Karmakar, Basab Raj

From: Ghosh, Sukamal


Sent: 21 April 2022 09:31
To: Karmakar, Basab Raj
Subject: FW: C.ETMT: Cable Tray/Route designation system

FYI

From: Patel, Stavan - AM/NS India - CDE (HAZ) <Stavan.Patel@amns.in>


Sent: 24 February 2022 10:59
To: Ghosh, Sukamal <sukamal.ghosh@arcelormittal.com>
Cc: Savarkar, Sachin - AM/NS India - Projects (HAZ) <Sachin.savarkar@amns.in>; Bhatt, Deep - AM/NS India -
Projects (HAZ) <Deep.Bhatt@amns.in>; Kumar, Mohit - AM/NS India - Projects (HAZ) <Mohit.Kumar2@amns.in>;
Singh, Ankita - AM/NS India - Projects (HAZ) <ANKITA.SINGH@amns.in>; Mandal, Amit
<Amit.Mandal@arcelormittal.com>; Singha, Rajesh <Rajesh.Singha@arcelormittal.com>; Das, Sanjoy
<sanjoy.das@arcelormittal.com>; Purkait, Sagnik <sagnik.purkait@arcelormittal.com>; Hait, Subhendu
<subhendu.hait@arcelormittal.com>; Mukherjee, Kalyan <kalyan.mukherjee@arcelormittal.com>; Parikh, Srujan
<srujan.parikh@arcelormittal.com>; AMNSCDE <AMNS_CDE@amns.in>
Subject: RE: C.ETMT: Cable Tray/Route designation system

Dear Sukamal ji,

Pl. find our observation in trailing mail for.

Regards,
Stavan Patel

From: Ghosh, Sukamal <sukamal.ghosh@arcelormittal.com>


Sent: 23 February 2022 12:01
To: AMNSCDE <AMNS_CDE@amns.in>; Gaurav Ladva <gaurav_ladva@milliconconsultants.com>
Cc: Savarkar, Sachin - AM/NS India - Projects (HAZ) <Sachin.savarkar@amns.in>; Patel, Stavan - AM/NS India - CDE
(HAZ) <Stavan.Patel@amns.in>; Bhatt, Deep - AM/NS India - Projects (HAZ) <Deep.Bhatt@amns.in>; Kumar, Mohit -
AM/NS India - Projects (HAZ) <Mohit.Kumar2@amns.in>; Singh, Ankita - AM/NS India - Projects (HAZ)
<ANKITA.SINGH@amns.in>; Mandal, Amit <Amit.Mandal@arcelormittal.com>; Singha, Rajesh
<Rajesh.Singha@arcelormittal.com>; Das, Sanjoy <sanjoy.das@arcelormittal.com>; Purkait, Sagnik
<sagnik.purkait@arcelormittal.com>; Hait, Subhendu <subhendu.hait@arcelormittal.com>; Mukherjee, Kalyan
<kalyan.mukherjee@arcelormittal.com>; Parikh, Srujan <srujan.parikh@arcelormittal.com>
Subject: FW: C.ETMT: Cable Tray/Route designation system

Dear Gaurav,

This has reference to tagging system for cable and cable tray.
Please find the tagging procedure as we have discussed now.
You may please update and resend wherever further correction is required.

A. Tagging for cable coming from MRSS-2 to CRM-2 complex.


i) Power Cable
Source Panel with area code-Destination Panel with area code-P0-Sequence number
Example: MRSS2-33KVSWB12-CRM2-UTL-33KVSWBD5-P0-XXX
(It is coming from MRSS-2 33 KVSWBD panel 12 to CRM-2 utility 33 KVSWBD panel 5)

ii) Control Cable

1
iii) Source Panel with area code-Destination Panel with area code-C0-Sequence number
MRSS2-33KVSWB12-CRM2-UTL-33KVSWBD5-C0-XXX

P0=MV Power Cable


P1=LV Power Cable
C0=110 V Control Cable
C1=24 V Control Cable
AMNS Comment:
S0 = Signal Cable

B. Tagging for cable coming inside CRM-2 complex.

i) Power Cable
CGL4.E1-Source Panel-Destination pane/equipment tag-P0-Sequence number
Example: CGL4.E1-LVDB1-P16-P1-XXX
(It is going from Entry ECR LVDB 1 to Pump-16)

AMNS Comment:
CGL4.E1-Source Panel-Destination pane.Feeder number/equipment tag-P0-Sequence number
CGL4.E1-LVDB1.F02-P16-P1-XXX
(It is going from Entry ECR LVDB 1 (Feeder F02) to Pump-16)

ii) Control Cable


CGL4.E1-Source Panel-Destination pane/equipment tag-P0-Sequence number
Example: CGL4.E1-RIO1-P16-C1-XXX
(It is going from RIO 1 to Pump-16)

AMNS Comment:
CGL4.E1-Source Panel.Terminal Number-Destination pane/equipment tag-P0-Sequence number
Example: CGL4.E1-RIO1.X001-P16-C1-XXX

iii) Instrument Cable


CGL4.E1-Source Panel-Destination pane/equipment tag-P0-Sequence number
Example: CGL4.E1-RIO1-PT001-I1-XXX
(It is going from RIO 1 to Pressure Transmitter)

AMNS Comment : Use “S”for signal/instrument cable instead of “I”.


CGL4.E1-Source Panel.Terminal Number -Destination pane/equipment tag-S0-Sequence number
Example: CGL4.E1-RIO1.X001-PT001-S0-XXX

E1=Entry ECR
E2-Intermediate ECR
E3=Exit ECR

C. Cable Tray Tagging System

Area Code-Route Number-Tray Layer (bottom most being /Left most being 1)-H/M/L/C/S

H= 33 KV Cable Tray
M=6.6 kV Cable Tray
L= 415 V Cable Tray
C=Control Cable Tray
S=Signal Cable Tray
2
Example: CGL4.F.1.6-S
( It is at CGL#4 furnace area route 1 and 6 number tray from bottom and carrying signal cable).

Regards,
Sukamal Ghosh

From: Ghosh, Sukamal


Sent: 21 February 2022 16:09
To: Bhatt, Deep - AM/NS India - Projects (HAZ) <Deep.Bhatt@amns.in>; Kumar, Mohit - AM/NS India - Projects (HAZ)
<Mohit.Kumar2@amns.in>; AMNSCDE <AMNS_CDE@amns.in>
Cc: Patel, Stavan - AM/NS India - CDE (HAZ) <Stavan.Patel@amns.in>; Savarkar, Sachin - AM/NS India - Projects
(HAZ) <Sachin.savarkar@amns.in>; Mandal, Amit <Amit.Mandal@arcelormittal.com>; Purkait, Sagnik
<sagnik.purkait@arcelormittal.com>; Singha, Rajesh <Rajesh.Singha@arcelormittal.com>; Hait, Subhendu
<subhendu.hait@arcelormittal.com>; Das, Sanjoy <sanjoy.das@arcelormittal.com>
Subject: FW: C.ETMT: Cable Tray/Route designation system

Dear All,

We need to finalise the cable and cable tray numbering system for CRM-2 plant.
Please share if there is any existing designation system

Otherwise we would like to propose the following

Cable and Tray numbering System


Unit number-Plant number- ECR Designation-Service Designation-Voltage code-Sequence Number

Lets take CRM-2 number as 178 in AMNS Hazira. You may inform if there is any other number.
Plant Number: PLTCM-1, CGAL-2, CGL#3-3 and CGL#4-4, Utility area-5, Finishing area-6.
ECR Designation: CGL#4 has three ECR so, entry will be 1, intermediate will 2 and exit will be 3. Utility has one ECR so
it will be 1.
Voltage Code: 0 is MV cable, 1 is LV cable, 2 is control cable 110 V, 3 is instrument cable 24 V.

Example:
LV Power cable coming from CGL#4 entry ECR:
CRM2.4.E1.SWBD1-Destination tag-P0-Sequence number

LV Power Cable tray coming from CGL#4 entry ECR


CRM2.4.AREA P0-Sequence number

Control cable coming from CGL#4 entry ECR:


178-4-1-CC-2-XXX

Control Cable tray coming from CGL#4 entry ECR


178-4-1-CT-2-XXX

Instrument cable coming from CGL#4 entry ECR:


178-4-1-IC-3-XXX

Instrument cable tray coming from CGL#4 entry ECR


178-4-1-IT-3-XXX

Regards,
Sukamal Ghosh

3
From: Banerjee, Biplab <biplab.banerjee@primetals.com>
Sent: 21 February 2022 12:03
To: Ghosh, Sukamal <sukamal.ghosh@arcelormittal.com>
Cc: Kundu, Kinkini <kinkini.kundu@primetals.com>
Subject: RE: C.ETMT: Cable Tray/Route designation system

Dear Sukamal Da,

Please give us if you have any reference for Route and Tray numbering system.

Best regards,
Biplab Banerjee

Primetals Technologies India Private Limited


A joint venture of Mitsubishi Heavy Industries and partners
EA IN EN
5th Floor, Tower - C, DLF IT Park-I,
08 Major Arterial Road, New Town (Rajarhat),
Kolkata 700156, India.
T:+91 33 66291000
F:+91 33 66291300
M:+91 8697749396
biplab.banerjee@primetals.com

-----Original Appointment-----
From: Banerjee, Biplab
Sent: 18 February 2022 13:00
To: Banerjee, Biplab; Ghosh, Sukamal; Kundu, Kinkini
Subject: C.ETMT: Cable Tray/Route designation system
When: 18 February 2022 17:00-17:30 (UTC+05:30) Chennai, Kolkata, Mumbai, New Delhi.
Where: Microsoft Teams Meeting

________________________________________________________________________________

Microsoft Teams meeting


Join on your computer or mobile app
Click here to join the meeting

Or call in (audio only)


+91 22 6259 0665,,,,110009522# India, Mumbai
Phone Conference ID: 110 009 522#
Find a local number | Reset PIN

Learn More | Meeting options

________________________________________________________________________________

You might also like