Exam 1-200 Q&A

Download as pdf or txt
Download as pdf or txt
You are on page 1of 161

You are working on a project to build a multi-story complex in

your city, and you are about to start project planning. As a


starting point for initial project planning, what is the first thing
you should do?

Review the project charter to understand the high-level information about the project.

Conduct a project kick-off meeting to inform and engage stakeholders and gain commitment.

Begin the process of identifying stakeholders so they can be engaged as necessary for
project planning.

Develop the project schedule to manage timely completion of the project

Explanation
The question states that project planning is about to begin which suggests that project initiation has been
completed. The project charter is created during the Develop Project Charter process as part of project
initiation. The project team uses the project charter as a starting point for initial project planning. The type
and amount of information in the project charter varies depending on the complexity of the project and
the information known at the time of its creation. At a minimum, the project charter should define the
high-level information about the project that will be elaborated in the various components of the project
management plan.

Question: 5 Correct

A project has a senior stakeholder whose input is important, and


who needs to be kept informed about the project’s status. Rather

EXAM 01/200 QA
than receive updates from the project manager, this stakeholder
prefers to contact a team member directly. The stakeholder has a
connection with this team members that is unrelated to the
project and thinks that this is a way to obtain information on the
project’s true status. What should the project manager do?

Ask the stakeholder how the additional information that they feel is missing from current
communications may be provided.

Keep the team member properly informed about project status so that the stakeholder
receives the same information from both sources.

Leave the connection in place, since the information coming via the team member is
unofficial and will not create problems.

Tell the team member not to accept calls from the stakeholder, because these calls have an
adverse effect on the team member’s members productivity.

Explanation
Not good practice that the stakeholder communicate with this team members that is unrelated to the
project because will not provided with the true status of the project.The Project manager should be
proactive and ask the stakeholder how the additional information that they feel is missing from current
communications may be provided.

Question: 6
Correct

You are in the process of estimating the number of work periods


needed to complete individual activities with estimated

EXAM 01/200 QA
resources. One of the documents you are using contains
information on categories of labor, material, and equipment
required to complete your project. This document is known as:

Resource breakdown structure ( RBS )

Resource Calendars

Organization breakdown structure (OBS)

RACI Chart

Explanation
Based on the scenario described, the project team is performing the Estimate Activity Durations process.
An input to this process is the resource breakdown structure (RBS) which is a hierarchical list of team
and physical resources related by category and resource type that is used for planning, managing, and
controlling project work. Each descending level represents an increasingly detailed description of the
resource until the information is small enough to be used in conjunction with the WBS to allow the work to
be planned, monitored, and controlled. [PMBOK 6th edition, Page 198]

Question: 7
Correct

Joseph is a project manager who is deep into project execution.


Currently, he is looking for information about the quality
management issues that have been escalated by the team, as well
as recommendations for process, project, and product
improvements. What should he do?

EXAM 01/200 QA
change control board (CCB).

Request the details about the new requirements, evaluate them with the project team, and
recommend whether to continue or close the project.

Evaluate the impact on the project, coordinate with the sponsor and close the project.

Evaluate and incorporate the changes to the project management plan to start executing
them.

Explanation
Keyword ( , important changes MUST be made to the requirements ) Any changes in project requirement
can impact the baseline will require formal change request to take the approval from CCB. SO the project
manager should Request that the stakeholders specify the new requirements and present them to the
change control board (CCB). other options not correct because the chnage request can not be
implemented without the approval by CCB. the other option ( close the project after evaluate the impact
on project not correct )

Question: 9
Correct

Based on the following diagram, what is the total duration of the


project?

EXAM 01/200 QA
EXAM 01/200 QA
17

15

22

21

Explanation
The critical path is Start-A-D-E-G-H-End, and the duration of the critical path with the data given is 17.

Question: 10
Correct

Rekha is a project manager on a large construction project.


Rekha had originally planned to use both of the company's tower
crane simultaneously for a project but has just learned that one
of them will be unavailable. Rekha adjusts the schedule so that
the components are created sequentially using the one remaining
tower crane. Unfortunately, this action affects the critical path
and delays the planned finish date of the project. Which of the
following techniques has been used by Rekha in this situation?

Resource leveling

Fast tracking

EXAM 01/200 QA
Reserve analysis

Critical path method

Explanation
Resource leveling is a resource optimization technique in which start and finish dates are adjusted based
on resource constraints with the goal of balancing the demand for the resources with the available
supply. Resource leveling can often cause the original critical path to change which is what happened in
the scenario described. Adjusting the schedule to accommodate the loss of one of the tower crane is an
example of resource leveling. [PMBOK 6th edition, Page 211]

Question: 11
Correct

You have been managing a construction project in a developing


country, and now you are closing the project. The project
completed on schedule and under budget. The general manager
of your company heard about the success of your project and
wants a summary overview of project performance so that he can
talk about your success at the next board meeting. What should
you provide to him?

Final report

lessons learned register

Lessons learned repository

EXAM 01/200 QA
Project Charter

Explanation
The scenario suggests the project has been closed. In other words, the Close Project or Phase process
is now complete. The final report is one of the outputs from this process. The final report includes
information such as a summary level description of the project, a summary of any risks and issues
encountered and how they were addressed, a summary of how the final product, service or result was
achieved, and more. Since the vice president wants a summary overview of project results, providing the
vice president with the final report will likely meet their needs and is, therefore, of the choices provided,
the best answer to the question asked. [PMBOK 6th edition, Page 127]

Question: 12
Correct

A project manager is in the process of identifying the likely


stakeholders on a project and their interests in the project. The
project manager has just compiled a list of potential
stakeholders' names. What should the project manager do next?

Conduct stakeholder analysis

Conduct kick-off meeting to inform and engage stakeholders and gain commitment

Develop the scope management plan

Develop the stakeholder engagement plan

Explanation
The question suggests that the project is still in the initiation stage, with the initial iteration of the Identify
Stakeholders process, and has yet to progress to project planning. At this point, the project manager has

EXAM 01/200 QA
only compiled a list of potential stakeholders' names. With only a list of individual and group names, the
next logical step is to perform stakeholder analysis. Stakeholder analysis, an example of the data
analysis technique which can be used during the Identify Stakeholder process, results in a list of
stakeholders and relevant information such as their positions in the organization, roles on the project,
expectations, attitudes, and their interest in information about the project. Therefore, of the available
choices, conducting stakeholder analysis is what the project manager should do next.

Question: 13
Correct

You are a project manager in an IT project. You and key


stakeholders start conducting a project benefit analysis. Because
of the solutions that have not been identified, an engineer from
another department has informed you that there are affected
systems. As a project manager, what should you do?

Document the issue in the issue log

Identify all stakeholders

Review the project benefit analysis to consider the additional impact

Update the risk register

Explanation
The issue log is a project document used to identify and monitor issues that occur in the project. The
issue log can be updated with any new issues found during the project and described in the scenario
because of the solutions that have not been identified causing the system are affected. Making this
choice the best answer to the question asked.

EXAM 01/200 QA
Question: 14
Correct

After contract sign-off , a project manager learns that the vendor


has a reputation of not delivering according to the contract. To
ensure the vendor’s compliance, what should the project
manager do?

Perform periodic inspection of the vendor’s work and progress.

Cancel the current contract and select another vendor

Conduct a make-or-buy analysis to verify vendor reliability

Insist on a firm fixed price contract (FFP) with the vendor

Explanation
To ensure the vendor’s compliance, the project manager should perform periodic inspection of the
vendor’s work and progress to take the corrective action as per the contract at the right time.

Question: 15
Correct

You are a project manager in an IT project. During the


deployment of a new system, an unexpected power outage
occurs. What should the project manager do?

EXAM 01/200 QA
Refer to the risk register and inform key stakeholders

Risk categorization

Risk probability and impact assessment

Perform a qualitative risk analysis

Explanation
As an unexpected power outage occurs, the project manager should first Refer to the risk register and
inform key stakeholders to handle this scenario. Risk categorization and Risk probability and impact
assessment are T&T in Perform a qualitative risk analysis process, therefore they can be excluded.

Question: 16
Correct

You have been appointed a project manager for a new project.


After several weeks, you discover that the accounting department
has declined all charges because the project was not approved.
What should the project manager have done to prevent this?

Obtained the project charter approval from the project sponsor

Planned the resources necessary to start the project

Verified that the business case was authorized by the project initiator

EXAM 01/200 QA
Obtained the fund needed to start the project

Explanation
The sponsor or initiator of the project is responsible to establish (approve and issue) the charter and can
take the help of the prospect project manager to develop it. the project manager should Obtain the
project charter approval from the project sponsor because the project charter is a document that formally
authorizes the existence of a project
and provides the project manager with the authority to apply
organizational resources to project activities. PMBOK 6th edition page, 75

Question: 17
Correct

The project manager is trying to get sign off for a series of


marketing materials. The work is rejected by the stakeholders
responsible for sign off because of incorrect use of marketing
standards. What should the project manager do before sending
materials to the stakeholders again?

Perform quality control checks before validating the scope

Validate the scope before performing quality control

Create a work breakdown structure before validating the scope

Validate scope before communicating the project status

Explanation
In the scenario, the work is being validated by the stakeholders, but there are quality concerns noted by
the incorrect use of standards. Ideally, the Control Quality process should be completed before the scope

EXAM 01/200 QA
You are a project manager in a construction project. What should
you do to ensure the successful delivery of the project?

Identify the project’s risks and necessary success criteria.

Meet with stakeholders to communicate the schedule budget, and cost impact in the event of
a project delay.

Establish a management reserve to handle the unknown risks when occurs

Conduct a team-building activity

Explanation
Identify the project’s risks and the necessary success criteria.

Question: 20
Correct

You are a project manager assigned to a new airport construction


project. You want to Create WBS but the project is new to your
company and there is no previous experience and documentation
as a reference. Which of the following tools will help the project
manager?

EXAM 01/200 QA
Explanation
Knowledge of customer requirements, organizational policies and industry standards and project metrics.
PMBOK 6th Page, 332

Question: 22
Correct

You are a project manager to construct a new building in a


typhoon prone area and may impact the schedule and quality. As
a project manager, what should you do?

Outsource the project and transfer the risk

Establish a contingency reserve

Perform Quantitative Risk Analysis, and plan risk response

Develop the risk management plan and establish a management reserve

Explanation
The best risk response strategy appropriate for this project, (( Outsource the project and transfer the risk
to complete this work and shifting ownership of a threat to a third party to manage the risk and to bear the
impact if the threat occurs.

Question: 23
Correct

During the control quality process, the quality team has

EXAM 01/200 QA
discovered a large number of defects on the deliverables. The
project sponsor told the project manager go proceed to validate
scope process for approval. As a project manager, What should
you do next?

Evaluate the impact of defects on the project and inform the sponsor

Validate Scope Process

Ignore the sponsor and direct team to complete the deliverables

Request training for the team members and rework

Explanation
The project manager should first Evaluate the impact of defects on the project and inform the sponsor.

Question: 24
Correct

What is the key purpose of the Monitoring and Controlling


process group?

Measure project performance in order to identify and quantify any variances and perform
approved corrective actions

Perform preventive actions so that no variances ever occur in the project lifecycle

EXAM 01/200 QA
Conduct daily status meetings

None of the above

Explanation
Measure project performance in order to identify and quantify any variances and perform approved
corrective actions. Preventive actions should be identified and implemented during this process group but
they will not ensure that variances won't take place throughout the project lifecycle. Only conducting daily
status meetings will not assist in monitoring and controlling the project. Refer to PMP Exam Outline in the
Monitoring and Controlling Process Group ( Task no. 1 )

Question: 25
Correct

Which of the following statements is correct regarding the kickoff


meeting?

Kickoff meeting is conducted not only to inform but also to engage and gain commitment
from stakeholders

Just to get the commitment

Just to inform

Just to inform and engage stakeholders

Explanation
the kickoff meeting is conducted to communicate the start of the project, the key milestones, and other
information to inform and engage stakeholders and gain their commitment. Refer to PMP Exam Outline in

EXAM 01/200 QA
To align project goals with business needs

To satisfy the customer

To satisfy project requirements

To satisfy the sponsor

Explanation
According to the examination content outline, following the change management plan ensures that
project goals remain aligned with business needs. Refer to PMP Exam Outline in the Monitoring and
Controlling Process Group ( Task no.2 )

Question: 28
Correct

You are a project manager managing a large software project.


Your project team sent confidential information to the
subcontractor by mistake. What could have prevented this
situation?

Reviewing the Communication management Plan

Reviewing the stakeholder engagement Plan

Reviewing the Scope management Plan

EXAM 01/200 QA
Review stakeholder register

Explanation
The communications management plan is a component of the project management plan that describes
how project
communications will be planned, structured, implemented, and monitored for effectiveness.
The plan contains the following information: Person responsible for authorizing the release of confidential
information; Stakeholder communication requirements; Escalation processes; Timeframe and frequency
for the distribution of required information and Person responsible for communicating the information.
[PMBOK 6th edition, Page 377]

Question: 29
Correct

You are managing a project with a budget of 9,000, and 1,500 has
been spent. However, you only completed $1000 worth of work.
Your schedule says that you should have completed 50% of the
work. What is the estimate at completion (EAC)?

US$13500 ( Based on performance data )

US$ 9000 ( Based on original project Budget )

US$ 9000 ( Based on performance data )

US$13500 ( Based on original project Budget )

Explanation
The most common formula for EAC is BAC/CPI. CPI=EV/AC =1000/1500= 0.66 So, EAC=9000/0.66

EXAM 01/200 QA
Person or groups who will receive the information, including information about their needs, requirements,
and expectations and Methods or technologies used to convey the information, such as memos, email,
press releases, or social media . [PMBOK 6th edition, Page 444, 377 ]

Question: 31
Correct

Jack is the project manager of a project that is halfway through


the execution. Because of the increased volatility of prices, one
of the vendors asks the project manager to make a price change
that will affect the project contract. As a project manager, what
should you do next?

Submit a change request and analyze the impact

Ask the CCB for approval

Implement the approved change

Analyze the impact and Update the Project management plan

Explanation
As a price change will affect the project contract, the project manager should Submit a change request
and analyze the impact then take approval from CCB then update affected baselines then Implement the
approved change.

Question: 32 Correct

EXAM 01/200 QA
You are managing a project to build a multi-story complex in your
city. During the project kick-off meeting, two project team
members had a disagreement around whether to include a
specific test within testing scenarios for the new product or not.
As the project manager, what should you do?

Postpone the discussion for a later time

Reject adding the new test

Add the suggested scenario

Ask each one of them to explain the logic behind his opinion

Explanation
If you were to “Add the suggested scenario” (answer option a.), or “Reject adding the new test“(answer
option b.) it will be a premature decision as you didn’t discuss the reasoning behind both opinions, and
since this is the project kick-off meeting and there’s no time pressure for resolving the conflict “Postpone
the discussion for later time“ (answer option a.) seems an appealing approach, if you were to “Ask each
one of them to explain the logic behind his opinion” ” (answer option d.) it won’t be the right time for such
discussion. The best course of action is to “Postpone the discussion for a later time” (option c.).

Question: 33 Correct

A project has been initiated that has several project stakeholders


from various departments. Some stakeholders are unavailable for
the facilitation meeting to discuss end-to-end processes. To

EXAM 01/200 QA
satisfy their own personal agenda, the project owner requests
that the meeting take place without all stakeholde’s present. What
should the project manager do?

Set up a facilitation meeting without all stakeholders to obtain initial requirements.

Discuss stakeholder availability with the sponsor.

Hold a separate meeting with those stakeholders who are unavailable.

Reschedule the meeting to accommodate all stakeholders.

Explanation
Set up a facilitation meeting without all stakeholders to obtain initial requirements.Then Hold a separate
meeting with those stakeholders who are unavailable. Option ( Reschedule the meeting to accommodate
all stakeholders. ) not correct because the project owner requests that the meeting take place without all
stakeholde’s present.

Question: 34
Correct

The project manager works in risk management and creating a


risk register. The risk register records details of all the risks
identified at the beginning and during the life of the project. What
tool or technique should the project manager use to generate a
list of all possible project risks?

EXAM 01/200 QA
Brainstorming

Monte Carlo

Tornado diagram

Probability and impact matrix

Explanation
Brainstorming is a data-gathering technique that can be used for identify risk process and The goal of
brainstorming is to obtain a comprehensive list of individual
project risks and sources of overall project
risk. PMBOK 6th edition page, 414

Question: 35
Correct

A multiphase project that has been executed with internal


resources has reached a phase gate. The key project
stakeholders want to determine if the phase has met its success
criteria, and whether or not the project should progress to the
next phase. In addition to the project management plan, which
documents will be required?

Business documents and project charter

Agreements including procurement contracts

EXAM 01/200 QA
Lessons learned register and lessons learned repository

Risk register and risk report

Explanation
The business documents and project charter are needed to determine whether or not the project should
progress to the next phase. The project charter will provide the project's success criteria. The business
documents include the business case and benefits management plan. The business case documents the
business need and the cost-benefit analysis that justifies the project. The benefits management plan is
used to measure whether the benefits of the project are being achieved as planned. [PMBOK 6th edition,
Page 21]

Question: 36
Correct

Your project has been progressing well so far. Due to an


expected increase in the cost of raw materials which was not
factored as project risk, you are in need of some management
reserve. The management reserve is available but the sponsor
asks you to do something to obtain it. What is the sponsor asking
you to do?

To follow the change approval process to move the required management reserve funds to
the cost baseline

There is no need for a management reserve as the risk was not factored, and therefore it
may be funded from the contingency reserve

To put in a request to the sponsor for the management reserve

EXAM 01/200 QA
Question: 38
Correct

You have identified a risk that will negatively affect your security
project. You and your team have decided to use an older
encryption technology because of the high risk associated with
the new technology. What type of risk strategy are you using?

Avoidance

Transfer

Exploitation

Mitigation

Explanation
The Project team avoid new technology because of the high risk associated.

Question: 39
Correct

A project manager analyzed the project’s communication


requirements and decided that 10 out of the 30 stakeholders in
the project would only need voicemail updates of certain
information. This type of communication method is called:

EXAM 01/200 QA
Push communication

Pull communication

Interactive communication

On-demand communication

Explanation
Voicemail is an example of Push communication. [PMBOK 6th edition, Page 374]

Question: 40
Correct

A project management team is developing a project management


information system (PMIS) as a collaboration tool for internal and
external stakeholders. A dashboard is update monthly with
information on the project’s performance.
What type of
communication method does this describe?

Pull Communication

Interactive Communication

Corporate intranet

EXAM 01/200 QA
Project progress reporting.

Explanation
Keyword (dashboard) is update monthly with information on the project’s performance to help the internal
and external stakeholders to get the information any time by using the PMIS. its an example of pull
communication. Very important question for real exam. [PMBOK 6th edition, Page 374]

Question: 41
Correct

You are a project manager in a construction project. During a


review, the civil engineer informs you that the concrete
production rate has changed over the last three months. What
analysis should be conducted?

Trend analysis

Control chart

Earned value (EV).

Scatter diagram

Explanation
Trend analysis examines project performance over time to determine whether performance is improving
or deteriorating. Graphical analysis techniques are valuable for understanding performance to date and
for comparing to future performance goals in the form of completion dates. [PMBOK 6th edition, Page
227]

EXAM 01/200 QA
Question: 42
Correct

Six Sigma methodology incorporates many powerful tools to use


in continuous improvement projects and programs. Six Sigma are
tools in which of the following processes?

Manage Quality

Plan Scope management

Close project or phase

Define Scope

Explanation
Very important for PMP Real Exam. Six Sigma is the most common quality improvement tools used to
analyze and evaluate opportunities for improvement[PMBOK 6th edition, Page 296]

Question: 43
Correct

A project manager is asked to contribute to a document to


describe what is intended to be achieved with a project once it is
successfully finished, and how this will be measured. What could
be the name of that document?

EXAM 01/200 QA
Benefits management plan

Project management plan

Change management plan

Statement of work

Explanation
The project benefits management plan is the document that describes how and when the benefits of the
project
will be delivered, and describes the mechanisms that should be in place to measure those
benefits. A project benefit
is defined as an outcome of actions, behaviors, products, services, or results
that provide value to the sponsoring
organization as well as to the project’s intended beneficiaries.
[PMBOK 6th edition, Page 33]

Question: 44
Correct

You are managing a railway track construction project. The key


stakeholders and the Project sponsor approved the project
management plan. What is the next step?

Conduct the project kick-off meeting

Identify Stakeholders

Direct and Manage Project Work

EXAM 01/200 QA
Update Business Case

Explanation
ِAfter approval the project management plan, the next step is Conduct kick-off meeting, communicating
the start of the project, key milestones, and other relevant information in order to inform and engage
stakeholders and gain commitment before the project execution. Refer to PMP EXAM CONTENT
OUTLINE- PLANNING PHASE - TASK NO 11 & 12

Question: 45
Correct

At the midway of the project, the sole provider has delayed the
delivery of the materials for the project that lead to an effect on
the Project schedule. Keeping the supplier with the same delivery
rate will provide further delays, and replacing the supplier will
lead to cost overrun. What will you do next?

Work with the supplier to solve the problem

Get another supplier

Cancel the contract

Escalate the Problem to Procurement Department

Explanation
Tricky question and very important for the PMP exam. Keyword (sole provider) so the project manager
should Work with the supplier to solve the problem.

EXAM 01/200 QA
Question: 46
Correct

During the implementation phase, the project sponsor left the


project and a new sponsor has been assigned. What should you
do next?

Update the stakeholder register

Update RACI Chart

Update the Project Management Plan

Update Stakeholder Engagement Plan

Explanation
When identifying a new stakeholder during the project, the First step is to update the Stakeholder
register.

Question: 47 Correct

You and your team have done extensive brainstorming and


discussions. You have also looked up the Organizations process
assets and have come up with an exhaustive list of risks. You and
your team members feel fairly confident now that you know all
the risks. You decide to prioritize the risks and only focus on the
high priority ones. A team member indicates that a large number

EXAM 01/200 QA
of risks have very low priority. What should you do next?

Update risk register

These risks can be dismissed

Perform Quantitative Risk Analysis

These risks can be accepted

Explanation
After performing Qualitative Risk Analysis, the Risk Register is updated included watch list which stated
the low priority Risks for continued monitoring. [PMBOK 6th edition, Page 427]

Question: 48
Correct

In your project, one of your project team members leaves the site
early at 1:00 pm on Friday and didn't finish his tasks on time. As a
project manager, what should you do next?

Conduct One-on-One Meeting with the team member

Meeting with the project team members and evaluate the impact on the project.

Schedule training sessions for the team member to optimize his performance.

EXAM 01/200 QA
Release a team member

Explanation
The first step is to Conduct One-on-One Meeting with the team member to understand why he leaves the
site early and why he does not finish his tasks on time.

Question: 49
Correct

While reviewing the statement of work (SOW), two stakeholders


disagree on what the project should include. As a project
manager, What should you do?

Hold a meeting with the two stakeholders to resolve the conflict and reach agreement.

Document the conflict in the issue log before participating in the development of the project
charter.

Include the stakeholders' comments for future reference in the project charter.

Document the stakeholders’ points but include the remaining stakeholders’ input in final
decision making.

Explanation
Conflict management is a part pf Interpersonal and team skills that can be used for the initiation process.
Conflict management can be used to help bring stakeholders into alignment on the objectives, success
criteria, high-level requirements, project description, summary milestones, and other elements of the
charter. so the project manager should be proactive and meet with the two stakeholders to resolve the
conflict and reach an agreement. PMBOK 6th edition page, 80

EXAM 01/200 QA
Question: 50
Correct

A project manager is leading a project to investigate the


feasibility of constructing a dam to generate hydroelectric power.
The project needs to be analyzed from a technical, economic, and
social point of view. The project manager has created the project
charter on behalf of the project sponsor, and it is now approved.
Which of the following processes should be performed next?

Plan Scope Management

Develop Project Charter

Scope Baseline

Identify Risks

Explanation
After the project charter is approved the next step should identify stakeholder but this option not included
in the Choices so the correct answer is Scope management plan because it includes: Process for
preparing a project scope statement and Process that establishes how the scope baseline will be
approved and maintained. option no.4 the business case prepared before the project. the above question
very important and you will counter like this idea in real exam .

Question: 51 Correct

EXAM 01/200 QA
A project manager must provide cost estimates to stakeholders.
What should the project manager present to avoid unreasonable
cuts in the budget that will undermine the project?

Bottom-up cost as the basis for the estimate.

High-level costs summarized by resource.

Cost estimates as per historical data and other variables.

Cost estimates using expert judgement.

Explanation
Bottom-up estimating is a method of estimating a component of work. The cost of individual work
packages or activities is estimated to the greatest level of specified detail.PMBOK Page 244

Question: 52
Correct

Two new team members have just joined the project you are
leading. The project is large and involves many stakeholders. You
want to get the new team members up to speed with the overall
dynamics of the project and engage effectively with the project
stakeholders. What should you do?

EXAM 01/200 QA
Review the stakeholder register with the new team members

Schedule a meeting with the new team members and all project stakeholders

Submit a change request to update the stakeholder engagement plan

Ask the team members to record any issues they encounter into the issue log

Explanation
The stakeholder register is a project document that contains all current information about the
stakeholders. The stakeholder register includes stakeholder identification information, assessment
information, and stakeholder classification. It is used by the project team to maintain information about
the stakeholder's expectations and interests with the project. By reviewing the stakeholder register with
the new team members, the project manager can provide them with the information about each project
stakeholder, politics surrounding the project, and other relevant details about the project and the
stakeholders that may help the new

Question: 53
Correct

You work for Rory’s, a golf equipment manufacturer. Your


organization is installing some new manufacturing equipment,
and you are managing the project. Your project sponsor has
asked for an EAC and has told you that he wants you to use ETC
work considering CPI and SPI factors. If EV = 145, PV = 162, AC =
148, and BAC = 200, what is EAC?

210

EXAM 01/200 QA
58

207

63

Explanation
The EAC formula for this question is AC + [(BAC – EV) ÷ (CPI × SPI)]. First, calculate CPI, which is EV ÷
AC: therefore, $145 ÷ $148 = .$98. SPI is EV ÷ PV; therefore, $145 ÷ $162 = .$90. Plugging in the
numbers from the question, you get $148 + [($200 – $145) ÷ (.$98 × .$90)] = $210.

Question: 54
Correct

As a project manager, you are leading a software development


project as a result of observation and conversation, you notice
some of the team members need to improve their skills. What
should you do FIRST?

Review the Resource Management Plan

Update Cost Baseline

Schedule training sessions for the team member to optimize his performance.

Acquire new members

Explanation
The Resource Management Plan include Training strategies and Methods for developing the project

EXAM 01/200 QA
team. [PMBOK 6th edition, Page 319]

Question: 55
Correct

A project manager is in charge of managing a large construction


project of 4 billion USD. Various teams from different countries
are involved in this project and the teams need to work
cohesively and seamlessly for the success of the project. The
task of one team member is highly dependent on that of other
team members. Which of the following is important for the overall
success of project integration?

Communications management plan

Change management

Adherence to professional code of conduct

Detailed definition of the work packages

Explanation
The communication management plan is vital for the success of project integration.

Question: 56
Correct

EXAM 01/200 QA
You have recently been assigned as the project manager for a
company that has a history of implementing system integration
projects and you don't have prior experience. What should you
do?

Seek expert judgement

Meet with the sponsor

Review the project charter

Refer to the project statement of work (SOW).

Explanation
keyword ( you don't have prior experience ) so the project manager should seek expert judgment.

Question: 57
Correct

Your company has signed a fixed-price contract with the seller


organization to finalize the project requirement. Which of the
following estimating technique would be best in order to estimate
the activity cost?

Bottom-up-Estimating

EXAM 01/200 QA
Three Point Estimating

Parametric Estimating

Analogous Estimating

Explanation
Bottom-up will give you the most accurate estimates, and it requires a well-defined scope & accurate
WBS.

Question: 58
Correct

A project manager is working with the project team to estimate


durations for the identified project activities. The team is looking
to achieve the most accurate estimate possible. What estimating
technique can they use to generate the desired result?

Three-point estimating

Top-down estimating

Parametric estimating

Analogous estimating

Explanation
Three-point estimating, it uses three estimates (most likely, optimistic, and pessimistic) to calculate the
average value of activity duration. It reduces the bias, risks, and uncertainties from the duration

EXAM 01/200 QA
calculation. It is more accurate than the analogous technique and Parametric estimating. Analogous
estimating is also referred to as top-down estimating.

Question: 59
Incorrect

During the middle of the project, the project manager has been
exposed to an accident, and a new project manager has been
assigned. What should the new project manager do next?

Update project management plan

Update Organizational process assets ( OPA )

Update resource calendar

Update project charter

Explanation
Since he is a new project manager, so the communication management plan should be updated. Also,
the resource management plan is a component of the project management plan. Option Update project
charter) incorrect because the sponsor who can update or modify the project charter according to
PMBOK

Question: 60
Correct

A project management office (PMO) assigns a resource to a

EXAM 01/200 QA
Update the change management plan to track and communicate change.

Escalate all changes to key stakeholders to obtain agreement before implementation.

Ensure that all potential changes are part of the risk mitigation plan.

Explanation
The project stakeholders want to understand changes before they occur.Because of the change
management plan is a part of the project management plan, so the project manager should Revise the
project plan to handle upcoming change requests.

Question: 62
Correct

Your company has created an electronic network to share


information between stakeholders and access to information at
any time. Which communication method is used?

Pull communication

Push communication

Multidirectional communication

Interactive communication

Explanation
An electronic network is a form of Pull communication. [PMBOK 6th edition, Page 374]

EXAM 01/200 QA
Inspection

Independent estimate

Claims administration

Explanation
The scenario suggests the Control Procurements process is underway. Audits are among the tools and
techniques of this
process and are typically used to evaluate a documented procedure to ensure the
procedure is being carried out
according to plan and analyzed for improvements. In this situation, an
audit can be used to review the schedule for the
delivery of material per the contract. The audit results
inform the project manager whether changes need to be made to
the schedule. If the seller is delinquent
in delivering the material, the audit results will also allow the project manager to
determine what, if any,
corrective action should be taken. An audit, as a tool of the Control Procurements process, is how
contract performance is monitored via a
structured review of the procurement process. The project
manager would conduct an audit to compare the
supplier's obligations to deliver material as outlined in
the contract versus their actual performance. Results of the
audit would determine if corrective action
needs to be taken.(PMBOK Guide) – Sixth Edition, Page(s) 498

Question: 66 Correct

You are working on a project to construct four buildings complex.


The project management plan calls for completion of one building
per year at a cost of US$ 100 Million each. At the end of year
three,
1st Building was completed at a cost of US$100 million &
2nd Building completed at a cost of US$120 million & 3rd
Building only 50% completed at a cost of US$ 60 million To meet
the original project management plan, what monthly performance
is needed until the end of year four?

EXAM 01/200 QA
125 percent

120 percent

110 percent

115 percent

Explanation
Here he ask to calculate the TCPI , to meet the original project management plan you should use the
equation TCPI= (BAC-EV) / (BAC-AC) ....... BAC= 4*100 M = 400 M & AC= 100 M+ 120M + 60M = 280
M & EV= 2.5/4 X 400 M =250 M So the TCPI= (BAC-EV) / (BAC-AC) = ( 400 M -250 M ) / ( 400 M - 280
M ) = 1.25 = 125 %

Question: 67 Correct

As per the Below Table, what is the Critical Path?

EXAM 01/200 QA
A-B-C-E & A-B-D-E

A-B-C-E & A-D-E

EXAM 01/200 QA
A-C-E

A-B-D-C

Explanation
There are 3 paths in this network diagram are as follows: ABCDE, ABDE, ADE. Since paths ABCDE,
ABDE is the longest paths with zero float for all of the activities, it represents the critical path.

Question: 68
Correct

A project manager in the final closure phase of the project. Which


of the following should the project manager refer to ensure that
requirements approved in the requirements documentation are
delivered?

Requirement Traceability Matrix

Stakeholder Engagement Assessment Matrix

Scope Management Plan

Project Management Plan

Explanation
The requirements traceability matrix is a grid that links product requirements from their origin to the
deliverables that satisfy them. The implementation of a requirements traceability matrix helps ensure that
each requirement adds business value by linking it to the business and project objectives. It provides a
means to track requirements throughout the project life cycle, helping to ensure that requirements
approved in the requirements documentation are delivered at the end of the project. Finally, it provides a

EXAM 01/200 QA
structure for managing changes to the product scope. . [PMBOK 6th edition, Page 148]

Question: 69
Correct

A quality defect on project deliverables. In Which Category are


these risks included?

Technical Risk

External Risk

Commercial Risk

Management Risk

Explanation
[PMBOK 6th edition, Page 406]

Question: 70
Correct

Using the following values, calculate the Management reserve:


Project Budget = 100,000
EAC = 120,000
AC = 5,500
BAC=70,000

30,000

EXAM 01/200 QA
Question: 72
Correct

You are a project manager in a big construction project. A strike


by local workers occurs due to the lateness workers' payments.
That leads to delays in a major component delivery. What is the
process the project manager could have been done differently to
prevent this type of situation?

Develop Schedule

Monitor Risk

Identify Stakeholder

Control Scope

Explanation
To prevent this type of situation, we must go to planning. So choice B & D are wrong and C not related.
when developing Schedule, we identify milestones which payments related to milestone and progress.
Develop Schedule Process include What-if scenario analysis as a tool. What-if scenario analysis is the
process of evaluating scenarios in order to predict their effect, positive or negative, on project objectives.
A schedule network analysis is performed using the schedule to compute the different scenarios, such as
delaying a major component delivery, such as a strike. [PMBOK 6th edition, Page 213] . The above
question very important and you will counter like this idea in the real exam.

Question: 73 Correct

EXAM 01/200 QA
Without consulting the project manager, a functional manager
removes key project resources in order to assign them
operational tasks. Since these resources are now focused on
operational tasks rather than deliverables, the deliverables run
late. What should the project manager do first?

Negotiate time allocation to prioritize the resources’ workload.

Ask to have the resources replaced immediately.

Escalate the functional manager’s actions to the sponsor.

Extend the project timeline.

Explanation
The functional manager removes key project resources in order to assign them operational tasks.The
scenario ask what should you do FIRST. The project manager should FIRST Negotiate time allocation to
prioritize the resources’ workload. It’s a strategic way to distribute the work throughout your team to keep
your teams busy and productive.

Question: 74
Correct

You are a project manager of a company and you are in the


execution phase. The environmental authorities sent a notice to
the project manager to stop work. What should the project

EXAM 01/200 QA
manager have done to avoid this?

Identified stakeholders.

Identified project risks

Defined a detailed scope of work.

Developed a detailed project management plan.

Explanation
To prevent this situation, the project manager should identify all the stakeholders that can impact the
project. Very important question for Real pmp exam

Question: 75
Correct

During project closure and transferring of the completed project


deliverables to the operations group, the project manager
discovers that an audit report from an early project phase is
missing. What should the project manager do?

Inform the operations group about the missing audit report.

Ask the operations group to accept the project without the audit report.

EXAM 01/200 QA
Complete project closure and Update the OPA

Remove the audit report from the required project documents and update the project
management plan

Explanation
Ethically, the project manager must inform the operations group about the missing audit report.

Question: 76
Correct

After receiving a request for proposal (RFP), some potential


vendors have questions about the terms and conditions. What
should the project manager do to ensure that all vendors have a
clear and common understanding?

Conduct a bidder conferences

Resubmit the RFP.

Send a clarification to the vendors via email.

Schedule a meeting with individual vendors.

Explanation
After receiving a request for proposal (RFP) and prior to proposal submittal , some potential vendors
have questions about the terms and conditions. SO the project manager should conduct a Bidder
conference (also called contractor conferences, vendor conferences, and pre-bid conferences) this
meeting between the buyer and prospective sellers prior to proposal submittal. They are used to ensure
that all prospective bidders have a clear and common understanding of the procurement and no bidders

EXAM 01/200 QA
You are a Project Manager in a construction company. Jone is the
sponsor of your project and has just developed the project
charter, and has also provided you with a list of the project's key
stakeholders that he has identified. He then asks you to
immediately gather the requirements. What should be your next
step as the project manager?

Conduct the stakeholder identification process to identify all stakeholders

Develop a stakeholder engagement plan

Prepare a power/interest matrix for key stakeholders

Start working on define activities

Explanation
Stakeholder identification is an important process in the initiating phase of a project and should be
performed immediately after the project charter has been developed. Although the project sponsor has
provided you with a list of what he considers "key" stakeholders, you must perform the Identify
Stakeholders process until "all" stakeholders have been identified. Only then can you move on to the
Planning processes of Plan Stakeholder Management and Collect Requirements.

Question: 80
Correct

You have recently been assigned as a project manager to manage


a project that was terminated three months ago because of
funding related issues, but which has since been re-initiated. You

EXAM 01/200 QA
want to find out the exact reasons for the termination of the
project. You also want to know which deliverables were produced
from the terminated project. Which of the following
documentation should you review to obtain this information?

Project or phase closure documents

Operational and support documents

Historical Database

Final Product, Service, or Result

Explanation
Project or phase closure documents, consisting of formal documentation that indicates completion of the
project or phase and the transfer of the completed project or phase deliverables to others, such as an
operations group or to the next phase. During project closure, the project manager reviews prior phase
documentation, customer acceptance documentation from the Validate Scope process, and the
agreement (if applicable) to ensure that all project requirements are completed prior to finalizing the
closure of the project. If the project was terminated prior to completion, the formal documentation
indicates why the project was terminated and formalizes the procedures for the transfer of the finished
and unfinished deliverables of the cancelled project to others.. [PMBOK 6th edition, Page 128]

Question: 81
Correct

During the execution of the project, you had to manage a change


request. You evaluated the impact of the change on the other
constraints of the project, then you got the change request

EXAM 01/200 QA
approved by CCB. The next step a project manager should do is:

Update Project Management plan.

Implement the Approved change.

Inform stakeholders with new status of the project.

Update the Issue Log.

Explanation
The next step after approved the change request by CCB is to update change log and Update the Plans
and affected baselines before implementing the approved change request.[PMBOK 6th edition, Page115
]

Question: 82
Correct

You are a project manager of a company and your project is


currently in the execution phase. In your project there is an issue
requires the execution of the contingency plan, which impacts
the schedule baseline. As a project manager, what should you
do?

Issue a change request.

EXAM 01/200 QA
Perform risk audit.

Review the cost impact.

Do nothing as this would cause changes to the baselines

Explanation
The execution of the contingency plan will impact the project schedule, so the next step is to Issue a
change request. Change requests are processed for review and disposition through the
Perform
Integrated Change Control process.

Question: 83
Correct

During the initiation phase, the project manager classifying a list


of project stakeholders and discovers an interested stakeholder
with little authority. How should manage this stakeholder?

Keep informed

Keep satisfied

Manage Closely

Monitor

Explanation
it's important for the real exam. The stakeholder is interested in the project with little authority so you will
keep him informed.

EXAM 01/200 QA
Question: 84
Correct

Which of the following techniques can ensure that the


stakeholders are engaged at appropriate project phases and to
obtain or confirm their continued commitment to the success of
the project?

Stage gate meetings

Managing project team

Setting ground rules

Performance audits

Explanation
Stage-gate or phase review meetings give to project stakeholders a chance to review project progress
and planned future actions. This gives them a chance to have their voice heard and recorded. The rest of
the choices are techniques that are internal to a project. [PMBOK 6th edition, Page 21]

Question: 85
Correct

If the outsourced deliverables don’t meet the agreed-upon


acceptance criteria. What should the project manager reference
to verify this with the contractor?

EXAM 01/200 QA
Statement of work (SOW).

Request for proposal (RFP).

Procurement management plan

Quality log

Explanation
The SOW include: ** Description of the procurement item.
** Specifications, quality requirements and
performance metrics.
** Description of collateral services required. **Acceptance methods and criteria.
PMBOK 6th edition page, 481

Question: 86
Correct

You are working on a complex project which involves multiple


team members and sponsors. As a project manager, what should
you do before obtaining the project approval and buy-in?

Complete a stakeholder analysis

Meet with the stakeholders

Perform a Qualitative and Quantitative risk analysis

EXAM 01/200 QA
scope do not occur.

Question: 88
Correct

You are a project manager of the DFJ Project. Your project is


behind Schedule and the sponsor suggests reducing the time for
quality assurance testing. What should the project manager do
first?

Follow the Quality Management Plan

Perform quality audit.

Perform quality control measurements.

Change the quality requirements.

Explanation
The Project manager should Follow The quality management plan because it describes how applicable
policies, procedures, and guidelines will be implemented to achieve the quality objectives. It describes
the activities and resources necessary for the project management team to achieve the quality objectives
set for the project. include Quality control and quality management activities planned for the project.
[PMBOK 6th edition, Page286 ]

Question: 89
Correct

EXAM 01/200 QA
You are managing a large project. when you starting to get
approval for management reserve to use for unforeseen work
happen in the execution phase, you were dealing with an
interested stakeholder who has no authority. How can you handle
that?

Inform the stakeholder

Monitor

keep satisfied

Manage closely

Explanation
The stakeholder Interested and no authority so the project manager should inform the Stakeholder.

Question: 90
Correct

You are a project manager of the HDN Project. The customer has
requested a change in the scope which you have processed
through a change request and it is approved from CCB. Now, you
are in the process of implementing this change into the project. In
which of the following processes do you implement the approved
change?

EXAM 01/200 QA
Direct and manage project work

Perform integrated change control

Monitor and control project work

Control scope

Explanation
Approved change requests will be implemented through the Direct and Manage Project Work process.
[PMBOK 6th edition, Page120 ]

Question: 91
Correct

You receive an urgent change request from the client. You review
the request and find that it might cost a lot if you implement this
change request. What will be your next step?

Discuss the cost impact with the client

Implement the change

You will not allow any change request

Since it increases the cost, reject it

EXAM 01/200 QA
Explanation
You should discuss the impact of the change request on the project cost with the client. You cannot
process the change request unless the client agrees with its impact on any project objective.

Question: 92
Correct

You are in the execution phase of a project to build an


automobile. The project team develops a new response for an
existing risk that will reduce the schedule by 20 days. What
document should the project manager update?

Risk register

Risk breakdown structure (RBS).

Risk management plan

Schedule management plan

Explanation
The risk register is updated when appropriate risk responses are chosen and agreed upon. PMBOK 6th
edition, Page, 448

Question: 93
Correct

During the projct execution, your customer comes to you and

EXAM 01/200 QA
tells you about a minor requirement that he forgot during the
collect requirement process. He assures you that there will be no
effect on the cost if you implement his request. What will your
next step be?

Evaluate the impact with team members

You will deny his request

Update Scope Baseline

Implement the change

Explanation
You should first evaluate the impact of the change with the team member then inform the customer of the
impact on project constraints.

Question: 94
Correct

If the change control board (CCB) recently approved two change


requests. 1st was due to sending late communications to
stakeholders. 2nd was a delay in activity on the critical path due
to insufficient resources. As a project manager, what should you
do FIRST?

EXAM 01/200 QA
Communication management plan.

Project schedule.

Explanation
keyword ( documented initially ) Since the project manager is aware of the rainy season will happen on a
yearly basis, therefore it should be recorded in the project charter.

Question: 96
Correct

During the review of a control chart, you notice that the process
has 3 points between mean and lower control limit and 4 points
between upper control limit and specification limit. How will you
consider this process?

Need solution

Cannot be determined

In control

Customer only can take decision for this process

Explanation
Although the Points is within the customer’s specification limits, it is outside the control limit. Therefore,
you will take corrective action so as to avoid any possible defect. [PMBOK 6th edition, Page 304]

Question: 97
Correct

EXAM 01/200 QA
As part of earned value management (EVM), The budget at
completion (BAC) for the project is $100,000 and the estimate at
completion (EAC) is $120,000. If the schedule performance index
(SPI) is equal to 1.0. What is the cost performance index (CPI)?

Less than 1.0

Greater than 1.0

Equal to 1.0

Equal to 1.2

Explanation
EAC= BAC/CPI so CPI=100,000,000/120,000,000=0.83 so the CPI Less than 1.0

Question: 98
Correct

You are a Project manager participating in developing the project


charter. Which of the Following help you in this Process?

letters of intent

EXAM 01/200 QA
Project Management Plan

Deliverables

Stakeholder register

Explanation
Agreements are used to define initial intentions for a project. Agreements may take the form of contracts,
memorandums of understanding (MOUs), service level agreements (SLA), letters of agreement, letters of
intent, verbal agreements, email, or other written agreements. Typically, a contract is used when a
project is being performed for an external customer. [PMBOK 6th edition, Page78 ]

Question: 99
Correct

You are at the closure of your construction project when the PMO
head called you asking to ensure the transfer of liability of the
buildings to the operation department. What should you do to
achieve a PMO request?

Obtain financial, legal, and administrative closure

Obtain Formal Acceptance from customer

Collect lessons learned and update knowledge base

Prepare and share the final project report

Explanation

EXAM 01/200 QA
Refer to PMP Exam Outline in the Closing Process Group ( Task no. 3 )

Question: 100
Correct

Ben is the project manager for a mobile application development


project. An issue has occurred and one of the team members
identifies a workaround, but fails to inform the project manager.
After a few weeks, a similar issue appeared again that impact the
project. What should have done to prevent this situation?

Performing a root cause analysis

Updating the risk register

Escalate the problem to the sponsor

Revising the responsibility assignments matrix (RAM).

Explanation
To prevent this issue from appearing again,. he should Performing the root cause of the problem and
documented it in the lessons learned.

Question: 101 Correct

During the execution of the project, you had to manage a change


request. You evaluated the impact of the change on the other

EXAM 01/200 QA
constraints of the project then you got the change request
approved by CCB. The next step a project manager should do is:

Ask the Sponsor for authorization.

Implement the Approved change.

Update Project Management plan.

Update the Issue Log.

Explanation
Customer or sponsor approval may be required for certain change requests after CCB approval unless
they are part of the CCB. [PMBOK 6th edition, Page115 ]

Question: 102
Correct

You got information that a very powerful stakeholder who was


not identified in your stakeholder list isn’t happy with your
project performance. He asked for some updates to be done in
the project. What is the first action project manager should do?

Update Stakeholder register.

Implement the change.

EXAM 01/200 QA
Issue a change request to CCB.

Analyze the impact of the request on the project.

Explanation
Very important for the real exam. Keyword ( the Stakeholder not identified ) so the first step you should
update him in the Stakeholder register.

Question: 103
Correct

You are the new project manager who has never managed a
project before. You have been asked to plan a new project. Which
of the following will help you to improve your chance of choices?

Historical information.

Configuration management.

Stakeholder analysis.

Your intuition and training.

Explanation
Because you have no experience, you will have to look at the experience of others. This information is
captured in the historical records from previous projects.

Question: 104
Correct

EXAM 01/200 QA
You have recently been assigned to lead a project that is halfway
into execution. The project is behind schedule and under budget,
but the customer is not happy with the performance of the
project. What is the FIRST thing you should do?

Meet with the customer.

Renegotiate the contract.

Reschedule baselines.

Discuss it with the project team.

Explanation
First, you need to find out why the customer is not happy. Then meet with the team and determine
options.

Question: 105
Correct

Bill is the project manager of the construction Project. He and the


project team have identified a risk event in the project with a high
probability of occurrence and the risk event has a high-cost
impact on the project. Bill discusses the risk event with Virginia,
the primary project customer, and she decides that the

EXAM 01/200 QA
requirements surrounding the risk event should be removed from
the project. The removal of the requirements does affect the
project scope, but it can release the project from high-risk
exposure. What risk response has been enacted in this project?

Avoidance

Mitigation

Transference

Acceptance

Explanation
Risk avoidance is when the project team acts to eliminate the threat or protect the project from its impact.
Avoidance may involve changing some aspect of the project management plan or changing the objective
that is in jeopardy in order to eliminate the threat entirely, reducing its probability of occurrence to zero.
Examples of avoidance actions may include removing the cause of a threat, extending the schedule,
changing the project strategy, or reducing scope. [PMBOK 6th edition, Page 443 ]

Question: 106 Correct

You are the project manager of the GHY Software Project. Before
the implementation of a system upgrade, one of the team
members discovers a critical defect in the current system that
must be fixed. What should the project manager do?

EXAM 01/200 QA
Inform the project sponsor and follow the perform integrated change control process.

Implement the fix

No action taken because the project scope has been finalized

Update the Risk register

Explanation
Keyword ( critical defect must be fixed ) so the correct answer is to Inform the project sponsor and follow
the perform integrated change control process to fix the defect.

Question: 107
Correct

During the implementation phase, you want to compare the


baseline to the actual results and determine if the variance is
within the threshold amount or if corrective or preventive action
is appropriate. Which of the following techniques can help you?

Variance Analysis

Trend analysis

Decomposition

EXAM 01/200 QA
Control chart

Explanation
Variance analysis is used to compare the baseline to the actual results and determine if the variance is
within the threshold amount or if corrective or preventive action is appropriate. [PMBOK 6th edition,
Page170 ]

Question: 108
Correct

Your project team works in two different buildings across the


city. The team has been struggling to perform effectively, morale
is low and has a difficult time resolving problems. What would be
the BEST team development technique to resolve this issue?

Co-location

Training

Rewards

Mediation

Explanation
Colocation involves placing many or all of the most active project team members in the same physical
location to enhance their ability to perform as a team. Colocation strategies can include a team meeting
room, common places to post schedules, and other conveniences that enhance communication and a
sense of community.[PMBOK 6th edition, Page340 ]

Question: 109
Correct

EXAM 01/200 QA
A tool that provides a visual representation of human resource
allocation to a project, number of working hours, and availability
on the project over a series of time periods is a:

Resource Histogram

Resource Breakdown Structure (RBS)

Organization Breakdown Structure (OBS)

Stakeholder Register

Explanation
Resource Histogram shows the required number of hours that will be needed from each department or
person for each week or month during the project. [PMBOK 6th edition, Page719 ]

Question: 110
Correct

During the execution of an IT project, a project manager warns of


the possibility that the main server may fail due to constant,
local-area electrical outages. The project manager sign a contract
to rent an additional server from a local company. What strategy
is the project manager using?

EXAM 01/200 QA
Mitigate

Transfer

Enhance

Share

Explanation
In risk mitigation, the action is taken to reduce the probability of occurrence and/or impact of a threat. the
project manager wants to reduce the probability and impact by renting the generator.[PMBOK 6th edition,
Page443 ]

Question: 111
Correct

You are in the middle of your project and working on a


deliverable which is 90% completed. It is time for the yearly audit.
A team of auditors are about to come and verify if you are
following the process as defined or not. However, as the
deliverable is about to be completed, you check it and measure
all dimensions to find any possible dimensional defects. What
process is this?

Control quality

EXAM 01/200 QA
Manage quality

Plan quality management

Control scope

Explanation
In the quality control process, you inspect the deliverable for any possible defects. As you are doing an
inspection, you are in the quality control process. Please note that although the quality audit is performed
in the manage quality process, it has not started yet and you are doing an inspection, which is a tool of
the quality control process. [PMBOK 6th edition, Page303 ]

Question: 112
Correct

As a project manager, in which document will you find


information about the acceptable level of project and product
quality and how to ensure this level of quality in its deliverables
and processes?

The project management plan

The Scope Management Plan

Work Performance data

Project Charter

Explanation

EXAM 01/200 QA
The acceptable level of project and product quality and how to ensure this level of quality in its
deliverables and processes are part of the information in the project management plan as it includes the
quality management plan as one of its components, so, option (The project management plan) is the right
answer.

Question: 113
Correct

After the project charter is approved, what should you do NEXT?

Prepare Scope Management Plan

Prepare Project Scope Statement

Scope baseline

Prepare a business case

Explanation
After the project charter is approved the next step should identify stakeholder but this option not included
in the Choices so the correct answer is Scope management plan because it includes: Process for
preparing a project scope statement and Process that establishes how the scope baseline will be
approved and maintained. option no.4 the business case prepared before the project. the above question
very important and you will counter like this idea in real exam.

Question: 114
Correct

The project near to complete, unidentified stakeholder request a

EXAM 01/200 QA
Review the risk management plan to update risks.

Create a cause and effect diagram to quantify impact.

Remove the process from the quality management plan.

Explanation
Although the project is going well and there are no known quality issues, but the quality management
processes are necessary , It applies to all projects to Meet customer requirements and decrease the
employee attrition, errors, or rework. SO the project manager should Create a team culture that is
committed to quality.

Question: 116
Correct

You are managing a large construction project. Your project team


works in two different buildings across the city. You want to
communicate the vision and inspire the project team to achieve
high performance. Which of the following skills help the project
manager?

Leadership

Political awareness

Emotional intelligence

EXAM 01/200 QA
Feedback

Explanation
Successful projects require leaders with strong leadership skills. Leadership is the ability to lead a team
and inspire them to do their jobs well. It encompasses a wide range of skills, abilities, and actions.
Leadership is important through all phases of the project life cycle. There are multiple leadership theories
defining leadership styles that should be used as needed for each situation or team. It is especially
important to communicate the vision and inspire the project team to achieve high performance. [PMBOK
6th edition, Page 350 ]

Question: 117
Correct

You are managing a construction project. After identifying risks,


you start the qualitative risk analysis process and now you are
going to prioritize them. Which of the following techniques are
you going to use?

Probability and impact matrix.

Scatter diagram.

Sensitive analysis.

Tornado diagram.

Explanation
After identifying risks, your next step will be to prioritize them. To do so you will use the probability and
impact matrix. [PMBOK 6th edition, Page 408 ]

EXAM 01/200 QA
Question: 118
Correct

After identifying and analyzing risks you and your team start to
risk response process, you find a risk which would be difficult for
you to manage. You discuss the issue with management and a
decision is taken to transfer the management of this risk to your
Program manager. What risk response strategy is this?

Escalate

Transfer

Mitigate

Workaround

Explanation
Escalation is appropriate when the project team or the project sponsor agrees that a threat is outside the
scope of the project or that the proposed response would exceed the project manager’s authority.
Escalated risks are managed at the program level, portfolio level, or other relevant parts of the
organization, and not on the project level. [PMBOK 6th edition, Page 442 ]

Question: 119
Correct

You are managing a construction project, your cost performance


is not as planned and your Project is over budget. Therefore, you

EXAM 01/200 QA
Ensure that the product meets customer requirements.

Deliver the product.

Update the issue log.

Explanation
keyword ( may ) The Quality issue may or may not cause the product to be rejected by the customer. SO,
the project manager should first Review the quality checklist. Quality checklist used to verify that a set of
required steps has been performed or to check if a list of requirements has been satisfied. . Quality
checklists should incorporate the acceptance criteria included in the scope baseline. After reviewing the
Quality checklist by the project manager and verifying the existence of an issue, the issue must then be
presented to the customer and if he not accept the product then it must be recorded in the issue log to
start track and find the solution.

Question: 121
Correct

You are the project manager of the HDM Project. Your project
must be completed by September 11 and cannot exceed $10,000.
$10,000 is an example of which one of the following?

Constraint

Management reserve

Scheduled completion date

EXAM 01/200 QA
Assumption

Explanation
because the Constraints are limitations placed upon the project that the project manager and team must
work within. there are scope, schedule and cost constraints.i. cost constraint (how much funding has
been allocated). and the three constraints are commonly called the triple constraints.

Question: 122
Correct

You are the project manager of the GHQ Project. A team member
informs you with a serious concern that impacts the project. You
start to record the details, identifies an owner, and sets a realistic
date for resolution. What document did the project manager
update?

Issue log

Risk register

Stakeholder register

Change log

Explanation
The issue log will help the project manager effectively track and manage issues, ensuring that they are
investigated and resolved [PMBOK 6th edition, Page 96]

Question: 123
Correct

EXAM 01/200 QA
You have identified a risk that may cause safety concerns for the
workers completing the task. You’ve decided to hire a third party
to complete this work because the risk is too great to accept
internally. Which risk response is this?

Transference

Avoidance

Acceptance

Mitigation

Explanation
The transfer involves shifting ownership of a threat to a third party to manage the risk and to bear the
impact if the threat occurs. Agreements may be used to transfer ownership and liability for specified risks
to another party. A is incorrect because mitigation is any effort to reduce or eliminate the risk. B is
incorrect because acceptance means just that: the risk has been accepted. C is incorrect because
avoidance is changing the project management plan to avoid the risk altogether. [PMBOK 6th edition,
Page 443 ]

Question: 124
Correct

As the project manager of a large project, you are determining the


accuracy of the deliverables before closing a project. What

EXAM 01/200 QA
process should be used to determine this and is an input to
formalizing acceptance?

Control Quality

Manage quality.

Control scope.

Accepted deliverables

Explanation
Its a tricky question and very important for the real PMP Exam. Validate Scope is the process of
formalizing acceptance of the completed project deliverables. The verified deliverables obtained from the
Control Quality process are reviewed with the customer or sponsor to ensure they are completed
satisfactorily and have received formal acceptance of the deliverables by the customer or
sponsor.
Verified deliverables is the key inputs of validate scope process and outputs of Control quality process.
[PMBOK 6th edition, Page 164]

Question: 125
Correct

You are working in a matrix organization and managing a project.


The functional manager transferred some resources you need
from your project to another project. What should you do next?

Negotiate with Functional Manager to assign a new resources

EXAM 01/200 QA
Escalate this problem to the sponsor

Complete the project without this resources

Update Stakeholder Engagement plan

Explanation
In matrix organizations environment The project manager should effectively negotiate and influence
others who are in a position to provide the required team and physical resources for the project. [PMBOK
6th edition, Page 329,330]

Question: 126
Correct

A project manager was assigned to a project when the project


charter was in development. Which of the following is an input
that the project manager will use to develop the project charter?

Cost Benefit Analysis and organizational strategies

Enterprise environmental factors and Project Acceptance Criteria

Agreements and Make-or-Buy analysis

Organizational Process Assets and Project Scope Statement

Explanation
A business case includes Cost-Benefit Analysis and organizational strategies. [PMBOK 6th edition, Page

EXAM 01/200 QA
68,75]

Question: 127
Correct

Your project is complete and the product is ready to be delivered.


The client inspects the deliverable and accepts it. What process
is this?

Validate scope

Close project or phase

Close procurement

Control Quality

Explanation
In the Validate Scope process, the customer accepts the deliverables or the product. [PMBOK 6th
edition, Page166 ]

Question: 128
Correct

You are busy with an important milestone, and after that, you
have to deliver a deliverable to the client. Since the client is
known for his difficult behavior, management is worried whether
the client will accept the deliverable. Therefore, they tell you to

EXAM 01/200 QA
check the product acceptance criteria again before calling the
client. What document will you look at to get this information?

Project scope statement

Control Chart

WBS dictionary

WBS

Explanation
In the project scope statement, you can see the product acceptance criteria. [PMBOK 6th edition,
Page154 ]

Question: 129
Correct

Your project is very complex and due to a scope change, you


need a few additional experts, which you did not think of earlier.
You request that your company provide you with some experts
for consultancy work. Although your company has provided you
with those experts, they are located in a different geographical
location. In this situation, how will you get their input?

Create a virtual team

EXAM 01/200 QA
Keyword ( concrete’s performance and quality requirements ) The Procurement statement of work (SOW)
Include, specifications, quantity desired, quality levels, performance data, period of performance, work
location, and other requirements. The SOW describes the procurement item in sufficient detail to allow
prospective sellers to determine if they are capable of providing the products, services, or results.
Sufficient detail can vary based on the nature of the item, the needs of the buyer, or the expected
contract form. PMBOK 6th edition Page, 477

Question: 131
Correct

You are a project manager assigned at the initiation phase. Which


of the following documents will help you while developing the
project charter?

Business case

Brainstorming

Final report

Project Management Plan

Explanation
The approved business case is the business document most commonly used to create the project
charter. [PMBOK 6th edition, Page 77]

Question: 132
Correct

EXAM 01/200 QA
Statement of work (SOW)

Kick-off meeting

Business case

Explanation
Identify key deliverables based on the business requirements in order to manage customer expectations
and direct the achievement of project goals. Refer to PMP Exam Outline in( initiating) task no.02

Question: 134
Correct

Sayed is managing a project. The project is about three-fourths


done when the site engineer reports that due to inherent
complexities in a specific task, the deliverables would be delayed.
This would involve additional analysis and then implementation.
He requests that this new work be added to the scope and also
the time required to be added to the schedule. You and the site
engineer have analyzed the impact of this change to cost, and
have written up a change request and requested approval from
the change control board. Just today, you have received approval
from the change control board - what should be the immediate
course of action?

Make sure that the scope baseline and schedule baseline are updated to reflect the
approved change before implementing the change.

EXAM 01/200 QA
Perform Quality Assurance

Ascertain the impact of this change to scope, schedule and cost before making any change

Start work immediately

Explanation
As the change has been approved you should always update the baseline ( in this case the scope and
schedule baseline) before implementing the change. This will ensure that you track performance against
the new scope and schedule and not the old benchmarks.

Question: 135
Correct

You are a project manager in Critical Project for your


organization. Your project is behind schedule and over budget.
Therefore, the Project Sponsor asks you if the team members
may work on weekends. As a Project manager, what should you
do to persuade the team members to work during their
weekends?

Recognition and rewards

Ask the Management what should you do

Ignore the Sponsor

EXAM 01/200 QA
A project manager realizes that a new government regulation
affects the current project, and to be compliant with the new law,
the scope of the project should be changed. The team is now
analysing the impact on the schedule and budget. Which tool or
technique should the project manager have considered before
this issue occurred?

Stakeholder analysis.

Stakeholder register.

Risk management plan.

Risk register.

Explanation
Keyword ( tool or technique ) Only Stakeholder analysis is the tool and technique in identify stakeholder
process. PMBOK 6th edition Page, 512

Question: 138
Correct

While having a coffee with a key stakeholder in your project that


you have a good relationship with, he was surprised that you do
not have the information that your project will be canceled due to
future changes in company plans, and your team members will be

EXAM 01/200 QA
released. As a Project manager, what should you do?

Review the communication management plan and validate why you did not get this
information through it.

Hold a meeting with your team and inform them about what will happen.

Hold a meeting with stakeholders and discuss this information openly with them

Hold a meeting with the sponsor and discuss this info with him.

Explanation
Keyword ( you do not have the information that your project will be canceled) so the PM should Review
the communication management plan because this plan contains the Information to be communicated
and the Person or groups who will receive the information. [PMBOK 6th edition, Page 377]

Question: 139
Correct

You are working as a research assistant studying the growth of


bacteria under different environmental conditions. Based on your
experiments, you conclude that the longevity of bacteria
increases as the temperature increases. What type of diagram
can you use to illustrate your observation?

Scatter diagram

EXAM 01/200 QA
After this he will decide whether take corrective action or not.

Question: 142
Correct

As a Project Manager, you are estimating the duration of your


project activities using Using a triangular distribution formula.
For a particular project activity, your Optimistic estimate is 14
days, Pessimistic estimate is 49 days, and Most Likely estimate is
27 days. What should be the expected duration of this activity?

30

50

25

32

Explanation
triangular distribution allows the estimator to include three estimates: optimistic, pessimistic, and most
likely. The expected duration is calculated using the equation: Expected Duration = [P + ML + O]/3,
where P is the pessimistic estimate, ML is the most likely estimate, and O is the optimistic estimate.
Using this method, the correct answer 14+49+27/3=30 days.

Question: 143 Correct

EXAM 01/200 QA
While sequencing activities, the team defines that:
• Activity A
has a duration of three weeks. • Activity C with a duration of four
weeks, will start first. • Activity B with a duration of two weeks,
will start after completion of activity A
• Activity D, with a duration
of four weeks, will start with a lead time of one week upon
completion of activity B
• Activity E with a duration of five weeks,
will start after the completion of activity C
• Activity F, with a
duration of three weeks, will have a start to start dependency with
activity E, with a lag time of three weeks What is the project’s
shortest possible duration?

10 weeks.

9 weeks.

8 weeks.

12 weeks.

Explanation
To calculate the project’s shortest possible duration , you should start drawing the network and sum the

EXAM 01/200 QA
duration of the longest path to calculate the shortest possible duration
First Path ( A-B-D = 8 Weeks )
Second Path ( C-E-F = 10 Weeks )

Question: 144
Correct

In order to determine the target fuel efficiency for a hybrid car


being designed, a Project Manager is looking at published
statistics for similar models in the industry. The technique being
used is called:

Benchmarking

Brainstorming

Statistical sampling

Scatter diagrams

Explanation
What the Project Manager is trying to do is essentially look at the industry benchmark and make sure that
the product is in line with it. This is the benchmarking technique.

Question: 145
Correct

During project execution, a project manager learns that a team


member’s functional manager believes they shouldn’t execute a

EXAM 01/200 QA
certain task. What document should the project manager review
to resolve this?

RACI (responsible, accountable, consult, and inform) chart

Organisational chart

Work breakdown structure (WBS)

Resource management plan

Explanation
The RACI chart is useful for ensuring team members' roles and responsibilities are clear, especially when
the team consists of internal and external resources.PMBOK 6th edition Page, 317

Question: 146
Correct

What should the project manager use to compare different


suppliers and rate their proposals?

Evaluation criteria

Bid documents

Bidder conferences

EXAM 01/200 QA
Qualified seller lists

Explanation
Evaluation criteria used to compare different subcontractors and rate their proposals. The buyer seeks to
ensure that the proposal selected will offer the best quality for the
services required. PMBOK 6th edition
Page, 478, 479

Question: 147
Correct

You are the project manager of the OQH Project and are working
with the project stakeholders to determine the project
requirements. You and the stakeholders are brainstorming
privately to come up with as many solutions to the project as
possible. After the brainstorming session, a recorder documents
all the solutions on a white board so everyone can see the ideas
and how they may be related. After the solutions have been
documented, you lead the group through a voting process to
discuss and rank each idea and requirement that has been
proposed. What is this requirement gathering technique called?

Nominal group technique

Affinity diagram

Brainstorming

EXAM 01/200 QA
Mind mapping

Explanation
This is an example of the nominal group technique, in which you ask for as many ideas and solutions as
possible, and then the group ranks the concepts to help guide the requirements development. The
nominal group technique enhances brainstorming with a voting process. This then allows the most useful
ideas to be prioritized and taken up for further brainstorming. [PMBOK 6th edition, Page 144]

Question: 148
Correct

While working on the project in the Manage Quality process, you


are determining the factors that may influence specific
characteristics of a product under development and can improve
the product’s final characteristics. What technique are you
using?

Design for X (DfX)

Analogous estimating

Benchmarking

Cost of quality

Explanation
Design for X is a set of technical guidelines that may be applied during the design of a product for the
optimization of a specific aspect of the design. DfX can control or even improve the product's final
characteristics. [PMBOK 6th edition, Page 295]

EXAM 01/200 QA
Question: 149
Correct

During the initiation phase, the project manager wants to manage


customer expectations and direct the achievement of project
goals. in order to achieve this, he starts to Identify key
deliverables based on the business requirements. Which of the
following techniques should the project manager use to prioritize
the key deliverables?

Expert judgement

Rolling wave planning.

Assumption analysis.

Sensitivity analysis

Explanation
Expert judgment important tool in develop project charter process . Expert judgment is defined as
judgment provided based upon expertise in an application area, Knowledge Area,
discipline, industry,
etc., as appropriate for the activity being performed. Such expertise may be provided by any group
or
person with specialized education, knowledge, skill, experience, or training.
For this process, expertise
should be considered from individuals or groups with specialized knowledge of or training
in the following
topics:
** Organizational strategy,
** Benefits management,
** Technical knowledge of the industry and
focus area of the project,
** Duration and budget estimation, and
** Risk identification.
** Prioritize the key
deliverables

EXAM 01/200 QA
Question: 150
Correct

You are managing a project which will provide e-learning


solutions to your customer. The requirements of this project are
not clearly defined in the beginning and there will be
modifications based on customer feedback as the project
evolves. You plan as much as you can and work based on that.
You continue the planning as you learn more about the project.
Which techniques will be most helpful to define activities on the
project?

Rolling wave planning

Templates

WBS

Scope management

Explanation
Rolling wave planning is a form of progressive elaboration where work to be accomplished in the near
term is planned in detail and future work is planned at a higher level of the WBS. Therefore, work can
exist at various levels of detail, depending on where it is in the project life cycle. As more information is
known about upcoming events, the near-term higher-level work packages can be decomposed further

Question: 151
Correct

EXAM 01/200 QA
During a planning meeting for soccer field construction project,
the team decides to conduct a site survey to determine the
ground conditions before engineering the design. What risk
management process is the team implementing?

Risk identification.

Risk planning.

Risk analysis.

Risk response planning.

Explanation
The project team is implementing the Risk identification process to identify the risks that may impact the
project before engineering the design.

Question: 152
Correct

Two team members on your project often disagree. You need a


conflict resolution method that provides a long-term resolution.
You decide to use which one of the following approaches?

Problem solving

EXAM 01/200 QA
Question: 155
Correct

A Project Manager working on a critical deliverable encounters a


major change that affects the schedule baseline and the next
milestone deliverable. You have assessed the impact of the
change on the project constraints with your team, and the change
control board just approved a change request. In which process
will this change be implemented?

Direct and manage project work

Perform integrated change control

Monitor and control project work

Develop project management plan

Explanation
Direct and Manage Project Work is the process of leading and performing the work defined in the project
management plan and implementing approved changes to achieve the project’s objectives. [PMBOK 6th
edition, Page 90]

Question: 156 Correct

One day before the launch of the product, the project terminated

EXAM 01/200 QA
due to important distribution needs that were not identified. What
should have been better developed to prevent this?

Communication management plan

Stakeholder engagement plan

Risk management plan

Resource management plan

Explanation
Keyword ( distribution needs that were not identified ). The scenario implies there is a problem with
project communications. To avoid this situation, the project manager should have been better developed
the Communication management plan.The plan contains the
following information:
** Stakeholder
communication requirements;
** Information to be communicated, including language, format, content,
and level of detail;
** Escalation processes;
** Reason for the distribution of that information;
**
Timeframe and frequency for the distribution of required information and receipt of acknowledgment or
response,
if applicable;
** Person responsible for communicating the information;
** Person responsible
for authorizing release of confidential information;
** Person or groups who will receive the information,
including information about their needs, requirements, and
expectations;
** Methods or technologies
used to convey the information, such as memos, email, press releases, or social media;
** Resources
allocated for communication activities, including time and budget;

Question: 157
Correct

You are using quantitative risk analysis and modeling technique


that helps to determine which risks have the most impact on a
project. Your goal is to find whether the occurrence of a

EXAM 01/200 QA
particular threat would be merely an inconvenience or would ruin
the project. Which of the following tools will be most appropriate
for your analysis?

Tornado Diagram

Control chart

Expected monetary value

SWOT analysis

Explanation
A tornado diagram is a diagramming method to display sensitivity analysis data by examining all the
uncertain elements at their baseline values. It gives a quick overview of how much the project will be
impacted by various elements. The element with the greatest impact on the project appears at the top.
This diagram can be used to determine sensitivity in cost, time, and objectives and is helpful in
determining detailed response plans for elements with greater impacts.

Question: 158
Correct

A project has a duration of three years. Midway through the


project, the project manager resigned. A new project manager
was assigned, and at the first meeting, the project team told him
that a flood may happen within the next few months and will
affect the project equipment. What should the project manager do
next?

EXAM 01/200 QA
Review a risk management plan

Using a management reserves

Using a workaround

Update the risk register

Explanation
(Review a risk management plan), the Keyword in this question the ( new) project manager so the first
thing the new project manager will do it review risk plan after this he will decide what will he do.

Question: 159
Correct

The project team learns from a key stakeholders that some


deliverables have been forwarded for approval without their
knowledge. What should the project manager have done to
prevent this situation?

Verified the communication management plan.

Notified the project team.

Scheduled a meeting with the customer and the project team

EXAM 01/200 QA
All of the following are true regarding resource calendars, except
for which one?

Resource calendars are an output of the Develop Schedule process.

Resource calendars are an output of the Acquire Resources process.

Resource calendars consider quantity, capability, and availability of equipment and material
resources.

Resource calendars show the resources’ vacation time.

Explanation
Resource calendars are an input, not an output, of the Develop Schedule process as one of the project
documents utilized. [PMBOK 6th edition, Page 205, 328]

Question: 162
Correct

Susan is the project manager on a construction project. When


she hears that her project has run into a snag due to weeks of
bad weather on the job site, she says “No problem, we have
insurance that covers cost overruns due to weather.” What risk
response strategy did she use?

EXAM 01/200 QA
Transference

Mitigation

Sharing

Avoidance

Explanation
( Transference), the keyword for this question (( insurance )). The transfer involves shifting ownership of
a threat to a third party to manage the risk and to bear the impact if the threat occurs. A transfer can be
achieved by a range of actions, which include but are not limited to the use of insurance, performance
bonds, warranties, guarantees. [PMBOK 6th edition, Page 443]

Question: 163
Correct

You are a project manager in the execution stage of the project.


Your team members are conducting a meeting to examine and
document the effectiveness of risk responses in dealing with
overall project risk and with identified individual project risk.
What is the project team doing?

Risk review meeting

Reserve analysis

Risk reassessment

EXAM 01/200 QA
Status meeting

Explanation
You can see like this question in the real Exam, Risk reviews are scheduled regularly and should
examine and document the effectiveness of risk responses in dealing with overall project risk and with
identified individual project risks. [PMBOK 6th edition, Page 457]

Question: 164
Correct

You are managing a project in which your team members all work
in the same geographic location and have worked together
previously on many projects. There are seniors and junior team
members. Senior team members feel that they are always
overloaded and junior team members are not learning that fast.
As a Project manager, what should you do?

Recognition and Rewards throughout the project

Focus on decreasing sources of conflicts

Team-building activities

A kick-off meeting

Explanation
People are motivated when they feel they are valued in the organization and the rewards are given to
they demonstrate this value. Most project team members are motivated by an opportunity to grow,

EXAM 01/200 QA
accomplish, and apply their professional skills to meet new challenges. A good strategy for project
managers is to give team recognition throughout the life cycle of the project rather than waiting until the
project is completed. [PMBOK 6th edition, Page 342]

Question: 165
Correct

During the risk review meeting, you start to use a technique to


examine and document the effectiveness of the Risk Management
process. What technique are you using?

Risk audits

Risk urgency assessment

Trend analysis

Ishikawa analysis

Explanation
Risk audits are a type of audit that may be used to consider the effectiveness of the risk management
process. [PMBOK 6th edition, Page 456]

Question: 166
Correct

You have signed a multi-year contract with a customer to


complete a project for a fixed price. Since the duration of the

EXAM 01/200 QA
contract is long, you have added a provision to adjust the price of
the contract according to the market inflation. What kind of
contract is this?

Fixed price with economic price adjustment

Cost plus fixed fee

Firm fixed price

Time and materials

Explanation
The fixed price with economic price adjustment: This type is used whenever the seller’s performance
period spans a considerable period of years, or if the payments are made in a different currency. It is a
fixed-price contract, but with a special provision allowing for predefined final adjustments to the contract
price due to changed conditions, such as inflation changes or cost increases (or decreases) for specific
commodities. [PMBOK 6th edition, Page 471]

Question: 167 Correct

A security team notifies a project manager of a change in security


procedures. The project manager uses the change control
process to update the project management plan. After seeing the
change, a stakeholder complains that it was unnecessary
because the project is almost complete. What should the project
manager do?

EXAM 01/200 QA
Convince the stakeholder of the benefits resulting from the change.

Create a change request to reverse the change until a consensus is reached.

Add a risk to the risk register to track the impact of stakeholder disagreement.

Ignore the stakeholder’s concern and follow the new procedures.

Explanation
The project manager used the change control process to update the project management plan because
its a very important change and necessary for the project. The project manager with the team member
have evaluated the impact of this change on project constraints and then approved by the CCB. SO he
should Convince the stakeholder of the benefits resulting from the change. Option ( Create a change
request to reverse the change until a consensus is reached. ) not good because the change already
approved after the consensus of CCB. Option ( Ignore the stakeholder’s concern and follow the new
procedures. ) not good practice to ignore the stakeholder’s requests. Option ( Add a risk to the risk
register to track the impact of stakeholder disagreement.) Not correct because this not a risk and the
change has been approved.

Question: 168
Correct

Which of the following data representation technique helps you


to classify the identified stakeholders?

Power/ interest grid

EXAM 01/200 QA
Focus groups

Stakeholders assessment grid

Stakeholders register

Explanation
Power/interest grid, grouping the stakeholders based on their level of authority (power) and level of
concern about the project’s outcomes (interest). [PMBOK 6th edition, Page 512]

Question: 169
Correct

Which of the following documents links product requirements


from their origin to the deliverables that satisfy them and
provides a structure for managing changes to the product scope?

Requirements tractability matrix

Project charter

Risk register

Requirements documentation

Explanation
Requirements tractability matrix is a grid that links product requirements from their origin to the
deliverables that satisfy them. [ PMBOK 6th edition, Page 148]

EXAM 01/200 QA
area for the phone without increasing the expenses of the project.
What is the best risk response to plan?

Exploit

Mitigate

Accept

Transfer

Explanation
( Exploit) because of the approach for increasing the storage area for the phone not increasing the
expenses of the project so its opportunity, the best risk response is Exploit.

Question: 172
Correct

Fixed Price Contract is a form of ______ risk:

Transferring

Avoiding

Mitigating

EXAM 01/200 QA
Working around

Explanation
The Buyer using Fixed Price Contract to Transfer the Risk to the Seller.[PMBOK 6th edition, Page 443]

Question: 173
Correct

You are a project manager for a big project. You want to


outsource some of the works. The project schedule is very tight
and the scope not well defined. What type of contract should you
sign?

Cost Plus Incentive Fee Contracts (CPIF)

Firm fixed price contract (FFP)

Cost Plus Fixed Fee Contracts (CPFF)

Fixed Price Incentive Fee Contracts (FPIF)

Explanation
The project scope not well defined so you can easily remove option Fixed Price Incentive Fee Contracts
(FPIF) and Firm fixed price contract (FFP). Option Cost Plus Incentive Fee Contracts (CPIF) is the Best
because this type Provide low risk for the buyer from CPFF. [PMBOK 6th edition, Page 472]

Question: 174
Correct

EXAM 01/200 QA
Updated the risk management plan.

Explanation
To avoid this situation, the project manager should have done conducted review meetings to
communicate project status to stakeholders periodically.

Question: 177
Correct

You are a project manager for a new software project. During


managing stakeholder expectations, at the end of the design
phase, you found one of the key stakeholders complain of one of
work package still not complete. You do not agree and review
with him the WBS dictionary but the stakeholder is still
unsatisfied. What is the next document you should review?

Scope Baseline

Requirement management plan

Scope management plan

WBS

Explanation
Scope baseline contains the approved project scope statement which includes Project scope description,
Acceptance criteria, and Project deliverables.

EXAM 01/200 QA
Question: 178
Correct

During a study of benefit analysis, the project sponsor requires


that you submit a proposal for an implementation strategy. What
should you do next?

Identify high level risk, constrains and assumptions

Review the SOW

Invite the stakeholder for discussions

Identify the key deliverable

Explanation
Identify high-level risks, assumptions, and constraints based on the current environment, organizational
factors, historical data, and expert judgment, in order to propose an implementation strategy. Refer to
PMP Exam Content Outline ( Domains ) in the initiation phase. Task no 4

Question: 179 Correct

You have just learned that your project's sole equipment supplier
has gone out of business. It is an unanticipated risk and will
cause a delay in the project until a new vendor can be selected
and contracts put in place. What do you do?

EXAM 01/200 QA
Explanation
Important aspects of project scope control include determining the cause and degree of variance relative
to the scope baseline and deciding whether corrective or preventive action is required. PMBOK 6th
edition Page, 170

Question: 181
Correct

A multinational company with a cross-border project wants to


implement new software that will impact several departments.
The project manager needs to guarantee alignment of
stakeholder expectations with the final product. What should the
project team develop?

Stakeholder engagement plan.

Project statement of work (SOW).

Stakeholder engagement assessment matrix.

Risk breakdown structure (RBS)

Explanation
The stakeholder engagement plan identifies the management strategies and actions required to
effectively engage stakeholders.The stakeholder engagement plan provides
guidance and information on
managing stakeholder expectations.The stakeholder engagement plan include specific strategies or
approaches for engaging
with individuals or groups of stakeholders. PMBOK 6 edition page, 509 , 522

Question: 182
Correct

EXAM 01/200 QA
You are a Project Manager working on a project to create high-
efficiency electric motors for a company introducing a new
electric golf cart. Your company's president is keenly interested
in the project and requests a chart that shows the number of
defects per deliverable and ranking of the causes of defects.
Which type of chart would BEST meet this request?

Histograms

Control chart

Statistical sampling

Scatter diagram

Explanation
Histograms show a graphical representation of numerical data. Histograms can show the number of
defects per deliverable, a ranking of the cause of defects, the number of times each process is
noncompliant, or other representations of project or product defects. [PMBOK 6th edition, Page 293]

Question: 183 Correct

During a project review meeting, the project manager observes


that one team member performed tasks beyond the scope of
work. What should the project manager do?

EXAM 01/200 QA
Procurement audit

Inspection and audit

Performance Review

Explanation
If you make Make or buy decision in planning procurement, you could prevent this situation. [PMBOK 6th
edition, Page 473]

Question: 185
Correct

During the implementation phase, you are informed that one of


the suppliers who is working on your project has taken another
project. As a project manager, what should you do next?

Performance review

Procurement review

Change management plan

Remove the supplier from your project.

Explanation
Performance reviews for contracts measure, compare and analyze quality, resource, schedule, and cost
performance against the agreement. This includes identifying work packages that are ahead or behind
schedule, over or under budget or have resource or quality issues. [PMBOK 6th edition, Page 498]

EXAM 01/200 QA
Question: 186
Correct

A supplier delivers equipment that fails to meet customer


requirements. Investigations determines that the supplier
misunderstood the requirements and make incorrect
assumptions without clarifying them with the customer. What
communication methods should the project manager have used
to avoid this?

Interactive

Push

Pull

Active listening.

Explanation
( Interactive communication ) is The best communication methods can be using to avoid the supplier
misunderstood the requirements with the customer.

Question: 187 Correct

A project manager wants to confirm that the project team

EXAM 01/200 QA
Do nothing

Update the project management plan

Update the change log

Explanation
Since the team members implemented a change request without through the CCB, as a project manager
you should send the change to CCB for approval. .

Question: 189
Correct

During the testing phase, your engineering team implemented a


solution to correct a defect they discovered. The solution didn't
have an impact on cost or time. You know the case now; as a
Project manager your action should be:

Add the corrective action to a Lessons learned register

Update management plans

Escalate the team member who did the action without letting you know

Issue a change request to CCB

Explanation

EXAM 01/200 QA
The lessons learned register is updated with information on the source of quality defects and how they
could have been avoided as well as approaches that worked well. [PMBOK 6th edition, Page 306]

Question: 190
Correct

You are in the planning process of an R1b project. You realize


that your schedule requires more resources in certain months of
the project than what are available to you. Your senior
management has clearly instructed that you will not be able to
obtain additional resources for the project. So, you instruct your
planner to adjust the schedule to accommodate these
constraints. What are you instructing the planner to do?

Resource leveling

Crashing

Fast tracking

Evaluation and Review Technique

Explanation
Resource leveling. A technique in which start and finish dates are adjusted based on resource
constraints with the goal of balancing the demand for resources with the available supply. [PMBOK 6th
edition, Page 211]

Question: 191
Correct

EXAM 01/200 QA
A recently promoted project manager must facilitate the weekly
status update meeting. What should the project manager do to
ensure a productive meeting?

Circulate a defined agenda in advance

Limit attendance to the project team and stakeholders

Avoid or smooth over any disagreements

Carefully read the latest meeting minutes

Explanation
This question is a good example of the type questions that will be encountered on the real exam.
Meeting
management is taking steps to ensure meetings meet their intended objectives
effectively and efficiently.
The following steps should be used for meeting planning:
** Prepare and distribute the agenda stating the
objectives of the meeting.
** Ensure that the meetings start and finish at the published time.
** Ensure the
appropriate participants are invited and attend.
** Stay on topic.
** Manage expectations, issues, and
conflicts during the meeting.
** Record all actions and those who have been allocated the responsibility
for completing the action.
PMBOK 6th edition page, 386

Question: 192 Correct

While you are in one of the first meetings for your new project
that you have been assigned to early, two team members were
discussing new ideas that each one thinks is correct and their

EXAM 01/200 QA
opinion is the best for the project. You didn't interact or cut the
discussion, as you know this is a normal discussion in this
phase, which is?

Storming

Norming

Performing

Supporting

Explanation
Storming. During this phase, the team begins to address the project work, technical decisions, and the
project management approach. If team members are not collaborative or open to differing ideas and
perspectives, the environment can become counterproductive. [PMBOK 6th edition, Page 338]

Question: 193
Correct

A project manager develops a business case during project


initiation. What area should the project manager consider when
developing the business case?

Business benefits provided by project deliverables and the organizational strategy.

EXAM 01/200 QA
Business benefits provided by project deliverables and portfolio analysis .

Expected resource performance and the project’s contribution to the strategic portfolio
objectives.

Expected resource performance and cost-benefit analysis.

Explanation
When developing the business case, the project manager should consider the business benefits provided
by project deliverables and the organizational strategy. Conduct benefit analysis with relevant
stakeholders to validate project alignment with organizational strategy and expected business value.
PMP Exam Content Outline in Initiation Task no ( 7 )

Question: 194
Correct

A project manager wants to recruit another team member to


replace an architect who resigned. What document should
capture this change?

Responsibility assignments matrix (RAM)

Organizational process Assets.

Project management plan.

Ground rules

Explanation

EXAM 01/200 QA
RAMs are used within the group to designate roles,
responsibilities, and levels of authority for specific
activities. The matrix format shows all activities associated
with one person and all people associated
with one activity. This also ensures that there is only one person
accountable for any one task to avoid
confusion about who is ultimately in charge or has authority for the work. PMBOK 6th edition Page, 317

Question: 195
Correct

You are Creating a network diagram for your project.


Activity A (5
days ) can start immediately. Activity B ( 3 days ) can start after
Activity A is complete.
Activity C ( 2 days ) can start after Activity
B is complete.
Activity D (4 days ) can start after Activity A and B
are complete.
Activity E ( 3 days ) can start after Activity C and D
are complete.
While having all Activities as FS relation, what is
the Float of Activity D?

0 Day

2 Day

1 Day

3 Day

Explanation
After drawing the network, you will determine that Activity D on the Critical Path. So the float = zero

Question: 196
Correct

EXAM 01/200 QA
The project manager has a project that is three months behind
but is surprisingly markedly under budget.
She has decided to try
to make up time, but needs to minimize the project risk. What is
the best thing to do?

Crash the project

Fast track the project

Redefine the scope

Perform resource levelling

Explanation
Crashing (adding resources) may be done as the project is within budget and crashing usually incurs an
extra cost. Fast-tracking will increase the risk therefore not an option.

Question: 197
Correct

Based on the following table, which of the following activities will


be within the budget and behind schedule?

EXAM 01/200 QA
Activity A

Activity B

Activity C

Activity D

Explanation
To solve this question, you should calculate the CV and SV for all activities:
Activity A: CV=EV-AC (
7000-7000 = 0 ) & SV= EV-PV ( 7000-8000 = -1000 ) so the project is within budget and behind schedule
. Activity B: CV=EV-AC ( 10,000-9000 = 1000 ) & SV= EV-PV ( 10,000-9000 = 1000 ) so the project is
under budget and ahead of schedule . Activity C: CV=EV-AC ( 9,000 - 8500 = 500) & SV= EV-PV ( 9,000
- 8000 = 1000 ) so the project is under budget and ahead of schedule . Activity D: CV=EV-AC ( 8,000 -
11,000 = -3000) & SV= EV-PV ( 8,000 - 11000 = -3000 ) so the project is over budget and behind
schedule .
SO the Correct answer is Activity A

Question: 198 Correct

During the planning phase of your project, the project and


product requirements have been identified by the project team
members. Which of the following were used to accomplish this?

EXAM 01/200 QA
Observations conversations,benchmarking and affinity diagram

Mind mapping, affinity diagram and Brainstorming

Observations conversations, trend analysis and work breakdown structure (WBS)

Network diagram,Benchmarking, and project scope statement.

Explanation
You can easily remove two options that include Network diagram and WBS. Also, Mind mapping and
Brainstorming both used to generate new ideas so not a good choice. So the best answer to identify the
project and product requirements are Observations conversations, benchmarking, and affinity diagram.
PMBOK 6th edition page, 142

Question: 199
Correct

You are a project manager for a project and you have received an
acceptance of project deliverables and held the lessons learned
session. To close the project, what should you do next?

Update the organizational process Assets.

Validate the scope.

Release the resources.

EXAM 01/200 QA
Conduct performance evaluation.

Explanation
The project manager has received an acceptance of project deliverables and held the lessons learned
session so the validate scope process and Conduct performance evaluation have finished. Release the
resources is the next step after update OPA.

Question: 200
Correct

The project charter has been signed, and a project management


plan is in place. What should the project manager do next?

Assign the project team.

Develop the project schedule

Team-building activities

Meet with the project sponsor.

Explanation
The project charter has been signed and the project management plan is in place, this mean that the
initiating and planning phase is finished and the next process is the execution phase. So, Assign the
project team is the Correct answer.