Nodes Activity Time (Weeks)

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Name:

Score:

Test I:
1. Given the following data for building to be constructed:

Time
Nodes Activity
(weeks)
1-2 A Demolition and clearing 8
2-3 B Excavation 14
2-5 C Underground installations 6
3-4 D Foundation and column 5
4-5 E Dummy 0
4-6 F Construction of second floor 6
4-7 G Roof framing and roofing 6
5-7 H Ground floor slab 4
5-8 I Mechanical and electrical services 12
6-7 J Construction of exterior walls 12
7-8 K Dummy 0
7-9 L Construction of interior partitions 10
8-9 M Mechanical and electrical fixtures 12
9-10 N paining and finishing 8

Required:
a. Draw the network diagram.
b. Determine the Early Start, Early Finish, Late Start and Late Finish
c. Determine the Total Float and Free Float
d. Find the CPM of the project.
e. What is the duration of the project?
f. Make a data sheet corresponding to this project.
g. If the project starts on May 23, 2011, what is the completion date of the project considering
that the man works 5 days in a week (Mon. to Fri) including holidays?

2. Using the information given below:

Immediately Normal Crash


Normal Crash
Activity Follows Duration, Duration,
Cost, P Cost, P
activity days days
A 1,000 1,100 None 3 2
B 2,000 2,000 A 4 4
C 1,600 1,600 B 4 4
D 250 300 C 3 2
E 500 600 A 2 1
F 600 800 B, E 3 1
G 800 1,100 F, I 3 1
H 3,000 3,800 A 6 2
I 400 700 H 2 1
J 1,000 1,000 I 4 4
K 500 500 C, G, J 2 2
L 500 1,000 D 2 1
M 600 600 K, L 2 2
Required:
h. Draw the network diagram.
i. Determine the Early Start, Early Finish, Late Start and Late Finish.
j. Determine the Total Float and Free Float
k. Find the CPM of the project.
l. What is the normal duration of the project?
m. Make a data sheet corresponding to this project.
n. If the project starts on May 23, 2011, what is the completion date of the project considering
that the man works 5 days in a week (Mon. to Fri) including holidays?
o. What is the normal cost of the project?
p. Give the least cost of completing the job in the least possible time.

3. Define the following terms:

a. PERT
b. CPM
c. Project
d. Free Float
e. Gantt chart
f. Management
g. Construction
h. Dummy
i. Network
j. Event

4. Enumeration:

a. Differentiate PERT/CPM
b. Three Time Estimate
c. Network Diagram composition
d. Conventional way of making network

5. Project:

a. Estimate the Bill of Material(BOM) of your own 2 nd storey floor plan:


-Structural plan
-Architectural plan
-Plumbing plan
b. Tabulate all the data gathered.
c. Make a manpower computation
d. Put it in a data sheet.
e. Show all the computation.
f. Define the estimate duration of the project using the estimated material, manpower and
rate of work.
g. Draw the Gantt chart and time scaled network diagram
h. S-curve and bar chart of the project.