The following summary of work includes construction progress from August 21st to September 21st , 2020.
c. Covered Walkway –
- Formworks are done off-site and will be delivered once work will start. Work shall
commence by the first week of October.
d. Fence
- Layout of fence is done. Work shall commence once excavated work from the other is
backfilled.
2. Schedule Summary
Contract completion Date: January 21, 2021
Contractor’s Estimated Completion Date: December-January
Total Overall % of Work: 25%
Reason for Delay: Manpower
Comments:
A Progress Chart is provided that represents percentage of completion as it relates to the required,
scheduled and actual completion dates.
Based on the progress observed, it appears that the project is
Reason of delay is man power, additional requirements for workers due to the new regulation
because of the pandemic takes time.
Based on the progress observed, the renovation of existing guard house is ahead from its timeline.
The construction of new canteen building is managing to comply with the given timeline. Projected
completion date of December-January is what the contractor is targeting.
Progress Chart
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
21-Aug 21-Sep 21-Oct 21-Nov 21-Dec Jan
Scheduled Actual
3. Mitigation Measures
Contractor has put out measures such as employing more personnel and working overtime shifts.
4. Conclusion/Recommendation
The overall project progress stands at 25% against 30%. The contractor has set programs to
increase labor/personnel and introducing overtime on selected activities to ensure that the delays
are worked over in the stipulated time frame.