Nothing Special   »   [go: up one dir, main page]

Data Center Design

Download as pdf or txt
Download as pdf or txt
You are on page 1of 36

DATA CENTER DESIGN

OVERVIEW
Presented by Horst Pfendt

Critical Facilities Round Table


7th QUARTERLY MEETING

December 17, 2004


DATA CENTER DESIGN OVERVIEW
INTRODUCTION
In the next couple of hours I will touch on
various aspects of Data Center Design
The intend today, is not to have a detailed
discussion, but to have an overview only of
various elements of Data Center Design
The goal is to get feed-back in what topics the
group is interested in so we can schedule a
more detailed presentation in the future
DATA CENTER DESIGN
OVERVIEW
The following items will be discussed:
Project Development and Execution Process
Organizing and Staffing
Building Design: Interior/Exterior
Power Distribution
Process Cooling
Commissioning
Energy Efficiency
DATA CENTER DESIGN
OVERVIEW

The Project Development and Execution


Process (PDEP) consists of five phases
1. Identify and Assess Opportunities
„ Clearly frame the goal to be pursued and
insure alignment with business objectives
„ Perform a preliminary assessment of
uncertainties and associated risks
„ Plan for the next phase of the process
DATA CENTER DESIGN
OVERVIEW

PDEP (continued)
2. Generate and Select Alternatives
- Generate alternatives and reduce the
uncertainties of each alternative
- Develop the expected value for selected
alternatives & select the preferred
alternative
- Plan for the next phase of the process
DATA CENTER DESIGN
OVERVIEW
PDEP (continued)
3. Develop Preferred Alternatives
- Fully define the scope of the alternatives &

develop detailed execution plans


- Check for expected value to meet business

objectives
- Refine estimates & economic analysis to meet

funding requirements
- Submit for funding approval, as appropriate
DATA CENTER DESIGN
OVERVIEW

PDEP (continued)
4. Execute
„ Implement execution plan and finalize
operating plan
„ Collect, analyze, and share metrics and
lessons learned
DATA CENTER DESIGN
OVERVIEW

PDEP (continued)
5. Operate and Evaluate
„ Monitor performance of the asset
„ Benchmark performance of the assets
against objectives and competitors
„ Share results and lessons learned
„ Continue performance assessment and
identify other opportunities
DATA CENTER DESIGN
OVERVIEW
Organization and Staffing
„ Project Manager familiar with Company
Policy/Operation
„ In-House Personnel; i.e. Building Engineer

„ Architect

„ Asset Protection Consultant

„ Electrical Consultant

„ Mechanical Consultant

„ Structural Consultant

„ Data Center Relocation Team


DATA CENTER DESIGN
OVERVIEW

Site Selection
„ New/Old/Own/Lease/Outsource Building
„ Environmental Hazards
„ Transportation
„ Access to Site
„ Utility Service
„ Telecommunication Service
DATA CENTER DESIGN
OVERVIEW

Project Total Data Center Requirements


in sq. ft.
„ Hardware Requirements
„ Power Requirements
„ Process Cooling Requirement
„ Access Floor Requirement
„ Support Space (Non-Raised Floor)
„ Circulating Areas
DATA CENTER DESIGN
OVERVIEW

Exterior Consideration
„ Utility
„ Access to Data Center
„ Security
„ Wall and roof Construction
DATA CENTER DESIGN
OVERVIEW
Interior Consideration
„ Floors
„ Walls
„ Building Column Spacing
„ Hallways
„ Freight Elevator
„ Storage/Uncrating Area
„ Power Distribution
„ Process Cooling
„ Water Detection
DATA CENTER DESIGN
OVERVIEW

Commissioning
„ Commissioning is a process that extends
through all phases of the project
„ The goal of commissioning is to obtain a
facility that operates efficiently, according
to the design intent
DATA CENTER DESIGN
OVERVIEW
Commissioning (continued)
„ Commissioning:
Š Provides owners with a facility that operates in
accordance with original design intent
Š Reduces energy and operating costs by having systems
function at maximum efficiency
Š Reduces the number of contractor call backs
Š Reduces Occupant complaints due to discomfort
Š Provides documentation, training and education for
operators and facility managers
DATA CENTER DESIGN
OVERVIEW
Commissioning (continued)
„ The following should be in the commissioning
specification
Š Responsibilities of parties involved in the project
Š Description of the commissioning process
Š Requirements for pre-functional performance test
Š Requirements for functional performance test
Š Requirements for O&M manuals
Š Requirements for O&M training
Š Requirements for documentation
Š Requirements for “as-built” drawings
DATA CENTER DESIGN
OVERVIEW

Energy Efficiency
Energy Efficiency vs. Energy Conservation
…Both activities lower energy
consumption. However, conservation
implies a decrease in service; energy
efficiency must meet or exceed the quality
of service that it replaces…
DATA CENTER DESIGN
OVERVIEW
Energy Efficiency
„ We use the EPA’s five-step approach in our energy
efficiency management plan
Š Lighting efficiency upgrade (Green Lights)
Š Building tune-up (re-commissioning)
Š Building load reduction
Š HVAC distribution system upgrades
Š HVAC plant upgrade
DATA CENTER DESIGN
OVERVIEW

Energy Efficiency Case Study


Office/Warehouse Building
„ Benefits of Green Lights Program
Š Environmental
„ Reduced Power Plant emission-1,000,000 KWH/Year
„ Eliminated PCB Ballasts
Š Reduced Energy Costs
„ Energy Savings-$115,000/year
„ PG&E Rebate-$60,000
„ Project Payout <Nine Month
DATA CENTER DESIGN OVERVIEW
Energy Efficiency Case Study
Office/Warehouse Building (continued)
„ Benefits of Mechanical Upgrades
Š Reduced Energy Usage
„ Electrical Savings: 249,600 KWH/Year
„ Demand Savings: 249KW
„ Gas Savings: 1,416 Therms/Year
Š Reduced Energy Costs
„ Energy Savings: $80,000/Year
„ PG&E Rebate: $60,000
„ Project Payback: < 2 Years

You might also like