Manpower Plan: Gmco Contracting Company

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

GMCO CONTRACTING COMPANY

INOCHEM TANK PROJECT

CONTRACT NO:

MANPOWER PLAN
SHIFT HOURS WORKED:6:00 am to 5:00 pm
Morning Shift FROM :
Afternoon Shift 10 Hrs/ Day
INDIRECT MANPOWER & STAFF Days No. Man/Days Unit/Rate Total Price DIRECT MANPOWER Days No. Man/Days Unit/Rate Total Price
Tank Welder 180 8 1440 0
Tank Fitter 180 12 2160 0
Helper/Rigger 180 6 1080 0
Electrican 180 1 180 0

CONTRACTOR TITLE DATE


MOHAMED ATEF BADAWY PROJECT MANAGER 25/5/2021
COMPANY COMMENTS AND/OR EXCEPTIONS:

COMPANY REPRESENTATIVE: TITLE: DATE: