EDITED-FORM CA of Priti Gera
EDITED-FORM CA of Priti Gera
EDITED-FORM CA of Priti Gera
To
The Interim Resolution Professional
Shyam Arora
96, Aravali Apartment, Alaknanda, New Delhi-110019
Email: arora.shyaam@yahoo.com
Madam/Sir,
I, PritiGera, hereby submits this claim in respect of the corporate insolvency resolution
process of SRS Real Estate Ltd. The details for the same are set out below:
RELEVANT PARTICULARS
1. Name of the Mrs. PritiGera
financial
creditor
2. Identificatio Mrs. PritiGera, W/o Krishan Lal Gera
n number of
the financial
creditor PAN:----------
(If an
incorporate
d body,
provide
identificatio
n number
and proof of
incorporatio
n. If a
partnership
or
individual,
provide
identificatio
n records of
all the
partners or
the
individual)
3. Address and ADDRESS: C-572, Sector 15A, Faridabad, 121007
e-mail
address of
the financial Email: krishangera34@gmail.com
creditor for
corresponde
nce.
4. Total (i) Amount Paid:Rs. 58,00,000/-
amount of (ii) Interest @ 8% on refund calculated from the respective dates of
claim (in deposit Rs. 38,13,763/-
Rs.)
Total Claim [(i)+(ii)]=
Rs.96,13,763
7. Therefore, it can be inferred from the above terms of the receipt that
after the expiry of the aforesaid period, the amount of Rs. 57,81,000/-
will be treated as the consideration towards the purchase of the said
unit and the Claimant will be treated as the owner of the unit.
10. That it is submitted here that, as per reports and newspaper articles the
Respondent has already taken a loan of Rs. 140 crore from L.I.C.
Housing Finance Ltd., Delhi by mortgaging 612 flats of the Project.
That despite taking such huge loan amounts from financial
institutions, the Respondent lured innocent allottees to paying their
hard-earned monies to the Respondent with the promised that they
will return the amounts within one year or the allotment of a Unit in
the Project (which was initially provided as a security) will become
absolute. It is humbly submitted that such tactics of the Respondent,to
take such large amount of money from the Claimant and other
allottees for the development of its Project, clearly shows that the
Claimant just wanted to fraudulently and illegally extract money and
thereby commit fraud without actually having the intention to fulfill
its part of the promise as per the BBA.
11. It is pertinent to mention herein that as per the agreed terms of the
Security Deposit Receipt, the Respondent failed to repay the amounts
within a period of one year thereby the allotment of the Unit to the
Claimant became absolute.
13. It is apropos to mention here that the clause 1.14 of the BBA entitled
the Respondent to charge 18% p.a. of the interest in case of delay in
making the payments upto 3 months and thereafter at the rate 24%
p.a. by the Claimant, however, clause 5 of the BBA restricts the
Claimant from claiming any damages or compensation from the
Respondent for delay in handing over of possession. There is a huge
discrimination in the remedies available to the Claimant and the
Respondent under the Allotment Letter and the BBA.
14. That, as mentioned above that the terms and conditions of the
Allotment letter/BBA are illegal, unfair, unreasonable and one sided
and a perusal of the clauses shows the stark incongruities on the
remedy available to the Claimant and the Respondent. The
Respondent compelled the Claimant to abide the terms of the
Allotment Letter/ Agreement having arbitrary terms and conditions
wherein it is clearly mentioned that in case of failure to give the
timely possession, the Respondent shall not be liable to any
compensation penalty or interest which is totally unfair, one-sided and
is not even binding on the allottee.
15. The Hon’ble Supreme Court of India has laid down in various
judgments that the courts will have power to strike down the
contract/agreement having arbitrary and one-sided terms and
conditions. As per the Judgment passed by the Hon’ble Supreme
Court of India in the Case of “Pioneer Urban Land & Infrastructure
Ltd. Vs. Govindan Raghavan, Civil Appeal 12238 of 2018, it was
held that Builder could not seek to bind the purchaser with such one-
sided contractual terms.
The relevant paras from the judgementare as follows:
“A term of contract will not be final and binding if it
is shown that the flat purchaser had no option but
to sign on the dotted line, on a contract framed by
the Builder. The contractual terms of the
agreement dated 08.05.2012 are ex-facie one-sided,
unfair and unreasonable. The incorporation of
such one-sided clauses in an agreement constitutes
an unfair trade practice as per Section 2(1) (r) of
the consumer protection act, 1986 since it adopts
unfair methods and practices for the purpose of
selling the flats by the Builder.”
16. The Allotment Letter/ Agreement is biased and one sided. It does not
specify anywhere that in case the Respondent Company fails to
deliver the timely possession of the unit, the Buyer/Claimant have the
right to seek refund the entire amount without any forfeiture. The
Respondent has nowhere mentioned any remedial measures to be
taken in case of deficiency or failure of services.
17. That suddenly the news of misdeeds by the Respondent were
highlighted in News Channels and social media and the same came to
the knowledge of the Claimant. Thereafter, the Claimant inquired and
came to know that number of complaints of cheating, fraud and
misappropriation were filed against the Directors of M/s SRS Real
Estate Ltd. Further, it also came to the knowledge of the Claimant that
multiple cases were already registered against the Respondent for
committed similar acts of cheating and fraud with various allottees by
adopting the same practice as in the case of the Claimant.
20. That after few days, it came to the knowledge of the Claimant that the
permissions obtained by the Respondent for the construction &
development of the Project was illegally obtained by concealing the
material facts and was in connivance with the local administration.
Therefore, the same were cancelled by the appropriate Government
Authority. Thereafter, the Claimant again called the Respondent in
order to demand the refund ofher hard-earned money along with
interest from the Respondent. However, the Respondent again tries to
mislead the Claimant by offering an alternative Unit which was
previously mortgaged to some other party and thereby again trying
tocommit afraud against her.
21. That the Claimant has been in regular compliance of the terms and
conditions of the BBA. Also, despite paying a huge amount of Rs.
58,00,000/- towards the total sale consideration, the Respondent again
sent a payment demand letter on 05.06.2018 in order to extract money
from the Claimant whereas the status of construction of the Project
was negligible and in a dismal state.
A copy of the demand letter dated 05.06.2018 is annexed herein
as Annexure- C/4
22. That in reply to the demand letter dated 05.06.2018, the Claimant sent
a legal notice dated 14.06.2018 wherein the Claimant clearly stated
that the true facts that the Claimant has already paid a huge amount
towards the consideration of the said unit in form of cash and in return
of the same, the Respondent has neither given the possession of the
said unit to the Claimant nor refund the amount and thereby, violated
the terms of the Agreement executed between them.
23. That the claimant requested the respondent many times over phone,
E-mails, Letters and by meeting them personally and sought
information on the status of the project and also the probable
time/date of handling over possession but no effective response came
from the Respondent. It is pertinent to note that after few days, the
Claimant on visiting the project site was shocked to see that there was
absolutely no construction going on in the site and the Respondent
would not be able to handover the possession of the unit anytime
soon.
24. It is submitted that all the concerns and grievances raised by the
Claimant fell on the deaf ears of the Respondent. The Respondent
being in a dominant position has arbitrarily extracted monies from the
claimant in the name of investing the same in development work of
the project, however, the Respondent diverted the hard earned money
of the Claimant and misused the same for his own use and purpose.
25. That on 29.07.2019 as a last resort, the Claimant also filed a Police
complaint against the Respondent in Sector-31 Police Station for their
misconducts. Thereafter, as it was a prima facie case, the Police
authorities had lodged the FIR against them and a chargesheet has
already been filed in the court against their criminal liability.
A copy of the FIR is annexed herein with as Annexure-C/7
26. That the Claimant has not been compensated with even a penny till
date by the Respondent for the delay in delivery. Thus, the
Respondent Company has resorted to unfair practices by way of
making incorrect, false and misleading clauses in the BBA.
27. That the Respondent failed to complete the project and substantially
failed to discharge its obligations. Therefore, the Claimant intends to
withdraw from the project owing to unreasonable delay in completion
of the project and hence the Respondent is liable to return the amount
deposited by the Claimant along with an interest.
28. That inordinate delay in handing over possession of the unit clearly
amounts to deficiency of service on account of the Respondent
Company and the Claimant have rightly claimed to withdraw from the
project and claim total refund of amount along with the interest. That
in view of the above facts the Learned Authority is requested to direct
the Respondent to refund the money of the Claimant as they have
been subjected to mental and financial harassment by the Respondent
by illegally demanding money when the project is nowhere near
completion. It is also pertinent to mention here that the construction
work of the project is way behind than its schedule and there is no
hope for completion of the same in near future, and it is submitted that
the Claimant cannot be expected to endlessly wait for the possession.
This Principle has been settled by the Hon’ble Apex Court in the
matter of Fortune Infrastructure and Ors. Vs. Trevor D’Lima and
Ors. (Judgment dated March 12, 2018). The Hon’ble Apex Court in
the abovementioned matter has held that
FINANCIAL CREDITOR
DECLARATION
I, PritiGera, W/o Krishan Lal Gera currently residing at C-572, Sector 15A, Faridabad,
121007, do hereby declare and state as follows: -
1. SRS Real Infrastructure Ltd., the corporate debtor was, at the insolvency
commencement date, being the……………..day of…………..20……., actually
indebted to me for a sum of Rs. 27,27,500/-.
2. In respect of my claim of the said sum or any part thereof, I have relied on the
documents specified below:
3. The said documents are true, valid and genuine to the best of my knowledge,
information and belief and no material facts have been concealed therefrom.
4. In respect of the said sum or any part thereof, neither I, nor any person, by my
order, to my knowledge or belief, for my use, had or received any manner of
satisfaction or security whatsoever, save and except the following:
5. I am a related party of the corporate debtor, as defined under section 5 (24) of the
Code.
6. I am eligible to give voting instruction to the authorized representative by virtue
of proviso to section 21 (2) of the Code even though I am a related party of the
corporate debtor.
Date:
Place:
VERIFICATION
I, PritiGera, the claimant hereinabove, do hereby verify that the contents of this proof of
claim are true and correct to my knowledge and belief and no material fact has been
concealed therefrom.
(Signature of claimant)
PritiGera