Validation (Drug Manufacture)
Validation (Drug Manufacture)
Validation (Drug Manufacture)
Validation in the pharmaceutical and medical device industry is defined as the documented act
of demonstrating that a procedure, process, and activity will consistently lead to the expected
results. It often includes the qualification of systems and equipment. It is a requirement for Good
Manufacturing Practices and other regulatory requirements. Since a wide variety of procedures,
processes, and activities need to be validated, the field of validation is divided into a number of
subsections including the following:
Cleaning Validation
Process Validation
Analytical Method Validation
Computer System Validation
Similarly, the activity of qualifying systems and equipment is divided into a number of
subsections including the following:
Contents
[hide]
1 History
2 Reasons for Validation
3 Validation Master Plan
4 The Validation Process
5 Computer System Validation
6 Scope of Computer Validation
7 Risk Based Approach To Computer Validation
8 See also
9 References
[edit] History
The concept of validation was first proposed by two Food and Drug Administration (FDA)
officials, Ted Byers and Bud Loftus, in the mid 1970’s in order to improve the quality of
pharmaceuticals (Agalloco 1995). It was proposed in direct response to several problems in the
sterility of large volume parenteral market. The first validation activities were focused on the
processes involved in making these products, but quickly spread to associated processes
including environmental control, media fill, equipment sanitization and purified water
production.
The concept of validation was first developed for equipment and processes and derived from the
engineering practices used in delivery of large pieces of equipment that would be manufactured,
tested, delivered and accepted according to a contract (Hoffmann et al. 1998). The use of
validation spread to other areas of industry after several large-scale problems highlighted the
potential risks in the design of products. The most notable is the Therac-25 incident, (Leveson &
Turner 1993). Here, the software for a large radiotherapy device was poorly designed and tested.
In use, several interconnected problems led to several devices giving doses of radiation several
thousands of times higher than intended, which resulted in the death of three patients and several
more being permanently injured.
In 2005 an individual wrote a standard by which the transportation process could be validated for
cold chain products.[citation needed] This standard was written for a biological manufacturing company
and was then written into the PDA's Technical Report # 39, thus establishing the industry
standard for cold chain validation. This was critical for the industry due to the sensitivity of drug
substances, biologics and vaccines to various temperature conditions. The FDA has also been
very focused on this final area of distribution and the potential for a drug substances quality to be
impacted by extreme temperature exposure.
The validation process consists of identifying and testing all aspects of a process that could affect
the final test or product. Prior to the testing of a process, the system must be properly qualified.
Qualification includes the following steps: (These steps are common practice for equipment (IQ,
OQ and PQ).
Design Qualification (DQ)- Defines the functional and operational specification of the
instrument, program, or equipment and details the rationale for choosing the supplier.
Installation Qualification (IQ) - Demonstrates that the process or equipment meets all
specifications, is installed correctly, and all required components and documentation
needed for continued operation are installed and in place.
Operational Qualification (OQ) - Demonstrates that all facets of the process or equipment
are operating correctly.
Performance Qualification (PQ) - Demonstrates that the process or equipment performs
as intended in a consistent manner over time.
Component Qualification (CQ) - is a relatively new term developed in 2005. This term
refers to the manufacturing of auxiliary components to ensure that they are manufactured
to the correct design criteria. This could include packaging components such as folding
cartons, shipping cases, labels or even phase change material. All of these components
must have some type of random inspection to ensure that the third party manufacturer's
process is consistently producing components that are used in the world of GMP at drug
or biologic manufacturer.
There is often overlap between Installation, Operational, and Performance Qualification and
sometimes these are performed simultaneously.
Figure 2: OPQ Validation Process (adapted from the typical V-Model)
Probably the best known industry guidance available is the GAMP Guide, now in its fifth edition
and known as GAMP5 published by ISPE (2008). This guidance gives practical advice on how
to satisfy regulatory requirements.
The overall risk posed by a computer system is now generally considered to be a function of
system complexity, patient/product impact, and pedigree (Configurable-Off-The-Shelf or
Custom-written for a certain purpose). A lower risk system should merit a less in-depth
specification/testing/validation approach. (e.g. The documentation surrounding a spreadsheet
containing a simple but "GxP" critical calculation should not match that of a Chromatography
Data System with 20 Instruments)
Determination of a "GxP critical" requirement for a computer system is subjective, and the
definition needs to be tailored to the organisation involved. However in general a "GxP"
requirement may be considered to be a requirement which leads to the
development/configuration of a computer function which has a direct impact on patient safety,
the pharmaceutical product being processed, or has been developed/configured to meet a
regulatory requirement. In addition if a function has an direct impact on GxP data (security or
integrity) it may be considered "GxP critical".
[edit] See also