MB Passive Active Floors Jan17
MB Passive Active Floors Jan17
MB Passive Active Floors Jan17
Contents
Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
References. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Cover images
Bottom insert: 4 West Building, University of Bath, which uses the Concretcool
system, see pages 16 and 17. Photo: courtesy of Cowlin Construction Ltd.
This page: 160 Tooley Street, London uses the thermal mass provided by the
concrete to help optimise the building's passive cooling performance. See
page 26.
CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING 3
3. A growing appreciation of visual concrete and the role it can play in the
‘fabric first’ approach to energy efficient design.
Kg CO2 /m2/year
Figure 1: Benchmark CO2 emissions from office buildings4. Bermondsey Square, London, which features exposed hollowcore slabs.
Photo: courtesy of Igloo Regeneration Limited.
4 CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING
Peak temperature
Up to 8 degrees difference
delayed by up to
between peak external
six hours
and internal temperature
Internal temperature
30oC with high thermal mass
Internal temperature
with low thermal mass
External
temperature
15oC
In the case of the 300mm slab, it can be seen that the soffit temperature
Thermal mass in naturally ventilated slowly increases over the course of several days in response to the onset
26
25
Start of hot weather
18
0 1 2 3 4 5 6 7 8 9 10 11 12 13
Day
No. of sub- 1. Visual comfort Scores up to 2.8% (daylight, glare, view etc)
BREEAM category Weighting categories 2. Safety & security
3. Thermal comfort Scores up to 1.9% (thermal modelling of design)
1. Health & wellbeing 15% 6 4. Water quality
5. Acoustics performance Scores up to 1.9% (meets acoustic standards)
2. Management 12% 5 6. Indoor air quality Scores up to 5.6% (0.95% for nat. vent. capability)
3. Transport 8% 5 1. Reduced CO2 emissions Scores up to 8.1%
2. Energy monitoring
4. Water 6% 4 3. Efficient external lighting
4. Low/zero carbon tech. Scores up to 2.7% (0.54% for night time cooling)
5. Energy 19% 9 5. Efficient cold storage
6. Efficient transport systems
6. Pollution 10% 5
7. Efficient laboratory systems
7. Waste 7.5% 4 8. Efficient equipment (process)
9. Drying space
8. Land use & ecology 10% 5
1. Life cycle impacts Scores up to 4.8% (based on Green Guide rating)
9. Materials 12.5% 5 2. Hard landscaping
3. Responsible sourcing Scores up to 2.9%
Total 100% 4. Insulation
5. Designing for robustness
Innovation 10% 0
The concrete mix is usually specified by the structural engineer based on System control
strength and durability requirements. But for visual concrete the mix is
adjusted to aid placing, compaction and to achieve a consistent finish. In terms of control, the main objective is to take maximum advantage
The siting of the project is important because the constituents of concrete of night cooling whilst avoiding over-cooling, which can result in
are locally sourced and vary depending on the local geology. With all this uncomfortable conditions at the start of the day and may cause the
determined, a coordinated concrete specification should be prepared, heating to be activated. Experience gained in the operation of buildings
giving structural and architectural requirements. It is best practice at the with FES over the last few years has helped refine and standardise the
early stages to consider having test panels made. Consideration should also general approach used. More information on ventilation control can be
be given to panel layouts. Joints between formwork panels are often visible, found in a companion guide entitled Utilisation of Thermal mass in Non-
so the architect should detail how the panels are to be laid out. Choose Residential Buildings, which is available from The Concrete Centre website.
reinforcement spacers that minimise visual impact while the falsework
design should minimise potential deflection which could be particularly
noticeable in plain walls. While high quality finishes are achieved in
concrete, a completely uniform finish as struck is unrealistic as some
variation and blemishes are part of concrete’s visual character. If a blemish-
free surface is required, consider a plain concrete finish, allow for blowholes
to be filled and the surface made good with a finishing coat.
The properties of these floors are summarised in Figure 5, including details A summary of the approximate cooling output that can be expected from
of the specific FES systems they are compatible with. A detailed overview the main FES/floor options is provided in Figure 6. It should be noted that
of these systems is provided in this section of the guide, starting with the in some buildings additional cooling of around 25 W/m2 may be provided
most basic, passive approach and ending with the more sophisticated by natural ventilation10 i.e. from openable windows, although this will
water-based systems. diminish during hot weather.
Flat slab
Exposed hollowcore slab with cores supplied by
mechanical ventilation plus water cooling
Construction: In-situ
Span: 5m to 12m, but most economic
up to 9m. Can be 6m to 13m with
post-tensioning. Exposed profiled slab with embedded cooling/
heating pipework
Compatible FES systems: All systems
except TermoDeck.
Comments: Quick, versatile and easy
to construct. Exposed flat slab with embedded cooling/
heating pipework
System 1:
Construction: maintain comfortable conditions in buildings with good solar shading and
Works with all slab types i.e. in-situ, precast and composite. relatively low internal heat gains.
Flat slabs provide the simplest and most cost-effective floor solution and
Description:
are economical for spans up to about 9m, or slightly more with post-
Flat or profiled slab cooled at night by natural ventilation from perimeter tensioning. Profiled slabs offer an alternative e.g. with a coffered, troughed
windows and assisted in some cases by an atrium with high level openings or wave-form soffit, which reduces the weight and helps optimise the span
providing stack ventilation. that can be achieved. These can be either precast or cast in situ with the
option of post-tensioning (see PowerGen case study on page 13).
Maximum slab cooling output (approximate):
15-20 W/m2 (flat slab) Another benefit of profiled slabs is the increased surface area of the soffit,
20-25 W/m2 (profiled slab) which enhances the convective heat flow with the space below, enabling
it to be doubled in some instances. However, radiant heat flow to and
Key benefits: from the soffit is largely unaffected by the extra surface area, so the overall
increase in cooling output is limited to around 25% or 5 W/m2 compared to
¢¢ Highly energy efficient if building is controlled well.
a flat slab. Other benefits of a profiled slab can include enhanced daylight
¢¢ Relatively simple to design and operate. penetration and acoustic control, along with generally pleasing aesthetic
¢¢ Little to no maintenance. qualities.
¢¢ Works with all concrete slab types.
¢¢ Applicable to new build and existing concrete buildings where the slab
can be exposed.
¢¢ Cooling output can be increased if required e.g. with the addition of
chilled beams or by embedding dormant pipework that can be used in
the future if required.
Key considerations:
¢¢ Use is limited to spaces with relatively low heat gains and occupant
density.
¢¢ Cooling performance is more weather dependent than other FES
options.
¢¢ External noise, pollution and/or security issues may preclude the use of
natural ventilation.
¢¢ Good occupant understanding and control needed to optimise year-
round performance.
Case studies:
¢¢ Headquarters of the Cambridge Federation of Women’s Institutes
(see opposite).
The most basic form of FES system uses an exposed concrete soffit with
night cooling via openable windows, to regulate slab temperature during
the day. Whilst the cooling output is modest, it is generally sufficient to
CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING 11
Photo: courtesy of Timothy Soar Louvre grilles in the back wall enable cross ventilation.
12 CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING
System 2:
Key considerations:
¢¢ Space requirements for air handling plant.
¢¢ Higher capital and operating costs than a naturally ventilated building
(energy and maintenance).
¢¢ Mixed-mode ventilation has the potential to achieve greater control
and better overall performance than provided by natural ventilation
alone, but must be appropriately designed, commissioned and
controlled13.
CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING 13
PowerGen Headquarters
Location: Coventry plaster to form the coffers. This was invaluable for confirming and
tuning the design of the coffer profile and light fittings, and for
Year: 1994
testing the acoustic performance and artificial lighting levels.
Client: PowerGen
When Laing Midlands were appointed as design and build
Architect: Bennetts Associates contractors, they adopted the approved scheme and worked closely
Structural engineer: Curtins Consulting Engineers with the design team. The on-site mock-ups played an important
role in incorporating key refinements such as the prefabrication
M&E engineer: Ernest Griffiths & Son of slab reinforcement into the final design solution. The choice of
FES system: Exposed, coffered slabs and mixed-mode ventilation. natural ventilation required the service engineers Ernest Griffiths &
Son to consider all aspects of the building design. The arrangement
In many respects the 13,000m2 PowerGen Headquarters, completed of relatively narrow open plan office areas on either side of the
in 1994, represents a landmark in high thermal mass, passive office three storey atrium provided the ideal layout for good natural
design and has provided a successful template for many subsequent ventilation. The building management system controls the top row
buildings. The design offers a good balance between daylighting, of windows, which are opened at night to allow cool air to flow over
natural ventilation, thermal mass and office layout which has proved the coffered concrete soffit. Computer simulations by environmental-
effective in providing a comfortable, low-energy environment. modelling specialist EDSL were used to accurately model the office
environment and predict peak internal temperatures, taking into
The layout consists of two parallel floor plates separated by a central consideration external effects, internal heat loads and the passive
atrium and lies on an east-west axis, providing good daylighting and cooling effects of the exposed concrete. The modelling also helped
air-flow. The structural frame is made from reinforced concrete with to develop the design strategy and establish the right mix of
exposed, in-situ coffered floors which are central to the building’s use thermal mass and natural ventilation. It also showed that night time
of thermal mass to provide a stable internal temperature. This proved ventilation was able to exploit the long-term thermal dynamics of the
to be very effective during the summer of 1995, one of the hottest on floor. The latter were provided by the careful use of exposed concrete
record, during which the building performed very well. The recorded with sufficient thickness to absorb heat gains over many days.
internal temperatures closely matched predictions from thermal
modelling undertaken at the design stage. Internal heat gains are minimised by placing areas that require
airconditioning, such as the computer suite and kitchens, at the east
Detailed analysis of PowerGen’s overall design intent established and west ends of the building. The larger, heat-generating office
that the office space requirements would be best met by a series of equipment, such as photocopiers, is grouped into segregated rooms,
narrow floor plates. This would allow connection across the office out of the open-plan space. Staff have considerable control of their
space and encourage personal communication between occupants. environment as the lower windows may be opened manually during
The size of the floor plates also needed to accommodate a variety of the day.
departmental offices and allow for future flexibility. Within the 10.8m
x 7.2m structural grid are three coffers, each 2.4m wide, which span
from atrium to external window. The coffers’ elliptical cross-section
is designed to improve the acoustic performance of the office space
by focusing unwanted noise onto the acoustically absorbent wings
of the interior lighting rafts suspended beneath each coffer. The
lighting rafts partially up-light the coffers to enhance their sculptural
form. They also incorporate smoke detectors and the PA system. In
long section, the coffers taper towards their ends to increase the
penetration of natural light into the office space from the external
windows and the atrium.
System 3:
can lower the air temperature by several degrees under average conditions
(evaporative cooling is also applicable to other systems with mechanical
ventilation detailed in this guide). The highest cooling performance
is achieved by using the TermoDeck switch-flow system. This enables
the temperature to be adjusted in individual rooms and can be used
in conjunction with mechanical or evaporative cooling. The system is
regulated by a switch unit incorporating a changeover damper to re-route
the supply air; when a room needs extra cooling, the air-supply route
through the slabs is changed directly to the core that contains the ceiling
diffuser, rather than the normal route through all three cores. The shorter
distance helps to prevent the supply air taking heat from the slab.
Innovate Green Office: The concrete mix incorporates fly ash as a cement replacement to
reduce embodied CO2, and Lytag, which is a lightweight aggregate
speculative office also made from fly ash. The external concrete walls provide an
airtight, weatherproof envelope in a single component and have
been designed to ensure solar gains from window openings are
Location: Leeds minimised. The walls achieve a very good U-value of 0.15 W/m2K
and are externally insulated to allow the concrete to be exposed
Year: 2007
internally for its thermal mass.
Client: Innovate Property
With the high level of insulation and airtightness achieved, heat
Architect: Rio Architects loss is reduced to a point where internal gains from people and
computers etc. are almost sufficient to maintain comfortable
Structural engineer: Scott Wilson
conditions from autumn to spring. The mechanical ventilation
M&E engineer: King Shaw Associates system recovers these gains, which are stored in the floor slabs for
beneficial re-use. Summer cooling is provided by a combination
FES system: Exposed hollowcore slabs and mechanical ventilation
of passive night-cooling and active cooling from the chiller, using
(TermoDeck™).
the TermoDeck system as a thermal store in a strategy similar to ice
The Innovate Green Office, completed in 2007, is a speculative storage i.e. to attenuate the peak cooling load and cut the size of the
development that achieved an impressive BREEAM rating of 87.55%; cooling plant.
the highest score ever awarded. Designed for Innovate Property by
The office achieved an average daylight factor of 4.5% so artificial
Rio Architects and King Shaw Associates, at first glance the office
lighting is only required for about 20% of the working year. External
does not look particularly ‘green’. There are no wind turbines or
vertical shades and internal blinds control excess gains and glare.
solar panels, yet the building emits 80% less CO2 than a typical air-
Other sustainable elements of the scheme include a vacuum
conditioned office, producing around 22kg of CO2 per m2 per year.
drainage system that utilises harvested rainwater for flushing the
This equates to a saving of roughly 350 tonnes of CO2 every year. The
toilets. This virtually eliminates the need for treated mains water to
approach developed by the project team achieves these savings by
convey sewage. The overall volume of waste discharged from the
fully applying the principals of fabric energy efficiency, rather than
building is reduced by 75%. Permeable paving and a natural wetland
relying on the addition of renewable systems. An engineering led
area prevents storm water flooding.
exercise produced an environmentally and commercially sustainable
plan, with the sustainability credentials of each element being The success of this speculative office development can be attributed
considered in conjunction with the client’s need for flexible and to the integrated approach given to fabric energy efficiency and
economically viable office space. structural requirements, which have been met using readily available
construction materials and technologies.
Yorkshire Forward, the regional development agency, worked with
Innovate Property to fund a proportion of the cost of prototyping
sustainable construction methods. The building services are
designed to produce minimal emissions helped by low energy
lighting, heating and cooling. Electricity is provided by a 30kW
base load combined heat and power (CHP) system with a matched
absorption chiller taking advantage of the waste heat in the summer.
System 4:
The aluminium ducts are cast into the slab to form a series of parallel U
shape runs, each of which is between 7-10m in length (see front cover
image). The ducts are linked at one end to a mechanical ventilation system,
Construction: whilst the other end feeds a supply diffuser that is typically located on the
soffit, but can be on a perimeter bulk head. If located in the floor it can
Applicable to in-situ and composite flat slabs.
provide displacement ventilation. The ductwork is made by an extrusion
process and is available in a diameter of either 60mm or 80mm, both
Description:
incorporate a number of corrugated internal fins, effectively tripling the
An in-situ or composite lattice girder slab, incorporating proprietary internal surface area. This enhances the heat transfer rate between air and
aluminium ventilation ducts16 (known as ConcretCool). The fresh air supply concrete, achieving an efficiency of up to 90%18. It also results in a pressure
is channelled through the ducts in a similar manner as the TermoDeck drop of around 7 Pa/m or 50-70 Pa for a typical duct run. However, the
system (see page 14), with cooling/heating provided by a combination of overall fan pressure for an installed system is not unduly high.
the ventilation supply and the radiant output of the soffit.
Plastic spacers are used to ensure the correct position of the ducts between
Maximum slab cooling output (approximate): the upper and lower reinforcement and this prevents the ducts floating up
65 W/m2 when concrete is poured. However, a small amount of upwards movement is
encouraged as this lifts the plastic spacers clear of the formwork, preventing
Key benefits: the ends from remaining visible when the formwork is struck. To stop
¢¢ High cooling output. the ingress of water/wet concrete, the ductwork elbows and other joints
incorporate a watertight seal. The addition of ductwork into the slab does not
¢¢ Provides radiant and convective cooling.
affect the structural performance as it is located in the neutral zone i.e. in the
¢¢ Widely used in mainland Europe.
central area where the slab experiences least tension/compression.
¢¢ Flexible system that can be configured to meet a range of
design requirements. The basic operating principle is very similar to that of the TermoDeck
system (see page 14); on summer nights the air handling plant channels
¢¢ Provides an alternative to water as a means of actively cooling
cool external air through the embedded aluminium ducts, removing heat
concrete slabs.
from the concrete ready for the following day, when the heat flow naturally
¢¢ C
orrugated fins inside the ducts (see image below) increase heat
reverses and the floor cools the fresh air supply, whilst the soffit provides
transfer between the air and the slab.
radiant cooling. During the heating season, the floor warms the air supply
to almost the same temperature as the soffit i.e. around 21°C, which can be
Key considerations:
achieved with minimal or no supplementary heating for much of the season.
¢¢ Soffit located supply diffusers cannot be easily reconfigured to
reflect changes to internal layout.
¢¢ Performance is partially dependent on ambient conditions.
¢¢ The internal fins enhance heat transfer, but also have modest impact on
fan power.
Case studies:
¢¢ 4 West Building, University of Bath (see opposite).
4 West Building series of circular aluminium ducts embedded in the slab to create
U shape runs of up to 10m in overall length. Each duct is linked at
University of Bath one end to the mechanical ventilation system, whilst the other end
feeds a supply diffuser typically located on the soffit. The ducting is
available in diameters of 60mm and 80mm, with the latter used in
Location: Bath the 4 West Building. It is made using an extrusion process, enabling
corrugated internal fines to be formed, effectively tripling the internal
Year: 2010
surface area for maximum heat transfer.
Client: University of Bath
On summer days, the building’s fresh air supply is cooled by the floor
Architect: Stride Treglown Tektus slabs as it passes through the ducts prior to entering the occupied
space. At night, the heat flow reverses, and the cool fresh air supply
Structural engineer: Ramboll
removes the accumulated heat from the slab, so the cycle can be
M&E engineer: Roger Preston & Partners repeated the following day. During the heating season, the floor
warms the air supply to almost the same temperature as the soffit.
Main contractor: Cowlin Construction
Further heating is provided by TRV controlled radiators. Windows can
FES system: Exposed, in-situ slabs incorporating the be opened to supplement the mechanical ventilation and enhance
Concretcool™ system. the level of control occupants have over the internal environment.
The 4 West Building at the University of Bath accommodates Whilst the Concretcool system has been widely used in mainland
general teaching areas, student services and office space. It was Europe, the 4 West project is the first application of this technology
completed on time and within budget in April 2010 and achieved a in the UK. Cowlin Construction, the main contractor, worked closely
BREEAM rating of ‘Excellent’. Built over six floors, the concrete frame with LTi Advanced System Technology who are the UK distributor
construction has in-situ concrete floors incorporating the Kiefer for this system. Two months before work started on the concrete
Concretcool system, which uses mechanical ventilation to regulate frame, LTi gave a presentation to the construction team so they could
the temperature of the exposed soffits. understand the system and develop a plan to ensure it was fully
integrated into the works. The aluminium ducts were pre-cut at the
Prior to this systems development there were only two methods for German factory, so all the components arrived ready for installation.
using mechanical ventilation to directly cool the slab. Firstly, by using 31 days were allowed for the work, but ease of installation enabled
an underfloor ventilation supply, which typically offers a modest this to be reduced to 15 days. The project manager for Cowlin
increase in cooling output, or secondly by using the TermoDeck Construction commented that any initial uncertainty about working
system (see page 14) which performs well, but is limited to precast with the new product was soon dispelled as it proved to be very
hollowcore flooring. The German Kiefer system provides a third robust and user-friendly.
option and can be used with in-situ concrete floors. It comprises a
System 5:
Maximum slab cooling output (approximate): Not withstanding any limitations on cooling output imposed by the system
65 W/m2 (flat slab) supplying the chilled water, the main restriction on performance is the risk
80 W/m2 (profiled slab)19 of condensation forming on the soffit if the surface temperature is allowed
to drop too low. The point at which this occurs is governed largely by the
Key benefits: relative humidity of the air in the room, and the lower limit for the surface
temperature is generally about 19-20°C, although it may be slightly lower
¢¢ High cooling output.
if mechanical ventilation is used with the ability to regulate humidity. In
¢¢ Ability to continually regulate the soffit temperature. summer, the flow temperature to the slab is typically between 14-20°C,
¢¢ Unobtrusive and silent. increasing to around 25-40°C during the heating season.
¢¢ Can be integrated with virtually any slab design.
Although water cooling may be the primary method for regulating
¢¢ Modest flow temperature permits use of energy efficient sources of temperature in summer, night time ventilation can also be used to remove
heating and cooling. accumulated heat from the slab, with the option of supplementary water
cooling used as necessary to achieve the required soffit temperature at the
Key considerations:
start of the next day. The CAFOD Headquarters combines both techniques
¢¢ Void formers can be incorporated into slab to optimise structural to optimise overall performance and energy efficiency.
efficiency i.e. weight/span.
¢¢ Good on site practice needed to ensure accidental damage to pipes The basic design sequence23 of a bespoke water-based system is as follows:
from drilling etc. is avoided. The in-situ option is potentially more ¢¢ Determine the zoning requirements of the building and associated
vulnerable to general on site damage before the concrete is placed. heating and cooling loads.
¢¢ Define the available areas for the coils, taking into account any
Case Studies: structural constraints.
¢¢ CAFOD Headquarters, London (see opposite). ¢¢ Calculate the cooling circuit requirements to match the zoning and
¢¢ IFDS House Barclays Bank/Basilica, Basildon. active soffit area.
¢¢ Incorporate the coil layout into the construction plans.
¢¢ Design the interconnecting pipework between the coils and the chilling
and heating plant.
CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING 19
CAFOD Headquarters Concrete forms an important part of the overall design strategy,
and the complex geometry on each floor resulted in the use of
(Romero House) an in-situ concrete slab, which was formed using simple plywood
shuttering. The concrete mix incorporates cement replacement in
the form of ground granulated blast furnace slag (GGBS), helping
Location: Southwark, London lower embodied CO2. With the exception of the stairwell, the
exposed concrete is painted white to improve reflectivity and help
Year: 2010
increase the daylighting toward the centre of the floor plan. The
Client: Catholic Agency for Overseas Development (CAFOD) exposed stair wall has a rough, needle-gunned finish providing a
powerful visual contrast to the painted concrete and galvanised
Architect: Black Architecture steel stair. The exposed concrete soffit on each floor incorporates
Structural engineer: WSP the Velta Thermally Active Building System (TABS) i.e. embedded
PEX cooling pipes, which off set some of the building’s heating and
M&E engineer: King Shaw Associates cooling load; the system is only designed to handle what can’t be
Main contractor: Volker Fitzpatrick achieved passively. The network of embedded pipes are linked to a
ground source heating and cooling system incorporating five closed
FES system: Exposed, in-situ slabs with embedded water cooling loop boreholes and a heat pump. Each borehole is 125m deep and
pipes and mixed-mode ventilation. produces water at around 12°C. Some additional heating is provided
by trench heaters on each floor. Roof mounted PV panels generate
CAFOD’s £8.6m Headquarters is situated on a former car park
around 3,500 kWh per year, whilst hot water is provided by a solar hot
adjoining St George’s Cathedral in Southwark. The five storey 3,000m2
water system.
building reflects the charity’s core values through its restrained
design and low environmental impact. The building makes use of A mixed-mode ventilation strategy allows occupants to open
a range of passive and low energy systems, including rainwater high-level windows (using winders) for natural ventilation during
harvesting, stack ventilation and a thermal mass system that the summer, with mechanical underfloor ventilation taking over
combines passive and active features. Overall, the office achieved a during periods of particularity high or low external temperatures
BREEAM rating of ‘Excellent’. when windows are best kept shut. Exhaust air is drawn passively
across the soffit by the stack effect created by warm air rising
Romero House is composed of three distinct elements. The triangular
through the atrium and exiting at roof level. Monitoring during
open plan office floors are separated from the ancillary spaces by
the summer of 2010 showed that the active thermal mass and
an atrium circulation spine. This arrangement encourages people
ventilation strategy achieved a very stable internal temperature that
to leave their floor to use the breakout spaces, toilets and meeting
only varied by around 2-3 degrees across each day24 and typically
rooms. A half level stepped section gives occupants the option
stayed around 22-23°C. During the hottest period when the external
to use facilities on upper and lower floors and so increases the
temperature reached 32°C, internal conditions did not exceed 26°C.
opportunities for communication and social interaction. Overall, the
This impressive performance should be further enhanced by minor
design helps promote a sense of community within the organisation
adjustments to the internal layout carried out to improve air flow; on
while fulfilling CAFOD’s spatial needs.
one floor storage units were too high, preventing air from circulating
properly25.
System 6:
Construction: For a general overview of water-based systems see: Exposed soffit with
Hollowcore slabs are a precast option only. An in-situ concrete topping embedded cooling/heating pipework on page 18.
of around 50mm is typically placed on the slab to enhance the overall
Hollowcore slabs are made from pre-tensioned, precast concrete with
structural performance.
continuous hollowcores to reduce self-weight and provide good structural
efficiency. Overall, the weight is around 32% less than for an equivalent
Description:
solid slab. In this water-based system, plastic pipework (PEX) is cast into
Precast, hollowcore slabs with PEX plastic pipework embedded near the the slab about 60mm above the soffit. Services such as cables and pipes
soffit for heating and cooling. In contrast to the TermoDeck system, the for sprinklers etc. can be routed through the cores. Alternatively, cables can
cores are not active i.e. do not form part of the ventilation supply. However, be placed in the in-situ concrete topping. The joint between slabs is visible
the two systems can be combined, increasing the overall cooling output, from below and can be plastered over or partially obscured by the lighting
see Figure 6 on page 9. raft, however it is not particularly conspicuous and is typically ignored.
Maximum slab cooling output (approximate): Hollowcore slabs are available with top strand reinforcing, which removes
65 W/m2 any camber that might otherwise be present ensuring a flat soffit.
Key benefits: Along with other water-based options in this guide, the cooling/heating
output is chiefly radiant as ventilation is handled separately. However,
¢¢ High cooling output.
since this system option uses hollowcore slabs, it offers the opportunity of
¢¢ Ability to continually regulate the soffit temperature. utilising the otherwise dormant cores to channel mechanical ventilation
¢¢ Provides the benefits of a precast solution. into the space and use some of the thermal mass to regulate the air
¢¢ Relatively low cost option. temperature. This provides greater convective cooling, which may increase
the overall cooling output to approximately 90 W/m2 26. This system is
¢¢ Economic across a wide range of spans of up to 15m.
commercially available by specifying a combination of Systems 3 and 5 in
¢¢ Modest flow temperature permits use of energy efficient sources this guide.
of heating and cooling.
¢¢ Soffit finish suitable for painting on site if required.
¢¢ Can be combined with the TermoDeck system to increase the
cooling capacity.
Key considerations:
¢¢ Soffit finish may be slightly more utilitarian than some of the
alternative floor options.
¢¢ Units typically limited to a maximum width of around 1200mm.
¢¢ Good on site practice needed to ensure accidental damage to
pipes is avoided.
¢¢ System limited to flat slabs.
Case studies:
¢¢ Vanguard House, Daresbury Science and Innovation Campus,
Warrington (see opposite).
CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING 21
Vanguard House The building uses a combination of passive design and geo-thermal
technology to provide heating and cooling. During the summer
months water extracted from a 120m borehole supplies the precast
Location: Daresbury Science & Innovation Campus, Cheshire hollowcore floor slabs with plastic pipework embedded close to
the soffit. These were manufactured by Creagh Concrete, under the
Year: 2011
product name Climaspan. Each precast unit spans up to 10m, and
Client: North West Development Agency is 1.2m wide x 0.3m deep. The cooling/heating pipework is located
at a depth of 60mm from the soffit and, to ensure it could not be
Architect: Fletcher Architects
accidentally damaged during construction, site operatives were issued
Structural engineer: Pick Everard with shanked drill bits with a limited drilling depth. The units make
use of top strand reinforcing which virtually eliminates the camber
M&E engineer: Atkins / Giffords
that can sometimes be visible with exposed hollowcore floors.
Main contractor: Cowlin Construction
The water cooling system, often referred to as a ‘Thermally Active
FES system: Exposed, hollowcore slabs with embedded cooling/ Building System’ or TABS, was designed by Velta and can provide up
heating pipework (e.g. Climaspan™). to 65 W/m2 of cooling. At Vanguard House it is used in conjunction
with night cooling to optimise summertime performance. During
Vanguard House provides three-storeys of office and laboratory the heating season, the temperature of the ground water is boosted
space, covering 3,600m². The client, North West Development using a heat pump before being supplied to the floor units. Tenants
Agency wanted a low carbon, BREEAM ‘Excellent’ facility (which have individual control of the system to regulate heating and cooling
was achieved) for its latest phase of development at the Daresbury in their space.
Science & Innovation Campus; a UK centre of excellence in
accelerometer research.
System 7:
The precast units are typically around 1.5-2.4m wide and include most, if
not all, of the bottom reinforcement. The top reinforcement is fixed on site
prior to placing the in-situ concrete topping. Void formers can be used to
reduce weight and increase the span up to a maximum of around 12m.
The surface finish of the soffit is typically very good, and the concrete
mix design can be tailored to achieve a specific visual appearance as
an alternative to painting. For example, at the Manchester Metropolitan
University Business School the concrete mix used a combination of white
Construction: cement and ordinary Portland cement.
Composite i.e. precast soffit with in-situ concrete topping. Void formers can
The PEX plastic pipes are located on top of the reinforcement, making
be used to optimise the structural efficiency and increase the span.
the reinforcement work more efficiently and provide some additional
Description: protection against accidental drilling of the pipework. During the
manufacturing process, the pipework is pressure tested with air before the
Factory produced, high quality precast soffit that acts as permanent
concrete is placed to ensure there are no leaks. Once installed on site, it is
formwork to an in-situ concrete topping. PEX plastic pipework for cooling/
kept pressurised with water so its integrity can be monitored during the
heating is embedded in the precast soffit.
construction process and enable any accidental damage to be more easily
found and rectified.
Maximum slab cooling output (approximate):
65 W/m2 (flat slab)
Key benefits:
¢¢ High cooling output.
¢¢ Ability to continually regulate the soffit temperature.
¢¢ Combines the benefits of a high quality precast finish with an in-situ
concrete slab.
¢¢ Soffit can be left unpainted if preferred.
¢¢ Quick to construct and provides a safe working platform that requires
little or no propping.
¢¢ Available in a broad range of widths.
¢¢ Modest flow temperature permits use of energy efficient sources of
heating and cooling.
Key considerations:
¢¢ Void formers can be incorporated to optimise weight and
structural efficiency.
¢¢ Good on site practice needed to ensure accidental damage to pipes
from drilling etc. is avoided.
¢¢ Early design consideration needed so holes for services can be
allowed for.
¢¢ System limited to flat slabs.
Case studies:
¢¢ Manchester Metropolitan University Business School (see opposite).
Photo: courtesy of Hanson UK
CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING 23
Manchester the contractor Sir Robert McAlpine enabled them to work with the
project team and embed the water pipes.
Metropolitan University The contractor hoped to install a fully precast system with embedded
27 water pipes, but following the tender process Hanson’s Coolslab
Business School system was selected as the best option. Coolslab is a development
of Hanson’s Omnicore product, a precast soffit panel which acts as
permanent formwork, to an in-situ concrete topping containing
Location: Manchester
polystyrene void formers. The pipework is cast into the panels at the
Year: 2011 precast factory and is pressure tested before being despatched. The
concrete specified for the panels uses a combination of 75% white
Client: Manchester Metropolitan University
cement and 25% ordinary Portland cement to create a light finish.
Architect: Feilden Clegg Bradley Studios Whilst this increased the cost of the mix, overall there was a saving as
it was cheaper than the alternative option of painting the soffit.
Structural engineer: WYG
M&E engineer: AECOM Hanson worked with cooling and heating systems developer
Velta, which has seen its products used widely across Europe. Velta
FES system: Exposed, lattice girder soffit slabs with embedded specialises in Thermo-Active Building Systems (TABS), which uses
water cooling pipes (Hanson Coolslab™). plastic water cooling/heating pipes embedded in the building
structure. For Manchester Metropolitan University, Sir Robert
McAlpine and Hanson developed a bespoke 1.5m wide slab with an
overall depth of 475mm spanning 12m. Once on site, the slabs were
craned into position and the joints propped underneath to achieve a
10mm positive camber, as engineers had calculated a maximum sag
of 20mm due to self weight.
System 8:
Case studies:
¢¢ Conquest House, London (see opposite).
¢¢ Barclaycard Headquarters, Northampton.
¢¢ Empress State Building, London.
CONCRETE FLOOR SOLUTIONS FOR PASSIVE AND ACTIVE COOLING 25
Conquest House:
refurbished office
Location: London The existing concrete soffits have been fully exposed in the office
areas and, where necessary, made good before being painted with
Year: 1950s, refurbished 2012
vinyl matt emulsion. Raised access floors are installed at 285mm
Client: GMS Estates above slab level, providing space for cable distribution and a
pressured supply plenum for the mechanical ventilation system.
Architect: Emrys Architects
This could have significantly impacted on the floor to ceiling height
Structural engineer: Elliot Wood Partnership if suspended ceilings were also installed, but the problem has been
avoided by using multi-service chilled beams suspended below soffit
M&E engineer: Arup
between existing downstand beams. This has ensured a minimum
FES system: Exposed concrete slab with multi-service chilled beams. distance of 2.7m is achieved on the lower ground floor, increasing
to an average of around 2.8m on the other floors. The mechanical
Conquest House is a 1950s office block in the heart of the plant has been located at roof level and in a lower ground floor
Bloomsbury conservation area. Like many buildings of its type, it plant room, both of which are linked by two vertical cores. The
had out-lived its useful life and required extensive redevelopment façade is effectively sealed during normal building operation, but
to provide high-quality, contemporary office space to live up to can be opened during any system failure or for smoke clearance. The
its prestigious location by Grays Inn Fields. This has now been internal temperature is controlled between 22°C and 26°C during
completed and the 22,500 sq ft, six floor building has been fully the summer and 20°C +/- 2°C in the winter. Heating is provided by
renovated and extended to a high standard of finish. A glazed atrium perimeter trench heaters and cooling by the chilled beams, with the
to the rear creates valuable breakout space and floods light into the concrete soffit providing a stabilising effect on internal conditions
building. A dramatic link bridge suspended within the atrium allows that helps aid summertime comfort.
access to the rear courtyard garden.
In 2011, the UK’s first PassivHaus accredited office building was completed at Watermead
Business Park, Leicester. Mechanical ventilation is used in combination with an air source heat
pump, which preheats the air in winter. It is also warmed by heat recovered from the extract air
via a high efficiency plate exchanger. The fresh air supply comes from an array of plastic pipes
buried 1.5m below the car park.
The brief for the East Park Design Centre called for state-of-the-art facilities that would allow a
broad spectrum of design disciplines to collaborate. The extensive natural ventilation control
and actuation system was designed to not only manage the CO2 levels, but also ensure the
temperature within the building is maintained within comfortable limits. This is achieved with
over 400 chain actuators which control the louvres and high level vertical vents.
The brief from Greenfields Community Housing was for a flexible head office that demonstrated
and embodied the organisation’s commitment to the environment. The layout is deigned to
achieve good cross ventilation via high level windows, with perforated panelling above the
internal glazed partitions to ensure air flow is not impeded. In periods of hot weather, night time
ventilation is used to cool the building fabric. Mechanical ventilation is also available via a raised
floor, allowing a mixed-mode approach that takes full advantage of natural ventilation during
the summer months.
160 Tooley Street is a mixed-use development of nearly 20,000m2, constructed for Great
Portland Estates. Thermal mass provided by the exposed concrete helps optimise the building’s
passive cooling performance and provides radiant cooling that complements the convective
cooling from the displacement ventilation system.
References
1. CoreNet Global, 2008
2. Hirigoyen, J. Sense and Sustainability, BSD, Issue 10, Nov, 2009.
3. Non-domestic Real Estate Climatic Change Model, Royal Institute of Chartered Surveyors, 2012.
4. The values plotted for the “typical” and “best practice” offices are based on those published in the 2012 edition of CIBSE Guide F (Energy efficiency in
Buildings) with a 25% +/- margin added. A value for passively cooled, high thermal mass offices is not published in guide F and the value used is
therefore based on an average of the following, with 25% +/- margin added:
1. Edinburgh Gate Building, Harlow
2. Innovate Building, Leeds
3. Elizabeth Fry Building, Norwich
4. Ionica Building, Cambridge
5. Canon Headquarters, Reigate
6. Inland Revenue building, Nottingham
7. BRE Building 16, Watford
8. National Trust HQ, Swindon
5. Chartered Institute of Building Services Engineers (CIBSE), Mixed Mode Ventilation, Applications Manual AM13, CIBSE, 2000
6. Incropera, F. DeWitt, D. Fundamentals of heat and mass transfer, 3rd edition, John Wiley & Sons, 1990.
7. De Saulles, T. Increased cooling potential with in-situ and precast flooring, CONCRETE, The Concrete Society, August 2012.
8. Eaton, K.J., Amato, A., Comparative Environmental Life Cycle Assessment of Modern Office Buildings, SCI Publication 182, Steel Construction Institute, 1998.
9. Kaethner, S. C., Burridge, J. A., Embodied CO2 of Structural Frames, The Structural Engineer, Vol 90, May 2012, pp 33-40.
10. BRE Digest 399, Natural Ventilation in Non-Domestic Buildings, BRE, 1994.
11. Avery. B., Building Study, Architects Journal, 21 July 2005.
12. Braham, D., Barnard, N., Jaunzens, D., Thermal Mass in Office Buildings: Design Criteria, BRE Digest 454, Part 2, BRE, 2001.
13. De Saulles, T. Utilisation of Thermal Mass in Non-Residential Buildings, CCIP-020, The Concrete Centre, 2006.
14. Arup Associates, Sustainable Buildings are Better Business: Can We Deliver Them Together?, British Council for Offices, 2002.
15. Kennett, S., Location location location?, Building Services Journal, June 2004.
16. The ductwork is made by Kiefer in Germany. The UK distributor is LTi Advanced System Technology (www.lti-ast.co.uk)
which also provides system design expertise for the Concretcool system.
17. Concrete Core Cooling with air – Concretcool. PDF document from Kiefer website (www.kieferlkima.de), 2011
18. Kiefer C., Concrete Core Cooling with Supply Air, Kiefer Special Print Edition of TAB 6/2002.
19. Buro Happold, Thermal Performance of the Thermocast System, Research Report 008939 for Tarmac plc, 2004.
20. For example, Velta and Warmafloor.
21. Arnold, D., Othen, P., What a Mass, HAC, 2002.
22. Arnold. D., Building Mass Cooling: Case Study of Alternative Slab Cooling Strategies, CIBSE National Conference, Harrogate, Oct 1999.
23. Based on guidance provided by LTI Advanced System Technology (www.lti-ast.co.uk)
24. Velta Sustainable Design and Construction Forum held at Lords Cricket Ground on the 24th March 2011.
25. FM World, Simply Cafod, December 2010 (www.fm-world.co.uk/features)
26. Based on an approximate calculation of the cooling performance undertaken by The Concrete Centre.
27. Case study is based on three sources: 1) An article by Declan Lynch in the New Civil Engineer (Cool concrete for clever brains, Nov 2010). 2)
Notes taken at the Velta Sustainable Design and Construction Forum on 24th March 2011. 3) Case study information from Velta’s website (www.velta-uk.com).
The Concrete Centre’s vision is to make The Concrete Centre provides design
concrete the material of choice. We provide guidance, seminars, courses, online
material, design and construction guidance. resources and industry research to the
Our aim is to enable all those involved in the design community.
design, use and performance of concrete to
realise the potential of the material. For more information and downloads, visit:
www.concretecentre.com/publications
The Concrete Centre is part of the www.concretecentre.com/events
Mineral Products Association, the www.concretecentre.com/cq
trade association for the aggregates,
asphalt, cement, concrete, dimension stone, Subscribe to our email updates:
lime, mortar and silica sand industries. www.concretecentre.com/register
www.mineralproducts.org
Follow us on Twitter:
@concretecentre
@thisisconcrete
www.concretecentre.com
The Concrete Centre, Gillingham House, 38-44 Gillingham Street, London SW1V 1HU
Ref. TCC/05/26
ISBN 978-1-908257-09-03
First published 2012 – updated January 2017
© MPA The Concrete Centre 2017
All advice or information from MPA The Concrete Centre is intended only for use in the UK by those who will evaluate
the significance and limitations of its contents and take responsibility for its use and application. No liability (including
that for negligence) for any loss resulting from such advice or information is accepted by the Mineral Products
Association or its subcontractors, suppliers or advisors. Readers should note that the publications from MPA The
Concrete Centre are subject to revision from time to time and should therefore ensure that they are in possession of
the latest version.
Printed onto 9Lives silk comprising 55% recycled fibre with 45% ECF virgin fibre.