Nothing Special   »   [go: up one dir, main page]

Project Profile On Electronic Fan Regulator & Light Dimmers

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

KVIC- PMEGP

PROJECT PROFILE ON ELECTRONIC FAN REGULATOR & LIGHT DIMMERS

Introduction :
Electronic Fan regulator is n eletronic device consisting of diacs, triacs, potentiometric resistances to provide step less
control of fan speed. This is an energy saving device and has advantage over the conventional type of fan regulators
having more energy losses. These regulators can also be used as a speed regulator for many other smll F.H.P.
motors used in mixer, light dimmers etc. with appropriate current readings.

1 Name of the Product : ELECTRONIC FAN REGULATOR & LIGHT DIMMERS

2 Project Cost :
a Capital Expenditure
Land : Own
Work shedsq.mtrs
in sq.ft RENTED 0 Rs.
Equipment : Rs. 30,000.00
10MHZ Oscilloscipe, Multimeters, Drilling Machines (1/4"), Coil
Winding machine (Manual), Hand Tools/Jigs/Fixtures, Offie
equipment & Furniture, Pre-operative expenses etc.

Total Capital Expenditure Rs. 30,000.00


b Working Capital Rs. 100,000.00
TOTAL PROJECT COST : Rs. 130,000.00

3 Estimated Annual Production Capacity: (Rs. in 000)


Sr.No. Particulars Capacity in tons Rate Total Value
1 ELECTRONIC FAN REGULATOR & 10000.00 609.20
LIGHT DIMMERS
TOTAL 10000.00 0.00 609.20

4 Raw Material : Rs. 300,000.00

5 Labels and Packing Material : Rs. 48,000.00

6 Wages (1-Skilled ) : Rs. 36,000.00

7 Salaries (1-Manager) Rs. : 72,000.00


PAGE ( 2 )

8 Administrative Expenses : Rs. 50,000.00

9 Overheads : Rs. 20,000.00

10 Miscellaneous Expenses : Rs. 66,000.00

11 Depreciation : Rs. 3,000.00

12 Insurance : Rs. 300.00

13 Interest (As per the PLR)


a. C.E.Loan : Rs. 3,900.00

b. W.C.Loan : Rs. 13,000.00

Total Interest Rs. 16,900.00

14 Working Capital Requirement :


Fixed Cost Rs. 192,200.00

Variable Cost Rs. 417,000.00

Requirement of WC per Cycle Rs. 101,533.00

15 Cost Analysis
Sr.No. Particulars Capacity Utilization(Rs in '000)
100% 60% 70% 80%
1 Fixed Cost 192.20 115.32 134.54 153.76
2 Variable Cost 417.00 250.20 291.90 333.60
3 Cost of Production 609.20 365.52 426.44 445.66
4 Projected Sales 800.00 480.00 560.00 640.00
5 Gross Surplus 190.80 114.48 133.56 152.64
6 Expected Net Surplus 188.00 111.00 131.00 150.00
Note : 1.All figures mentioned above are only indicative.
2.This is model project profile for guidence
3.Cost of Project, and its profitability will be changed depends on the area, availability
of raw Material, man power, power requierement and various other factors etc..