ANALISA HARGA SATUAN PEKERJAAN

PROP / KAB / KODYA : JAWA TIMUR


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Perbaikan Lapis Pondasi Agregat Kelas A, Terpasang
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja jam 0,1402 11.500,00 1.612,48


2. Mandor jam 0,0175 15.000,00 262,91

JUMLAH HARGA TENAGA 1.875,39

B. BAHAN

1. Agregat A M3 1,2000 200.000,00 240.000,00

JUMLAH HARGA BAHAN 240.000,00

C. PERALATAN
1. Wheel Loader jam 0,0083 402.944,00 3.348,10
2. Dump Truck jam 0,5672 282.865,00 160.448,82
3. Motor Grader jam 0,0010 349.399,00 334,45
4. Vibratory Roller jam 0,0175 214.486,00 3.759,30

JUMLAH HARGA PERALATAN 167.890,67

D. JUMLAH ( A + B + C ) 409.766,06
E. BIAYA UMUM 2,0 % x D 8.195,32
F. BIAYA KEUNTUNGAN 8,0 % x D 32.781,28
G. TOTAL ( D+E+F ) 450.742,66
H. PEMBULATAN 450.700,00