SAUDI ARAMCO ID/PIEU - 4-April-2018 - REV. 2018.01.00 (Standards Cutoff -January 31, 2018) Rev. 2018.01.

00 31-Jan-18

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Concrete Coatings Pre-Installation Inspection SAIC-H-1003 4-Apr-18 CIVIL-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A Surface preparation, moisture testing and environmental condition inspection

The coating shall be applied after the full curing time of concrete in SAES-H-003
A1
accordance to SAES-Q-001. Sec. 8.1.3

New concrete must have a moisture content of 4% or less before the


coating applications commence.
SAES-H-003
A2
Note: Test report SATR-H-1003 " Concrete Moisture Field Test Sec. 8.1.5
(For Coating Purposes)" shall be available for review/verification of
concrete moisture condition.

Surface temperature, humidity and dew point readings shall be recorded.


The work shall not proceed if the substrate temperature shall be less than SAES-H-003
A3
3°C (5°F) above the dew point, or any ther deviations from the coating Sec. 9.3.1
manufacturers' data sheet.

Remove any protrusions and sharp edges with an abrasive carborundum SAES-H-003
A4
brick, power grinding, or power brushing prior to coating concrete. Sec. 7.2.1.1

Surfaces shall be sound such that a metal object run over the concrete SAES-H-003
A5
shall not loosen any particles. Sec. 7.2.1.1

Surface contaminants such as laitance and form oils must be


removed. Form oils, grease, etc. shall be removed by steam SAES-H-003
A6
cleaning with a water emulsifying detergent added. Laitance Sec. 7.2.1.2
shall be removed by wire brushing.

Materials that cannot be removed by steam cleaning or abrasion can be


removed by Hydochloric acid etching; The adequacy of the water flushing SAES-H-003
A7
shall be checked by placing litmus paper on the wet surface to ensure that Sec. 7.2.1.3
it is fully neutralized.

New concrete shall be roughened to the texture of medium grit sandpaper SAES-H-003
A8
by grit blasting when it has a troweled or "formed" smooth surface. Sec. 7.2.1.4

The tensile strength of heavy duty surface concrete by ASTM D4541 shall
SAES-H-003
A9 meet or exceed 175psi for immersion service and 260 psi for industrial
Sec. 7.2.2
floors.

Remove all loose concrete, surface contaminations, sealants, and old


coatings by abrasive blasting (or other mechanical means) and/or hot water SAES-H-003
A10
high pressure washing as appropriate, prior to making concrete repairs and Sec. 7.3.1
coating application.

Saudi Aramco: Company General Use


Neutralize acidic surfaces with an alkaline cleaner such as soda ash SAES-H-003
A11
(sodium carbonate) followed by a high pressure fresh water rinse. Sec. 7.3.2b

Saudi Aramco: Company General Use