Gatipora Road Estimate Redwana
Gatipora Road Estimate Redwana
Gatipora Road Estimate Redwana
for
Amount
S.No. Description (in
lacs)
1 Temporary/ Permanent
Restoration of Shopian Bijbehara Road in Km 16th
by Way of RCC Jacketing 9.55
Total = 9.55
Add 1.5% for Work Charge & Contingencies = 0.14
Grand Total = 9.69
Say 9.70 Lacs
S. Rate Amount
Item of work Qty. Unit
No.
1 Supplying, stacking and laying of naturally
occouring gravel close graded maximum 75mm
granular sub base course nallah including
sorting, spreading to template, watering and
consolidation to required gradient and chmaber
with 80-100KN road all inclusive leads, lifts,
loading, unloading carrying of materilas from
nearest source to site of work complete finished
work to be measured.
KM 3-
2 1000 3.70 7400.00
30 1000
Total 7400.00
Add 5% curves 370.00
Total 7770.00 Cum 1000.00 7770000
Grand Total = 7770000
Say 77.70 Lacs
Detailed Estimate for Providing and Laying of GSB Filling & G-I
For
S. No. Amount
Particulars Unit Qty. Rate
Superintending Engineer
PW(R&B) Circle Pul/Spn Chief Engineer
HQ Pulwama PW(R&B) Kashmir
Detailed Estimate for Providing and Laying of WBM Grade-III
for
S. No. Amount
Particulars Unit Qty. Rate
1 Providing, laying, watering and compacting
with quarry stone aggregate (53-22.40mm) and
screening of size 11.20mm to specified lines,
grades and cross sections including supplying
and spreading stone dust including carriage upto
site of work complete 75mm thick.
Superintending Engineer
Chief Engineer
PW(R&B) Circle Pul/Spn PW(R&B) Kashmir
HQ Pulwama
Typical Estimate for Construction of 1KM B-Wall(Kaccha/Paccha)
For
1 x100(1.09+0.6/2)x2=169Cum
Superintending Engineer
Chief Engineer
PW(R&B) Circle Pul/Spn PW(R&B) Kashmir
HQ Pulwama
Typical Estimate for Construction of 300 M Plain Cement Concrete Drain.
For
Bottom Slab=1x4.60x4.30x0.4=7.91Cum
Side Walls=2x4.60x0.45x2=8.28
Cum Deck
Slab=1x4.6x3.90x0.40=7.18 Cum
Haunch=4x4.60x(0.30x0.30/2)=0.828
Cum. Total=
24.2 Cum
Cum 24.20 9106.65 220380.93
5 Centering and shuttering including Sqm 4%of 9173
strutting,propping etc and removal of conc.
form work:-
6 PL and placing high strength deformed Kgs 247.25 82.69 20445
steel including cost of binding wire.
Quantity vide item no. 3=1.978Cum
@125kg/Cum
Superintending Engineer
Chief Engineer
PWD (R&B) Circle Pul/Spn PW(R&B) Kashmir
HQ Pulwama
Detailed Estimate of 2X3M Span RCC Culvert.
For
Construction of Road from Gattipora to Sanimarg via Zeerbuth including
construction of 2x30mtr. And 1x15mtr. Span bridge at Gattipora
S.No. Item of work Unit Qty. Rate Amount
inRs.
1 Trench excavation in hard soil lead upto
50Mtr and lift upto 1.5 mtrs
1x9.10x4.50x2.65=108.52 Cum Cum 108.52 375 40695
2 P/L Dry stone soling Duly Hand Packed
and consolidated with hand rammers
incl. all
carraiges.=1x9.10x4.30x0.15=5.87Cum
Bottom
Slab=1x9.10x4.30x0.4=15.65Cum
Side Walls=2x9.10x0.45x2=16.38 Cum
Deck Slab=1x9.10x3.90x0.40=14.2
Cum
Haunch=4x9.10x(0.30x0.30/2)=0.41Cum
. Total=
46.64 Cum
Cum 46.64 9106.65 424734.16
5 Centering and shuttering including Sqm 4%of 17695
strutting,propping etc and removal of conc.
form work:-
2x9.10x1.50x2.65 = 72.35Cum
Cum 72.50 1000.00 72500.00
Total = 619557
Superintending Engineer
Chief Engineer
PW(R&B) Circle Pul/Spn PW(R&B) Kashmir
HQ Pulwama
Detailed Estimate of 1x15M Span RCC Culvert.
For
Construction of Road from Gattipora to Sanimarg via Zeerbuth
including
construction of 2x30mtr. And 1x15mtr. Span bridge at Gattipora
S.No. Item of work Unit Qty. Rate Amount
inRs.
1 Trench excavation in hard soil lead upto
50Mtr and lift upto 1.5 mtrs
1x4.60x4.50x2.65=54.855 Cum Cum 54.8 375 20550
2 P/L Dry stone soling Duly Hand Packed
and consolidated with hand rammers incl.
all carraiges.=1x4.60x4.30x0.15=2.96
Cum
Cum 2.96 1000 2960
3 Cast in situ Conc.with nominal mix M-
7.50 grade with 40mm nominal size agg.
Bottom Slab=1x4.60x4.30x0.4=7.91Cum
Side Walls=2x4.60x0.45x2=8.28
Cum Deck
Slab=1x4.6x3.90x0.40=7.18 Cum
Haunch=4x4.60x(0.30x0.30/2)=0.828
Cum. Total=
24.2 Cum
Cum 24.20 9106.65 220380.93
5 Centering and shuttering including Sqm 4%of 9173
strutting,propping etc and removal of conc.
form work:-
6 PL and placing high strength deformed Kgs 247.25 82.69 20445
steel including cost of binding wire.
Quantity vide item no. 3=1.978Cum
@125kg/Cum
Superintending Engineer
Chief Engineer
PWD (R&B) Circle Pul/Spn PW(R&B) Kashmir
HQ Pulwama
Detailed Estimate For Providing & Laying RCC Pipes.
For
Superintending Engineer
Chief Engineer
PWD (R&B) Circle Pul/Spn PW(R&B) Kashmir
HQ Pulwama