Makkah Reservoir Progress Report 23-12-2021
Makkah Reservoir Progress Report 23-12-2021
Makkah Reservoir Progress Report 23-12-2021
PROGRESS REPORT
Period: 18‐Dec‐21 To 23‐Dec‐2021
Date: 26‐Dec‐2021
TIME FRAME OVERALL CONSTRUCTION PROGRESS
0.00% 20.00% 40.00% 60.00% 80.00% 100.00%
9% 91%
OVERALL ACTUAL 4.95%
OVERALL PLANNED 4.80%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% PAGE 1
Rehabilitation of One Million Reservoir in Makkah Al Mukarramah
Activity ID Activity Name Original Planned Planned Actual Actual Performance % 2022 2023
Duration Start Finish Start Finish Complete O N D J F M A M J J A S O N D J F M A M J J A SO
Rehabilitation of One Million Reservoir in Makkah
609
Al Mukarramah
19-Oct-21 18-Oct-23 19-Oct-21 4.95%
02-Dec-21 A, GENERAL
GENERAL 57 19-Oct-21 02-Dec-21 19-Oct-21 02-Dec-21 100%
Rehabilitation Works Inside Reservoir 201 19-Oct-21 15-Jun-22 19-Oct-21 0% 15-Jun-22, Rehabilitation Works Inside Reservoir
Repair Concrete Materials 176 31-Oct-21 12-May-22 31-Oct-21 18.54% 12-May-22, Repair Concrete Materials
Waterproofing Materials 150 06-Dec-21 13-Jun-22 06-Dec-21 2.29% 13-Jun-22, Waterproofin g Materials
Excavation and General Fill 250 17-Nov-21 17-Sep-22 17-Nov-21 11.43% 17-Sep-22, Excavation and General Fill
Filter layer type 2 258 02-Apr-22 07-Feb-23 0% 07-Feb-23, Filter layer type 2
Stones (riprap) for slope protection 222 06-Nov-22 29-Jul-23 0% 29-Jul-23, Stones (ripr
Ready Mix concrete Inside 125 02-Jan-22 01-Jun-22 0% 31-May-22, Ready Mix concrete Inside
GRP PIPES AND ACCESSORIES 78 08-Jan-22 07-Apr-22 0% 06-Apr-22, GRP PIPES AND ACCESSORIES
Collection sump / lift station 221 05-Oct-22 22-Jun-23 0% 22-Jun-23, Collection sump
Suction lift pump 221 05-Oct-22 22-Jun-23 0% 22-Jun-23, Suction lift pump
Borehole and Vibrating wire piezometers 108 22-Jan-22 01-Jun-22 0% 01-Jun-22, Borehole and Vibrating wire piezometers
22-Jul-23, ENGINEER
ENGINEERING DOCUMENTS AND SUBMITTALS 477 25-Dec-21 22-Jul-23 0%
Rehabilitation Works Inside Reservoir 117 25-Dec-21 15-May-22 0% 15-May-22, Rehabilitation Works Inside Reservoir
Rehabilitation Works Inside Reservoir 173 17-Nov-21 15-Jun-22 17-Nov-21 2.12% 14-Jun-22, Rehabilitation Works Inside Reservoir
Remedial Works In Peripheral Columns & Pre. Wall Inside 131 01-Dec-21 10-May-22 01-Dec-21 0.04% 10-May-22, Remedial Works In Peripheral Columns & Pre. Wall Inside
Zone 1 83 01-Dec-21 22-Feb-22 01-Dec-21 0.09% 22-Feb-22, Zone 1
Zone 2 70 13-Feb-22 10-May-22 0% 10-May-22, Zone 2
Remedial Works In Drainage Channel,Service Road & Entrance Gate 95 11-Jan-22 07-May-22 0% 07-May-22, Remedial Works In Drainage Channel,Service Road & Entrance Gate
Zone 1 50 11-Jan-22 09-Mar-22 0% 09-Mar-22, Zone 1
Zone 2 45 10-Mar-22 07-May-22 0% 07-May-22, Zone 2
Remedial Works In Soffit Of The Roof Slab & Pre. Radial & Ring Beams 115 01-Dec-21 30-Apr-22 01-Dec-21 0% 30-Apr-22, Remedial Works In Soffit Of The Roof Sla b & Pre. Radial & Ring Beams
Zone 1 62 01-Dec-21 27-Feb-22 01-Dec-21 0% 27-Feb-22, Zone 1
Zone 2 67 12-Feb-22 30-Apr-22 0% 30-Apr-22, Zone 2
Remedial Works In Culvert (Service Gallery) 138 01-Jan-22 14-Jun-22 0% 14-Jun-22, Remedial Works In Culvert (Service Gallery)
Zone 1 138 01-Jan-22 14-Jun-22 0% 14-Jun-22, Zone 1
Reservoir Basin 173 17-Nov-21 15-Jun-22 17-Nov-21 2.37% 14-Jun-22, Reservoir Basin
Waterproofing Lining System 172 17-Nov-21 15-Jun-22 17-Nov-21 3.24% 13-Jun-22, Waterproofin g Lining System
Activity ID Activity Name Original Planned Planned Actual Actual Performance % 2022 2023
Duration Start Finish Start Finish Complete O N D J F M A M J J A S O N D J F M A M J J A SO
Zone 1 144 17-Nov-21 11-May-22 17-Nov-21 5.19% 11-May-22, Zone 1
Zone 2 108 31-Jan-22 15-Jun-22 17-Nov-21 1.3% 13-Jun-22, Zone 2
Drainage System 103 06-Feb-22 11-Jun-22 0% 11-Jun-22, Drainage System
Zone 1 74 06-Feb-22 08-May-22 0% 08-May-22, Zone 1
Zone 2 80 10-Mar-22 11-Jun-22 0% 11-Jun-22, Zone 2
Access Road Area 42 21-Apr-22 14-Jun-22 0% 14-Jun-22, Access Road Area
Zone 1 34 21-Apr-22 05-Jun-22 0% 05-Jun-22, Zone 1
Zone 2 28 14-May-22 14-Jun-22 0% 14-Jun-22, Zone 2
Collection Room 99 06-Feb-22 06-Jun-22 0% 06-Jun-22, Collection Room
Civil Works 65 06-Feb-22 21-Apr-22 0% 21-Apr-22, Civil Works
Mechanical Work 24 23-Apr-22 25-May-22 0% 25-May-22, Mechanical Work
Flowmeters 5 26-May-22 31-May-22 0% 31-May-22, Flowmeters
Piezometers 5 01-Jun-22 06-Jun-22 0% 06-Jun-22, Piezometers
Modification Of Discharge Channel 85 01-Mar-22 13-Jun-22 0% 13-Jun-22, Modification Of Discharge Channel
Rehabilitation Works Inside Reservoir 8 07-Jun-22 15-Jun-22 0% 15-Jun-22, Rehabilitation Works Inside Reservoir
Rehabilitation Works Inside Reservoir 8 07-Jun-22 15-Jun-22 0% 15-Jun-22, Rehabilitation Works Inside Reservoir
Activity ID Activity Name Original Planned Planned Actual Actual Performance % 2022 2023
Duration Start Finish Start Finish Complete O N D J F M A M J J A S O N D J F M A M J J A SO
Rehabilitation Works Outside Reservoir 10 08-Oct-23 18-Oct-23 0%
10.00%
9.00%
8.00%
5.77%
7.00%
4.95%
4.80%
4.50%
4.33%
6.00%
5.00%
4.00%
3.00%
0.97%
0.47%
0.44%
0.43%
0.30%
2.00%
1.00%
0.00%
PREVIOUS WEEK CUM. PREVIOUS WEEK CURRENT WEEK CUM. CURRENT WEEK FORECAST NEXT WEEK CUM. FORECAST NEXT
WEEK
PLANNED % ACTUAL %
PAGE 5
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
3.00%
3.50%
4.00%
0.15%
21/Oct/21
0.11%
0.35%
28/Oct/21
0.38%
0.63%
4/Nov/21
0.67%
0.64%
11/Nov/21
0.68%
0.67%
18/Nov/21
0.78%
0.59%
25/Nov/21
0.91%
0.47%
2/Dec/21
Planned %
0.36%
0.40%
9/Dec/21
0.31%
0.43%
16/Dec/21
0.30%
Actual %
0.47%
23/Dec/21
0.44%
0.97%
30/Dec/21
1.10%
6/Jan/22
0.97%
13/Jan/22
1.18%
20/Jan/22
1.24%
27/Jan/22
Cum Planned Total Cost %
1.38%
Makkah Reservoir Overall Cash Flow
3/Feb/22
1.53%
10/Feb/22
1.54%
17/Feb/22
1.69%
24/Feb/22
2.82%
3/Mar/22
Cum Actual Total Cost %
3.18%
10/Mar/22
3.32%
17/Mar/22
3.50%
24/Mar/22
3.47%
31/Mar/22
PAGE 6
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
3.00%
3.50%
4.00%
0.00%
21/Oct/21
0.00%
0.00%
28/Oct/21
0.00%
0.00%
4/Nov/21
0.00%
0.00%
11/Nov/21
0.00%
0.06%
18/Nov/21
0.30%
0.19%
25/Nov/21
0.76%
0.19%
2/Dec/21
Planned %
0.05%
0.19%
9/Dec/21
0.05%
0.19%
16/Dec/21
0.05%
Actual %
0.19%
23/Dec/21
0.05%
0.85%
30/Dec/21
0.93%
6/Jan/22
0.66%
13/Jan/22
1.03%
20/Jan/22
1.12%
27/Jan/22
Cum Planned Total Cost %
Construction Overall Cash Flow
1.37%
3/Feb/22
1.62%
10/Feb/22
1.57%
17/Feb/22
1.79%
24/Feb/22
2.43%
3/Mar/22
Cum Actual Total Cost %
3.06%
10/Mar/22
3.27%
17/Mar/22
3.49%
24/Mar/22
3.46%
31/Mar/22
PAGE 7
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
50.00%
55.00%
60.00%
65.00%
70.00%
75.00%
80.00%
85.00%
90.00%
95.00%
100.00%
0.00%
1.00%
2.00%
3.00%
4.00%
5.00%
6.00%
7.00%
8.00%
9.00%
10.00%
21/Oct/21 0.00%
0.00%
28/Oct/21 0.00%
0.00%
4/Nov/21 0.15%
0.17%
11/Nov/21 0.18%
0.20%
18/Nov/21 0.49%
0.52%
25/Nov/21 1.06%
Planned %
1.07%
2/Dec/21 0.80%
0.75%
9/Dec/21 1.01%
0.97%
16/Dec/21 1.10%
Actual %
0.94%
23/Dec/21 1.24%
1.43%
30/Dec/21 1.40%
6/Jan/22 1.50%
13/Jan/22 1.56%
20/Jan/22 1.55%
27/Jan/22 1.55%
Cum Planned Total Cost %
1.55%
Procurement Overall Cash Flow
3/Feb/22
10/Feb/22 1.54%
17/Feb/22 1.70%
24/Feb/22 1.78%
3/Mar/22 4.38%
10/Mar/22 4.38%
Cum Actual Total Cost %
17/Mar/22 4.41%
24/Mar/22 4.59%
31/Mar/22 4.56%
PAGE 8
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
50.00%
55.00%
60.00%
65.00%
70.00%
75.00%
80.00%
85.00%
90.00%
95.00%
100.00%
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
4.89%
21/Oct/21
3.54%
11.68%
28/Oct/21
12.62%
19.29%
4/Nov/21
20.68%
19.29%
11/Nov/21
20.68%
16.21%
18/Nov/21
14.89%
5.78%
25/Nov/21
5.19%
4.37%
Planned %
2/Dec/21
3.92%
0.00%
9/Dec/21
0.00%
0.00%
16/Dec/21
0.00%
Actual %
0.00%
23/Dec/21
0.00%
0.00%
30/Dec/21
0.00%
6/Jan/22
0.00%
13/Jan/22
0.00%
20/Jan/22
Mobilization Cash Flow
0.00%
27/Jan/22
Cum Planned Total Cost %
0.00%
3/Feb/22
0.00%
10/Feb/22
0.00%
17/Feb/22
0.00%
24/Feb/22
0.00%
3/Mar/22
Cum Actual Total Cost %
0.00%
10/Mar/22
0.00%
17/Mar/22
0.00%
24/Mar/22
0.00%
31/Mar/22
PAGE 9
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
50.00%
55.00%
60.00%
65.00%
70.00%
75.00%
80.00%
85.00%
90.00%
95.00%
100.00%
0
200
400
600
800
1,000
1,200
1,400
39
21/Oct/21
0
83
28/Oct/21
0
98
4/Nov/21
12
98
11/Nov/21
48
94
18/Nov/21
254
74
25/Nov/21
Weekly Planned Manpower
342
68
2/Dec/21
333
92
9/Dec/21
279
110
16/Dec/21
164
102
23/Dec/21
184
165
30/Dec/21
Weekly Actual Manpower
206
6/Jan/22
241
13/Jan/22
328
20/Jan/22
370
27/Jan/22
341
3/Feb/22
Makkah Reservoir Manpower Histogram
403
10/Feb/22
Cum Planned Total Manpower
393
17/Feb/22
426
24/Feb/22
432
3/Mar/22
431
10/Mar/22
669
17/Mar/22
708
24/Mar/22
Cum Actual Total Manpower
724
31/Mar/22
PAGE 10
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
100
150
200
250
300
350
400
0
50
9
21/Oct/21
0
18
28/Oct/21
0
18
4/Nov/21
20
18
11/Nov/21
46
12
18/Nov/21
82
0
25/Nov/21
Weekly Planned Equipment
96
0
2/Dec/21
133
0
9/Dec/21
172
0
16/Dec/21
151
0
23/Dec/21
166
58
30/Dec/21
Weekly Actual Equipment
61
6/Jan/22
40
13/Jan/22
77
20/Jan/22
77
27/Jan/22
74
3/Feb/22
Makkah Reservoir Equipment Histogram
83
10/Feb/22
87
Cum Planned Total Equipment
17/Feb/22
114
24/Feb/22
103
3/Mar/22
98
10/Mar/22
103
17/Mar/22
83
24/Mar/22
Cum Actual Total Equipment
102
31/Mar/22
0
PAGE 11
200
400
600
800
1,000
1,200
1,400
Construction Activities
Sr No. Summary of On‐goingActivities
1 Cadastral Survey works inside the tank
2 Chiseling and demolition of concrete face up to Steel reinforcement for precast wall panel sector 1&2
3 Performing shop Drawings for Zone 1
4 Performing hummer tapping &Visual inspection SOFFIT OF THE ROOF SLAB/SHELL for Sector no (1 & 2)
PAGE 12
Construction Activities
Sr No. Summary of Next Week Activities
1 Chiseling and demolition of concrete face up to Steel reinforcement for precast wall panel sector 1&2
2 Send shop Drawings for Cross Section
3 Performing hummer tapping &Visual inspection SOFFIT OF THE ROOF SLAB/SHELL for Sector no (1 & 2)
4
PAGE 13