PMT 10106
PMT 10106
PMT 10106
Man-Power Leveling
Note: The source of the technical material in this volume is the Professional
Engineering Development Program (PEDP) of Engineering Services.
Warning: The material contained in this document was developed for Saudi
Aramco and is intended for the exclusive use of Saudi Aramco’s employees.
Any material contained in this document which is not already in the public
domain may not be copied, reproduced, sold, given, or disclosed to third
parties, or otherwise used in whole, or in part, without the written permission
of the Vice President, Engineering Services, Saudi Aramco.
Contents Pages
Figure 2, that follows, has the labor resource totaled by each day. By observation, one can see
that the man-power is leveled, since the man-power varies between 3 and 6 men per day. There
are no man-power peaks and valleys. If there were greater variations, the activities with float time
would have their start or finish dates changed within the float time to level the man-power.
ACT NO.
100 - 102 4 4 4
Engineering Encyclopedia
102 - 104 2
108 - 110 3 3 3 3 3 3 3 3 3 3
110 - 112 3 3 3 3 3 3 3 3 3 3
114 - 116 5
116 - 118 5 5 5 5 5 5 5
118 - 120 5 5 5 5 5 5 5 5 5 5
120 - 122 6
122 - 124 5 5 5 5
124 - 130 5 5 5
NO. MEN 4 4 4 5 5 5 5 5 5 5 5 5 3 3 3 3 3 3 3 3 3 3 3 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 6 5 5 5 5 5 5 5 0
2
Engineering Encyclopedia Project Management
Man-Power Leveling
The previous example had unlimited man-power availability. In most cases, the man-power is
limited. In the case of limited man-power, one must again adjust the start and completion dates of
the activities within the float times to minimize the required man-power per day or to stay within
the given man-power limits. In Figure 3 that follows, the man-power was limited at 4 men. The
CPM network was then adjusted to use a maximum of 4 men per day and a minimum crew size of
2 men. Man-power adjustment may extend the project completion date. The first activities to be
changed are the activities with float time. After the first activities are exhausted and if the man-
power is still too high, the critical activities must be adjusted. Adjusting the critical activities will
delay the project completion date.