Desmet Ballestra India PVT LTD: Inspection Test Plan
Desmet Ballestra India PVT LTD: Inspection Test Plan
Desmet Ballestra India PVT LTD: Inspection Test Plan
REV. NO. :- R1
100201960 Rev.-001/100201844 Rev.-001
DRG NO. :- 100200180 Rev.-001/100201830 Rev.-001
INSPECTION TEST PLAN
DATE :- 14.09.2021/15.09.2021/15.09.2021 & 15.09.2021
CLIENT :- DESMET BALLESTRA INDIA PVT LTD INSPECTION BY:- DESMET & M/s LR ITEM NO. 14A,14B,14S,24B1-24B2 PREPARED BY :- AVS
DRYING AIR CYCLONE/COOLING AIR
PROJECT :- WASIL2 MANUFACTURED BY :- SYSCON ENGINEERS DESCRIPTION . CYCLONE/SOLVENT CYCLONE & APPROVED BY :- DESMET & M/s LR
MISCELLA STRAINER
Serial Inspection Scope
Activites Type of Check Extent of Insp. Reference Document Format of Report
No VENDOR DESMET L/R Remarks
1.00 DESIGN
1.10 Approved Drawing Document Review 100% ASME SecVIII Div.1 (Ed.2019) Approved Drawing - H -
Inspection Report /
3.10 Plates ( Shell, Dish etc) Dimensional, Visual, Review of 100% Approved Drgs., P.O. M.T.C. (as per EN10204 P W R Check test shall be carried out @ NABL Lab only.
Material T.C. Specification -3.1) Lab Test Report
Inspection Report /
3.20 Nozzles Pipes & External Coil Dimensional, Visual, Review of 100% Approved Drgs., P.O. M.T.C. (as per EN10204 P W R Check test shall be carried out @ NABL Lab only.
Material T.C. Specification -3.1) Lab Test Report
Flanges & Fittings (Nozzle Flanges, Sight Glass Dimensional, Visual, Review of Approved Drgs., P.O. Inspection Report /
3.30 100% M.T.C. (as per EN10204 P W R
Flanges) Material T.C. Specification
-3.1)
4.00 Fabrication
4.10 Long Seam & Cir-Seam Joints Visual, Dimensional 100% Approved Drgs. Inspection Report P W R
4.20 Dish forming Visual, Dimensional & DP check on 100% Approved Drgs. Inspection Report P W R
Knuckle Portion
4.30 Nozzle Set-up to shell & Dish, Visual, Dimensional 100% Approved Drgs. Inspection Report P W R
5.00 NDT
5.10 D.P. Test. Of backchip joints (L/S & C/S Joints) Visual 100% Approved Drgs. OR Applicable Inspection Report P W R
Standard
5.20 RADIOGRAPHY Review of Radiographic films Ass per approved Approved Drgs. OR Applicable Radiography Report P R -
drgs. Standard
5.30 Pneumatic test of R.F Pads Leak Detection @ 1.5 KG/CM2 100% Approved Drgs. Inspection Report P R R
Page : 1
DESMET BALLESTRA INDIA PVT LTD
QAP NO. :- SE/QAP/1678 A,B,C,D & E/14A,14B,14S,24B1-24B2
REV. NO. :- R1
100201960 Rev.-001/100201844 Rev.-001
DRG NO. :- 100200180 Rev.-001/100201830 Rev.-001
INSPECTION TEST PLAN
DATE :- 14.09.2021/15.09.2021/15.09.2021 & 15.09.2021
CLIENT :- DESMET BALLESTRA INDIA PVT LTD INSPECTION BY:- DESMET & M/s LR ITEM NO. 14A,14B,14S,24B1-24B2 PREPARED BY :- AVS
DRYING AIR CYCLONE/COOLING AIR
PROJECT :- WASIL2 MANUFACTURED BY :- SYSCON ENGINEERS DESCRIPTION . CYCLONE/SOLVENT CYCLONE & APPROVED BY :- DESMET & M/s LR
MISCELLA STRAINER
Serial Inspection Scope
Activites Type of Check Extent of Insp. Reference Document Format of Report
No VENDOR DESMET L/R Remarks
6.00 Final Inspection
6.10 NDT Verification Weld Map review, Reports 100% Approved Drgs. Inspection Report P H W
Verification.
Approved Drgs. / Technical
6.20 Final Visual & Dimensioanl Check Dimensional & Visual 100% Inspection Report P H W
Specification
7.00 HYDROTEST
7.10 Vessel Hydro/Pneumatic - Test Leak Detection 100% Approved Drgs. Inspection Report P W W Holding time 30 Minutes
8.10 Pickling & Passivation of SS Parts Removal of oxides from weld 100% Approved Drgs. Inspection Report P W R
surface & cleanliness of surface
SA 2.5 Blasting, Visual &
8.20 Painting of CS surfaces 100% Approved Drgs. Inspection Report P W R
Paint DFT
8.30 Final Visual Check AFTER Painting Visual 100% Approved Drgs. / Technical Inspection Report P W R
Specification
9.00 DOCUMENTATION
Approved Drgs &
9.10 Review of Final Documents Documentaion & record 100% Inspection Report P H -
As Per P.O. Specification
LEGENDS : H - HOLD ( OFFER FOR WITNESS & OBTAIN CLEARANCE ), R/W - RANDOM WITNESS, R - REVIEW ONLY, W - WITNESS A - REVIEW & APPROVED, P - PERFORM, AWL - ADANI WILMAR LTD
NOTES: 1) PMI to be carried out after complete fabrication & prior to Hydrotest.
Page : 2