous components. From the hydroformylation reactor, the products were separated
with the first Gas- Liquid Separator (GLS 1), which separated the aqueous phase of
cobalt and water from the organic phase components in a process referred to as cobalt
plating. The cobalt was regenerated as an active catalyst, to save cost, and sent back to
the oxo reactor for further reaction. The organic phase of GLS-1 goes for further
separation in a second GLS which stripped the initial reactants (propylene and synthesis
gas) for recycle back to oxo reactor. Liquid phase of n-/iso- butyraldehyde, alcohols,
heavy ends and remnant water exits the GLS 2 operating at 55°C and 1 bar.
A vital separation technique was involved proceeded from GLS-2. A distillation column
1 (DC 1) with 36 trays and made of Ferritic Stainless Steel 430 is employed which gave a
top product of n-/iso- butyraldehyde and bottoms of alcohols etc. Further distillation was
employed to separate normal and iso- butyraldehyde in DC 2. The McCabe Thiele- Plot
iv
is of stream properties of DC 2 indicated the number of required trays as 42. Tray
thickness and spacing of 3 mm and 457.2 mm was employed for both the enriching and
rectifying section of the 25.89 m heighted DC 2. Sieve hole pitch was 15mm while
diameter was 5mm. Flooding rate of 80% was computed for both sections and it was
ratified that there was no flooding. The Murphee plate efficiency and overall column
efficiency was within acceptable ranges (> 80 %). Log Mean Temperature Difference
(LMTD) for the partial condenser was 31.51°C. Mechanical design specifications for the
DC 2 construction were computed in this report. The top product of DC 2 was mainly
iso- butyraldehyde (35.704 kmols/hr), while the bottoms was mainly n- butyraldehyde
To maximize output of 2- EH, the iso- butanal obtained from DC 2 operation was routed
capacity cracker unit had operating specifications of 275°C and 1 bar, but designed at 1.1
bar and 302.5 °C and made of Low- Alloy Steel material for good heat retention. A
recycle process was proposed for the cracker unit which had a limited conversion yield of
80%. Aldol condensation with 2 % w/w aqueous NaOH (9.2 kmols/ hr) took place on the
n- butanal product from DC 2. The Aldol condenser reactor produced 69.946 kmols/hr of
2- Ethyl hexanal, an intermediate reactant for 2- EH. (Improved recycle process for the
v
Process design for the 2- EH also involved the control and instrumentation of the
processes and equipment to achieve the design objectives and safety. Control of operating
conditions of the oxo reactor was described, with preferred controller as Proportional
Integral Derivative (PID) Controller. A PID controller was chosen for operation to
eliminate the challenge of runaway temperature increase by the derivative component and
the offset error by the integral component. Simulation results suggested the
hydroformylation (HFR) vessel temperature was kept at safe operating condition using
coolant stream and a Temperature controller (TC) with Controller Gain Kc = 2 and
Settling Time Ti = 5min. A controller scheme was also designed for level control to avoid
the splashing of the reactants and prevent the mixing of pure tops from the bottoms. The
proposed controller was proportional controller which can tolerate offset. This controller
allows offset depending on the magnitude of the controller gain which is the only
controller parameter to be varied in this case. HFR liquid level was kept at safe fill of
85% using a bottom product valve (BPV) and a PID level controller (LC) with Kc = 2
and Ti = 10min. The mass flow rates of propylene stream and synthesis gas stream going
into hydroformylation reactor (HFR) were controlled by propylene stream valve (PV) and
synthesis gas stream valve (SGV) respectfully using a PID controller of 0.1 Kc
An acceptable design must present a process that is capable of operating under conditions
which will yield a profit. A simple costing procedure is carried out for the 2- EH Plant to
vi
Estimates were prepared using data and Chemical Engineering cost index method in
Literature, considering Port Harcourt (Rivers State, Nigeria) as the location of the plant.
Old cost information was obtained and extrapolated using the Index Method to the
present 2012 costs. These costs were then converted to Naira using appropriate foreign
exchange rates.
The Purchased Cost of Equipment (PCE) was valued at #428,171,790, while the Physical
Plant Costs (PPC) or direct costs was obtained by the factorial costing method at 3.4
times PCE, and valued at #1,455,784,086. Indirect costs were the expenses which are
not directly involved with material and labor which included design and engineering,
contractor’s fee etc, and were valued at #650,602,838.70k. The Fixed Capital Investment
(FCI) was obtained by summing up the direct and indirect costs, and valued at
#2,106,386,925.70k. The Working Capital was 15% of the FCI and both gave the Total
The start- up cost, or for first- run of plant for production, was valuated at 15% of TC1.
With a selling price at #130.56k, the 72,000 tons/year 2- Ethylhexanol plant is expected
Finally, procedures for safe operation and start- up of the 72000 tons/year 2-
vii
CONTENTS
Title Page i
Letter of Transmittal ii
Contents viii
Abbreviations xxi
1.1 Background 1
viii
CHAPTER TWO: LITERATURE REVIEW 8
2.4.4 Utilities 20
ix
2.6.3 Solubilities of gases at 30 Bar in the liquid
at 1 atm 24
x
CHAPTER FOUR: PROCESS DESIGN BALANCES 34
4.1.1 Hydrogenation 38
4.1.4 Cracker 43
4.2.2 Cracker 64
Aldol Condenser 73
xi
5.4 Design Conditions and Physical Properties of
Hydrogenation Reactor 74
xii
CHAPTER SEVEN: MECHANICAL DESIGN OF N- AND ISO-
8.3 Control Scheme for the Liquid Level within the Reactor 158
xiii
CHAPTER NINE: COST ESTIMATION AND ECONOMIC
PROCEDURES 182
xiv
10.3.1.5 Instruments 201
xv
REFERENCES 213
APPENDICES 218
xvi
LIST OF TABLES
Table 5: Material Balance Data for Inputs and Outputs of OXO Reactor 49
Table 6: Material Balance Data for Inlets, Outputs and Off- Gases for GLS 1 52
xvii
Table 15: Flow Properties of Distillation Column (DC) 2 92
xviii
LIST OF FIGURES
xix
Fig 17: Plot of Chemical Engineering Cost Index 163
xx
ABBREVIATIONS
2-EH: 2-Ethylhexanol
xxi
PID: Proportional Integral Derivative
xxii
1
CHAPTER ONE
INTRODUCTION
1.1 Background
2-Ethylhexanol (2-EH) is a clear, colourless liquid with a characteristic odour, which has
been described as sweet and floral (Genium, 1999; WHO, 1993) and as intense and
unpleasant (HSDB, 2004; Verschueren, 2001). This compound occurs naturally in food
(e.g., corn, olive oil, tobacco, tea, rice, apricots, plums, apples, nectarines, tamarind grapes,
and blueberries) and is also used as a flavor additive in foods (WHO, 1993). In the
react violently with oxidizing materials and strong acids. 2-Ethylhexanol is soluble in
The chemical formula, structure, registry numbers, synonyms and trade names for 2-ethyl
also a valuable intermediate in the chemical and petrochemical industry. It ranks after the
lighter alcohols (methanol to butanol) as the most important synthetic alcohol. The main
outlet for 2-ethylhexanol (2-EH) is the production of phthalate plasticizers, such as di-octyl
phthalate (DOP), which are used in the manufacture of polyvinyl chloride (PVC). The next
largest outlet for 2-EH is for the manufacture of the acrylate esters which are used in
2
adhesives and surface-coating materials such as acrylic paints, in printing inks and as
impregnating agents.
has recorded an average annual growth rate of 2.5% from 1986 – 2000. The future of 2-
ethylhexanol demand lies in the demand for phthalates such as DOP; the largest volume
phthalate ester; and is expected to remain flat or decline slightly due to competition from
other phthalates and environmental pressure. An issue for 2-EH producers is that DOP has
been dogged by health hazard and environmental concerns, and phthalates in general are
under pressure. On the positive side, there is increasing demand for other derivatives of 2-
butyraldehyde was originally obtained from acetaldehyde via ethylene but this has been
synthesis gas (carbon monoxide and hydrogen). The catalytic process now mostly uses
rhodium catalysts rather than the older cobalt hydro carbonyl catalysts.
The esters of 2-Ethylhexanol with dicarboxylic acids are excellent plasticisers for synthetic
resins and rubbers and include phthalates, adipates and sebacates .Its main application is as
a feedstock in the manufacture of low volatility esters, the most important of which is di-
(2-ethylhexyl) phthalate (DOP or DEHP). Other plasticizers that can be obtained from 2-
Ethylhexanol are the corresponding ester of adipic acid and para- hydroxylbenzoic acid.
2-Ethylhexanol is also used as a solvent and has a particular niche use in the formation of
lacquers and coatings when slow evaporation is desired. 2-Ethylhexanol is also an excellent
defoaming agent for use in the photographic, varnish, rubber latex, textile printing and
2-Ethylhexanol (2-EH) is a clear, colorless, mobile and neutral liquid with a characteristic
odor. It is miscible with most common organic solvents, but its miscibility with water is
very limited. It enters into the reactions that are typical for primary alcohols. For instance,
it readily forms esters with various acids. 2- Ethylhexanol is the oldest, best known and
The distinct physical and chemical properties of 2-ethylhexanol are summarized in Table 2.
A summary of the environmental fate and half-lives for 2-ethylhexanol is provided in Table
3 (HSDB, 2004). Appendix B gives the Material Safety Data Sheet (MSDS) for safe
handling of 2- Ethylhexanol.
5
volatilization: 1.7days.
Soil Biodegradation,
plasticizers for PVC resins, hexyl esters and arylates (OECD, 1995). 2-Ethylhexanol is also
used as a solvent (dyes, resins, oils, antifoaming agents and nitrocellulose), a wetting agent
(organic synthesis, paint lacquer, baking finishes, inks, rubber, paper, lubricant,
photography and dry cleaning) and in textiles (finishing compounds and mercerizing
textiles) (Verschueren, 2001; Genium, 1999). In addition, the WHO reported an annual
production of 209 kilograms of 2-ethylhexanol for use as a flavor additive to food (WHO,
1993).
2
Source: HSDB, 2004.
7
Examples of other applications for 2-Ethylhexanol are summarized below. The list is by no
means complete.
Low-volatility solvent (e.g. for resins, waxes, animal fats, vegetable oils and
petroleum derivatives).
Low-volatility ingredient in solvent blends for the dyestuffs and coatings industry.
production of the corresponding diester of maleic acid for use as a starting material
for surfactants.
for electrolytes.
In antifoams for almost all aqueous systems (e. g. in the textile and paper
industries).
8
CHAPTER TWO
LITERATURE REVIEW
The economics of the various processes for the manufacture of 2- Ethylhexanol are
strongly dependent on the price of the feedstock used. The industrially significant synthetic
pathways are the Acetaldehyde route, Oxo route, Aldox process and the Shell Variant
process. Davy Process Technology (formerly Kvaerner) and Dow (Union Carbide) jointly
have led the development of newer catalytic technologies and have developed a phosphite
ligand modified rhodium catalyst. The two companies have also dominated the licensing of
2-EH process technology. Shell has developed and operates a one-step process that
Discussed below are various ways of producing acetaldehyde from different source of raw
material.
The acetaldehyde route starts from ethylene and operates at near atmosphere pressure.
Aldox process is a case in which co-catalysts are added to the actual Oxo catalyst enabling
aldolization to occur in the same phase. The present invention provides a process for
may be practiced in its most basic form as a distillation. It may also be practiced as part of
a multi-stage continuous process. In either form it begins with a feed stream comprising n-
sufficient to hydrolyze the oligomeric contaminants to and then distill substantially all of
ethylhexanol.
selectivity i.e. at a higher n/i ratio. However, the reaction velocity is lower & part of the
multiple stage distillations to separate, in the first case the first runnings, a fraction
containing the main amount of 2-ethylhexanol, and the residue. In the second case this
improvement residing in cracking the distillation residue by heating the same at 200 to
The cracked products are separated from the non-cracked products and the cracked
homogeneously catalyzed industrial process for the production of aldehydes from alkenes.
This process has undergone continuous growth since its invention in 1938; this chemical
reaction entails the addition of a formyl group (CHO) and a hydrogen atom to a carbon-
carbon double bond. The process typically is accomplished by treatment of an alkene with
temperatures between 40 and 200 °C (Ojima et al., 2000). Transition metal catalysts such
The reaction begins with the generation of coordinatively unsaturated metal hydrido
carbonyl complex such as HCo(CO)3. Such species bind alkenes, and the resulting complex
example, the hydroformylation of propylene as given in this report can afford two isomeric
Versus
These isomers result from the differing ways of inserting the alkene into the M-H bond. Of
course, both products are not equally desirable. Much research has been dedicated to the
hydrogen partial pressures favor the hydrogenation of the resulting aldehyde(s) to the
alcohol(s). For the reaction mechanism it is believed that the aldehyde initially forms a Co-
For the Aldol condensation process, the aldolization reactor may be a mixing pump, a
packed column or a stirring vessel. Local overheating in the reaction mixture must be
avoided since this may cause secondary reactions & thus decrease yields. Subsequent
The oxo process represents the most important synthetic route accounting for over 95% of
converted into an Oxo crude product. The crude Oxo product is a mixture of valuable
byproducts (n– and iso–7 butanol) and the heavy ends. The individual components of the
H2 + CO + CH3CH=CH2 → CH3CH2CH2CHO
n – Butyraldehyde is converted into butyraldol via an alkali catalyzed reaction and then
and iso – butyraldehyde can be selectively converted into 2- Ethylhexenal and then further
processed to 2-EH. However, due to the presence of isobutyraldehyde and the unavoidable
formation of isomeric n/iso and iso/iso aldols (or C8 diols), the quality of the resulting 2-
Basically similar reservations pertaining to the quality of the resulting 2-EH also apply to
the processing of the heavy ends of the Oxo synthesis which also yields 2-EH after
additional hydrogenation. However, one drawback is that in molar terms only 2/3 of the
butanol feedstock is converted into 2-EH, the remaining third resulting as sodium
butanoate.
Commercial 2- Ethylhexanol has the following typical specifications: assay, 99.5% min;
color, water-white; acidity, 0.015% max (acetic acid); specific gravity, 0.8344 at 200C;
boiling point, 184.6 at 760 mmHg. Anhydrous 2-ethylhexanol does not attack common
metals. Tanks constructed from normal steel are reliable for storing 2-ethylhexanol. If
severe demands are imposed on the quality of the product, the tanks should be constructed
Moisture in the atmosphere must be excluded by storing the product under a blanket of
inert gas or by installing a dehumidifier. Drums should be kept tightly closed in a well-
published by the manufacturing chemists association. (Always refer to the Material Safety
Analytical methods based on many of the reactions common to alcohols and alkyl- alcohols
result of the fact that a combination of vacuum and pressure operation has made it possible
for the reaction to be carried at a lower temperature and without excess propylene and
synthesis gas, also the hydrogenation of the 2-ethylhexanol from 2- Ethylhexanal can be
done without the use of steam for heating or refrigerating for condensing or absorption
below usual cooling water temperature. In view of the above, the chosen process has the
following advantages:
16
b) The reaction has less unfavorable side reactions and hence higher yields due
condensers.
e) The mechanical and operating losses of 2- EH are low, owing to the simple
process flow-sheet, lack of recycling, and the few units. The process is
The oxo process presents no significant pollution problems. All byproducts –off –gas, low
boiling and high boiling liquids – can be easily used as fuel to recover their calorific value.
The separation of the cobalt in the catalyst system has been improved so much in the recent
years that the catalyst loss in the effluents is considerably reduced. The wastewater can be
It also has some possible disadvantages: the synthesis gas may contain several percent
methane, which act as an inert in the reactor. Traces of water introduced with the synthesis
gas are not harmful. However, Impurities such as hydrogen sulfide and triethylamine
prevent reaction with the active cobalt complex to form catalytically inactive complexes.
Also, Oxygen must be excluded from the system, during the start up phase when the active
catalyst concentration is being established. Oxygen has been shown to inhibit cobalt
17
permissible. Polymer grade (99+%) pure propylene is needed to be fed vaporized, and
designing for propylene conversions of greater than 95% per pass is required to minimize
propylene losses in the blow down vent stream. There were some problems in mechanical
design and construction materials to withstand corrosion and erosion, but these have been
The equations of the reactions that will take place in the selected process are:
ΔH°298=-262.0 kJ/mol
Ni
H 3 C CH 2 CH 2 CH C(C 2 H 5 ) CHO 2H 2 H 3 C (CH 2 ) 3 CH(C 2 H 5 ) CH 2 OH
ΔH°298=-433.0 kJ/mol
18
propylene and synthesis gas, assuming an operating period of 8,000 hours on stream.
The objective of this design work is to prepare a complete plant design for the production
of 72000 tonnes per year of 2-ethylhexanol using propylene and synthesis gas, choosing the
oxo route and assuming a production run- time of 8000 hours on stream. The first stage of
the process is a Hydroformylation (oxo) reaction from which the main product is n-
butyraldehyde. The feeds to this reactor are synthesis gas (CO/H2 mixture) and propylene
in the molar ratio 2:1, and the recycled products of iso- butyraldehyde cracking. The
reactor operates at 130oC and 350 bar, using cobalt carbonyl as catalyst in solution. The
main reaction products are n- and iso-butyraldehyde in the ratio of 4:1, the former being the
required product for subsequent conversion to 2-ethylhexanol. In addition, 3 per cent of the
propylene feed is converted to propane whilst some does not react. Within the reactor,
however, 6 per cent of the n-butyraldehyde product is reduced to n- butanol, 4 per cent of
small extent yielding high molecular weight compounds (heavy ends) to the extent of 1 per
The reactor is followed by a gas-liquid separator operating at 30 bar from which the liquid
phase is heated with steam to decompose the catalyst for recovery of cobalt by filtration. A
phase of aldehyde, alcohols, heavy ends and water, which is free from propane, propylene,
This mixture then passes to a (first) distillation column which gives a top product of mixed
into an iso-butyraldehyde stream containing 1.3 per cent mole n-butyraldehyde and an n-
carbon monoxide and hydrogen by passage over a catalyst with steam. After separation of
the water and un-reacted iso-butyraldehyde, the cracked gas is recycled to the
The n-butyraldehyde is treated with a 2 per cent w/w aqueous sodium hydroxide and
in the presence of a Raney nickel catalyst with a 99 per cent conversion rate. In subsequent
stages of the process (details of which are not required), 99.8 per cent of the 2-ethylhexanol
(ii) Synthesis gas: from heavy fuel oil, after removal of sulfur compounds and
2.4.4 Utilities
b) To prepare a process diagram for the plant showing the major items of
c) To prepare an equipment schedule, listing the main plant items with their
services required.
d) To prepare energy balances for the hydroformylation reactor and for the iso
condenser.
hydroformylation reactor
a) To prepare a cost estimate of the equipment needed for the plant and hence
the installed plant cost assuming Port Harcourt as the preferred location.
22
H 3 C - CH = CH 2 + H 2 H 3 C - CH 2 - CH 3 ΔH°298=-129.5 kJ/mol
ΔH°298=-135.5kJ/mol
ΔH°298=-262.0 kJ/mol
Ni
H 3 C CH 2 CH 2 CH C(C 2 H 5 ) CHO 2H 2 H 3 C (CH 2 ) 3 CH(C 2 H 5 ) CH 2 OH
ΔH°298=-433.0 kJ/mol
23
Propylene -47.7
Propane -42.1
n- Butyraldehyde 75.5
n- Butanol 117.0
2- Ethylhexanol 184.7
2.6.3 Solubilities of gases at 30 Bar in the liquid phase of the first gas-liquid
separator
H2 0.08
CO 0.53
Propylene 7.5
Propane 7.5
24
T°C x y
where x and y are the mol fractions of the more volatile component (isobutyraldehyde) in
CHAPTER THREE
PROPOSAL
From the narrative of the design problem given in Section 2.4.2, a graphical depiction of
the design process was constructed in an unsimulated Process Flow Diagram (PFD) using
The various processes occurring along the reaction path are highlighted under the
The feed to the reactor consists of propylene and Synthesis Gas. The propylene feed is
made up of fresh propylene feed (1) and recycled propylene (24) from the Cracker, and
stripped propylene from GLS 2(15). The Synthesis gas feed (2) is first used to strip
Reactor. A fraction of the synthesis gas used for stripping is purged (16) to reduce the
concentration of inerts such as CH4, N2 and Propane. The Hydroformylation Reactor is run
at 130oC and 350 bar using Cobalt carbonyl as catalyst in solution. The Cobalt (4) is fed
into the reactor already in solution. In the reactor, the Cobalt reacts with the Carbonyl to
OGUNGBENRO
Adetola E
CHE/2007/083
October- 2- 2012
30
Hydrogenator
29*
14b C
15
12
MIX-103
16
13 24
32
22
3 23
5 11 Mixer Cracker
Mixer 4
25
18 29b
1 10 28
20
6 7 Separator
Oxo R
Compressor VLV-100 12b
Reactor L L
C Mixer2 17 Aldol
RCY-1
Cooler
2 Reactor
8 9 12* C
E-100 DC 29
4 2 P-100
19
GLS-1 VLV-101 GLS DC
2 1 21
26
27a
17* Mixer 21b
14 3
27
Filter
R
RCY-2
Hydro (di) Cobalt (tetra) Carbonyl HCo(CO)4 is generally believed to be the active catalyst
form or at least the precursor to the active catalyst form which also may be HCo(CO)3. The
Higher the Hydrogen partial pressure in the Hydroformylation Reactor and the higher the
Temperature, the greater the concentration of hydro cobalt Carbonyl and hence the greater
of carbon monoxide, may split off carbon monoxide and form cobalt cluster forms that
gradually contain more cobalt and less carbonyl functions, and which are less and less
soluble in the reaction medium, up to the point where the cobalt compounds comes out of
solution in forms that contain little carbon monoxide and approach the state of cobalt metal
or are metallic. This phenomenon is referred to as “cobalt plating”. These clusters and
lower carbonyl containing forms of cobalt are inactive for the hydroformylation reaction. It
is well known that at a given temperature and cobalt concentration, a certain partial
pressure of carbon monoxide is required in order to maintain the stability of the cobalt
carbonyls and to prevent the cobalt to come out of solution and deposit inside the
hydroformylation catalyst is, under constant operating conditions, affected by the gas
composition, e.g. the levels of inerts and those of H2 and carbon monoxide.
For this reason, it is desired to maintain sufficient concentration of Hydrogen in the reactor
to prevent plating out of the Cobalt. This also ensures that the Cobalt is in its active hydro
28
reactor. This is the reason for recycling unreacted hydrogen (32) from the Hydrogenation
reactor into the (MIX-103) to the Hydroformylation Reactor. The concentration of Cobalt
Cobalt plating takes place in GLS-1 by passing saturated steam into it. The steam raises the
temperature of the solution sufficiently for most of the carbonyl to vaporize and plate out
the Cobalt Metal. The GLS is used to separate the aqueous phase (cobalt + Water) from the
organic phase (Butanals & Butanols) since they are immiscible (10). The aqueous phase is
subsequently passed into a filter where some of the water is removed (14) and cobalt +
water (4) are recycled back into the Reactor. Water in the Reactor should not be more than
1.5 weight% of the Propylene feed. GLS-1 operates at 160oC and 30 bar.
The organic phase (12) from GLS-1 is passed through a valve to drop its Pressure to 1 bar;
then cooled to 55oC by a cooler. The temperature and pressure are chosen so as to ensure
that the propylene (B.P -47.4oC) is in gaseous form and the Butanols (108-117oC) and
Butyraldehydes (64.5 – 75.5oC). Fresh synthesis gas is used to strip out propylene, CO and
H2
.
29
The feed to DC 1(17) is first preheated using a Heat Exchanger (Hx-1) to a temperature of
72.55oC.The mixture (17*) is passed into the Distillation column which gives a top product
of mixed butyraldehydes and bottoms containing mixed butanols and heavy ends. The top
product is fed into a second distillation unit which separates the mixture into iso- and n-
butyraldehyde.
The top product (20) from DC 2 is a stream of 98.7% iso-butyraldehyde and 1.3% n-
The Cracker converts iso-butyraldehyde at a pass yield of 80% back to Propylene, CO and
H2 by passage over a catalyst bed with steam. A recycle stream is connected to increase the
quantity and also more reactive during Cracking. The Cracker operates at 275oC and 1Bar.
The phase separator separates out the Propylene, CO, H2 gas, the liquid phase (water) and
the organic phase (un- reacted butyraldehydes) which is recycled into the Cracker.
30
The n-butyraldehyde is treated with a 2% w/w aqueous NaOH and undergoes and Aldol
Bar.
The iso-butyraldehyde passes through the Aldol reactor unreacted. The butyraldehydes exit
the reactor as vapor. The 3-Phase separator separates out a liquid phase of aqueous NaOH,
which is purged before it is recycled back into the Aldol Reactor (25) to prevent
The aqueous phase (29) is pumped into the Hydrogenation Reactor at 50bar (29*). In
exchange with the outgoing materials and adding additional heat by means of high-pressure
pipe coils. A pipe coil is the only convenient and efficient method of heating, for the
reactor is usually so large that heating it is very difficult. It is usually better practice to add
all the heat needed to the materials before they enter the reactor and then simply have the
that once the process is started; the problem may be one of heat removal. This is
accomplished by allowing the heat of reaction to flow into the ingoing materials by heat
exchange in the reactor, or, if it is still in excess, by recycling and cooling in heat
exchangers the proper portion of the material to maintain the desired temperature.
31
operation is usually with a stoichiometric excess of hydrogen which is recycled back into
the Hydroformylation Reactor as stated above (32). The operating conditions of the Reactor
are 150oC and 50 bar. The Product of this reaction 2-Ethylhexanol is recovered at a purity
the resulting stream approach a desired operating condition in the next stage. These include
mixers, valves, compressors, coolers, recycles etc. Table 4 gives a breakdown of these
Equipment Used
of a gaseous stream
condition
equipment temperature of a DC 1
process stream by
coolers (reduce) or
heaters(increase)
components of a Reactor
component, and
collectables/purged
streams
33
Equipment Used
constituents of a
process stream;
cobalt catalyst
filtration
Stream
pressure of flowing
streams
principle as
compressors; except
CHAPTER FOUR
Oguntoye (2008) considered a similar design process for the production of 40000 tons/year
Ethylhexanol (at 99% purity) with a feed of 8535.89 kg/hr of propylene and synthesis gas.
recycle of input feeds and purging of tie- materials and other miscellaneous streams.
Important modifications achieved are in the Aldol Condenser & Cracker processes which
In preparing this report, two methods have been identified as most feasible in arriving at
the material balances for the multi- integrated units of the plant. A choice is the selection of
a basis for propylene feed, which will include that obtained from cracked iso-
butyraldehyde, stripped propylene from the 2nd Gas- Liquid Separator, and fresh
give the various products to be obtained at the end of the hydroformylation process. Ratios
reactors can then be considered along the path of reactions to arrive at a particular 2-
Ethylhexanol throughput for the chosen propylene basis. Scaled ratios of given throughput
(72,000tons/year) to obtained throughput will then provide the amount of propylene feed
35
that would have given the desired throughput. The process calculations are then repeated to
An alternative method which was adopted for compilation of the material balance given in
this report involved starting from the actual throughput given (i.e. 72000tons/year),
the oxo reactor. The second method was preferred as it assures no scaling marginal errors
In computing the energy balance for the cracker and oxo reactor, basic assumptions were
made on the change of temperature from inlet through reference to the exit temperature.
Heat losses to the environment and those due to mixing were considered negligible, and the
mass flow flowrate of utilities (cooling water and steam) were calculated from heat balance
equations.
A simplified Block Flow Diagram (BFD) of the Process Flow Diagram (Fig 2) is as
presented in Fig 3. The material balance will be computed based on the BFD in Fig 3.
Recycled Streams
MIXER 36
Purge 1 Purge 2
Dry Steam 35
Stream of alkene
bar
Filter
Cobalt
275°C 1 bar
Recycle
DC 2 Mixed Aldehydes
ALDOL REACTOR
SEPARA
2- EH (90%) Major n- stream
HYDROG TOR
ENATOR
Runtime (i.e. total number of operating hours of the plant in a year) = 8,000 hours
9000
Throughput= 69.109kmols/ hr
130.23
69.109
Actual Amount produced= 69.247kmols/ hr
0.998
4.1.1 Hydrogenation
Ni
H 3C CH 2 CH 2 CH C (C 2 H 5 ) CHO 2 H 2 H 3C (CH 2 ) 3 CH (C 2 H 5 ) CH 2 OH
(Rxn 1) 2- Ethylhexenal 2- Ethylhexanol
Ni
Catalyst
2 Ethylhexenal 2 Ethylhexan ol
99%
Convers
ion
H2
From (Rxn 1), 69.247 kmols/hr of 2- Ethylhexanol had been produced at stoichiometric
69.247
= 69.946 kmol / hr
0.99
From (Rxn 1); 1 mole of 2- Ethylhexenal requires 2 moles of hydrogen (H2). However,
69.946 kmoles/hr of the aldehyde was sent in but 69.247 kmoles/hr was converted.
hydroformylation (oxo) reactor i.e. 138.494 kmoles/hr H2 was recycled into OXO reactor.
= 69.946-69.247
From (Rxn 2), 2 moles of n- butyraldehyde produced 1 mole of 2- Ethylhexenal and 1 mole
2% w/w Aq.
NaOH
K
F1 ALDOL REACTOR
90% CONVERSION
EFFICIENCY
Recycle, R1
Ethylhexenal.
By relationship provided,
R1= 0.1F1
Feed to Distillation Column 2 is mixed aldehydes after alcohols have been removed by
DC1, & others (propane, propylene, CO & H2) have been removed by GLS 2.
= 0.944P
D, xD
FDC2 = D+W
ZF = 0.203
W,xw
F1 141.305
= 143.02kmols / hr
0.988 0.988
0.740128 P 139.445
P 188.41kmols / hr
F 177.86kmoles / hr
D F W 177.86 143.02
D 34.835kmols / hr
4.1.4 Cracker
Top Product D goes into cracker. 34.835 kmols/hr of stream goes into cracker; only 34.382
been purged.
FC
CRACKER
R2
( FC R2 ) * 0.2 R2
34.382 R 5 R2
R2 8.5955kmols / hr
44
Total number of moles of iso- butyraldehyde that goes into cracker (with recycle)
From stoichiometry of cracking process (Rxn 3); 1 mole of iso- butyraldehyde cracks into
= 136.075 kg
= 13743.53 kg
188.41
198.326kmoles of propylene actually went into OXO reactor
0.95
= 310.709 kmoles/hr
= 3.967 kmoles/hr
= 5.95 kmoles/hr
= 151 kmoles/hr H2
= 153.801 kmoles/hr CO
= 4.6606 kmoles/hr N2
= 332. 472
To determine exact amount of propane leaving the OXO reactor, it requires taking excess
GLS 1: A certain amount of propylene dissolves in GLS 1 while the remaining is given off.
= 103.08 kg
3.966 kmols/hr of propylene were fed into GLS 1, i.e., 3.966 * 42.08 = 166.89 kg
GLS 2:
103.08
Amount of propylene into GLS 2= = 2.45 kmols/hr
42.08
48
This amount of propylene is completely stripped by synthesis gas, and recycled back to
OXO reactor.
7
Propane in Fresh feed= *152.9 11.509kmols/ hr
93
= 17.459 kmols/hr
Table 5 gives the material balance outlook on components involved in the oxo reactor.
Cobalt is 1% by weight of the inputs into hydroformylation reactor. However, unlike heavy
ends that is purged, Cobalt is constantly being recycled; hence, no need to include it in
material balance.
kg Cobalt=
1
((198.33 * 42.08) (196.7785 * 28) (332.472 * 2) (11.509 * 44) (4.6608 * 28) (1.2428 * 16)
99
146.59
49
Table 5: Material Balance Data for Inputs and Outputs of OXO Reactor.
CO 196.7785 8.3658
H2 332.472 127.561
N2 4.6608 4.6608
n- butyraldehyde - 141.684
isobutyraldehyde - 36.175
n- butanol - 9.0437
Q, Steam
Oxo Exit
GLS 1
Off gases
From solubility properties of the gases, we calculate the amount that dissolves in GLS 1.
Dissolved gases are sent into GLS- 2. Undissolved components of the gases above and
166.89 103.08
Off gas propylene= 1.516kmols/ hr
42.08
234.2424 7.28
Off gas CO= 8.1058kmols / hr
28
255.122 1.1
Off gas H2= 127.011kmols/ hr
2
768.196 103..08
Off gas propane= 15.116kmols/ hr
44
These changes in some component products from OXO exit were effected, as shown in
Table 6. Table 6 gives the inlet- outlet data for GLS-1, where the outlet proceeds to GLS-2,
Table 6: Material Balance Data for Inlets, Outputs and Off- Gases for GLS 1
Gases(kmols/hr)
(Recycled)
N2 4.6608 - 4.6608
3
INLET represents the exit of oxo reactor
53
By the design statement, the GLS 2 achieves total stripping of propylene (for recycle back
Also remnants of propane, CO, H2 are discharged. Table 7 gives data values for resultant
process in GLS 2.
A complete overview table on the flowrates (in kmols/hr) of the various material
components in the major equipment is as given in the Table 8. A number of streams were
considerations were given to equipment with limited efficiencies, such as the Aldol reactor
and cracker, and proper recycle processes were devised to ensure optimization.
kmols/hr of fresh feed, and others made up from recycled streams and cracked iso- butanal.
Also, 196.7785 kmols/hr of CO and 332.472 kmols/hr of Hydrogen (synthesis gas) will be
CO 0.26 - 0.26
H2 0.55 - 0.55
The energy balance for the Hydroformylation reactor and the Cracker unit was carried out
The reactants entering the reactor & cracker go from their entrance temperature to
The products go from the reference temperature to their nominal exit temperature.
Overall enthalpy change = mass of water × specific heat capacity of water × Temperature
change
(Iso)
Operating condition
T = 403.15k
P = 350 Bar
57
(kmol/hr)
H2 0 332.472 0
Nitrogen 0 1242.8 0
4
Appendix C, Table C-4, Van Ness, Smith & Abbott, Introduction to CHE Thermodynamics, 6th Ed; p. 637
58
Total Enthalpy of formation of the inlet components into the hydroformylation reactor =
Assuming there is no heat loss to the environment and the heat of mixing is negligible;
T
C p
Thus, Q = (net) niH°f + ni dT
T0
R
Where:
(mol/hr)
impurity)
Energy Balance
Water
Heat of Reaction
Inlet stream
Cooling Water
The Enthalpy in bringing the reactants from 403.15K to reference temperature (i.e H in )
+ Enthalpy of Formation ( H F ) at 298K + Any heat supplied (or removed) by Dry Steam/
Cooling water streams) equals the Enthalpy in taking the products from reference
Table 4 shows the extracted Cp values from the literature. The relationship below was used
T
ni C p dT where ni is the number of moles of a particular component,
T0
Cp = A + BT + CT2 + DT3
Table 11: Extracted Cp Data for Major Components (Coulson and Richardson, 2007)
n Hpropylene=
298 .15
2
198.330 3.71 0.235T (1.16E 04)T (2.20 E 08)T 3 1514225kJ / hr
403 .15
Similar values can be computed for other components. For certain components present in
both inlet and exit streams we simply take a net mole balance product on CP, since the
Hence; Hpropylene=
298 .15
2
(198.330 + 3.966) 3.71 0.235T (1.16 E 04)T (2.20 E 08)T 3 dT =
403 .15
-1544505.274kJ/hr
For CO= -699971.385 kJ/hr ; H2= -2396883.824 kJ/hr ; Propane =-257912.5186 kJ/hr
Evaluating= 1778840.221+471978.9746+117898.32+18259.60-(-257912.5186-
HLsat = 104.8KJ/kg
M1 = 2902.32kg/hr
4.2.2 Cracker
35 Bar
Unreacted Iso-butanal
35 Bar
Heat of formation + Sensible Heat + Dry steam enthalpy + Heat of reaction = (CO,
∑ = -7511.280 KJ
65
The operating temperature (435K) is out of range of T-max in which heat capacity values
properties of components to evaluate Reduced Temperature (Tr) and reduced pressure (Pr)
Residual enthalpy correlation by Lee/Kesler is used to estimate one sensible heat because
the operating condition of cracker is out of range of T-max and P-max Values within which
Calculation of sensible heat for raising temperature of inlet stream from 250C to 2750C
Component Tc Pc Tr Pr ω
The following values below were extenuated from the general Lee/Kesler Residual
∑niHR -4029.202 kJ
= -7511.280 - 4029.202
= -11540.482 kJ
H = -11540.482 kJ
Note: Negative sign of ΔHoR in Reaction Data given is reversed since the reaction is
reversed.
67
∑ ΔHoR ni 4480.657 kJ
Energy Balance
Sat.d Water
35Bar
of Reactants Heat
= -14571.105kJ
2327.674M2 = 14571.105 KJ
In computing the energy balances for the two reactors, a number of minimal assumptions
were optioned. For the oxo reactor operating at 350 bar and 403.5 K, the total enthalpy of
entry reactants is -193911.85113kJ/hr, while the enthalpy of formation of products (at 298
K basis) was -29598.9 kJ/hr The heat supplied from the utility stream (in this case cooling
water at 298 K) was obtained from heat balance as + 7117937.166 kJ/hr, and the
For the cracker unit, Dry saturated steam was supplied at 35 bar as utility at a mass flow
CHAPTER FIVE
To determine the feed stream volumetric flowrate, we sum up the IN column in Table 5:
Assuming a Feed molar volume of 0.10m3/kmol, the Feed stream volumetric flowrate =
= 74.50m3/hr
Assuming a 98% conversion in the reactor, the residence time can be interpolated from
Conversion(%) Time(min)
96.489 90
98 Tr
99.5 105.432
Tr = 99.250mins
70
= 123.24 m3
the operating temperature and pressure. Since the operating condition of the reactor is
Dimension of Oxo-Reactor: Heuristics have it that the reactor is generally 90% full and
123.24
Volume of the reactor = = 136.93 m3
0.9
2 * r 3 * D 2 L
Total Volume of the reactor tank = 2
3 4
Then, L = H – D, hence
71
4 * r 3 * D 2 ( H D)
Volume of the reactor, V =
3 4
* D 3 * D 2 ( H D)
V=
6 4
* D 3 * D 2 (2D)
V=
6 4
2 * D 3
V=
3
2 * D 3
Then, Volume of reactor = = 136.93m3
3
Diameter, D = 3.519m,
Length of cylinder = H - D
= (10.558 – 3.477)m
= 7.038m
From Table 8, the total feed input into the cracker = 0.453 +42.9775 = 43.4305 kmols/hr.
Also the molar flowrate of i-butyraldehyde feed into the cracking unit is 42.9775 kmol/hr
and that of n-butyraldehyde is 0.453 kmol/hr. Residence time still remains 99.25 mins
Mass flow rate of i-butyraldehydes = 72.12 kg/kmol × 42.9775 kmol/hr = 3099.5373 kg/hr
72
.
Mass = 3099.5373 kg/hr × hr = 5127.15 kg
Mass flow rate of n-butyraldehydes = 72.12 kg/kmol × 0.453 kmol/hr = 32.671 kg/hr
.
Mass = 32.671 kg/hr × hr = 54.042 kg
.
Volume = = = 0.068 m3
Heuristics have it that it is safe to have a storage tank filled up to 90% of its capacity
Assuming that the cracking unit have the same shape as the Oxo-reactor, then
2 * D 3
V= = 7.178 m3
3
Diameter D = 1.508 m
= 3.015 m
From Table 8, the total feed input into the Aldol Condenser is 141.305 + 1.7162= 143.0212
kmols/hr
From material balance, it has been calculated that the molar flowrate of n-butyraldehyde
feed into the Aldol condenser is 141.305 kmol/hr and that of i-butyraldehyde is 1.7162
Mass flow rate of n-butyraldehyde = 72.12 kg/kmol ×141.305 kmol/hr = 10190.92 kg/hr
.
Mass = 10190.92 kg/hr × hr = 16857.474 kg
.
Volume = = = 21.23 m3
Mass flow rate of i-butyraldehydes = 72.12 kg/kmol × 1.7162 kmol/hr = 123.772 kg/hr
.
Mass = 123.772 kg/hr × hr = 204.74 kg
Heuristics have it that it is safe to have a storage tank filled up to 90% of its capacity
Assuming that the Aldol condenser unit have the same shape as the Oxo-reactor, then
74
2 * D 3
V= = 23.873 m3
3
Diameter D = 2.251 m
Since the operating condition of the reactor is 115oC and 3bar, then, by heuristics
From Table 8, total feed input into the hydrogenation reactor = 280.3522 + 3.3642 +
From material balance, it has been calculated that the molar flowrate of hydrogen feed into
Assuming that the hydrogenation reactor have the same shape as the Oxo-reactor, then
2 * D 3
V= = 10387.984 m3
3
Diameter D = 17.054 m
Heuristics have it that it is safe to have a storage tank filled up to 90% of its capacity
Since the operating condition of the reactor is 150oC and 50bar, then, by heuristics
Table 12 gives the design parameters of these major plant items as calculated above.
From material balance, it was calculated that the fresh propylene feed from the propylene
tank is 152.9 kmol/hr. Having calculated the residence time which can be said to be
equivalent to the retention time of propylene in the propylene tank, at STP condition
.
Volume of Propylene = (152.9 kmol/hr × ) × 22.4 m3/kmol = 5665.45 m3
Heuristics have it that it is safe to have a storage tank filled up to 90% of its capacity
V= , where H = 3D
V=3 = 6294.95m3
From material balance, it was calculated that the fresh synthesis gas from the storage tank
is 310.709 kmol/hr. Having calculated the residence time which can be said to be
equivalent to the retention time of Synthesis gas in the storage tank, at STP condition
.
Volume of Synthesis gas = 310.709 kmol/hr × × 22.4 m3/kmol = 11512.804
m3
Heuristics have it that it is safe to have a storage tank filled up to 90% of its capacity
V= , where H = 3D
V=3 = 12792 m3
D = 11.072 m
H = 3 × 11.072 m = 33.216 m
From material balance, it was calculated that the fresh hydrogen gas from the storage tank
is 280.352 kmol/hr (with methane impurity). Having calculated the residence time which
can be said to be equivalent to the retention time of hydrogen gas in the storage tank, at
STP condition
Heuristics have it that it is safe to have a storage tank filled up to 90% of its capacity
V= , where H = 3D
V=3 = 11542.20 m3
D = 10.70 m
H = 3 × 10.70 m = 32.1 m
From material balance, it was calculated that the 2-Ethyl hexanol produced was 69.247
kmol/hr. Having calculated the residence time which can be said to be equivalent to the
retention time of 2-Ethyl hexanol in the storage tank and density of 2-Ethyl hexanol is
833.00 kg/m3
14917.336kg
.
Volume = = 17.908 m3
.
Heuristics have it that it is safe to have a storage tank filled up to 90% of its capacity
V= , where H = 3D
V=3 = 19.898m3
D = 1.283 m
H = 3 × 1.283 m = 3.850 m
The standard material of construction is carbon steel. It is usually the cheapest metal that
can be used in fabricating equipment. However, it generally is not used below -45.6oC
because of a loss of ductility and impact strength, nor is it generally used above 510 oC,
because of excessive scaling rates. It is not good for mildly acidic conditions, because
under these circumstances corrosion is greatly accelerated. Carbon steel cannot be used in
the production of most polymers because even trace amounts of iron discolor the product.
Glass-lined or stainless steel equipment is required for any product that may be ingested by
The temperatures and pressures in the processing equipment are a function of the
processing conditions and the properties of the substances used. For instance, the highest
temperature in a distillation column can be estimated by knowing the boiling points of all
the key components at the operating pressure. The highest boiling point will be close to the
The temperatures and pressures in the storage system depend on the physical properties of
Parameter
Table 14: Material of Construction and the Operating Temperatures and Pressure of the Major Items of Equipment
Equipment Physical Function Size (m3) Operating Material of Preferable Steam Cooling Water
Description Temperature Construction Characteristics
and Pressure
Hydroformylati Cylindrical For the 136.93 130 oC, 350 Austenitic Better corrosion - 2.9 tonnes/hr
on Reactor with a dome- reaction bar Stainless steel resistance and
shaped end between 304 (with few improved resistance to
Synthesis gas % molybdenum pitting.
and Propylene
gas
Gas-Liquid Cylindrical, Separation of 152.750 160 oC, 30 bar Low-Carbon Readily available, low 13.896ton/hr -
Separator 1 but with its the catalyst Steel (Type cost, excellent
lengthy side from the 304L and ductility and easily
place product 306L) welded
vertically
Gas-Liquid Cylindrical Separation of 147.328 55oC, 1 bar Low-Carbon Readily available, low 4.328 tons/hr -
Separator 2 with a dome- the gaseous Steel (Type cost, excellent
shaped end product from 304L and ductility and easily
the liquid 306L) welded
product
Distillation Oblong Separation of 157.928 72.55oC, 1 Ferritic Corrosion resistance 24.851ton/hr 16.746ton/hr
Column 1 Cylindrical butyraldehydes bar Stainless Steel and very resistant to
with a dome- from alcohols (Type 430) scaling and high-
shaped end temperature
Design Temperature & Pressure heuristically 1.1 times Operating Conditions
82
Distillation Oblong Separation of 179.50 65.02oC, 1 Ferritic Corrosion resistance 18.728ton/hr 16.746ton/hr
Column 2 Cylindrical n- and i- bar Stainless Steel and very resistant to
with a dome- butyraldehydes (Type 430) scaling and high-
shaped end temperature
-
o
Cracking unit Cylindrical Thermal 6.461 275 C, 1 bar Low Alloy Better corrosion 6.26tons/hr
with a dome- cracking of i- steel, austenitic resistance and
shaped end butyraldehyde type 20% Cr; improved resistance to
29% Ni; 2.5% pitting
Mo; 3.5% Cu
o
Aldol Cylindrical Aldol 23.873 115 C, 3 bar Austenitic Better corrosion - 16.540 ton/hr
Condensation with a dome- Condensation Stainless steel resistance and
Reactor shaped end of n- 316 (with few improved resistance to
Butyraldehyde % pitting
molybdenum)
Hydrogenation Cylindrical Hydrogenation 11452.204 150 oC, 50 bar Austenitic Better corrosion 14.325ton/hr -
reactor with a dome- of 2-Ethyl Carbon steel resistance and
shaped end Hexenal to 2- (with few % improved resistance to
Ethyl Hexanol molybdenum pitting.
e.g. Stainless
steel type 316)
Hydrogenator Oxo Reactor
K- 102: Regenerator
C3 + SYN GAS
Co Catalyst Filter
Cooling Water
n- Butanal
NaOH
CHAPTER SIX
M = 72.11 kg/kmol
85
Composition of DC 2
Inlet Exit
141.304 kmol/hr(Bottom)
From equipment schedule completed, feed into Distillation Column 2 (DC2) is 177.86
kmols/hr. This contains 0.797 mole fraction n- butyraldehyde and 0.203 mole fraction iso-
butyraldehyde.
TI= 72.65°C
J/mol°C (J/mol)
= 31176.764 J/mol
= 153.01366 J/mol°C
= 32347.3185J
32347.3185
q = 1.0375
31176.764
87
1.0375
Slope of q line = 27.634
1.0375 1
Fig 10 shows the x-y plot with the XB (iso-butyraldehyde concentration in bottoms), XD
feed) marked. The q-line is drawn from the point of intersection of XF and the 45 degree
line with a slope of 27.634 using the line equation: y-y1 = M(x-x1). M is the slope, x1:y1 are
the coordinates of intersection of XF and the 45° line. Thus, we substitute a value for x to
The XD operating line is drawn through the point of intersection of the x-y plot and the line
to intersect the y axis at point 0.0925 (Fig 10). This corresponds to XD/ (Rm + 1), where Rm
is the minimum reflux ratio. Since XD = 0.987, we calculate Rm to be 9.6703. The optimum
reflux ratio R is obtained by using typical values suggested in the literature, and usually
R = 1.5*Rm = 14.5054.
A new point XD/(R+1) is located on the y axis and the operating line of XD is drawn to pass
through this point. The operating line of XB is drawn to pass through the intersection of the
q-line and the new XD operating line and the steps are drawn as shown in Fig 11 to obtain
The number of trays obtained from the McCabe Thiele- Plot is 46 trays.
90
46
Fig 11: McCabe- Thiele Plot for Distillation Column (DC) 2 (No of trays =46)
91
FLOWRATES
Area of hole Ah
0.10
Area of Pitch Ap
92
0.2 0.5
20 g
Csb, flood = Unf
L g
0.2 0.5
16.1 739.58 2.584
Unf = 0.28
20 2.584
G 38948.55(kg / hr )
Volumetric Flow rate of Vapor=
3600 * g 3600( s / hr ) * 2.584(kg / m 3
= 4.187 m3/s
Lw
Let 0.70 ; Lw= weir length, DC= Column Diameter
DC
2 2
Area of Column (AC) = 0.25 * * DC 0.785 DC
94
L / 2
sin C w 0.7
2 DC / 2
C 88.85
2 C Lw DC C
Area of downcomer (AD) = 4 * DC 360 2 2 cos 2
2
DC
= 0.775 0.5 0.0688DC 2
4
An= AC - AD
Lw = 0.7*2.301= 1.611m
Lw ≈ 1.6m
AD = 0.0688*(2.301)2
= 0.3643 m2
= 4.1584- 2*(0.3643)
= 3.4298m2
Lw 1.6
0.696;
DC 2.3
L
C 2 arcsin w
DC
88.16
ACZ= 2(60mm) * Lw= 0.192m2
95
A CZ 0.192
0.0462
AC 4.1584
A CZ 4.6%A C
180 88.16
91.84
Waste Zone Area is AWZ
2
DC 0.06 *
2
Waste zone area, Awz = 2 * * DC
4 360 4 360
= 2 * 1.06085 1.0062
= 0.1092m 2
A WZ 0.1092
0.0262
AC 4.1584
= 3.731 m2
= 0.1 * 3.731
= 0.3731 m2
4 Ah 4 * 0.3731
Number of holes, nh =
d h
2
* (5 *10 3 ) 2
= 19002 Holes
pg 2
hd = K1 + K 2 ( )U h (Hobson et al., 1994) where
L
50.8
K2 2
; where CV = Discharge coefficient
CV
Tray Thickness, t T 3
0.6 ; we have that
Hole Diameter, d h 5
50.8
K2 = 92.77
0.74 2
Uh =
× ×
38948.55
(Uh)top = = 11.222 m/s (minimum)
2.584 * 3600 * 0.3731
38948.5
(Uh)bottom = = 11.421 m/s (maximum)
2.539 * 3600 * 0.3731
pg 2 2.584
(hd)top = K2( )U htop = 92.77* ( ) *11.2222
L 739.58
2.539
(hd)bottom = 92.77* ( ) *11.4212 = 41.244 mm of clear liquid
744.93
97
hσ = 409 (Hobson et al. 1994)
Ldh
16.1
hσ= 409* =1.78 mm of clear liquid
739.58 * 5
2
q 3
Height of crest over weir, hOW = FW * 664 * where
LW
36437.183
q= = 13.69 *103 m 3 / s
× 739.58 * 3600
2
13.69 * 10 3 3
hOW = 1.02*664* 28 mm of clear liquid
1.6
Head loss due to bubble formation, hσ + Pressure drop across dry hole, hd =
Flooding Check.
Since the maximum flow rate occurs at the bottom, flooding will be checked at the bottom.
Height of clear liquid over the dispersal, hds = hW + hOW + hhg*0.5 (For sieve trays);
(hOW)bottom = 27.9 mm
38948.55
Ua = 1.360m / s 4.46 ft / s
3600 * 2.539 * 3.4298
Pressure drop through aerated material, hl1 = β × hds = 0.61 × 71.9 = 43.859 mm
h1 ' 43.859
Actual height of froth, hf = 199.36mm
t 0.22
2
q
Head loss under the down-comer, hda = 165.2 b where
Ada
Lb 36437.183
qb =
×
= 13.59 *10 3 m 3 / s
L 3600.744.93
2
13.598 * 10 3
hda = 165.2 × 5.42mm
0.07504
Total head loss across the plate, ht = hd + hl' = 41.244 + 43.859 mm = 85.104mm
Total head loss across the rectifying section, hdc = ht + hw + how + hhg + had
162.424
Actual back-up, hdc = 324.848mm < 457.2mm
0.5
Since Actual back-up < Tray spacing, i.e. 324.848 mm < 457.2 mm, then it can be said that
et al., 1994)
= 0.226
38948.55
Ua = 1.231m / s
3600 * 2.562 * 3.4298
LW DC 1.6 2.3
Width of flow path on plate, Df = 1.95m
2 2
100
q
Liquid flow rate, w = ;
Df
36.437.183
q= = 0.01369m 3 / s
× 739.58 * 3600
w= 7.018 *103 m 3 / m s
(0.776 0.00457* 44) – 0.238 (1.231) (2.562) 0.5 (105 * 7.018 *10 -3
Ng =
(0.226)0.5
Ng = 2.619
hL Aa
θL = , where hL = Liquid hold-up on plate
1000qb
40.81* 3.4298
L 10.30 sec onds
1000 *13.59 *103
G Gm 38948.85
Stripping factor at top, λt = 0.49* m ; 1.069
Lm Lm 36437. 183
λ= 0.877
1
N og
1
N g N liq
1
= = 2.24
1 0.877
2.619 13.39
{ ( )}
Eoc = , where Ea = Murphee vapor efficiency
( )
0.5 0.5
L g 36437.183 2.562
For G *
38948.85 739.58 = 0.0551
L
1
Ea = 0.8935× ( ) = 0.8453
0.06
1 0.8935 *
1 0.06
Area of hole Ah
0.10
Area of Pitch Ap
0.2 0.5
20 g
Csb, flood = Unf
L g
0.2 0.5
18 745.6 2.73
Unf = 0.27
20 2.73
G 38948.55(kg / hr )
Volumetric Flow rate of Vapor=
3600 * g 3600( s / hr ) * 2.730(kg / m 3
= 3.963 m3/s
Lw
Let 0.67 ; Lw= weir length, DC= Column Diameter
DC
2 2
Area of Column (AC) = 0.25 * * DC 0.785 DC
L / 2
sin C w 0.67
2 DC / 2
C 83.62
2 C Lw DC C
Area of downcomer (AD) = 4 * DC 360 2 2 cos 2
2
DC
= 0.730 0.5 0.0575DC 2
4
Lw = 0.67*2.263= 1.516m
Lw ≈ 1.5m
AD = 0.0575*(2.263)2
= 0.2945 m2
= 4.0221- 2*(0.2945)
= 3.4331m2
Lw 1.5
0.652;
DC 2.3
L
C 2 arcsin w
DC
81.41
ACZ= 2(60mm) * Lw= 0.180m2
A CZ 0.180
0.0448
AC 4.0221
A CZ 4.5%A C
180 81.41
98.59
2
DC 0.06 *
2
Waste zone area, Awz = 2 * * DC
4 360 4 360
= 2 * 1.1015 1.0439
= 0.1152m 2
A WZ 0.1152
0.02865
AC 4.0221
= 3.1379 m2
105
= 0.1 * 3.1379
= 0.3138 m2
4 Ah 4 * 0.3138
Number of holes, nh =
d h
2
* (5 *10 3 ) 2
= 15982 Holes
pg 2
hd = K1 + K 2 ( )U h (Hobson et al., 1994) where
L
50.8
K2 2
; where CV = Discharge coefficient
CV
Tray Thickness, t T 3
0.6 ; we have that
Hole Diameter, d h 5
50.8
K2 = 92.77
0.74 2
Uh = × ×
106
38948.55
(Uh)top = = 13.579m/s (maximum)
2.539 * 3600 * 0.3138
38948.5
(Uh)bottom = = 12.629 m/s (minimum)
2.730 * 3600 * 0.3138
pg 2 2.539
(hd)top = K2( )U htop = 92.77* ( ) *13.5792
L 744.93
2.730
(hd)bottom = 92.77* ( ) *12.6292 = 54.175 mm of clear liquid
745.6
hσ = 409 (Hobson et al. 1994)
Ldh
18
hσ= 409* =1.97 mm of clear liquid
745.6 * 5
2
q 3
Height of crest over weir, hOW = FW * 664 * where
LW
49262.67
q= = 18.35 *10 3 m 3 / s
× 745.6 * 3600
2
3
18.35 *10 3
hOW = 1.02*664* 35.96 mm of clear liquid
1.5
Head loss due to bubble formation, hσ + Pressure drop across dry hole, hd =
Flooding Check
Since the maximum flow rate occurs at the top, flooding will be checked at the top.
Height of clear liquid over the dispersal, hds = hW + hOW + hhg*0.5 (For sieve trays);
38948.55
Ua = 1.241m / s 4.072 ft / s
3600 * 2.539 * 3.4331
Pressure drop through aerated material, hl1 = β × hds = 0.60 × 71.9 = 43.14 mm
h1 ' 43.14
Actual height of froth, hf = 187.57mm
t 0.23
2
q
Head loss under the down-comer, hda = 165.2 b where
Ada
Lt 49262.67
qb = ×
= 18.37 * 10 3 m 3 / s
L 3600 * 744.93
2
18.37 * 10 3
hda = 165.2 × 11.26mm
0.07035
Total head loss across the plate, ht = hd + hl' = 58.303 + 43.14 mm = 101.443mm
Total head loss across the stripping section, hdc = ht + hw + how + hhg + had
192.703
Actual back-up, hdc1 = 385.406mm < 457.2mm
0.5
Since Actual back-up < Tray spacing, i.e. 385.406 mm < 457.2 mm, then it can be said that
g , ave 8.025 * 10 3 * 10 3
Nsc,g = Gas phase Schmidt number =
g * Dg 2.635 * 0.148 * 10 4
= 0.206
38948.55
Ua = 1.196m / s
3600 * 2.635 * 3.4331
109
LW DC 1.5 2.3
Width of flow path on plate, Df = 1.9m
2 2
q
Liquid flow rate, w = ;
Df
49262.67
q= = 0.01837m 3 / s
× 744.93 * 3600
w= 9.6682 *10 3 m 3 / m s
(0.776 0.00457* 44) – 0.238 (1.196) (2.635) 0.5 (105 * 9.6682 *10 -3 )
Ng =
(0.206)0.5
Ng = 3.371
hL Aa
θL = , where hL = Liquid hold-up on plate
1000qb
58.303* 3.4331
L 10.90 sec onds
1000 *18.37 *103
G Gm 38948.85
Stripping factor at top, λt = 0.49* m ; 0.7906
Lm Lm 49262.67
110
λ= 0.6482
1
N og
1
N g N liq
1
= = 2.916
1 0.6482
3.371 14.01
{ ( )}
Eoc = , where Ea = Murphee vapor efficiency
( )
0.5 0.5
L g 49262.67 2.635
For G *
38948.85 744.93 = 0.0752
L
1
Ea = 0.946× ( ) = 0.8921
0.06
1 0.946 *
1 0.06
= 10.82 kg/s
= 31506500 kJ/kmol
= 436.923 kJ/kg
∴ ΔT = 40-25= 15oC
4727.50 * 1000
mc = 4285 * 15 = 73.55 kg/s
(T1 t 2 ) (T2 t 1 )
(T t )
ln 1 2
LMTD= (T2 t 1 )
4727.50 * 1000
600.13
∴ A assumed = 250 * 31.51 m2
= 0.29 m2
A assumed 600.13
2077.5
∴ Number of tubes (Ntubes) = a heat- transfer 0.29
≈ 2078 tubes
a pipe x N tubes
N tube passes
Flow area per pass (atube) =
Ntubepasses = 6
m pipe
pipe * a tube
Velocity of fluid (Vpipe) vp =
73.55
1.10m / s
∴ vp = 994.865 * 0.067
a) Shell side:
4 4 W 4 10.82
* 2
* 2
3
0.0004 3
Reynolds’s Number (NRE) = ( N tubes ) * L 2078 * 4.877
NRE= 136
1 1
3
1.51 * (D o * 2 g) 3 N RE 3
Nusselt’s Number, Nu = 2
= 182 .92
h o (D o )
Nu = K
Nu * K 182.92 * 0.121
ho
Do 0.0191 ) = 1158.80 W/m2K
b) Tube side:
m
Super icial Mass Velocity, G =
a
116
73.55
G = = 6586.567 kg/m s
0.067
6
(D )G 0.0157 ∗ 6586.567
N = = = 2.60 × 10
µ 0.4 × 10
µC 0.4 × 10 × 4.285 × 10
Prandtl Number, N = = = 14.17
K 0.121
h (D )
= 0.023(Re . )(Pr .
)
K
c) Fouling factor
1 1 Do 1
* Fouling Factor
Uo h o DI h i
1 1 0.0191 1
* 0.003
U o 1158.80 0.0157 53211.22
a) Tube Side :
4fLVp 2
**g
= 2 * g * D I
= 1.470 KPa
Pressure Drop in the end zones ΔPe = 2.5 ρ* Vp2 = 2.5 x 994 x 1.12 =3.00 KPa
Number of baffles =0
= 0.1475 m2
118
PT 1 2
2 * 0.86PT 2 * 4 * D O
4
* DO
De = 2
0.254 1 2
2 * 0.86 * 0.254 2 * 4 * 0.0191
4
* 0.0191
= 2
= 3.6795m.
m shell 10.82
Gs= Superficial velocity in shell = mshell = a shell 0.1475 = 73.36 kg/m2
G S * D e 73.36 * 3.6795
3
3.22 *10 7
(NRE) s = 8.3896 * 10
4f ( N b 1) D S G S 2 g
* 0.5
2 gD
∴ Shell side Pressure Drop ΔPs = e vapor
; Nb = 0
= 0.0405 KPa
119
Table 16 below gives an outline of the flow and properties of DC 2. Dimensioned sketch of
the distillation column, reboiler and condenser is given in Fig 12 and 13.
6.4 Notations
Flooding (%) 80 80
25.89
2.602m
2.602m
REBOILER
CONDENSER
CHAPTER SEVEN
DISTILLATION COLUMN
7.1.1 Shell
=1.1362 kg/cm2
stress relieved
Insulation thickness 75 mm
125
Height 4meters
Number of trays 28
Spacing 457.2 mm
Hole diameter 5 mm
Thickness 3 mm
Weir height 44 mm
0.5
PD i 2
ts = +C
2fJ - P
strip
J = 85% = 0.85
0.5
PR 2 W
th C
2fJ
1 RC 1 2462
W 3 3 1.77
4 R K 4 147.72
0.5
1.1362 * 246.2 2 * 1.77
th 8.687cm 87mm
2 * 950 * 0.85
OD 2
Diameter OD 2S f i cr
24 3
95.51 2
Diameter 95.51 2 * 1.5 * 0.75 = 104.5 inches=265.35 cm
24 3
Weight of Head = * 265.35 2 * 8.7 * 7.85 * 10 3
4
= 3776.74 kg
Weight of Shell
Fds
Cross sec tion Area of Shell
OR,
Fds = ρs (X)
ρs = 7850 kg/m3
= 0.00785 kg/cm3
tins = 75 mm = 7.5 cm
= 7.76*10-4 X kg/cm2
(3) Compressive stress due to liquid & tray in the column up to height (X) meters.
(x 1) D i 2
Fliq 1 * * liq
tt 4
2
( x 1) * 2.3
Fliq 1 * * 743.76
0.4572 4
= (x - 0.5428)*6758.84 kg
= (x-0.5428)*1.481 kg/cm2
Mw
Fwx
z
Pw = Wind Pressure
= 45 lb/ft2
1.8285x 2
Fwx = 6.73 * 10 6 x 2 kg/cm2
271605.47
Tensile:
Ft,max = fJ
x = 115 meters
132
t
0.125E
∴ Fc,max = Do
Do = 2462 mm
81
Fc,max = 0.125 * 2 * 10 6 8225kg / cm
2
2462
x= 344 meters
Since calculated height is greater than the actual tower height. So we conclude that the
ts = 0.081 meters
= 148375 kg.
= 11562.6 kg
= 123147 kg
3 0.5
H 2 W
-5
Tmin = 6.35 * 10 * min
D ts
3
0.5
33.64 2 148375
-5
= 6.35 * 10 *
2.3 0.081
= 4.81 secs
Tmax
∴ K2 = a coefficient to determine wind load =
Tmin
134
3 0.5
-5 H 2 W
Tmax = 6.35 * 10 * max
D ts
3
0.5
33.64 2 152609.6
= 6.35 * 10-5 *
2.3 0.081
= 4.875 secs
4.875
∴ K2 = 1.01
4.81
Total load due to wind acting on the bottom & upper part of vessel
PW = K1 K2 Pw HD
PW = wind load kg
= 5470.2 kg
= 6212.5 kg
MW, min = PW, min * 0.5 H = 5470.2 * 0.5* 33.64 = 92008.764 kg.m
135
MW, max = PW, min * 0.5 H = 6212.5 * 0.5 *33.64 = 104494.25 kg.m
Fz = f*J
22142.53 20532
95 x 105 x 0.85 =
t
t= 5.25*10-4= 525mm
As per IS:2825-1969, minimum corroded skirt thickness is 7mm, providing 1mm corrosion
allowance, a standard
Wmax M w , max
FC=
A Z
A=π (Do-L) *L
z= π*Rm2*L
D o L
Rm =
Z
1
Z= * D o L * L
2
3
152609.6 104494.25
FC 1
* (2.462 L ) * L
* D o
2
L * L
3
3Fc
Thickness of bearing plate tbp = L *
F
3 * 29940
tbp= 2.383 * = 0.0232 m= 23.2 mm
95 * 10 6
Bearing plate thickness of 23mm is required. As the plate thickness required is larger than
6 * M max 6 * 20232
tbp= 0.0113m ≈ 11 mm
F F
i.e. If gussets are used at 79 mm spacing then bearing plate thickness of 11 mm will be
sufficient.
(a) Minimum stress between the bearing plate and the concrete foundation.
Fmin=
= -1718374.76 kg/m2
138
Fmin is negative, ∴ the vessel must be anchored to the concrete foundation by means of
anchor bolts to present overturning owing to the bending moment induced by the wind
load.
= + 1015777.682
If hot rolled Carbon Steel is selected for bolts F = 57.3 MN/m2 =57.3 x 105 kg/m2
(ar* n) *F = n* Pbolt
5
Detailed Mechanical Drawings included in Appendix A
140
Number of shells =1
Number of passes = 6
PD i
ts=
2fJ - P
0.11 * 1219
ts = = 0.831 mm
2 * 95(0.85) - 0.11
PR C W
Thickness of Head, th =
2fJ
√ √
W = (3 + ) = (3 + . ×
) = 1.77
Since for the shell, there are no baffles, tie-nods & spacers are not required.
(b) Flanges
0.5
d o y Pm
d i y P ( m 1)
Gasket material chosen is asbestos with a suitable binder for the operating conditions.
Thickness = 10mm
0.5
d o 25.5 ( 0.11 * 2.75)
= 1.0022
d i 25.5 0.11 * ( 2.75 1)
= 1239 + (10*0.5)
= 1244 mm
= 1.0022 (1244)
= 1248 mm
. .
Minimum gasket width = = 0.002 m= 2 mm
. ×
Am = = 4.375 × 10-3m2
×
gi = .
= 1.414 go
R = Radial distance from bolt circle to the connection of hub & back of flange = 0.027
= 0.1363 * 106N
Hp = π*G* (2b) * m * p
144
Wg = π * Gby
Wg = 0.6037 × 106N
= 1.345m
× . × ×
= = 19.75N/mm2
× . × .
2y = 2 x 25.5 = 51 N/mm2
Feed = Water.
Wo = W1 + W2 + W3
× ×
Hydrostatic end force on area inside of flange, W1 =
W2 = H - W1
Gasket load, W3 = WQ - H = Hp
× . × . ×
W1 = = 0.1326 × 106N
W3 = 0.0143 x 106N
= 0.1506 x 106N
a1 = ; a2 = ; a3 =
146
. .
a3 = = 0.026
. .
a2 = = 0.03
= 4.9912 kJ
W= Sg
Am = 4.375 × 10-3
( . × . × )
W= × 138 × 106 = 0.7694 × 106
M = Mg = 0.020 × 106 J
MCf Y
t2 =
BSFO
× × .
Bs = Bolt spacing = = = 0.0310m
n= number of bolts.
Let Cf = 1
SFO = Nominal design stresses for the flange material at design temperature.
M = 0.020 x 106 J
B = 1.239
.
K= = = = 1.086
.
Y = 24
. × × ×
t= = 0.0622m
. × ×
tls = Gc
P = design pressure.
. × . ×
tls = 1.256 ×
= 0.0214m
148
. × . ×
th = 1.256 ×
= 0.0234m
. × .
Total depth of head (H) = = = 0.214m
R = D/2 = 620mm
( )
( )
M1 = QA [1 – ]
Q= L+
. .
= × (4.877 + 4× )
149
= 32732.42 kg.m
M1 = 32732.42 × 0.31 × [1 –
0.31
+ (0.62 − 0.214 )
(1 − 4.877 )
2 × 4.877 × 0.31
4 × 0.214
1+
3 × 4.877
= 96.703 kg.m
( )
M2 = ×[ − ]
( . . )
. × . . × .
M2 = ×[ × . − ] = 28629.58 kg.m
.
× .
f1 = × × ×
(k1 = k2 = 1)
.
= = 1.0096 kg/cm2
× . × .
f2 = × × ×
.
= × . × .
= 296.341 kg/cm2
× . × × .
fp = = = 419.031kg/cm2
× × .
Detailed drawings and dimensioned sketches suitable for submission to a drawing office
CHAPTER EIGHT
8.1 Background
Process control as an aspect of chemical engineering deals with the design and synthesis of
controllers tasked with the objective aims of achieving specific production rate, safety and
product specification. The design of instrumentation for equipment, vessels, piping and
fittings involves the science and control of systems, which measures and/or regulate
Instruments include many varied contrivances that can be as simple as valves and
For the hydroformylation reactor, it is desired to design and analyze the requisite
controllers and instruments to ensure optimal and safe operation. The build- up of the
control system was graphed with Aspen Plus 2006® after the process was studied and the
key variables that need control were identified including the available variables that
The reactor temperature was controlled by manipulating the coolant flow rate around
the reactor. The reactor liquid percent level was controlled by manipulating the flow rate of
the largest liquid boundary stream on the reactor i.e. L. The reactor pressure was controlled
152
by regulating the flow rate of the gases exiting the system, V. As earlier stated, the reaction
rate is very sensitive to CO/H2 concentrations in the system. It was therefore necessary to
flow-control the entry stream into the reactor. The control and instrumentation diagram is
Process description gives the hydroformylation reactor operating conditions as 1300C and
350bars. This temperature is assumed to be the temperature at which the reaction can
proceed without causing any form of danger or deviation from normal reaction path. A
little change in this can cause the system to function abnormally or out of control. Most
process are automated because of avoiding the risk of human error in the process, thus the
process is automated.
To achieve regulation of this temperature, the coolant flow rate will be controlled using
flow-rate controller (CFC). The valve of the coolant is first specified (described in details
in the next section) to be an air-to-close valve. This is due to the fact that it is anticipated
that when there is an emergency the best action the valve can take is to remain completely
open as this can subdue the abnormal increase in temperature. The temperature controller
used in this case is the PID (_proportional+integral+derivative). The major components are
CFC
Legend:
8.2.1 Sensor
The sensor is the element that measures the output variable, in this case, the reactor
temperature. Here we make use of the thermocouple which measures the temperature in
volts which corresponds to the signal of the controller. The measured value of the
temperature in volts as related to the actual value is shown by the block diagram below;
The sensor sends this measured value through a transmitter to the controller. Transmitters
are devices that produce an output signal, often in the form of a 0-15DC electrical current
signal, although many other options using current, frequency, pressure etc.
It is assumed that the time constant is so small such that the gain of the transmitter is
TO (volts )
Thus; Km ;
PV ( 0 C )
15 0
Km 0.15
180 80
The transmitter always acts in the ‘direct acting manner’ i.e. as the measured variable
A PID controller is chosen for operation to eliminate the challenge of runaway temperature
increase by the derivative component and the offset error by the integral component. The
relationship between the error signal and the output signal is given below;
The controller is the brain of the system. By simulation tuning process, different values of
these parameters will be used to obtain a reasonable stable response. The corresponding
signal sent out of the controller is sent to the final control element which in this case is the
control valve. The specification of the valve are performed by making reference to charts
such as those of the Masolenean and Fisher chart to obtain a specific size of the valve to be
HFR vessel temperature was kept at safe operating condition using coolant stream and a
The control valve throttles the flow of fluid through them by making use of the trim. The
major components of the valve are the head, the stem, the body, the trim, the actuator, the
pneumatic entrance hole, and the seat. The valve acts depending on the pressure of air
allowed into the valve pneumatic compartment. The valve used in this case is the air-to-
156
open valve. In specifying valves the major determinant is the safety requirement. The
If we fit an air-to-open valve at all locations and all our controllers are proportional
controllers (controllers whose output signal is proportional to the error signal). Our
( )= + ( ) ( )= ( )− ( )
157
Anytime the measured flow rate, temperature or pressure is higher than the preset (we want
it to close the valve either fully or partially) or when measured parameter is below the set
If at any time the measured parameter is higher than the set point, the controller error
become negative ( ( ) < 0), the controller output signal increases or decreases depending
on the sign of , in this case we want to reduce our output signal to allow the valve close,
( )= + ( ) ( )= ( )− ( )
>0 ( )= + ( ) ( )<0
We obtain a decreased output signal and our valve closes a little to regulate the flow and
restore to normalcy.
The process in the case is the cooling process. There is no material balance for this
dT
VC p FC p (Tinlet Toutlet ) ;
dt
Where;
8.3 Control Scheme for the Liquid Level within the Reactor
The objective of the level control is to avoid the splashing of the reactants and prevent the
mixing of pure tops from the bottoms. The proposed controller here is the proportional
controller which can tolerate offset. The scheme for the transmitter, valve are the same with
the control temperature system in Section 2.4, but here the Kc dictates the control system
because a proportional controller makes use only of the controller gain only to control the
process.
The level can be controlled by manipulating the flow-rate of the bottoms using an air-to
open valve. The reason for using an air-to-open valve is to disallow the wastage of
materials in the reactor in time of emergency. The valve fails close disallowing the reactant
from escaping from the reactor. The relationship between the error signal of the controller
This controller allows offset depending on the magnitude of the controller gain which ios
The mass flow rates of propylene stream and synthesis gas stream going into
hydroformylation reactor (HFR) were controlled by propylene stream valve (PV) and
synthesis gas stream valve (SGV) respectfully using a PID controller of 0.1 Kc (Controller
gain) and 5min integral time for both streams. HFR liquid level was kept at safe fill of 85%
using a bottom product valve (BPV) and a PID level controller (LC) with Kc = 2 and Ti =
10min.
Appendix C gives the simulation graph results of the various controllers (liquid and
temperature) for the hydroformylation reactor, both at start- up time and steady state.
160
CHAPTER NINE
9.1 Background
Chemical plants are built to make a profit, and an estimate of the investment required and
the cost of production are needed before the profitability of a project can be assessed. An
acceptable plant design must present a process that is capable of operating under conditions
which will yield a profit. Since net profit equals total income minus all expenses, it is
essential that the chemical engineer be aware of the many different types of costs involved
in manufacturing processes. Capital must be allocated for direct plant expenses, such as
those for raw materials, labour, and equipment. Besides direct expenses, many other
indirect expenses are incurred, and these must be included if a complete analysis of the
total cost is to be obtained. Some examples of these indirect expenses are administrative
A capital investment is required for any industrial process, and determination of the
necessary investment is an important part of a plant-design project. The total investment for
any process consists of fixed-capital investment for physical equipment and facilities in the
plant plus working capital which must be available to pay salaries, keep raw materials and
products on hand, and handle other special items requiring a direct cash outlay. Thus, in an
Capital cost estimates for chemical process plants are often based on an estimate of the
purchase cost of the major equipment items required for the process, the other costs being
estimated as factors of the equipment cost. The accuracy of this type of estimate will
depend on what stage the design has reached at the time the estimate is made, and on the
reliability of the data available on equipment costs. In the later stages of the project design,
when detailed equipment specifications are available and firm quotations have been
obtained, an accurate estimation of the capital cost of the project can be made.
The cost estimation technique to be adopted in this report is the Factorial Method
of cost Estimation (Lang, 1948). In this technique, the fixed capital cost of the project is
C f = fL Ce
(1)
Ce = the total delivered cost of all the major equipment items: storage tanks,
For the Fluid type 2- Ethylhexanol type being considered, fL= 4.7. Equation 1 can be used
to make a quick estimate of capital cost in the early stages of project design, when the
preliminary flow-sheets have been drawn up and the main items of equipment roughly
Other ancillary equipment required for plant installation include; One Filter Unit, Five units
of Mixers, Two Valves, One Pump, Two Recycle Units, One Compressor, Two units of
Heat Exchange equipment, a Separator, and storage tanks for feed, intermediate and
product chemicals.
The cost of the purchased equipment is used as the basis of the factorial method of
cost estimation and was determined as accurately as possible. It was also preferably based
on recent prices paid for similar equipment. Cost of equipment was researched online on
http://www.matche.com/equipcost was based on that obtained for the year 2007, hence, the
need for cost index for year 2012). Fig 17 gives the plot of chemical engineering plot
index.
163
(Source:www.processengineeringmanual.it)
At 2007, y = 32.36 × 2007 – 64411 = 535.52 (i.e. cost index at 2007 = 535.52)
At 2012, y = 32.36 × 2012 – 64411 = 697.32 (i.e. cost index at 2012 = 697.32)
164
The method usually used to update historical cost data makes use of published cost indices.
These relate present costs to past costs, and are based on data for labor, material and energy
(1991),
.
Hence, Present Cost= Original Cost (in 2007) * ( .
)
The original cost represents the bare vessel cost, and its product with the material and
pressure factor gives the actual vessel cost. Details of method used can be extracted
copiously from Chapter 6 of Coulson & Richardson Chemical Engineering Series (Vol 6,
For currency conversion, the conversion rate of 1 Dollar = 157.3 Naira; 1 Pound = 251.2
A. Reactors
Specs: Jacketed & Agitated; Material: Stainless Steel 304; Capacity: 137000 Litres; Atm to
25psi
Specs: Jacketed & Agitated; Material: Carbon Steel; Capacity: 114522500 Litres; Atm to
25psi Original Cost: $99100 (material factor = 1.0, pressure factor = 1.1)
Specs: Jacketed & Non- Agitated; Material: Stainless Steel 316; Capacity: 24000 Litres;
Atm to 25psi
Specs: Jacketed & Agitated; Material: Low Alloy Steels; Capacity: 6500 Litres; Atm to
25psi Original Cost: $111400 (material factor = 1.0, pressure factor = 1.1)
Specs: Vane Type; 250 psi rating; 240 inches diameter; Material: Carbon Steel 304L and
306L;
C. Distillation Columns
DC 1: Specs: Weight: 90800kg; Material: Ferritic Stainless Steel 430; No internals, large
#90,260,254.49k
D. Filter Unit
Specs: Gravity- type; Area: 18.58 m2 ; Material: Carbon Steel; Atm pressure
E. Coolers (2 Units)
Specs: Forced Draft; Cooling Load: 0.01 Million BTU/hr; Material: Carbon Steel; Atm
Pressure
F. Mixers (5 Units)
Specs: Material: Carbon Steel; Capacity: 7570 litres; Atm to 25 psi Internal
pressure
G. Pump
I. Compressor
Specs: Type: Air Rotary Screw; Material: Cast Iron; 125 psi I.R; 200 HP
J. Reboilers (2 Units)
K. Condensers (2 Units)
Specs: Vertical tube small, 32.52 m2 ; Carbon Steel; 300 psi I.R.
L. Storage Tanks
Cast Iron
Original Cost: $6, 900 (type factor = 0.85, pressure factor = 1.0)
gallons capacity
Original Cost: $7, 600 (type factor = 0.85, pressure factor = 1.0)
Bottom, 40000 gallons capacity, Carbon Steel & glass lined API
Original Cost: $8, 400 (type factor = 0.85, pressure factor = 1.0)
8 Pieces of Tanks for Intermediate Chemicals (Purge Streams, 2- ethyl hexanal, etc)
Original Cost: $4, 300 (type factor = 0.85, pressure factor = 1.0)
M. Recycles (2 Units)
#609,293.685k
171
N. Valves (2 Units)
#497,879.98k
Table 14 gives the summary and cumulative total cost of purchased equipment.
PCE is valued at Four Hundred and Twenty Eight Million, One Hundred and Seventy
investment costs. Total investment cost comprises of both direct and indirect costs and
typical factors for estimation of project fixed capital cost as given in table below (R.K.
DC 1 76,814,013.29
DC 2 90,260,254.49
Pump 2,419,766.35
Compressor 1,035,799.27
= PCE (1+0.4+0.7+0.2+0.1+0.15+0.5+0.15+0.05+0.15)
= PCE (3.4)
= #1,455,784,086
The Total Physical Plant Cost or Direct Cost is valued at One Billion, Four Hundred
and Fifty Five Million, Seven Hundred and Eighty Four Thousand, Eighty Six Naira
Only.
Table 4 below gives the breakdown of estimated direct costs of the plant using the factorial
method.
These represent expenses which are not directly involved with material and labor
of, and actual installation of complete facility. By the factorial method, indirect costs is
= #650,602,838.70k
174
9 0.15
= 1445784086 + 650602838. 70
= #2,096,386,925
Consider the Working Capital = 15% of Fixed-capital investment of fixed capital to cover
= #361,626,744.50k
Manufacturing Cost = Direct production cost + Fixed charges + Plant overhead cost.
(i) Depreciation: Depends on life period, salvage value and method of calculation-
about 10% of FCI for machinery and equipment and 2-3% for Building Value for
Buildings)
176
Using Depreciation = 10% of FCI for machinery and equipment and 3% for
(ii) Local Taxes (1-4% of Fixed Capital Investment) (remitted to Rivers State
Government)
8562435.75) = #303,984,378. 40
(iii) Direct Supervisory and Clerical Labour (DS & CL) (10-25% of OL)
#1,171,378,464
cost); includes for the following: general plant upkeep and overhead, payroll overhead,
Using Plant overhead cost = 60% of OL, DS & CL, and M & R
#172,541,533.20
Thus,
Manufacture cost = Direct production cost + Fixed charges + Plant overhead costs.
1. Administrative costs:
(about 15% of costs for operating labour, supervision, and maintenance or 2-6% of total
product cost); includes costs for executive salaries, clerical wages, legal fees, office
#43,135,383.30
(2-20% of total product cost); includes costs for sales offices, salesmen, shipping, and
advertising.
= #487,927,635
Cost
= #2,497,458,754
selling price of 2-ethyl hexanol is about 0.38 U.S Dollars per lb= $0.837 per kg
= #8,930,235,600
= 8930235600 – 2497458754
= #6,432,776,846
= #1,286,555,369
= #6,432,776,846 - #1,286,555,369
181
= #5,146,221,476
Hence, a net profit of Five Billion, One Hundred and Forty Six Million, Two Hundred and
Twenty One Million, Four Hundred and Seventy Six Naira is estimated on the 72,000
Pay-back period= ( )
= ( . )
= 100%
= 213.5 %
182
CHAPTER TEN
10.1 Background
All industrial plants require an extensive set of operating procedures which define the steps
required - for example - to start the plant up, to shut the plant down, to isolate pieces of
equipment for maintenance or to deal with emergency situations. In older plants, all of
these steps are carried out manually by human operators and are usually officially
automated modern plants the lower-level and more detailed steps are embodied in the plant
control system. It is clearly vital for reasons both of safety and efficiency that procedures
are of a high quality and therefore much effort goes into their generation and subsequent
maintenance. Fig 18 represents the main stages in the design, construction and running of
a chemical plant. It can be seen that operating procedures are a consideration at several
different points within this. At the design stage, where the process is first described at a
high level in Process Flow Sheets, and then in more details as Engineering Line Diagrams
(ELDs), they may form an implicit element of the design rationale - that is, the reasoning
lying behind the specific design decisions made. A designer will clearly avoid design
When the design is evaluated for safety and operability at the HAZOP stage, some of this
rationale may be drawn out as part of the HAZOP process, but investigation conducted
during the project suggests that it is unusual for operating procedures to be documented in
183
any formal and systematic way at this stage. An output of the HAZOP exercise may consist
of operating constraints as well as design changes, but in the case of the chemical process
detailed sets of operating procedures for a plant alongside their other commissioning work.
This is often a substantial exercise taking around two man-years of effort, and usually
A consequence is that if operability problems are uncovered during this process, as may
happen, they may force late changes to the design of the plant. If this occurs while the plant
is actually being constructed it is clearly undesirable and costly. Thus there is an advantage
in considering operating procedures in a more systematic way and earlier than at present.
This is an important motivation for the development of computer-based tools to aid in the
Once the plant is running, operating procedures may need modification in the light of
actual operations experience. If mechanisms for doing this in a controlled way do not exist,
there is a risk of operations practice diverging noticeably from the documented procedures.
based tools offers the means of reconciling the need for flexibility in the construction and
modification of plant operating procedures with the need for accuracy, consistency and
installed plant is fully functional and fit for purpose. A general sequence of steps in
The purpose of this activity is to trace all pipework and connections to verify the system
configuration and to visually inspect items of equipment to ensure that they are clean,
empty and fit for purpose as appropriate prior to undertaking water trials.
The purpose of this activity is to ensure that all instrumentation, alarm settings,
microprocessor signals and hardwire trips pertaining to the installation are functional. This
will also check that signals from the field instrumentation are displayed locally and are
being correctly relayed to the computer interface rack, as well as to the computer system.
The purpose of this activity is to clean all items of pipework and the vessels that make up
the installation. This task shall also ensure that there are no obstructions, blockages or any
potential contaminants in any of the process lines or vessels that may have resulted from
materials being left inside the system from the construction phase. If chemicals
incompatible with water are to be used, it is important that the pipelines and equipment are
186
thoroughly dried prior to introduction of the chemicals. This will be done by passing dry air
The main aim of this assessment is to verify the performance of all ancillary equipment.
This may include pumps, fans, heat exchangers, condensers (See Table 4)
The purpose of this activity is to check the calibration and performance of all vessels and
instrumentation pertaining to the installation. To a certain extent this will be carried out in
conjunction with the system pre-checks to ensure that the correct set points and alarm
Chemical Trials;
The aim of this activity is to verify the performance of the installation by simulating ‘live’
Start Up Protocol;
The purpose of this procedure is to provide guidance for bringing the installation online
The purpose of this procedure is to provide guidance for taking the installation offline
A Critical Path Network (Plan) with written procedures with related documents are
required. These should define for the facility, each plant system: The order in which the
systems will be started up; Individual activities at each stage; Operation testing
requirements; Durations, waiting times, cooling times; Total duration for starting up each
There have been numerous recorded incidents where failings by operators have been the
major contributing cause of major accidents. Provision of clear, concise and accurate
operating procedures is the most effective measure to prevent, control and mitigate such
events. Operating procedures should clearly lay down instructions for operation of process
plant that take into consideration COSHH, manual handling, permit to work, PPE
Regulations, quality, HAZOP, and HSE requirements. The procedure should represent a
definition of good or best practice that should be adhered to at all times. Process operatives
should be provided with guidance concerning the required operating philosophy to ensure
procedures; Commissioning; Plant Start-up; Plant Shut-down; Bulk loading and unloading;
procedure;
Plant trials have been successful and need to be incorporated into standard
operating procedures.
Clear demarcation of where limits of intervention cease and reliance upon the control
systems interface begins is a critical step in defining the operating procedures for a given
plant or process. During the hazard and operability stage, the justification of reliance upon
human intervention rather than automated systems should be established. These are
For some specific plant items, start-up is known to present particular additional hazards,
such as;
Vessels, Tanks, Reactors – ignition of flammable vapours introduced may occur for
The start-up and shut-down procedures should be ordered and phased so that interlinked
Emergency procedures
Any potential deviations to normal operation that cannot be addressed by design or control
procedures. These should detail how to make plant and process safe, minimising risks to
operators at all stages. They should cover PPE, the level of intervention which is safe and
when to evacuate. The procedures will need to tie in closely with the on and off-site
Management / supervision
person(s) for generation of operating procedures and supervision of plant and personnel.
The role of the supervisor in terms of training of operators, overseeing certain critical
190
operations and checking of logs and other activities to ensure compliance with operating
procedures. This should fulfil the requirements of the company’s health and safety policy.
10.3 Start- Up
Commissioning shall start from the point at which steps are taken to bring the Unit/facility
up to operating pressure and temperature and to cut in the feed. It shall be complete when
Due to the interdependence of some plant units, it is imperative from a process point of
view to commission utilities and some of the Units in advance of others, and the sequence
equipment/lines shall be followed. The detail procedures for testing of equipment and lines
and other pre-commissioning steps which are not included in such Standard shall be
prepared in accordance with the Company’s Engineering Standards by the Contractor and
Spades, blanks and other equipment installed for testing shall be removed on completion of
testing. Wherever a flange joint is broken after testing, e.g. on heat exchangers, pipe- work,
fired heaters and at machinery, then the joint rings or gaskets must be renewed. Particular
attention must be given to heat exchangers employing solid metal or filled gaskets, and
great care should be taken to ensure that all gaskets renewed after testing of heat
191
exchangers and are correctly fitted before tightening flanges. Where required, valves are to
Any temporary bolting which has been used shall be replaced and any temporary fittings
which may have been installed to limit travel, e.g., in expansion joints and pipe hangers,
Prior to commissioning, each item of equipment should have its name, flow-sheet number
The procedures described in this Section shall be carried out at the completion of
construction and before initial operation of the Unit. Appropriate phases should be repeated
after any major repair, alteration, or replacement during subsequent shutdowns. The phases
- Hydrostatic testing.
- Flushing of lines.
- Instruments.
- Catalyst loading.
- Tightness test.
a) Check line by line against flowsheet and locate all items. (Every line must be walked!
c) Indicate the location of all critical valves including valves at critical vent and drain
locations.
d) Check control valves, valves, and globe valves to see that they are installed properly
with respect to flow through their respective lines. Special attention must be given to check
f) Check that the following facilities have been installed so that the plant can be
commissioned and put on stream: Start-up bypass lines, Purge connections, Steam-out
connections, Drains, Temporary jumpovers, Blinds, Check valves, Filters and Strainers,
Bleeders, et cetera.
Hydrostatic pressure testing of the Units shall be performed to prove strength of the
materials and weld integrity after completion of the construction. The tests shall be made
on new or repaired equipment and pipings. Detail procedure for testing the equipment and
lines are to be prepared and documented. Fresh water containing a corrosion inhibitor shall
be used for hydrostatic test purpose unless otherwise specified in the Engineering Standard.
In systems where residual moisture cannot be tolerated, and where certain catalysts are
used, oil is the preferred test medium. If the water has to be used, the system should
afterwards be dried out with hot air. Special attention should be given to the points where
water may be trapped, such as in valve bodies or low points. If for any reason it is not
practical to carry out a hydraulic test, a pneumatic or partially pneumatic test may be
a) If the piping and equipment metal temperature never exceeds 50°C during
chlorides ion shall be used. b) If the piping and equipment metal temperature exceeds 50°C
condensate water, demineralized water or oil with minimum flash point of 50°C.
The testing medium should not adversely affect the material of the equipment or any
process fluid for which the system has been designed. Reference should be made to the
applicable codes in the case of pressure vessels to determine the minimum ambient and
fluid temperatures at which testing may be carried out. If it is desired to test vessels, tanks
194
or piping at temperatures below 16°C, attention shall be made to the danger of brittle
fracture occurring in carbon steels and ferritic alloy steels unless the materials have
adequate notch ductility properties. For any equipment or piping, water should not be used
for testing, when either the water temperature or the ambient temperature is below 5°C.
Hydrostatic testing at temperatures below this value may be carried out using gas oil,
During the hydrostatic test pressure with water the system loss should not exceed 2% of the
test pressure per hour unless otherwise specified. Evidence of water at valves, flanges, etc.
will indicate the leaking areas to be repaired if the system fails the test. All welds and
piping must be inspected for defects by looking for wet spots, therefore they should be
If piping is tested pneumatically, the test pressure shall be 110% of the design pressure.
Any pneumatic test shall be increased gradually in steps, allowing sufficient time for the
piping to equalize strains during the test. All joints welded, flanged or screwed shall be
swabbed with soap solution during these tests, for detection of leakage. Vents or other
connections shall be opened to eliminate air from lines which are to receive hydrostatic
test. Lines shall be thoroughly purged of air before hydrostatic test pressure is applied.
Vents shall be open when systems are drained so not to create buckling from a vacuum
effect. Relief valves must be removed or blinded prior to hydrostatic testing. After
completion of hydrostatic testing, all temporary blanks and blinds shall be removed and all
lines completely drained. Valves, orifice plates, expansion joints and short pieces of piping
which have been removed shall be reinstalled with proper and undamaged gaskets in place.
195
Valves which were closed solely for hydrostatic testing shall be opened. After lines have
been drained with vents open, temporary piping supports shall be removed so that
At the conclusion of the test, the system must be drained. If pumps have been included,
they must each be drained and refilled with oil to prevent rust forming in the seals. If
fractionating columns are included, the water must be displaced with sweet gas, nitrogen,
or an inert atmosphere rather than air to avoid corrosion and sticking of the valves on the
fractionating trays.
Only the following pressure tests should be carried out on heat exchangers;
a) On floating head shell and tube type exchangers, on tube side with bolted bonnets
removed.
c) On air-cooled types, the bundles are to be isolated and tested separately from associated
pipe- work.
After completion of test all equipment must be thoroughly drained and if necessary, dried
All tanks shall have bottoms, shells and roofs tested in accordance with API 650, latest
edition. Shells shall be tested by filling tanks with water. Vacuum testing shall be used for
all tank bottoms and roofs. Flame arrestors and other miscellaneous equipment that does
not have test pressure indicated shall be isolated from the test.
196
Certain types of instruments with their connecting process lead pipelines shall be tested at
the same pressure as the main pipelines or the equipment to which they are connected.
Such instruments normally include the following types: Displacer type level instruments,
Other types of instruments shall not be tested at line pressure, but shall have process lead
lines tested to the first block valve or valves nearest the instrument. Care shall be taken that
this equipment is protected by removal, or by blocking the instrument lead line and
disconnecting or venting the instruments. These types will normally include the following:
Instruments, In-Line Type Flow, Switches, Direct Connected Regulators, Open-Float Type
Level Indicators and Alarm Switches, Positive Displacement Type Flow Meters, Pressure
Special precautions shall be taken to insure that instruments and instrument lead lines to be
tested are vented and completely filled before testing, and are thoroughly drained after test.
Before the final bolting of coverplates and manholes, vessel interiors should be inspected
for cleanliness, completeness, and proper installation of internal equipment. Inspection list
d) Internal distributors.
h) Level instruments, location and range, internal float, external displacement and
All fluid handling equipment particularly piping, should be thoroughly cleaned of scale and
blowing or washing with air, steam, water and other suitable medium.
Some utility systems, such as water and high pressure steam, may be satisfactorily cleaned
with their normal media, introduced through normal channels. Other systems must, or
preferably should, be flushed with foreign media, admitted via temporary hose or pipe
connections. Thus, flushing may be accomplished on exhaust steam lines with high
pressure steam or air, and on fuel oil lines with steam, followed by air. The best way to
clean a typical utility or auxiliary system is to flush the supply main from source to end at
first and making an end outlet by breaking a flange or fitting if necessary, than flush each
lateral header in the same manner; and finally, flush the branch which takes off from the
198
headers. In some instances if required the weld-cap on the end of each header could be cut
Steam piping
Before blowing a steam line for cleaning, an open end for a free passage of the steam and
debris shall be provided. If the open end is a temporary provision, be certain the end is tied
down to prevent possible whipping caused by high velocity flow. All drains must be open
and the line free of water. Valving to steam traps shall be closed and the traps shall remain
out of service until the line cleaning is completed. Prior to starting stream flow all safety
precautions shall be taken. The area should be cleaned and guarded to prevent injury to
personnel. Steam shall slowly be introduced from the source and the line heated gradually.
The steam flow rate shall be limited to the condensate drainage flow rate. Condensate must
not be permitted to accumulate in order to avoid water hammer. As the piping heats and the
condensate diminish, the steam rate shall be increased. As the line heats, observe its
expansion and determine that there is no binding or distortion. After the piping is
thoroughly heated, the steam rate shall be increased to provide a hard blow. After blowing,
the line shall be permitted to cool and contract, then the preceding blowing to be repeated.
a) Process, utility and auxiliary systems shall mainly be washed with water. Any line not
accessible to water, or lines which would trap water in such a way that it could not be
drained, may be blown out with air. Most of the process and auxiliary lines may be flushed
through established circuits from vessels filled with water for the purpose. Machinery
To the maximum extent, the lines connected may be flushed with water contained within
vessels after hydrostatic testing. A single filling of a vessel may not provide sufficient
water to flush all lines for which it is the reservoir, in which case a continuous or
b) When washing exit lines of a vessel, it should be noted that, the vessel is adequately
vented to prevent a vacuum condition. Inadequate venting of vessels not designed for
c) In any system, to the maximum extent possible, flushing should be made downward, or
horizontally, and out at low points. The low point discharge opening may be temporary
openings made by disconnecting flanges or fittings. Normal drains may be used for
flushing outlets, provided they are equal to line size or nearly so. For best results, there
should be no restriction of the outlet or at any other point in a line undergoing cleaning.
200
e) Some lines, such as buried pump suction lines, must be flushed through a temporary
spool-piece and linesized valve flanged to one-end, and pointed to a safe location (not to
the pump suction). Compressed air is introduced to the other end and pressure allowed to
build. When the valve is suddenly opened, the sudden release of pressure will effectively
clean the line. Flushing shall be done through all vents, drains and other side connections,
f) Flushing line debris into equipment where it may become trapped or lodged shall be
avoided.
g) All control valves should be blocked off and bypassed until the major part of the foreign
matter has been removed from their systems. Then remove the bottom plate of the control
valve or, if the valve is closed, remove the valve itself from the line, and flush through the
opening thus created. Finally, replace the plate or valve and flush through the valve in
h) Flow meter and restriction orifices should not be installed until lines are clean. Any
i) At the conclusion of flushing any system, it shall carefully be checked to see that normal
alignments are restored, temporary connections are broken, and temporary breaks
reconnected, check valve flappers and/or coverplates replaced, and orifices installed, etc. In
201
the case of lines which will receive further cleaning during subsequent pump break-in, this
When flushing of process lines is finished, drain water from the system as completely as
possible. Provide ample top venting during the draining operation, or whenever the level is
being lowered in a vessel, to avoid pulling a vacuum on the equipment. Blow lines with air
The basic utility systems such as steam, water and air should be put in normal working
order after they have been cleaned so that supplies will be available for further operations.
10.3.1.5 Instruments
In general the instruments should be checked against the design data as well as to be
checked for installation, calibration and operation as per the following list:
a) Installation check
b) Calibration check
ii) Orifice plates are installed after hydrotest and line flushing.
c) Operation check
ii) All alarms are test actuated and interlock systems checked.
202
iii) Instruments, connecting piping, and pneumatic tubing are checked for leaks.
Mill scale, dirt, heavy greases, and other foreign materials that could enter the compressor
and result in operating and maintenance problems must be removed from the compressor
system as required in the Piping & Instrumentation Diagrams (P & IDs). The following
b) Make-up compressor suction lines and drums. Suction drums may be acid
1) The heater refractory dry-out, plant dry-out and chemical boil-out procedures can be
combined in the interests of saving time. It is likely, however, that the heat input during
either the heater refractory or the Unit dry-out procedures may be excessive for controlled
chemical boil-out. Therefore, combining the two or three operations may require a
2) The drying-out and boil-out periods present an opportune time to check out the operation
rotation to make certain that there will be no difficulties during final start-up.
Initial catalyst loading activities shall be performed according to the Licenser’s and/or
During equipment cleaning, lines have been disconnected, orifice plates and blinds
leakages due to gaskets which have been damaged, flanges or drains which have been left
open. Tightness test is to be carried out after final installation by air, steam, nitrogen or the
All joints, flanges, packing glands, etc. must be checked for leaks by means of a sensitive
detector, for example by using a soapy solution. Thermal insulation of flanges shall be
done only after the final pressure test of the section is completed.
Air or nitrogen are commonly used for tightness test purpose. Tightness test pressure will
depend on the operating pressure of the system under test. Normally shall be 1.2 times the
normal operating pressure provided that this does not exceed the set of the PSV existing in
204
the section. And, anyhow, the maximum test pressure is normally limited by the available
plant or Instrument Air pressure. When operating pressure is considerably higher that of
said air, a preliminary tightness test is done with air and final tightness test is done with
The acceptability of the test is given by the pressure drop that can occur in a limited period
of time. It is normally accepted that the tightness of a section is reasonably good when said
Placing the new Unit in operation can be made through several methods depending on the
experiences of operational crew. It is common practice to buy in product and start up the
last past of the process first and work backwards to the front. Raw materials are fed into the
plant – usually at reduced rate until reaction conditions have been established. As each
section is started up, establish as quickly as possible that process conditions are as
emergency shutdown.
The normal start-up activities can proceed when the following main commissioning and
Appendix D gives the general index for key components of a commissioning system file
The procedure describes in general terms, the steps to be followed for placing the Unit on
stream. The exact sequence of events depends on the flow scheme of the particular Unit;
however, the following steps must be completed before charging feed to the Unit.
Remove all welding gear from area and all maintenance tools not of a non-sparking nature,
clear away all planks and scaffolding. No further work to be done except with work permits
and, if necessary, specific welding permits. "No Smoking" signs must be re-installed, if
All utilities such as various types of steam, condensate, boiler feed water, fuels and plant
air, instrument air, nitrogen, and plant water shall be commissioned. Do not put cooling
water into exchangers, which are to be left with water side drains and vents open and
The Unit should be lined up and final check shall be carried out to introduce the feed to the
Unit. All safety precautions should be taken into account. The feed to be charged at turn
down ratio of the Unit design throughput according to the stepwise start up procedure
all times at a flow rate close to the design values in order to avoid coke deposition inside
the coils.
Once the plant is fully operational, the final proving trail or performance run is performed
The values or range of values for each independent variable - flow, temperature,
pressure, level, concentrations, etc. to which the plant must be operated to are
determined;
Control of plant operating conditions has been achieved i.e. temperature, pressures,
levels and analyses are reasonably constant or in the case of a batch process, there is
repeatability;
Daily material and energy balanced can be performed and that these agree with
There is need to verify the physical operation, capability and capacity of plant and
equipment;
208
Energy and mass balance; Process chemistry; Efficiencies, yields and quality; are all to
specification.
It is common practice to prove performance repeatability and plant integrity as part of the
Shutdown and Start Up the plants on several occasions and bring it up to test
conditions to prove repeatability. Also ramp down and ramp up while online;
procedures are fundamental aspects of a safety management system. The on-site emergency
plan, prepared for Regulation 9 of COMAH should address procedures for dealing with
practices include;
danger to
Description of the actions which should be taken to control the conditions at events
and to limit their consequences, including a description of the safety equipment and
resources available;
Evacuation of areas in the event of fire or toxic gas emission should be addressed in
Arrangements for training staff in the duties they will be expected to perform;
The emergency plan should be simple and straightforward, flexible and achieve necessary
Scheduled shutdown.
Maintenance shutdown.
Emergency shutdown.
Reactor trips.
The Standard Operating Procedures for each type of reactor must be adhered to when
shutting a reactor down. Appendix E discusses the likely problems that can arise from the
of the reactor when maintenance is required or feed supply is low or exhausted. The
shutdown procedure will depend on the type of reactor and the process chemistry.
Shutting off one or more of the reactant feeds to stop reactions and heat generation
Cooling and flushing products from the reactor by recirculating one of the feeds -
no reactions can take place when the other reactant flow is stopped.
When maintenance is required to the reactor equipment, it is possible that the equipment
Procedures where equipment is isolated (process, mechanical and electrical), cooled and
depressurized, purged and gas freed, cleaned, gas tested on a continuous basis prior and
during entry.
A planned reactor shutdown will prevent plugging of lines or plugged reactor, possible
damage to equipment, possible injury. To prepare the reactor for shutdown, the reactor can
be:
During decontamination, regular sampling of the atmosphere inside the reactor is required
to ensure toxic or explosive atmospheres do not build up inside the reactor that could be a
Gas testing must be carried out before anyone enters the vessel to ensure the atmosphere is
An emergency shutdown is initiated in the event of a fire, major spill, instrument failure,
Shutdown of a reactor unit can be initiated by the automatic shutdown system due to
abnormal temperature, levels, pressures or flows that can be above or below trip points.
When a reactor is to be shutdown for a short period of time for maintenance on auxiliary
A standby shutdown allows a quick start-up of the reaction unit after maintenance is
Standard Operating Procedures must be referred to, to shutdown each type of reactor to a
standby condition.
213
REFERENCES
New York.
Brownell L.E. and E. H. Young. 1959. ‘Equipment Design’ 1st edition, John
12, 2012).
D.E Seborg; T.F Edgar, W. Mellichamp. (2004). Process Dynamics and Control.
Weinheim.
Hancock, E. G. (ed.) (1973) Propylene and Its Industrial Derivatives (New York:
http://toxnet.nlm.nih.gov/cgibin/sis/htmlgen?HSDB.
215
Lewis, R.J. 1997. Hazardous Chemicals Desk Reference, Fourth Edition, Wiley
M.V Joshi. Process Equipment Design, 3rd Edition. Macmillan India Limited,
2000.
Oguntoye, O.E. (2008). 'A Design Report on the Production of 40,000 tons/year of
Octave Levenspiel. (1999). Chemical Reaction Engineering, 3rd Ed. John Wiley &
Reactions. (http://dx.doi.org/10.1002%2F0471264180.or056.01)
216
at http://cs3-hq.oecd.org/scripts/hpv/
Peters, M. & K.D. Timmerhaus. (1991). Plant Design and Economics for
R.H Perry and W.D. Green (eds). 1997. Perry’s Chemical Engineers’ Handbook,
Smith J.M.; H.C. Van Ness, M.M. Abbot. 2001. Introduction to CHE
http://chem-faculty.lsu.edu/stanley/webpub/4571-chapt16-
Fourth Edition, Wiley Interscience, John Wiley & Sons, New York, NY.
Contaminants. WHO Food Additives Series No. 32. Prepared by: The
<http://www.inchem.org/documents/jecfa/jecmono/v32je04.htm>
APPENDICES
219
APPENDIX A
7535
2 0
0
2 4
318
5462
(1)
(1)
1 180
4 0
(1)
3180
5546
318
392
779
1 SS1 3 CG SS2
(2)
(1)
90 90
1056
1056
705
705
3 180
3
153 15
Nozzles Couplings / Supports Design Specifications Shell Tube Filename; OGUNGBENRO Adetola Elijah
(1) (2)
(CHE/2007/083)
Label Size: Description Project. Label Size: Description Project. Design Pressure bar 1.11 1.11 Aspen Teams verification file
1 219.1 150 # ANSI W.N.RF 360153.5 SS1 2 133.0 Bolt Holes 360151 Test Pressure bar 1.0 1.0 Service of Unit:
2 219.1 150 # ANSI W.N.RF 360153.5 SS2 2 133.0 x 266.0 Slots 360151 Design Temperature °C 82.28 82.8 Item No.:
Date: 23/10/2012 Rev No.:
3 355.6 150 # ANSI W.N.RF 360153.5 Number of Passes 1 2
4 355.6 150 # ANSI W.N.RF 360153.5 Corrosion Allowance mm 20 4 Aspen Technology, Inc.
Radiographing Spot Spot
Midlothian, Virginia
Wt min: 148375 max: 152609.6086 Bundle: 5268 kg
A-1
Component O.D. Thk. Materials of Construction Dimensions: mm
Nozzle 1 Inlet 219.1 12.7 150 # ANSI W.N.RF Flg SA-105 on SA-106 Gr B Sml Pipe
Nozzle 2 Outlet 219.1 12.7 150 # ANSI W.N.RF Flg SA-105 on SA-106 Gr B Sml Pipe
Nozzle 3 Outlet 355.6 11.1 150 # ANSI W.N.RF Flg SA-105 on SA-106 Gr B Sml Pipe
Nozzle 4 Inlet 355.6 11.1 150 # ANSI W.N.RF Flg SA-105 on SA-106 Gr B Sml Pipe
Bill Of Material
Dwg No.: Rev:
3200 - 03
A-2
OD 1190
OD 1251
OD 1254
OD 1325
12.7 ID 1193 13
OD 1325
OD 1254
OD 1251
OD 1190
OD 1186
OD 1251
OD 1254
OD 1325
ID 1189 15
OD 1413
OD 1339
A-3
OD 1268
ID 1152
OD 1182
OD 1179
OD 1149
OD 1182
ID 1152
OD 1268
OD 1342
OD 1413
ID 1281 13
Dimensions: mm TEMA Type: E
Top View
Front Rear
355.6 355.6
574.2 412.9
752.0 590.7
57.1 104.3
Side View
A-4
Shell ID 2300 mm
Row Holes H G O.T.L. 1139.3 mm
Baffle cut to C/L 242.2 mm
40 14
39 28
38 32
37 40
36 42
35 48
34 40
33 56
32 48
31 60
30 62 F E
29 64
28 66
27 68
26 66 552
25 68
24 60
23 68
22 60
21 72 44.4
20 72 552
19 60
18 68 22.2
17 60
16 68
15 66 15.9
14 68
13 66
12 64 D C
11 60
10 50
9 48
8 56
7 34 27.5
6 40
5 36
4 34
3 28
2 24
1 14 25.8
B A
2078
A-5
0
550
934
0
13
1307 O.D.
6
270 90
1
7
23
62
180
Front End View Side View
Filename; OGUNGBENRO Adetola Elijah
Notes:
(CHE/2007/083)
All Dimensions In Millimeters Aspen Teams verification file
Bolt holes to straddle centerlines Service of Unit:
Weld joint details per drawing 20 Item No.:
Date: 23/10/2012 Rev No.:
A-6
0
414
1268 OD
270 90
51
18
63
180
Front End View Side View
Filename; OGUNGBENRO Adetola Elijah
Notes:
(CHE/2007/083)
All Dimensions In Millimeters Aspen Teams verification file
Bolt holes to straddle centerlines Service of Unit:
Weld joint details per drawing 20 Item No.:
Date: 23/10/2012 Rev No.:
A-7
6090
Plan
View
Elevation
View
11 12
A-8
0
318
215
270 90
215
318
180
39 C
1 Supports 1239 O.D. 13 Tk
A-9
60 22 Dia Bolt Holes
0
1283 Bolt Circle
13
1186 Dia
1251 Dia
1325 OD
90 270
10 Chamfer
180
56 Thk. 5
Front Head Cover Rear End View
51 5 Filename; OGUNGBENRO Adetola Elijah
Notes:
45 6 (CHE/2007/083)
All Dimensions In Millimeters Aspen Teams verification file
Bolt holes to straddle centerlines Service of Unit:
Item No.:
125 Date: 23/10/2012 Rev No.:
A-10
60 22 Dia Bolt Holes
0
1251 Dia
1190 Dia
1186 Dia
1251 Dia
1325 OD
270 90
10 Chamfer
180
32 Thk. Front End View 13 Front TubSh
5 22 5 Filename; OGUNGBENRO Adetola Elijah
Notes:
6 10 6 (CHE/2007/083)
All Dimensions In Millimeters Aspen Teams verification file
Bolt holes to straddle centerlines Service of Unit:
Item No.:
125 125 Date: 23/10/2012 Rev No.:
A-11
0
1149 Dia
1179 OD
90 270
180
14 Rear TubSh Rear End View
Filename; OGUNGBENRO Adetola Elijah
Notes:
32 Thk. (CHE/2007/083)
All Dimensions In Millimeters Aspen Teams verification file
27 5 Bolt holes to straddle centerlines Service of Unit:
Item No.:
125 Date: 23/10/2012 Rev No.:
A-12
10
10
1251 O.D.
1251 O.D.
1225 I.D.
1225 I.D.
6 Radius 6 Radius
33 31
Front Head Gaskets at Covers Front Head Gaskets at Tbshts
A-13
1179 O.D.
1159 I.D.
32
Rear Head Gaskets at Tbshts
3.175 Thk.
A-14
1251 O.D.
1339 O.D.
1225 I.D.
1313 I.D.
35 36
Front Shell Gasket Shell Cover Gasket
A-15
87
56 26
5
1325 OD
60 22 Dia Bolt Holes
Radius
1283 Bolt Circle
30
5
Dia
1254
125
1219 OD
2
1193 ID
Dia
1226
19 Fr Hd Flng Cover
A-16
87 63
26 56 32 26
5 5
1325 OD
1325 OD
60 22 Dia Bolt Holes
Radius
Radius
1283 Bolt Circle
30 30
5
5
Dia
Dia
1254
1254
125
1219 OD
1219 OD
125
2
2
1193 ID
Dia
1189 ID
1226 Dia
1226
A-17
57 62
26 25 31 26
6 5
1413 OD
1413 OD
44 22 Dia Bolt Holes
Radius
30
5
Dia
Dia
1342
125
1339
1307 OD
Radius
2
1281 ID
1314 Dia
30
5
125
1219 OD
12121689 DIiD
a
A-18
1268 OD
1268 OD
Dia
1179 ID
1182
1182
1152 ID
A-19
WELD WELD WELD WELD
JOINT JOINT JOINT JOINT
60
45
11 18 60 16 45 61
21 28 26 71
21 36 81
60
45
12 45
18 17 45 61
22
28 27 71
22
37 81
51
A-20
240
APPENDIX B
2-ETHYL-1-HEXANOL (OCTANOL)
Revision: 7 Last up date: October 14, 2008 Date issued: July 21,1999 Page 1/7
2. HAZARD IDENTIFICATION
Health effects: It is harmful if is swallowed, inhaled, or absorbed through skin.Vapors and mists
severely irritate the eyes and respiratory tract especially when heated. May affect central nervous
system, have a narcotic effect. May cause allergic skin reaction.
Environmental effects: No critical hazard to the environment in the ordinary sense of valid
regulations. This product is readily biodegradable. No ecological problems are to be expected
when the product is handled and used with due care and attention. 2-Ethylhexanol is not classified
as dangerous for environmental according to Directive 67/548/EEC, Annex I.
B-1
2-ETHYL-1-HEXANOL (OCTANOL)
MSDS No.02-11
Revision: 7 Last up date: October 14, 2008 Date issued: July 21, 1999 Page 2/7
3. COMPOSITION/INFORMATION ON INGREDIENTS
Inhalation: Inhalation of vapors or mist is irritating to the upper respiratory tract. May have
narcotic effect. Difficult breathing, coughing, headache, dizziness and drowsiness may occur.
Remove to fresh air. If not breathing, give artificial respiration. If breathing is difficult give
oxygen. Call a physician.
Skin contact: Causes skin irritation. May be absorbed through skin. May cause sensitization or
allergic skin reaction in some individuals. Prolonged skin contact may result in dermatitis.
Wash the contaminated skin with plenty of soap or mild detergent and water for at least 15 minutes
while removing contaminated clothing and shoes. If irritation persists after washing, get medical
attention.
Ingestion: May have narcotic effect. May cause abdominal pain, nausea, headache, dizziness and
diarrhea. Large doses may affect kidneys and liver. Give large amount of water to drink. If large
amounts were swallowed, get medical advise. Never give anything by mouth to mouth to an
unconscious person.
Suitable extinguishing media: Dry chemical, foam or carbon dioxide and water spray.
Unsuitable extinguishing media: Do not use a solid stream of water (water jet), since the stream
will scatter and spread the fire. Use water spray to isolate the hazard area and to keep fire-exposed
tanks cool.
Exposure hazards: 2-Ethylhexanol is a combustible and flammable liquid. In contact with strong
oxidizers may cause fire. Vapor/air mixtures are explosive above 750C. Vapor may flow along
surface to distant ignition sources and flash back. Carbon monoxide and dioxide may form when
heated to decomposition. In case of large fire and remove the containers if this it is possible.
B-2
2-ETHYL-1-HEXANOL (OCTANOL)
MSDS No.02-11
Revision: 7 Last up date: October 14, 2008 Date issued: July 21, 1999 Page 3/7
Protection of fire-fighters: Wear full protective clothing and self contained breathing apparatus
with full face piece operated in positive pressure mode.
Personal precautions: Remove all sources of ignition. Ventilate area of leak or spill. Persons
performing clean-up work should wear adequate personal protective equipment and a self-contained
breathing apparatus with full facepiece operated in the pressure demand or other positive pressure
mode. Keep unnecessary and unprotected personnel away from hazard area.
Environmental precautions: Prevent from contamination the ground and the surface water by
isolating the hazard area. Contain and recover liquid when possible. Keep closed containers and
dispose according to all applicable federal, state or local environment regulations
Methods of cleaning up: Absorb spills with dry sand, earth or similar non-combustible absorbent
material then collect into drums for later disposal. For large spills, dike and pump into suitable
containers for disposal. Use water spray to reduce vapors and flush area with water. Resulted
waste water will be treated in biological treatment plant. Dispose of under valid legal waste
regulations.
Special precautions: Do not use combustible materials, such as saw dust to absorb the spills.. Do
not flush to sewer! Use only non sparkling tools and equipment.
Handling: Protect containers from physical damage. Use non sparkling tools, electric equipment
and venting system. Sources of ignition such as smoking and open flames are prohibited when
2-ethylhexanol is handled. Do not use compressed air or oxygen for filling, discharging or
handling. The personel which handling the product must wear protective equipment.
Storage: Store in a tightly closed containers in a cool, dry, well ventilated area away from sources
of heat and incompatible substances. Drums must be equipped with self-closing valves, nitrogen
blanket. Containers of this material may be hazardous when empty since they retain product
residues (vapors, liquid).
Engineering control : A system of local and/or general exhaust is recommended to keep employee
exposure as low as possible. Local exhaust ventilation is generally preferred because it can control
the emissions of the contaminant at its sources, preventing dispersions of it into the general work
area. Ventilation equipment should be explosion- proof if explosive concentration of dust, vapor or
fume are present.
B-3
2-ETHYL-1-HEXANOL (OCTANOL)
MSDS No.02-11
Revision: 7 Last up date: October 14, 2008 Date issued: July 21, 1999 Page 4/7
Respiratory protection: For conditions of use where exposure to substance is apparent , consult an
industrial hygenist. For emergencies or instances where the exposure level are not known, use a
full face piece positive pressure air-supplied respirator.
Eye / Face protection : Use chemical safety goggles and/or a full face shield when is possible
Skin protection : Wear impervious protective clothing, including boots, gloves, lab coat apron or
coveralls as appropriate, to prevent skin contact.
Other precautions: Maintain shower, eye wash fountain and quick-drench facilities in work area.
General informations
Appearance Clear liquid
Odor Characteristic
Other informations
Melting point -76o C
Autoignition temperature 270 OC
B-4
2-ETHYL-1-HEXANOL (OCTANOL)
MSDS No.02-11
Revision: 7 Last up date: October 14, 2008 Date issued: July 21, 1999 Page 5/7
Hazardous decomposition products: Carbon monoxide and dioxide may form when heated to
decomposition. May produce acrid smoke and irritating fumes when heated to decomposition.
Acute toxicity
Inhalation: Inhalation of vapor or mist is irritating to the upper respiratory tract. May have narcotic
effect. Difficult breathing, coughing, headache, dizziness and drowsiness may occur. May be
absorbed into the bloodstream with symptoms similar to ingestion.
Skin contact: Causes skin irritation. May be absorbed through skin. May cause sensitization or
allergic skin reaction in some individuals. Prolonged skin contact may result in dermatitis.
Ingestion: May have narcotic effect. May cause abdominal pain, nausea, headache, dizziness and
diarrhea. Large doses may affect kidneys and liver.
Chronic effect: Persons with pre-existing skin disorders or eye problems or impaired liver, kidney
or respirator function may be more susceptible to the effects of the substance.
Ecotoxicity
Fish P. promelas LC50=29.7mg/l/96 hours
Onchorhynchus mykiss LC50 >7.5mg/l/96 hours
Daphnia Daphnia magna LC50=39mg/l/48 hours
Algae Desmodesmus subspicatus IC50=11.5mg/l/72 hours
B-5
2-ETHYL-1-HEXANOL (OCTANOL)
MSDS No.02-11
Revision: 7 Last up date: October 14, 2008 Date issued: July 21, 1999 Page 6/7
Bacteria Ps.putida EC50=540mg/l/18hours
Mobility: 2-Ethylhexanol may enter the environment from industrial discharges, municipal waste
treatment, plant discharges or spills. Due to the low vapor pressure, the chemical is extended in air
in limited amount. Volatilization is not a dominant transport process.
Because 2-ethylhexanol is slightly soluble in water, may be expected to sink rapidly soils as
consequence may be transported into groundwater by leaching through fissures rather than matrix
pores.
Persistence and degradability: When released into the air, this material may be readily degraded
by reaction with photochemically produced hydroxyl radicals with a half-life of 10 hours. When
released into the soil, watercourses and groundwater this chemical may be readily biodegraded
under aerobic conditions (95% after 5 days).
Other adverse effects: The substance has a harmfull effect on aquatic organisms. No ecological
problems are to be expected when the product is handled and used with due care and attention.
Do not allow to enter waters, waste water or soil!
Waste treatment: What ever cannot be saved for recovery or recycling should be handled as non-
hazardous waste. Any disposal practice must be in compliance with all local, regional and national
regulations. Do not dump into any sewers, on the ground, or into any body of water.
Packaging treatment: The empty containers/tanks are treated with steam and rinsed with plenty of
water. The resulted effluent are treated in the same way as waste. The empty and clean containers
are to be reused in conformity with regulations.
EC-Number: 203-234-3
B-6
2-ETHYL-1-HEXANOL (OCTANOL)
MSDS No.02-11
Revision: 7 Last up date: October 14, 2008 Date issued: July 21, 1999 Page 7/7
Hazard symbol: Xi Irritant
Precautions to be taken in handling and storing: Keep well ventilated the areas where
2-ethylhexanol is stored and handled.
Work hygienic practices: Avoid direct contact of substance with skin/eyes. Avoid the exposure of
personnel with with liver, kidney or lung damages to the substance.
Uses and Restrictions: Advice in this document relates only to product as originally supplied.
Other derivative chemicals will have different properties and hazard.
Chemical intermediate for organic synthesis.
Hazardous reaction: 2-Ethylhexanol is a combustible and flammable liquid. Vapours may travel
considerable far distances. Vapours are heavier than air, may cumulate along the ground and in
enclosed spaces. Do not empty into drains. When burning, it may emit pungent fumes and toxic
carbon monoxide.
MSDS Revisions: This Material Safety Data Sheet is made in accordance to European Regulations
and will replace the previous version 6 dated July 17, 2008.
Revised information:
This MSDS has been elaborated in accordance with Regulation (EC) No.1907/2006 REACH
The information contained here in is based on the present state of our knowledge. It characterizes the
product with regard to the appropriate safety precautions. It does not represent a guarantee of the
properties of the product.
This MSDS cannot cover all possible situations which the user may experience during handling and
processing. Each aspect of the user's operation should be examined to determine if, or where, additional
precautions may be necessary. All health and safety information contained within this MSDS should be
provided to the user's employees or customers.
B-7
248
APPENDIX C
REACTOR
Vessel temp, Tank Volume and Liq Vol % graphs at reaction start up
HFR-DL17 C-1
100.00
7.821 (m3)
80.00
60.00
HFR - Liquid Volume Percent (%)
33.43 (C)
40.00
29.72 (%)
20.00
0.00
40.00 41.00 42.00 43.00 44.00 45.00 46.00 47.00 48.00 49.00 50.00 51.00 52.00 53.00 54.00 55.00 56.00 57.00 58.00 59.00 60.00 61.00
Minutes
HFR - Vessel Temperature HFR - Tank Volume HFR - Liquid Volume Percent
Vessel Temp, Pressure Liquid vol Flow at reactor start up time
HFR-DL19 C-2
100.0
80.00
60.00
HFR - Liquid Volume SP (m3)
33.43 (C)
40.00
334.41 (bar)
20.00
2.323 (m3)
7.821 (m3)
80.00
60.00
HFR - Liquid Volume Percent (%)
33.43 (C)
40.00
21.01 (%)
20.00
0.00
38.00 40.00 42.00 44.00 46.00 48.00 50.00 52.00 54.00 56.00 58.00 60.00 62.00 64.00 66.00 68.00 70.00 72.00 74.00 76.00 78.00 80.00 82.00 84.00 86.00 88.00
Minutes
HFR - Vessel Temperature HFR - Tank Volume HFR - Liquid Volume Percent
Vessel Temp, Pressure Liquid vol Flow at reactor steady state time
HFR-DL19 C-4
100.0
80.00
60.00
HFR - Liquid Volume SP (m3)
33.43 (C)
40.00
20.00
2.47 (m3)
-1200
-1.225e+006 (kg
-1400
HFR - Liquid Volume Flow (m3/h)
-1600
-1786 (m3/h)
-1800
-2000
84.00 86.00 88.00 90.00 92.00 94.00 96.00 98.00 100.0 102.0 104.0 106.0 108.0 110.0 112.0 114.0 116.0 118.0 120.0 122.0 124.0 126.0 128.0 130.0 132.0 134.0
Minutes
APPENDIX D
FILE (Abridged)
Commissioning System File
Validated By Date:
D-1
Commissioning System File
System:
INDEX
1. System P&ID’s
2. Decontamination procedure & isolation register
3. System cleaning procedures
4. Hazard Study and actions
5. Equipment Check Sheets, off and on site checks
6. System Punch lists
7. Action upon Alarm Sheet
8. Handover Certificate Construction/Maintenance to Commissioning
9. Project documentation check sheet prior to introduction of safe chemicals
10. Safe Chemical Commissioning authorization and Pre-commissioning Procedures
11. Leak Test Checklist and Procedures
12. Instrument Check Sheet
13. Motor Check Sheet
14. Interlock Check procedures
15. Emergency Shut Down System check procedures
16. DCS sequence test procedures
17. Relief Stream Check Sheets
18. Critical Insulation Checks
19. Critical Gasket Installation Checks
20. Lubrication Check Sheet
21. PSSR, Plant Check-out prior to introduction of Hazardous Chemicals
22. Documentation Requirements for Ongoing Maintenance Group
23. Authority to Introduce Process Chemicals, check sheet & Certificate
24. Commissioning Procedures
25. Standard Operating Procedures
26. Commissioning to Plant Handover Certificate
D-2
3. System cleaning checklist & procedures
During the construction integrity test commissioning must follow with a cleaning
procedure for the pipe sections included in the test.
The Construction group may have the cleaning procedure incorporated within the
integrity test procedure, if this is the case commissioning need to create a list of
system pipe lines to track progress.
If required a line by line valve by valve procedure needs to be written for a
cleanliness check, these procedures are to be written utilizing the piping isometrics
as a guide.
D-4
e.g Off-Site Equipment Inspection
Check Sheet
Column/Tower
D-5
Post Punch list
Check sheet
PLEASE NOTE: This sheet should be completed post the actual punchlist as an “Aide Memoir”.
This check sheet should never be used as a substitute to actually physically checking the system being punch
listed.
Checked
No Description & signed off Comments
1 Has this system been totally checked against the relevant
P&ID?
7 Have all control valves been checked that they are fitted
correctly for direction of process flow?
D-6
Checked
No Description & signed off Comments
8 Have all filters, Non-return valves and other in-line pieces
of equipment been checked that they are fitted correctly
for direction of process flow?
9 Have all vents and drains Safety of location
been checked to ensure? Access
Direction of exhaust
Splashing
Pooling
Space for blind flange
removal and flexible pipe
fitting is adequate
Are there sufficient drains
on pipe including manifolds
10 Have All grounding straps been checked, no loose
connections or loose bolts?
11 Have all instruments and Accessibility
electrical items been Can gauges be read
checked for? Do impulse lines and cables
create a hazard
Are junction boxes in the
way
Are all stop buttons
accessible, labeled and
guarded if necessary
Motor guards checked and
tight, no loose screws
Has all instruments been
labeled in the filed
12 Have All relief streams been Exhaust lines clear
checked? Labeled
Relief valves tested &
tagged
Bursting discs fitted and
tagged
Supports appear adequate
13 Have all pipelines been checked to ensure no visible
mechanical damage has been made?
14 Has a list of all scaffolding to be removed prior to handover
been made and added to the punch list?
D-7
7. Action upon Alarm Sheet
POSSIBLE RESPONSES
D-8
Documentation check sheet prior to
chemical introduction
D-9
The following list details examples of pre-commissioning procedures that
commissioning can perform potentially during construction
These procedures can be numbered such that they can be easily referenced
on a detailed commissioning schedule.
D-10
24. Commissioning Procedures
Commissioning procedures, written during the preparation phase of the project are
the documents which in great detail, set out how the plant will be commissioned and
started up.
A detailed commissioning procedure should be compiled for each major activity that
the plant will undergo through the start-up. These documents are not check sheets,
they give a detailed descriptive of how the plant is made ready for normal operation.
A good commissioning procedure will detail the step, the method of performing the
step, any detail any relevant comments and observations.
D-11
COMMISSIONING TO PLANT
HANDOVER CERTIFICATE
I am satisfied that the system work has been commissioned and it is safe to allow continued operation.
Signature
Signature
Reservations to Handover
Item No. Description of Outstanding Work Item ID Action Req. Priority
From
D-12
267
APPENDIX E
Runaway Reaction
A runaway reaction occurs when reaction temperature continues to rise even after full
cooling is applied to the reactor.
A runaway reaction can be caused by:
loss of cooling.
loss of agitation.
loss of cooling.
Off-specification Product
Product can become off-specification for many different reasons, but some factors
which can contribute to off-specification product are:
sample taken was not a true representative sample or the sampling method
was incorrect.
faulty instruments.
feed variations.
impurities in feed.
E-2
Loss of Heating or Cooling
Loss of heating or cooling in the reactor could be caused by:
Sudden gas surges through the catalyst bed or liquid slugs entering the
catalyst bed.
E-3
Channelling causes poor contact between reactants and catalyst resulting in
incomplete reaction and off-spec product.
Channelling can be partially compensated for by adjusting flow rate and temperature
parameters, but the only permanent solution to channelling is to dump the catalyst and
re-pack the catalyst bed with fresh catalyst.
Corrective Action
Once problems are identified in a reactor, corrective action can be applied as follows:
Improper Sample If operating parameters appear normal, take new samples and have
them analysed.
Feed Variations or Take a new feed sample for analysis and compare the results
Impurities in Feed against the initial feed sample.
E-4
Reactor Problem Action Taken to Correct Off-Specification Product
Fouling of metal Check temperature rise or fall across the heat exchanger, water
surfaces in heat jackets or tubes. If temperature rise or fall is less than normal,
exchangers/water fouling has occurred which will require:
jackets or tubes. washing internal surfaces of exchangers, water jackets or
coils with cleaning solution then flushing with water or
steam to remove cleaning solution.
flushing with water or steam to remove cleaning solution.
Heating or cooling Ensure valve line-up to and from exchangers is correct and valves
medium not lined are fully open.
up to exchanger,
water jackets or
tubes.
E-5
Reactor Problem Action Taken to Correct Off-Specification Product
Even if the problem has been passed on to others to find and implement solutions,
follow up is essential – this makes sure that the problem is not lost in the system.
Always report problems outside of your responsibility and ensure that it is reported
and passed on to the appropriate person.
E-6
The shutdown will occur
at 1500 hours
In the case of emergency shutdowns or process trips, there is not time to give
advanced warnings, but communication must be made with unit suppliers and
customers as soon as possible after the trip or emergency shutdown to minimise the
adverse effects of the shutdown.
E-7