MWPS Daily Activity Report 28 August2011
MWPS Daily Activity Report 28 August2011
MWPS Daily Activity Report 28 August2011
NUBI 2A PROJECT
DAILY ACTIVITY REPORT
MWPS Site Works
REPORTED DATE : 28‐Aug‐2011
CUT OF TIME : 6.00 PM (DAYSHIFT)
HIGHLIGHT ISSUE
Complete 7 of 8 anchor
AHT Petrogas having problem with the sling arrangement at winch during anchoring activity
Accident occurred at 17:30 at flowline mezzanine deck. Tip point finger of pipe fitter pinched by pipe wrench while doing spade reinstatement
ACTIVITY
NO. TO DAY ACTIVITY PROGRESS NO. TOMORROW PLAN
Night Shift 1 Continue anchoring job EB 507
1 No Activity 2 Transfer material from tug boat to weather deck
3 Install scafolding at lower & mezzanine deck
4 Continue flushing remaining HHP flowline
Day Shift 5 Modification HHP flowline
1 Transfer material from tug boat to weather deck 6 Prepare hydrotest HHP flowline
2 Anchoring job EB 507 (7 of 8 completed) 7 Continue glanding at Choke Valve hydraulic panel
3 Install Padeyes for CP Guide Submerged Installation 8 Termination and glanding at TIT HP flowline (complete)
4 Install additional beam 16x45 9 Termination and glanding for PIT slot T2
5 Install 3 ea pipe support 10 Install support for ACS box and lighting cable tray
6 Flushing HHP flowline slot C, W, V, A2 & S
7 Install blind flange at slot C, W & A2
Install blind flange at slot C, W & A2
8 Install 2" HHP methanol line at slot U, S, R1, R2
9 Install spade at HHP flowline slot U
10 Install 10 ea thermowell at HHP flowline
11 Continue glanding at Choke Valve hydraulic panel
12 Termination and glanding at TIT HP flowline (complete)
13 Re‐tightening all transmitter cable gland
14 Pulling lighting cable
PROGRESS
No. Scope Description Progress % Completed : Plannned 91.2% Actual 87.2%
Structural Completion Date : Baseline 15‐Sep‐2011 Forecast 15‐Sep‐2011
S001 Preparation work, scaffolding & install gusset plate for Module 2 & 3 100%
S002 Preparation work, scaffolding & install gusset plate for Module 1 100%
S003 Install Anode 0%
S004 CP Guide Under Water 0% S‐Curve Plan vs Actual Progress
S005 Protection Frame 55%
120% 20.00%
S006 CP Guide Above Water 100%
S007 Extension Deck Module ‐2 99% 18.00%
Plan Daily Progress Actual Daily Progress
S008 Extension Deck Module ‐3 100%
100%
S009 Extension Deck Module ‐1 99% 16.00%
S010 Appurtenances 100% Cummulative Plan Daily Progress Cum Actual Daily Progress
Cummulative Progress Value
Piping 14.00%
80%
P001 Lifiting & positioning WHCP 100%
Daily Progress Value
2‐Aug
5‐Aug
8‐Aug
1‐Sep
4‐Sep
7‐Sep
10‐Sep
13‐Sep
12‐Jul
15‐Jul
18‐Jul
21‐Jul
24‐Jul
27‐Jul
30‐Jul