SECTION 16127 Cables, Low Voltage (600 Volts and Below)
SECTION 16127 Cables, Low Voltage (600 Volts and Below)
SECTION 16127 Cables, Low Voltage (600 Volts and Below)
SECTION 16127
CABLES, LOW VOLTAGE (600 VOLTS AND BELOW)
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation, and connection of
the low voltage power and lighting wiring.
//B. Definitions: The term HCF Type AC cable, as used in this specification,
shall mean Type AC cable in accordance with the National Electrical Code
with an insulated equipment grounding conductor, an internal bonding
strip of copper or aluminum and the outer metal armor or sheath of the
assembly shall be approved and identified as an acceptable grounding
return path. HCF Type AC cable may be used in Health Care Facilities
only as permitted by this specification. //
1.2 RELATED WORK
A. Excavation and backfill for cables that are installed in conduit:
Section 02200, EARTHWORK.
B. Sealing around penetrations to maintain the integrity of time rated
construction: Section 07270, FIRESTOPPING SYSTEMS.
C. General electrical requirements that are common to more than one section
in Division 16: Section 16050, BASIC METHODS AND REQUIREMENTS
(ELECTRICAL).
D. Conduits for cables and wiring: Section 16111, CONDUIT SYSTEMS.
E. Requirements for personnel safety and to provide a low impedance path
for possible ground fault currents: Section 16450, GROUNDING.
1.3 SUBMITTALS
In accordance with Section 01340, SAMPLES AND SHOP DRAWINGS, furnish the
following:
A. Manufacturer's Literature and Data: Showing each cable type and rating.
B. Certificates: Two weeks prior to final inspection, deliver to the
Resident Engineer four copies of the certification that the material is
in accordance with the drawings and specifications and has been properly
installed.
16127-1
09-01M
16127-2
09-01M
1. Annealed copper.
2. Shall be stranded for sizes No. 8 AWG and larger, solid for sizes No.
10 AWG and smaller.
3. Shall be minimum size No. 12 AWG, except where smaller sizes are
allowed herein.
C. Insulation:
1. THW, XHHW, or dual rated THHN-THWN shall be in accordance with UL 44,
and 83.
2. Direct burial: UF or USE shall be in accordance with UL 493.
3. Isolated power system wiring: Type XHHW with a dielectric constant of
3.5 or less.
D. Color Code:
1. Secondary service, feeder and branch circuit conductors shall be
color coded as follows:
2. Use solid color compound or solid color coating for No. 12 AWG and
No. 10 AWG branch circuit conductors and neutral sizes.
3. Phase conductors No. 8 AWG and larger shall be color-coded using one
of the following methods:
a. Solid color compound or solid color coating.
b. Stripes, bands, or hash marks of color specified above.
c. Color as specified using 19 mm (3/4 inch) wide tape. Apply tape in
half overlapping turns for a minimum of 75 mm (three inches) for
terminal points, and in junction boxes, pull boxes, troughs,
manholes, and handholes. Apply the last two laps of tape with no
tension to prevent possible unwinding. Where cable markings are
covered by tape, apply tags to cable stating size and insulation
type.
4. For modifications and additions to existing wiring systems, color
coding shall conform to the existing wiring system.
16127-3
09-01M
16127-4
09-01M
16127-5
09-01M
D. The finished application shall withstand a 200-ampere arc for not less
than 30 seconds.
E. Securing tape: Glass cloth electrical tape not less than 0.18 mm
(7 mils) thick, and 19 mm (3/4 inch) wide.
2.8 WARNING TAPE
SPEC WRITER NOTE: Use non-detectable type
for cemeteries only.
16127-6
09-01M
16127-7
09-01M
4. Where cable trays are used to support the cables, each cable shall be
securely fastened to transverse members of the cable trays. Cable
trays shall be independently supported in accordance with
manufacturer's recommendations and NEC.
5. Through Metal Framing: Cable shall be supported in accordance with
the NEC where run through metal framing members.
6. Fished Cables: Cables may be fished in existing structures only.
Supports are not required where cables are fished through existing
walls or above non-removable ceilings. Where cables are installed in
new structures, appropriate supports shall be provided.
I. PENETRATIONS
1. Cutting of Holes
a. Cut holes in concrete and masonry in new and existing structures
with a diamond core drill or concrete saw. Pneumatic hammer,
impact electric, hand or manual hammer type drills are not
allowed, except where permitted by the Resident Engineer as
required by limited working space.
2. Fire Stops: Where HCF Type AC cable passes through fire partitions,
fire walls or smoke partitions, install a fire stop that provides an
effective barrier against the spread of fire, smoke and gasses as
specified in Section, FIRESTOPPING SYSTEMS, with rock wool fiber or
silicone foam sealant only. Completely fill and seal clearances
between cables and openings with the fire stop material. Penetrations
shall meet the requirements of UL 1479.
3. Waterproofing: Where Type AC cable passes through floors, floors
shall be core drilled and appropriately sized sleeves shall be
installed for the cables. Sleeves shall terminate not less than 75 mm
(3 inches) above floor slabs and not less than 75 mm (3 inches) below
the ceiling of the floor below. Completely seal clearances between
the cable and sleeve and make watertight as specified in section,
SEALANTS AND CAULKING. //
3.3 INSTALLATION IN MANHOLES
A. Install and support cables in manholes on the steel racks with porcelain
or equal insulators. Train the cables around the manhole walls, but do
not bend to a radius less than six times the overall cable diameter.
//B. Fireproofing:
16127-8
09-01M
1. Where low voltage cables are installed in the same manholes with high
voltage cables, also cover the low voltage cables with arc proof and
fireproof tape.
2. Use tape of the same type as used for the high voltage cables, and
apply the tape in a single layer, one-half lapped or as recommended
by the manufacturer. Install the tape with the coated side towards
the cable and extend it not less than 25 mm (one inch) into each
duct.
3. Secure the tape in place by a random wrap of glass cloth tape.//
3.4 SPLICE INSTALLATION
A. Splices and terminations shall be mechanically and electrically secure.
B. Where the Government determines that unsatisfactory splices or
terminations have been installed, remove the devices and install
approved devices at no additional cost to the Government.
3.5 CONTROL, COMMUNICATION AND SIGNAL WIRING INSTALLATION
A. Unless otherwise specified in other sections of these specifications,
install wiring and connect to perform the functions shown and specified
in other sections of these specifications.
B. Except where otherwise required, install a separate power supply circuit
for each system so that malfunctions in any system will not affect other
systems.
C. Where power supply circuits are not shown for systems, connect them to
the nearest panelboards of suitable voltages, which are intended to
supply such systems and have suitable spare circuit breakers or space
for installation.
D. Install a red warning indicator on the handle of the branch circuit
breaker for the power supply circuit for each system to prevent
accidental de-energizing of the systems.
E. System voltages shall not exceed 120 volts and shall be lower voltages
where shown on the drawings or required by the NEC.
3.6 CONTROL, COMMUNICATION AND SIGNAL SYSTEM IDENTIFICATION
A. Install a permanent wire marker on each wire at each termination.
B. Identifying numbers and letters on the wire markers shall correspond to
those on the wiring diagrams used for installing the systems.
C. Wire markers shall retain their markings after cleaning.
D. In each manhole and handhole, install embossed brass tags to identify
the system served and function.
16127-9
09-01M
16127-10
09-01M
//3.10 INSTRUCTIONS
A. Furnish the services of a competent factory trained engineer or
technician for two, 2 hour periods for instructing VA personnel in the
use and installation of HCF Type AC cable. Sessions shall be
accomplished at the job site and the location will be determined by the
VA. The first 2 hour session shall be presented after submittal
approval, but before installation of any of the cable. Session may be
attended by contractor's staff (maximum of 4 personnel) in addition to
VA personnel. The last two hour session shall be accomplished two weeks
prior to the final inspection and shall be attended by VA staff only.//
- - - E N D - - -
16127-11