SMJI CONSTRUCTION

Porp : P.S.SIVAGANANAM
CIVIL ENGINEERING CONACTORS
NO.100/A, NEHAJI NAGAR,1ST STREET,
TONDIARPET,CHENNAI - 600 081
(RS.in 'LAKHS
PROJECTED BALANCE SHEET AS ON 31ST MARCH

LIABILITIES 2022 2023 2024 ASSETS 2022 2023 2024


CAPITAL ACCOUNT: FIXED ASSETS:
P.S.SIVAGANANAM TWO WHELLER
Balance 87.65 91.04 103.60 Dep 15% 1.75 1.51 1.29

NET PROFIT 6.19 9.76 16.85 LAND & BUILDING 9.56 9.56 9.56
93.84 100.80 120.45 BUILDING & CONSTRUCTIONS 18.60 18.60 18.60
DRAWINGS -2.80 (2.80) (2.80) LAND PURCHASED 49.10 49.10 49.10
91.04 103.60 123.25

SECURED LOAN: ADVANCE & DEPOSIT ; -


DEENA BANK OD 142.38 142.38 148.38 SALES TAX DEPOSIT 0.2 0.2 0.2
BANK OF BARODA LOAN 15.85 23.35 19.81 TELEPHONE DEPOSIT 0.3 0.3 0.3
MADRAS VETERINARY COLLAGE 4.00 4.00 4.00
EXE.ENGINEER JUNURM DEVISION 4.00 4.00 4.00
EXE.ENGINEER SLUM DEVISION 9.00 9.00 9.00

RETENTION MONEY REICVABLE 69.21 69.21 69.21


Outstanding Expenses TDS RECIVABLE 7.52 7.52 7.52
AUDIT & ACCOUNTING FEES 0.50 0.50 0.50 RETENTION MONEY 2022 -23 2.51 2.51 2.51
RETENTION MONEY 2023 -24 3.80 3.80 3.80
RETENTION MONEY 2024- 25 7.52 7.52 7.52
TDS 2022 -23 1.02 1.02 1.02
TDS 2023 -24 1.53 1.53 1.53
TDS 2024 -25 3.04 3.04 3.04
BILLS REICVABLE 41.04 76.75 98.69
AXIS BANK AC NO : 4504707 0.14 0.24 0.38
CASH IN HAND 0.08 0.42 0.67

TOTAL 233.92 269.83 291.94 TOTAL 233.92 269.83 291.94


NOTE: OUTSTANDING EXPENSES INCLUES IN SUNDRY CREITORD PAYABLE IN SUBSQUENT PERIOD
SMJI CONSTRUCTIONS
Prop : P.S.SIVAGANANAM
CIVIL ENGINEERING CONACTORS
NO.100/A, NEHAJI NAGAR 1ST STREET,
TONDIARPET,CHENNAI - 600081
PROJECTED TRADING AND PROFIT AND LOSS ACCOUNT
FOR THE YEAR ENDED 31st MARCH 2022 AND 2024.. Rs.in lakhs
PARTICULARS 2,022 2,023 2,024 PARTICULARS 2,022.00 2,023 2,024

TO Purchases 48.00 65.00 155.00 BY Contract receipts 100.00 150.00 300.00

" Labour Charges 29.52 46.25 82.82

" Repair & Maintance 0.42 0.70 0.90

" Site Expenses 0.94 1.61 2.01

" Bank Charges 0.18 0.49 0.60

" Interest on OD & Tream 0.84 2.75 3.18

" Postage & Couier 0.04 0.09 0.10

" Printing & Stationery 0.07 0.10 0.26

" C GST 6.14 9.14 18.00

" S GST 6.14 9.14 18.00

" Audit Fees 0.25 0.25 0.25

" Accounting Charges 0.25 0.25 0.25

" Transport Charges 0.72 4.21 1.56

" Depreciation 0.30 0.26 0.22

" NET PROFIT 6.19 9.76 16.85

TOTAL 100.00 150.00 300.00 TOTAL 150.00 300.00

note: Expenses are projected to near one lakh by clubbing other expenses