EIA Report Dera Murad Jamali Bypass On N 65
EIA Report Dera Murad Jamali Bypass On N 65
EIA Report Dera Murad Jamali Bypass On N 65
Ministry of Communications
National Highway Authority
ENVIRONMENTAL IMPACT
ASSESSMENT REPORT
(February, 2018)
Table of Contents
1. INTRODUCTION.......................................................................................................... 1-1
1.1 GENERAL .......................................................................................................... 1-1
1.2 PROPONENT OF THE PROJECT ...................................................................... 1-1
1.3 PROJECT BACKGROUND ................................................................................ 1-1
1.4 THE PROJECT ................................................................................................... 1-2
1.5 NECESSITY ....................................................................................................... 1-2
1.6 OBJECTIVES OF THE PROJECT ...................................................................... 1-2
1.7 PROJECT WORKS ............................................................................................. 1-2
1.8 PROJECT CATEGORISATION ......................................................................... 1-3
1.9 STANDARDS AND GUIDELINES .................................................................... 1-3
1.10 THIS REPORT .................................................................................................... 1-3
2. POLICY, LEGISLATION AND GUIDELINES ........................................................ 2-1
2.1 Introduction ......................................................................................................... 2-1
2.2 National Environmental Policy, Legislation and Guidelines ................................. 2-1
2.2.1 National Environmental Policy, 2005 ............................................................. 2-1
2.2.2 National Sanitation Policy, 2006 .................................................................... 2-2
2.2.3 National Climate Change Policy, 2012 ........................................................... 2-2
2.2.4 National Resettlement Policy, 2002................................................................ 2-3
2.2.5 National Conservation Strategy ...................................................................... 2-3
2.2.6 Biodiversity Action Plan (BAP) ..................................................................... 2-3
2.2.7 Pakistan Environmental Protection Act, 1997................................................. 2-3
2.2.8 Review of IEE and EIA Regulations, 2000..................................................... 2-4
2.2.9 National and International Environmental Quality Standards ......................... 2-4
2.2.10 Conduct of an EIA ......................................................................................... 2-4
2.2.11 Approval from Baluchistan Environmental Protection Agency....................... 2-5
2.2.12 Project Monitoring and Compliance ............................................................... 2-6
2.2.13 Effluent and Emission Self-Monitoring and Reporting ................................... 2-6
2.2.14 Baluchistan Wildlife Protection Act, 1974 ..................................................... 2-7
2.2.15 Canal and Drainage Act, 1873........................................................................ 2-7
2.2.16 The Forest Act, 1927...................................................................................... 2-8
2.2.17 Antiquities Act, 1975 ..................................................................................... 2-8
i
Table of Contents
ii
Table of Contents
iii
Table of Contents
iv
Table of Contents
v
Table of Contents
List of Figures
vi
Table of Contents
List of Tables
vii
Executive Summary
EXECUTIVE SUMMARY
1 INTRODUCTION
The submission of EIA and its approval from Environmental Protection Agency (EPA)
is mandatory according to Pakistan Environmental Protection Act (PEPA), 1997.
Section 12 (1) of the PEPA-1997 which states that:
“No proponent of a Project shall commence construction or operation unless he
has filed with the Federal Agency an initial environmental examination or,
where the Project is likely to cause an adverse environmental effect, an
environmental impact assessment, and has obtained from the Federal Agency
approval in respect thereof.”
PEPA-1997 is the apex law for mandatory EIA before project construction. The Act
was promulgated on December 06, 1997 by repealing the Pakistan Environmental
Protection Ordinance of 1983.
Three alternatives were considered for the proposed project namely 1)Option I, RD
112+800 to RD 125+450 (Western Side); 2) Option II, RD 112+800 to RD 129+450
(Western Side) 3) Option III, RD 112+800 to RD 125+550 (Eastern Side). Based on the
suitability of meeting of the project objectives and environmental and social benefits,
Alternative-3 was selected for the smooth traffic flow at Dera Murad Jamali.
Accordingly, the proposed Bypass along with the construction of bridge on Put Feeder
Canal was planned. The total cost of the proposed Project is 1,606,251,177 as per
Engineer‟s Estimate
viii
Executive Summary
In order to access the vehicle-wise traffic volumes, the Design Consultant undertook
classified 24 hours continuous traffic count surveys for three days in February 2017.
Traffic counts were done at the start of Dera Murad Jamali for various types of vehicles
plying in different directions.
The existing environmental conditions around the proposed project (falls in district
Nasirabad) were considered with respect to physical, biological and socio-economic
aspects. With the exception of the eastern side of the Dera Murad Jamali, the district
Nasirabad is a flat plain. There is nothing of geological significance in the district
which is entirely situated on alluvium.
The main types of soil in the district are Gora, Rohi, Doshai, Maira, Tibba, Kallar and
Bela or the raverine soil. The major land use in the project area is residential &
commercial. The climate of the Nasirabad district is hot and dry during summer and
moderately cold in winter. June is the hottest month with mean maximum and
minimum temperature of 50ºC and 27ºC respectively. The mean maximum and
minimum temperatures during January are 23ºC and 5ºC respectively. The average
annual rainfall in the district during 1961-98 is about 628.7 millimetres. The ambient
air quality monitoring of carbon monoxide (CO), sulfur dioxide (SO2), nitrogen
dioxide (NO2) and particulate matter (PM10) was carried out at Dera Murad Jamali.
All values are well within the permissible limits of their respective standards. Ground
water sample was collected from a hand pump at Dera Murad Jamali near management
office and was analyzed for microbiological and chemical parameters. All the physical,
chemical and biological parameters are well within prescribed limits. Chemical analysis
of sample of surface water from Put Feeder Canal indicated the presence of total
suspended solids as 200 mg/l, the Grease & oil content as 10 mg/l, chloride content as 1
mg/l and pH value as 6.9. The values of BOD, COD and TSS are higher than the
permissible limits of respective standards. The measured noise level values are in
compliance with national Environmental Quality Standards for commercial area i,e. 60
db (A). According to building code of Pakistan prepared by NESPAK, it is located in
Seismic Zone-2A of Pakistan (Lower limit of moderate damage).
Amaltas, Shisham, Kikar, Pipal, Banyan, Mulberry, Aam, Sirris and Lasura are the
common floral species of the project area. Wild bore is fairly common in Nasirabad
District and in the riverine area. Black buck, riverine deer, and hog deer are sometimes,
though rarely found in the Belas around project area. Hare and jackal are fairly
common all over the Nasirabad District. No wild life sanctuary or game reserve
(Critical Habitats), exists near the project area.
ix
Executive Summary
spoken by majority (97.3 percent) of the population of the district. The leading tribes
living in the project area are Abro, Jamali, Sasoli, Umrani & Blouchi. The
economically active population as enumerated in the last census is 4.18 percent of the
total population. There was no family identified during the survey that belongs to
indigenous people category.
5 PUBLIC CONSULTATION
Due to security alert of the area, public consultation was carried out on individual basis
under police squad in this project area with the instructions that limited conversations
should be done. The consultation process was carried out in accordance with the
requirements of Pakistan Environmental Procedures. Main objective of the consultation
was to share information with stakeholders on the construction of the proposed Bypass
and expected impacts on the physical, biological and socio-economic environment of
the project area. During the field survey different stakeholders identified were the
shopkeepers, local residents, office workers, drivers, schools, transport users and
pedestrians etc. The most commonly raised concerns during the meetings include
avoiding dumping construction material openly, control of dust and noise pollution,
scheduled sprinkling of water, minimize the cutting of trees, and proper compensation
for the loss of properties etc.
The project corridor is delineated according to two criteria: Right of Way (RoW);
which the NHA is legally entitled to, and Corridor of Impact (CoI), i.e., the width of the
corridor that will be impacted, directly or indirectly, by the project during the
construction and operation phases. Implementation of the project will require total
671,453.6 sq. m (26547.12) of land. It will also result in relocation of 19 houses, 182
trees of varying species and sizes, on both sides of the project. It is proposed that 728
trees of suitable species shall be planted along the Bypass at available spaces.
x
Executive Summary
As the project deals with the construction of the Bypass, so no hazardous waste will be
generated during the construction. Due to construction activities waste will be
generated at construction and contractors camp sites. The waste generated from the
camp sites will be disposed off through Municipal Committee. There are chances of
arising of issues related to cultural differences/conflicts between the contractor‟s
workforce and the local inhabitants, conflicts arising due to the mix of local and
migratory job seekers as the use of local resources and products will be increased.
Mitigation measures include timely and full public consultation and announcement of
mobilizing equipment. Borrow areas/ open pits and their excavation activities may
result in land disputes, soil erosion, loss of potential cropland, loss of vegetation,
landscape degradation, and damage to road embankments. Mitigation will involve
careful selection of the borrow areas, no excavation will be allowed within 300 meters
from both sides of the road and regular checking of soil erosion along the borrow areas
etc.
During the operation stage, raising of new trees at available spaces will have a positive
impact of permanent nature. With the improved flora of the project area, due to raising
of large number of trees, the fauna and especially the avi-fauna shall be attracted to the
area. No major adverse impact on groundwater is anticipated during the operational
phase. With the construction of Bypass, the traffic congestion will be reduced and the
traffic passing through Dera Murad Jamali will move in a smooth flow from the
Bypass; thereby reducing the emission levels in the city. After the construction of
proposed Bypass, the landscape of the project area will be changed in terms of road
infrastructure and planned plantation of trees.
xi
Section 1 Introduction
SECTION 1
1.INTRODUCTION
1.1 GENERAL
National Highway Authority (NHA) has taken a proactive step to conduct the
Feasibility study for construction of Bypass over N-65 at Dera Murad Jamali.
Accordingly, NHA has assigned this project to M/s Asif Ali Associates (Pvt.) Ltd. in
association with M/s AA Associates & M/s Turkpak International (Pvt.) Ltd. to carry
out this Feasibility Study.
National Highway Authority (NHA) is the proponent of the proposed Project with the
following address:
National Highway Authority
27 Mauve Area, G-9/1, Islamabad
Ph: 051-9260565
Advisor to Chief Minister of Baluchistan Mr. Mir Abdul Majid Abro vide letter No.
Adv/CM/IPC & Zakat/l5/183 dated 21st January 2015 requested to Chairman National
Highway Authority for construction of a bypass at Dera Murad Jamali on N-65 District
Nasirabad in province of Baluchistan.
On direction of Chairman NHA, Maintenance unit NHA Sibi conducted survey of the
project site and three alignment options were proposed. Detail is given as under:
i. The first alignment extends form N-65 at RD 112+800 to RD 125+450
having a length of 12.65 km. This alignment will bypass the city of Dera
Murad Jamali from western side. The proposed alignment of bypass will
terminate exactly in front of Uch Power Plant at RD 125+450.
ii. The second alignment of proposed bypass starts from the same starting point
as indicated above but it will be terminated at RD 129+450 having length of
16.65 km. The proposed alignment will pass behind the Uch power Plant
without causing any trouble to the entrance of this Power Plant.
iii. The alignment of this bypass starts 2 Km before Dera Murad Jamali, at RD
112+800 heading towards Eastern side of Dera Murad Jamali. The
alignment crosses railway crossing immediately after start point and
traverses through open fields. The alignment crosses Put Feeder Canal
approximately 2.2 Km away from existingN-65.The alignment crosses Foliji
road and again railway crossing and finally terminates in front of Uch
Power Plant at RD 125+550.
Subsequently, M/s Asif Ali & Associates (Pvt.) Ltd in association with M/s A.A
Associates (Pvt.) Ltd & M/s Turkpak International (Pvt.) Ltd have been appointed as
the Consultants by NHA to provide consultancy services for “Feasibility Study,
Environmental Impact Assessment & Detailed Design of Dera Murad Jamali Bypass”.
Contract Agreement between National Highway Authority (NHA) and the Consultants
was signed on August 08, 2016 for providing the aforesaid consultancy services.
1.5 NECESSITY
Dera Murad Jamali is located on N-65. Dera Murad Jamali is the main city of District
Nasirabad and traffic on N-65 passes through the entire city of Dera Murad Jamali.
Although a Railway track also runs parallel to the road, yet due to heavy flow of traffic,
the road always gets blocked and VIP / emergency vehicular movement gets trapped in
the heavy flow of traffic in the middle of the city. Threats of insecurity for VIPs also
prevail. Traffic accidents due to congested traffic flow, which result in loss of precious
lives, are commonly faced. Construction of this bypass will facilitate in two ways:-
Firstly, it would lessen the traffic congestion for the intercity / through traffic.
Secondly, the proposed bypass will give relief to the inhabitants of Dera Murad
Jamali from heavy traffic congestions, blockage and road accidents.
The scheme envisages the construction of a bypass at Dera Murad Jamali on N-65 in
District Nasirabad of Baluchistan province including a canal bridge over Put Fedder
Canal as per NHA standards and specifications. Road furniture comprising of lane
markings, traffic signs, guardrails and reflectors as per site requirement shall also be
provided.
The scope of work and Terms of Reference which broadly covers but limited to the
following:
Feasibility Study.
Detailed Design (keeping in view the present & future generated traffic).
Tender Drawings and Documents.
Environmental Impact Assessment (EIA) Study.
Land Acquisition (if required) &Utilities folders.
As per EPA Guidelines, the present Project is classified as “Schedule II” that requires
an EIA study and approval from the concerned authority, prior to the construction.
SECTION 2
2.POLICY, LEGISLATION & GUIDELINES
2.1 INTRODUCTION
The National Environmental Policy (NEP) was approved by the PEPA in its
10th meeting on 27th December 2004 under the chairmanship of the Prime
Minister of Pakistan and thereafter approved by the Cabinet on 29th June 2005.
NEP is the primary policy of Government of Pakistan that addresses the
environmental issues of the country. The broad Goal of NEP is, “To protect,
conserve and restore Pakistan‟s environment in order to improve the quality of
life of the citizens through sustainable development”. The NEP identifies the
following set of sectoral and cross-sectoral guidelines to achieve its Goal of
sustainable development.
a) Sectoral Guidelines:
Water and sanitation, Air quality and noise, Waste management, Forestry,
Biodiversity and Protected areas, Climate change and Ozone depletion,
Energy efficiency and renewable, Agriculture and livestock, and Multilateral
environmental agreements.
b) Cross-sectoral Guidelines:
NEP is a policy document and does not apply to projects. However, the
proponent should ensure that the project should not add to the aggravation of
the environmental issues identified in NEP and mitigation measures should
be adopted to minimize or avoid any contribution of the project in these
areas.
The National Climate Change Policy was approved by the Federal Cabinet on
26 September 2012. With an overall goal, to ensure that climate change is
mainstreamed in the economically and socially vulnerable sectors of the
economy and to steer Pakistan towards climate resilient development, the Policy
puts forward comprehensive policy objectives of sustained economic growth,
integration of climate change into inter-related national policies, pro-poor
gender sensitive adaptation and cost-effective mitigation, water, food and energy
security, DRR, effective decision making and coordination, creating awareness,
building capacities, and conservation of natural resources and long term
sustainability. It also seeks effective use of financial opportunities, and public
and private sector investment in adaptation measures.
Before the approval of NEP, the National Conservation Strategy (NCS) was
considered as the Government‟s primary policy document on national
environmental issues. At the moment this strategy just exists as a national
conservation program. The NCS identifies 14 core areas including conservation
of biodiversity; pollution prevention and abatement; soil and water conservation;
and preservation of cultural heritage, and recommends immediate attention to
these core areas in order to preserve the country‟s environment.
The proponent should ensure that the project should not add to the aggravation
of the 14 core environmental issues identified in the NCS and mitigation
measures should be adopted to minimize or avoid any contribution of the project
in these areas.
The Biodiversity Action Plan (BAP), which has been designed to complement
the NCS and the proposed provincial conservation strategies, identifies the
causes of biodiversity loss in Pakistan and suggests a series of proposals for
action to conserve biodiversity in the country.
The BAP recognises that an EIA is used as a tool at a project level to identify
environmental effects of a proposed project and to plan for reducing adverse
effects. The BAP further stipulates that an EIA needs to be initiated at an early
stage of project development and that public participation in the review of
potential effects is important.
The Pak-EPA Review of IEE and EIA Regulations, 2000 (the „Regulations‟),
prepared by the Pak-EPA under the powers conferred upon it by the PEPA,
provide the necessary details on the preparation, submission, and review of IEE
and EIA.
As per Schedule-A for policy and procedures for the filing, review and approval
of environment assessments the proposed project falls under the list of projects
which require an EIA. The projects in Schedule-A are generally major projects
and have the potential to affect a large number of people. The impacts of such
projects may be irreversible and could lead to significant changes in land use
and the social, physical and biological environment. The preparation of this
EIA satisfies the requirement of the 2000 Regulations.
As per the 2000 Regulations, the proponent will be required to submit the EIA
report to Baluchistan Environmental Protection Agency (BEPA) and seek
approval on the same from BEPA. The EIA report will need to be submitted to
BEPA. BEPA will grant its decision on the EIA as per the rules and procedures
set out in the 2000 Regulations. The following rules apply.
A fee is payable to BEPA for review of the EIA.
The EIA submittal is to be accompanied by an application in the format
prescribed in Schedule IV of the 2000 Regulations.
BEPA is bound to conduct a preliminary scrutiny and reply within 10 days
of the submittal of the report a) confirming completeness, or b) asking for
additional information, if needed.
BEPA will publish a public notice in any English or Urdu national
newspaper and in a local newspaper of general circulation in the area
affected by the project. The public notice will mention the following:
The date set for public hearing will not be earlier than 30 days from the
date of publication of the public notice.
In the review process, BEPA may consult a Committee of Experts, which
may be constituted on the request of the Director General (DG) BEPA.
On completion of the review process and the public hearing, the decision
of BEPA will be communicated to the proponent in the form prescribed in
Schedule VI.
Where an EIA is approved, BEPA can impose additional controls as part
of the conditions of approval.
BEPA is required to make every effort to complete the EIA review process
within 90 days of the issue of confirmation of completeness. However,
BEPA can take up to 4 months for communication of final decision.
The approval will remain valid for the project duration mentioned in the
EIA but on the condition that the project commences within a period of
three years from the date of approval. If the project is initiated after three
years from approval date, the proponent will have to apply for an
extension in the validity period. The BEPA on receiving such request may
grant extension (not exceeding 3 years at a time) or require the proponent
to submit a fresh EIA if in the opinion of BEPA changes in baseline
conditions or the project so warrant.
These rules authorise the Federal EPA and its authorised persons to obtain
and test samples from industries to verify self-monitoring reports and
calculation of pollution charges.
The ordinance also specifies three broad classifications of the protected areas:
national parks, wildlife sanctuaries and game reserves. Activities such as
hunting and breaking of land for mining are prohibited in national parks, as are
removing vegetation or polluting water flowing through the park. Wildlife
sanctuaries are areas that have been set aside as undisturbed breeding grounds
and cultivation and grazing is prohibited in the demarcated areas. Nobody is
allowed to reside in a wildlife sanctuary and entrance for the general public is by
special dispensation. However, these restrictions may be relaxed for scientific
purpose or betterment of the respective area on the discretion of the governing
authority in exceptional circumstances. Game reserves are designated as areas
where hunting or shooting is not allowed except under special permits.
The project is located outside of any wildlife protected area therefore the project
will not contravene with any provisions of this Act.
Canals are defined as channels, pipes and reservoirs constructed and maintained
by the Government for the supply for storage of water. Under section 27 of the
Act a person desiring to have a supply of water from a canal for purposes other
than irrigation shall submit a written application to a Canal Officer who may,
with the sanction of the Provincial Government give permission under special
conditions. The Act under section 61 also prohibits the damaging, altering,
enlarging or obstructing the canals without proper authority.
The Canal and Drainage Act (1873) prohibits corruption or fouling of water in
canals (defined to include channels, tube wells, reservoirs and watercourses), or
obstruction of drainage.
Although the Surrounding area has the presence of irrigation network, however
the project activities will be limited and will not cause any physical damage to
the canals. Similarly as the project is designed as a no discharge facility, there
will be no alteration in water quality.
The act empowers the provincial forest departments to declare any forest area as
reserved or protected. The act also empowers the provincial forest departments
to prohibit the clearing of forest for cultivation, grazing, hunting, removing
forest produce; quarrying and felling, lopping and topping of trees, branches in
reserved and protected forests. The project area is located outside any reserved
or protected forest area therefore the project will not contravene with any
provisions of the Act
The project site was screened by the EIA study team; nothing of any
archaeological interest was identified at the project site.
The Pakistan Penal Code (1860) authorises fines, imprisonment or both for
voluntary corruption or fouling of public springs or reservoirs so as to make
them less fit for ordinary use.
The guidelines on policy and procedures define the policy context and the
administrative procedures that will govern the environmental assessment
process, from the project pre-feasibility stage, to the approval of the
environmental report. According to the procedures laid out in the policy
guidelines, IEE‟s or ElA‟s are to be filed with the EPA of the province
where the project is to be implemented. The federal EPA has, however, been
given the right to review any environmental report at any time and the power
to revoke the decision of the provincial EPA, if it deems this to be necessary.
Projects have been classified in the policy guidelines by expected degree of
adverse environmental impacts. All projects proposed in environmentally
sensitive areas (including Game Reserves and Wildlife sanctuaries) require
an EIA.
The Procedures require proponents to prepare terms of reference for the
environmental assessment reports. They require that all EIA studies should
contain baseline data on the area and must contain a detailed assessment of
the potential environmental impacts and the recommended mitigation
measures. Consultations with the communities that are most likely to be
affected as well as relevant NGO‟s are to be an integral part of the EIA
process.
The guidelines on public consultation deals with possible approaches to
public consultation and techniques for designing an effective program of
consultation that reaches out to all major stakeholders and ensures the
incorporation of their concerns in any impact assessment study.
Guidelines for Solid Waste Management have been issued as a draft by the
Pakistan Environmental Protection Agency in coordination with JICA and
UNDP. These guidelines explain the waste generation, discharge and
composition.
This states the penalties for violations concerning pollution of air, water
bodies and land.
Subject to the provisions of this Act, and the rules and regulations, no person
shall operate a motor vehicle from which air pollutants or noise are being
emitted in an amount, concentration or level which is in excess of the
National Environmental Quality Standards, or where applicable the
standards customary under clause (g) of sub-section (I) of section 6.
The Clean Air Act legislation aims to control vehicular emissions, pollution
from industry and indoor air pollution in rural areas.
This act deals with the procurement of private properties for public
purposes. There are 55 sections in this act mainly dealing with area
notifications, surveys, acquisition, compensation, appointment awards,
dispute resolution, penalties and exemptions.
Article 25 lays down the right to equality before the law and prohibition
of discrimination on the grounds of sex alone; and
Article 37(e) makes provision for securing just and humane conditions
of work, ensuring that children and women are not employed in
vocations unsuited to their age or sex, and for maternity benefits for
women in employment.
The red list is published by IUCN and includes those species that are under
potential threat of extinction. These species have been categorized as
Endangered: species that are sent to be facing a very high risk of
extinction in the wild in the near future, reduction of 50% or more
either in the last 10 years or over the last three generations, survive
only in small numbers, or have very small populations.
Vulnerable in Decline: species that are seen to be facing a risk of
extinction in the wild, having apparent reductions of 20% or more in
the last 10 years or three generations.
Vulnerable: species that are seen to be facing a high risk of extinction
in the wild, but not necessarily experiencing recent reductions in
population size.
Lower Risk: species that are seen to be facing a risk of extinction that
is lesser in extent that for any of the above categories.
Data Deficient: species that may be at risk of extinction in the wild but
at the present time there is insufficient information available to make a
firm decision about its status.
Two species Greater spotted eagle and White eyed Pochard observed in the
project area are listed in IUCN Red List 2006. White eyed Pochard, which is
a migratory species listed on Appendix-II of CMS and categorized as Near
Threatened (NT) species in IUCN Red List 2006 was observed at the
evaporation pond.
The first two publications listed here provide general guidelines for the
conduct of an EIA, and address the EIA practitioners themselves as well as
project designers. While the Sourcebook in particular has been designed
with Bank projects in mind, and is especially relevant for the impact
assessment of large-scale infrastructure projects, it contains a wealth of
information which is useful to environmentalists and project proponents.
The Sourcebook identifies a number of areas of concern, which should be
addressed during impact assessment. It sets out guidelines for the
determination of impacts, provides a checklist of tools to identify possible
biodiversity issues and suggests possible mitigation measures. Possible
development project impacts on wild lands, wetlands, forests etc. are also
identified and mitigation measures suggested. The Sourcebook also
highlights concerns in social impact assessment, and emphasizes the need to
incorporate socio-economic issues in EIA exercises.
The EHS guidelines are technical reference documents with general and
industry-specific examples of Good International Industry Practice (GIIP).
These guidelines contain the performance levels and measures that are
generally considered to be achievable in new facilities by existing
technology at reasonable costs. Application of the EHS Guidelines to
existing facilities may involve the establishment of site-specific targets,
based on environmental assessments and/or environmental audits as
appropriate, with an appropriate timetable for achieving them.
The EHS guidelines for thermal power plants were published in December
2008 and include information relevant to combustion processes fueled by
gaseous, liquid and solid fossil fuels and biomass and designed to deliver
electrical or mechanical power, steam, heat, or any combination of these,
regardless of the fuel type (except for solid waste which is covered under a
separate Guideline for Waste Management Facilities), with a total rated heat
input capacity above 50 Megawatt thermal input (MWth) on Higher Heating
Value (HHV) basis. It applies to boilers, reciprocating engines, and
combustion turbines in new and existing facilities. A detailed description of
industry activities for this sector and guidance for Environmental
Assessment (EA) of thermal power projects is also provided in these
guidelines.
The client of the proposed project is National Highway Authority (NHA). The
management of NHA will ensure that all the proposed measures are effectively
implemented at the design, construction and operational stages of the project.
SECTION 3
3.DESCRIPTION OF THE PROJECT
3.1 GENERAL
Dera Murad Jamali is located between Sukkur and Sibi on N-65 in Nasirabad District,
Baluchistan. The prime Objectives of the proposed project are as follows:
Facilitate the general public, particularly the people of Dera Murad Jamali and
the surrounding areas
Enhance the efficiency of the road network
Reduce the number of accidents
To meet the requirements of increasing traffic volume, NHA has planned to construct a
Bypass around the Dera Murad Jamali city. The Length of this Bypass is 11+190 KM.
The proposed bypass starts in South of Dera Murad Jamali, traverses through western
outskirts of Dera Murad Jamali and ends in north of city after crossing the Put Feeder
Canal. Fig. 3.1 shows the location map of Dera Murad Jamali and Fig 3.2 Shows the
approved alignment of bypass.
The various Project components include construction of a new Bypass around Dera
Murad Jamali City. The Geometric Design features of the proposed bypass are
presented in Table 3.1.
S. Plain
Parameters Units
No. Terrain
1 Design speed KPH 100
2 Min. Radius Meter 437
3 Rate of Super elevation (Max.) % 6
4 Pavement cross slope % 2
5 Shoulder cross slope % 4
6 Formation width Meter 13.3
7 Pavement width Meter 7.3
8 Shoulder width (on each side) Meter 3.0
9 K-Value for crest curves 52
10 K-Value for sag curves 45
Horizontal:
11 Fill slopes 2:1
Vertical
12 Max. grade % 3
13 Min. grade % 0.3
14 Right of Way (ROW) Meter 60
15 Design life of road Years 10
Design of Road Section will be carried out on the basis of traffic counts, soil
investigations. Pavement design will be done according to AASHTO Guide for the
Design of Pavement (AASHTO 1993) with appropriate load factors. The final
pavement design will be cross- checked through mechanistic design method. The
pavement design will be based on Project traffic keeping overload factors in view.
Pavement will be designed for a life of 10 years.
The Right of Way (ROW) of the bypass is 60 meters. Major construction work will
generally remain confined within the ROW.
The materials used in construction of this bypass include coarse aggregates (crush), fine
aggregates (sand), soil, water, asphalt, reinforcement, cement etc. Almost all these raw
materials are locally available in the country.
i) Crushed Aggregate
Few sources of limited quantity are available in Ubhan Shah; however extensive
screening will be required. Good quality sand is available from Bolari, near
Hyderabad and it is the main source of sand supplied throughout Sindh
province.
iii) Sub-grade Material
The embankment material can be borrowed in huge quantities from Ubhan Shah,
near Kot Diji and Arore near Rohri. In most cases, the contractors will lease
private land in the vicinity on short term basis for the purpose of acquiring earth
material, after the approval of NHA designated Engineer.
v) Water
Camp sites will be selected keeping in view the availability of an adequate area for
establishing camp sites, including parking areas for machinery, stores and workshops,
access to communication and local markets, and an appropriate distance from sensitive
areas in the vicinity. Final locations will be selected by the contractor after the approval
from NHA.
The area requirement for construction camps will depend upon the workforce deployed
and the type and quantity of machinery mobilized. In view of the area required, it will
not be possible to locate camp sites within the ROW and the contractors will have to
acquire land on lease from private landowners.
Table 3.2 gives the typical workforce requirement for Dera Murad Jamali Bypass for
managerial staff, engineers and labourers.
85 labourers will be required during construction of the Road, out of which 30 will be
skilled, 15 will be semi-skilled and 40 will be unskilled labourers.
Table 3.2 Workforce Requirement for Construction Dera Murad Jamali Bypass
Workforce
No. Contractors Staff
Required
A. Managerial Staff
1 Project Manager 1
2 Office Manager 1
3 Accountant 1
4 Purchaser 1
5 Quantity Surveyor 1
6 Computer Operator 1
B. Site Staff
1 Material Engineer 1
2 Site Engineer 2
3 Surveyor 2
4 Foreman 2
5 Skilled Labourer 30
6 Semi-skilled Labourer 15
7 Labourer 40
Total 98
SECTION 4
4.DESCRIPTION OF THE ENVIRONMENT
4.1 GENERAL
The existing environment around the proposed Project Area has been studied with
respect to physical, ecological, cultural and socio-economic aspects.
The direct “Corridor of Impact” (COI) due to construction of this bypass is 60 meters,
which is within Right of Way (ROW) of the proposed bypass. However effect of the
loads generating from the moving traffic can be felt beyond the design ROW. Therefore
indirect COI is beyond the proposed ROW.
Human impacts such as road safety, traffic noise, vehicular emissions and other types
of associated pollution are already present along the proposed corridor for bypass.
These factors are therefore discussed as part of the existing environmental conditions in
the Project Area. This will allow the determination of baseline conditions against which
the incremental impact of the proposed Project can be assessed.
4.2 METHODOLOGY
The existing information to establish a baseline of the proposed Project Area was
collected from different Government Departments/Public Sector agencies. Further,
detailed field visits to the site were also carried out in order to have first-hand
information about the social and environmental conditions/issues of the Project Area.
Potential impacts of the proposed Project were ranked on the basis of their magnitude,
severity and reversibility.
In order to assess the impacts of the proposed Project on the people living in the
vicinity of the Project Area, detailed survey was conducted and existing
environmental/socio-economic conditions and salient features of the area were duly
observed. In addition, the relevant secondary data were also obtained from the District
Census Reports for Nasirabad. During the detailed site visit, relevant government
agencies/ departments were also consulted for the relevant data. To establish baseline
ambient air, noise and surface and groundwater conditions of the area; air and water
samples for laboratory analysis were collected from locations in the district, whereas
noise levels were measured at various locations.
Locations for conducting air and water sampling, and conducting noise measurements
were selected according to their likeliness to be affected from the proposed Project.
4.3.1 Climate
Interpretations of available meteorological data for the last five years from these
stations show that the project area experiences extreme temperatures. July and
August are the wettest months. Precipitation during these two months accounts
for more than half of the total annual rainfall. October and November are among
the driest months. May, June, July and August are among the hottest months of
the year with temperatures rising close to 50°C. December and January are the
coldest months.
The weather parameters of Jacobabad and Sibbi are provided in Table 4.1 and
Table 4.2.
The western hot winds blow particularly in the months of June and July.
Infrequent dust storms also blow during the hot season. The northern winds
blow during winter season. The humidity increases in the summer particularly in
the areas adjacent to the Put Feeder Canal.
Meteorological data from Jacobabad has been used for air dispersion modelling.
This data will be representative of climatic conditions prevailing within the
project area and its surroundings.
The temperature remains high during the months of May, June, July and August
and sometimes reaches up-to 50oC.
Table 4.1 Summary of Mean Temperature, Precipitation & Relative Humidity for Jacobabad
Table 4.2 Summary of Mean Temperature, Precipitation & Relative Humidity for Sibi
The region in which the bypass is situated is predominantly flat and semi-arid,
although irrigation has been introduced to provide water to enable crops to be
grown. The immediate vicinity of the bypass is sparsely populated. Emission
from the existing power plant operations and the vehicular exhaust emissions
from the national highway (N-65) may be considered as the significant sources
of ambient air pollution in the project area.
As part of study, air quality monitoring was carried out during the EIA field
visit. For establishing baseline ambient air quality conditions, two monitoring
sites were selected and ambient air samples were collected from:
1 At the start of Project Area
2 Near Uch Power Plant
4.3.3 Noise
The Indus River and its associated canals and water courses form the largest
irrigation system in the world. One of its associated canals is Put Feeder Canal
which originates from the right bank of River Indus at Guddu Barrage and
crosses N-65 at Dera Murad Jamali. Put Feeder Canal is the only perennial
surface water channel in the project area. Some seasonal streams also originate
from the Dera Bughti hills. These streams flow during rains, but with limited
flows.
Nasirabad District is irrigated by the Put Feeder Canal. The total length of the
canal is 171 km and has a present design discharge of nearly 190 m3/s (6700
cusecs). The canal serves cultivated command area (CCA) of about 458,425
hectares. The canal is perennial except for a closure/ maintenance period of
about one month. The land is also irrigated by tubewells.
The quality of Put Feeder Canal is generally good as the water is used for
irrigation and domestic purposes. In order to evaluate the water quality, surface
water samples were collected from Put Feeder Canal near Dera Murad Jamali.
Summary of water test results are given in Table 4.5 And details are presented in
Annexure – A.
Table 4.5 Summary Of Water Test Results
Guideline
Test Results
Values
Sr.
Parameters Method Unit Put
No. Drinking
Feeder NEQs
Water
Canal
0
1 Temperature - C 20 20 -
APHA-
2 pH @250C - 8.3 8.4 6-9
4500H+B
Total Suspended Solids
3 APHA-2540 D mg/L 65 - 200
(TSS)
4 Total Dissolved Solids APHA-2540 C mg/L 235 310 3500
APHA-3500C
5 Chlorine, Residual mg/L 0.12 0.03 1
G
6 Chromium (Cr) ASTM-D1687 mg/L 0.04 - 1
7 Copper (Cu) ASTM-D1688 mg/L 0.22 0.04 1
8 Zinc (Zn) ASTM-D1691 mg/L 0.06 0.01 5
Large aquifer sources of groundwater underline the Indus basin. They form an
important source of water supply throughout the Project Area with the use of
tube wells, motorised pumps and hand pumps. Groundwater in the Indus Basin
is, however, of variable quality and tends to be non-saline only near the surface
water bodies. Water is generally saline. Aquifers are recharged by means of
seepage during flood season. The depth of groundwater table varies from 8
metres to 15 metres in the project area.
The soil of Nasirabad district comprises silt, clay, silt loam, clay loam, and
sandy loam. On the basis of the soil reconnaissance, soil in the command area
(irrigated by canals), constituting the largest area of Dera Murad Jamali sub-
division, can be classified as sandy and loamy soil. It is more loamy soil in
dense agricultural field. In the Chattar sub- division, the area is sandy and clay
loam.
4.3.6 Seismicity
According to the seismic zone map of Pakistan, the Project Area (District
Nasirabad) lies in Zone 2B and Zone 3.
During the site visit of the project area, the sampling locations were randomly selected,
ensuring that sufficient locations are sampled for each habitat and the maximum
number of species belonging to each habitat is identified.
The project area is located outside any conventional protected area (national park,
wildlife sanctuary or game reserve) declared under the Baluchistan Wildlife Protection
Act, 1974.
4.4.1 Flora
Table 4.6 Floral Species Observed During the Site Visit in Project Area
Family Name
Local Name Life-Form Life-Span
Plant Specie
Cyperaceae
Cyperus rotundus Kabuh Sedge Perennial
Cyperus specie Sedge Perennial
Poaceae
Cynodon dactylon Chhabar Grass Perennial
Dactyloctenium
Gandheer Gaah Grass Annual
aegyptium
Desmostachya bippinata Drabh Grass Perennial
Eragrostis minor Makhni Gaah Grass Annual
Ochthochloa compressa Gandheer Gaah Grass Perennial
Oryza sativa Saari Grass Annual
Panicum antidotale Jhim Grass Perennial
Phragmites karka naaro Grass Perennial
Saccharum bengalense Booro Grass Perennial
Setaria ipalica Bajari Grass Annual
Sorghum bicolor Jowar Grass Annual
Triticum aestivum Gandum Grass Annual
Veazea nays Makae Grass Annual
Aizoaceae
Limeum indicum Dhoor Chhapri Herb Annual
Zelya petandra Wasanh/Waho Herb Annual
Asclepiadaceae
Calotropis procera Ak Shrub Perennial
Asteraceae
Conyza canadensis Gidar Buti Herb Annual
Eclipta alba Daryi Booti Herb Annual
Heliantbus annuus Soooraj Mukhi Shrub Perennial
Launaea procumbens Bhattar Herb Perennial
Xanthium indicum Bhurt Shrub Annual
Boraginaceae
Cordia myxa Lesuro Small tree Perennial
Heliotropium europeum Uth Charo Herb Annual
Capparidaceae
Cleome scaposa Khathoori Herb Annual
Chenopodiaceae
Saueda nudiflora Lano Sub-shrub Semi-perennial
Saueda fruticosa Lani Sub-shrub Semi-perennial
Convolvulaceae
Cressa cretica Oin Herb Annual
Family Name
Local Name Life-Form Life-Span
Plant Specie
Climbing
Convolvulus arvensis Naro Annual
herb
Prostrate
Cucumis melo Mitero Annual
herb
Euphorbiaceae
Euphorbia birta Kheer Wal Herb Annual
Fabaceae
Albaji maurorum Kandero Sub-shrub Perennial
Dalbergia sisso Taari Tree Perennial
Liliaceae
Allium cepa Peyaz Herb Annual
Malvaceae
Abutilon indicum Pat Teer Shrub Perennial
Mimosaceae
Acacia nilotica Sindhi Babur Tree Perennial
Albizia lebbeck Sarianh Tree Perennial
Prosopis cineraria Kandi Tree Perennial
Prosopis juliflora Devi Shrub Perennial
Molluginaceae
Glinus Herb Perennial
Rhamnaceae
Zizyphus mauritiana Jhangoori Ber Shrub Perennial
Solanaceae
Lycopersicom
Tamator Shrub Annual
sesculeupum
Solamun melonjina Wagan Shrub Annual
Solanum surattense Kanderi Wal Sub-shrub Annual
Tamaricaceae
Tamarix aphylla Lawo Tree Perennial
Tamarix indica Laie Large shrub Perennial
Verbenacea
Phyla domingenasis Pan Rush Perennial
Typha elephantina Pan Rush Perennial
Zygophyllaceae
Fagonia indica Dramaho Herb Annual
Fagonia bruuieri Dramaho Herb Annual
4.4.2 Fauna
Table 4.7 List of Birds, Mammals and Reptiles Observed during the Site Visit in the Project Area
Sr.
Common Name Scientific name
No.
Birds
1 Black Crowned Finch Lark Eremopterix nigriceps
2 Black Kite Milvus migrans
3 Blue Rock Pigeon Columba livia
4 Cattle Egret Bubulcus ibis
5 Common Myna/ Indian Myna Acridotheres tristis
6 Desert Wheatear Oenanthe deserti
Sr.
Common Name Scientific name
No.
7 Hoopoe Upupa epops
8 House Crow Corvus splendens
9 House Sparrow Passer domesticus
10 Hume‟s Wheatear Oenanthe alboniger
11 Pied Bushchat Saxicola caprata
12 Pied Kingfisher Ceryle rudis
13 Purple Sunbird Nectarinia asiatica
14 Red-vented Bulbul Pycnonotus cafer
15 Red-wattled Lapwing Hoplopterus indicus
16 White-breasted Kingfisher Halcyon smyrnensis
17 White-cheeked Bulbul Pycnonotus leucogenys
18 White / Pied Wagtail Motacilla alba
Mammals
19 Asiatic Jackal Canis aurius
20 Five Stripped Palm Squirrel Funambulus pennant
21 Indian Desert Jird Meriones hurrionae
22 Indian Gerbil Tatera indica
23 Long-eared Hedgehog Hemiechinus auritus
24 House Mouse Mus musculus
25 Little Indian Field Mouse Mus booduga
Reptiles
26 Brilliant Agama Trapelus (Agama) agilis
isolepis
27 Indian Monitor Varanus bengalensis
28 Saw Scaled Viper Echis carinatus
29 Glossy Bellied Racer Coluber ventromaculatus
30 Garden Lizard Calotes versicolor
This section deals with the social conditions of the project area. During the desk/ office
study, available reports/ documents were comprehensively studied. During the field
survey consultation with the residents, shopkeepers, pedestrians and drivers were
carried out and observations were taken after giving due consideration to the desk study
results.
Social organisation in the area is tribal. Tribe is the major entity which provides
identity, security and rights to individuals and families and who in return sow
their allegiance to their leader. A tribe is a segmentary organisation of kinship
groups consisting of many lineages and each lineage consisting of many agnatic
groups. Each agnatic group has its own leader, who is also the village headman
and is consulted for conflict or dispute resolution. Every lineage has one leader,
who is recognised by all of the constituent agnatic groups. The jurisdiction of
the tribal leader is extended to all areas inhabited or controlled by his tribe, and
also to other smaller tribal groups or lineages in the area.
The total area of the district is 3,387 square kilometers, which gives population
density of 73 persons per square kilometer in 1998 and population density of
144 persons per square kilometer in 2016 indicating a fast growth rate of the
district.
Dera Murad Jamali covers an area of1,986 km2. The total population of Dera
Murad Jamali is 157,429, out of which 82,627 are males and 74,802 are females
according to the housing census of 1998. According to the 1998 census, the
male-female ratio is 1.10:1 i.e. there are 110 men to every 100 women.
Table 4.8 gives population and annual growth rate since 1951 of district.
Over the period of time, the urban population has a low proportion in the
total population close to 16% in Census of 1998, whereas it was reported
high (27%) in Census of 1981. Majority of the population in Nasirabad
district lives in rural areas (about 84%). According to the 1998 Population
Census, female population has equal portion in both rural and urban
population i.e., about 47%. A narrow difference between gender ratio
among the genders was noticed both in the rural and urban areas.
B. Religion
C. Mother Tongue
Balochi and Sindhi are the major languages spoken in the district followed
by Brahvi and Sairaki. Urdu is used as a medium of education and as
means of communication between people with different ethnic
backgrounds. There is also a small number of Pushto and Punjabi speaking
population in the district.
E. Sex Ratio
Number of males for every 100 females was 111 as recorded in 1981, 1998
Census in the district. The ratio is projected to 111 per 100 females for
2010.
F. Marital Status
As per projected data for 2010, 19 percent of the total population was
never married, 77 percent married, 4 percent widowed/divorced. About
86% of the women of reproductive age (15-49 years) were married, and of
these married women, 81% had children.
Agricultural activity in the project area started after the construction of Put
Feeder Canal in 1970, the activity emerged in the immediate vicinity of the
Canal. The entire area around the bypass is now cultivated by irrigation
supplies from Put Feeder Canal and Rabi Canals. This indicate the
importance of the agricultural sector in the project area. The existing
standards and the management levels of agriculture in the project area are
very low. As a result the present subsistent agriculture does not produce
enough to meet the food and financial requirements of the farm population.
B. Livestock
Livestock is an important asset for the poor, particularly the landless and
farmers. In the project area, the communities near flocks of goats, cows
and sheep for commercial reasons and donkeys for water collection.
In the livestock management, the entire family participate except for those
keeping large herds, which employ wage paid workers on monthly wages
fixed for cow and goat/sheep.
4.5.4 Communications
Railways
The length of railway track is 39 kilometers and there are three railway stations:
Notal, Mangoli and Dera Murad Jamali in Nasirabad. The regular stop for
passengers express trains is at Dera Murad Jamali. Nasirabad has a place for
helicopter landings but there is no regular airway service. The nearest airport is
in Jacobabad (35 km).
Roads
(Kilometer)
Length by Surface Type Black Topped Shingle Total Length
2002 490 252 742
2010 413 251 664
2004-05 2009-10
Institute Type
Male Female Total Male Female Total
Primary Section 13,380 6,268 19,648 17,912 7,595 25,507
Middle Section 1,447 368 1,815 1,825 482 2,307
High Section 572 141 713 917 203 1120
Inter Colleges 232 0 232 0 0 0
Degree Colleges 0 0 0 565 82 647
Total 15,631 6,777 22,408 21,219 8,362 29,581
Source: Nasirabad District Development Profile 2011
The highly subsidized public healthcare system is major provider of curative and
preventive care services to the local population. The health facility infrastructure
in District Nasirabad includes:1 Hospitals, 3 Rural Health Centres (RHCs), 14
Basic Health Units (BHUs), 9 Civil Dispensaries (CDs), 3 Maternal and Child
Health Centres (MCHCs) 1 TB Clinic, 1 School Health Unit and 1 Health
Auxiliary unit. There are 50 beds out of which 30 are present in RHCs. The
community visits the District Head Quarter (DHQ) hospital and nearest BHU
and the government clinic and private clinic at Dera Murad Jamali.
Apart from the above health facilities, there is one non-functional Basic Health
Unit and two under construction health facilities (1 CD and 1 MCH Centre) in
the district. Moreover there is also a jail dispensary. The public-sector healthcare
system suffers from governance, funding, staffing and resource limitations.
A social/ impact assessment survey was carried out in the project area to identify
the impacts and their magnitudes on the affected population. Efforts were made
to consult maximum number of stakeholders, which included shop keepers,
residents, pedestrians and drivers, etc. The purpose of this survey was to get
response about the perceived impacts and preferences towards the project
implementation. Efforts were made to include the majority of the population in
the sample and contact the maximum population during the survey.
Survey Results
SECTION 5
5.PROJECT ALTERNATIVES
5.1 GENERAL
5.2 NO PROJECT
According to the Traffic Projection Survey it is estimated that in the future years more
and more people will be using the N-65. Without the Project bypass the existing road
from Sukkur to Quetta (N-65) will continue to be the main transportation corridor in
the area. Traffic volume on the existing N-65 (National Highway) is anticipated to
increase with the passage of time, as indicated from the traffic projection survey.
Traffic congestion is expected to increase in the future and road conditions are expected
to deteriorate due to ever increasing traffic volume.
Therefore, the “No Project” conditions will result in further worsening of the present
environmental conditions and increased disturbance to residents of the area and the
road users. Socio-economic conditions will also deteriorate due to lack of proper link
between Sindh and other provinces. The effect of “no build” alternative for N-65 would
therefore result in longer travelling times and accidents due to the shorter width of the
existing road.
The alternate transport modes include railways, air travel and other access roads. Air
access from Sukkur to the other parts of the country is already available and the people
of Dera Murad Jamali and surrounding areas use N-65 for access to the Sukkur Airport.
Rail track bound for Karachi and Quetta already passes along the road but this option
cannot be considered as an alternate keeping in view the traffic pattern and connectivity
with surrounding areas.
In terms of the movement of people and goods, road transportation facilitates majority
of travellers in the Project Area. Further improvement of the road system will enhance
economic development by providing reliable corridor for the movement of goods and
passengers to and from other provinces. For this and other reasons, the
implementation of the Project is the only viable solution for reducing traffic
congestion and providing safe and good quality route for movement of people and
goods. Different options for the proposed route were examined as discussed below:
(i) Improve the existing road with the same alignment by widening on both
sides
(ii) Upgrade the existing 2 lane road into 4 lane dual carriageway by
extending on both sides from centreline of the existing road; and
(iii) Construct a bypass around the Dera Murad Jamali city
The third option was selected by considering the above mentioned factors and the
bypass will be constructed. This alternative has the advantage of enhanced safety
during construction and operational stages, and less disruption to the passing
traffic during construction. It will also minimise resettlement of structures, trees and
other utilities. Provision of new bypass at Dera Murad Jamali will facilitate the traffic.
Its merits are discussed in section 5.5 hereafter.
First option was rejected because of the disturbance to the moving traffic during
construction. Also there will be more disturbances to the people living in the vicinity of
the project area if construction on both sides is initiated simultaneously.
Second option was not selected due to the increased resettlement of structures, trees and
other utilities. In this case project cost will also increase, which will be an unnecessary
burden on the national exchequer.
Bypasses are used to either shorten the travelling time on the highway route or to
specifically reroute traffic away from the existing cities/towns and commercial areas to
provide safety to the citizens living in the cities/towns. NHA has decided to provide a
bypass around Dera Murad Jamali so that the traffic moving between Sukkur and
Quetta can move without any hindrance. Traffic projection survey shows that traffic on
this important route will increase in the coming years. Provision of the bypass will also
facilitate the residents of Dera Murad Jamali who are vulnerable due to the passing of
high traffic volume within the city.
SECTION 6
6.PUBLIC CONSULTATION
6.1 GENERAL
This section describes the outcome of the public consultation sessions held with
different stakeholders that may be affected by the proposed project. Public consultation
is a mandatory part of the EIA process for development projects. The adequacy of the
public consultation and information disclosure is one of the basic criteria used to
determine the project compliance with the national / international safeguard policies.
The consultation process was carried out in accordance with the requirements of
Pakistan Environmental Assessment Procedures. The objectives of this process were to:
Stakeholders are those who have a direct or indirect interest in project development,
and who will be involved in the consultative process. During the field survey,
significant efforts were made to contact maximum household residing and shop owners
running their business within the proposed ROW of the project to identify the possible
categories of direct stakeholders and their stakes. The stakeholders identified during
field survey are the Project Affected Persons (PAPS) which consist of private land and
structure (shop) owners, shopkeepers (renters), local residents, pedestrian, factory
owners, school and hospital management, travellers and drivers. All the stakeholders
had different type of stakes and apprehension according to their professions and were
listed down along with their apprehensions.
For ascertaining the perceptions of different stakeholders about the project (during
construction/operation) consultation meetings were held with them. These
meetings were held in an open atmosphere, in which participants expressed their
views freely. Informal group discussions and gender consultation meetings were
also held, as an additional tool for the assessment of the perceptions of the
stakeholders.
b) Methods of Public Consultation
PAPs (legal title holders of land & structures) will lose their land
and shops due to land acquisition for the proposed project, which
1 PAPs
will ultimately result in permanent physical and economical
displacement of the PAPs, loss of business, family disturbance
Noise, air pollution, dust, access problem for the students &
Schools &
4 teachers, issue of parking of vehicles in the peak hours, disruption
colleges
of utilities, safety issues & disruption in the classes & studies.
Consultation meetings and informal group discussions regarding project impacts and
their probable mitigation measures were held with the PAPs (private land and shop
owners), local residents, shop keepers (renters), pedestrian, passengers, management of
District Headquarter Hospital Dera Murad Jamali and Al-Huda Public School.
Generally, it was found during the consultation process that people were already aware
of the proposed project. After the meetings with PAPs and other stakeholders, majority
of the respondents (95%) during sample survey showed their support for the proposed
project provided that proper compensation is paid for the loss of their land and land
based assets. This project will be beneficial not only for income generating activities
but also good for easement to traffic which is high traffic blockage area on N-65
highway and for the development of the area.
Figure 6.1 Group Photo with management and students of Al-Huda Public School DMJ
Scoping sessions were conducted with the shop owners, shop keepers (renters) local
residents, pedestrians and passengers.
PAPs demanded that they must be properly compensated for their physical and
economical displacement with some additional allowances so that they could improve
or at least restore their living standards up to prior level of the project.
The most common suggestions proposed during the meetings are listed below:
Commencement of the proposed project will cause permanent physical and
economical displacement of the local residents residing within the proposed
RoW. Local residents (affectees by land and structures) will lose their land and
housing structures and will suffer from permanent physical and economical
displacement that's why owners of land and structures must be compensated on
the basis of current market rates.
Local residents (affectees by land and structures) demanded that criteria of
payments should be translucent and fair;
As local residents (affectees by land and structures) are going to lose their land
and housing structures so they suggested that besides compensation based on
current market rates, some additional allowances should also be paid to them
owing to their physical and economical displacement;
Avoid dumping construction material openly;
Adopt measures to minimize dust, smoke, and noise pollution, and to control
spillages from construction machine;
Waste / debris produced during the construction due to construction of the road
should be disposed of properly;
Construction site should be fenced with the corrugated iron sheets to control the
noise and dust emissions and other hazards;
Sprinkling of water should be regular in the morning, noon and evening on the
daily basis;
Utilities disturbed at the site should be restored as early as possible;
Cutting of trees should be avoided at the maximum level;
Efforts should be made to transplant the trees according to the available
facilities;
Proper compensation should be paid to the affectees for the loss of their
properties;
Criteria of payments to the affectees should be transparent and fair; and
Local residents should be given priority in jobs during the construction phase;
Increase in traffic and safety hazards will create problems to local population
and surrounding communities. Accordingly, a detailed health and safety plan
must be developed to mitigate the construction and operation risks of the
proposed project on the local residents and surrounding communities.
The contractors and design consultants may include the following environmental and
safety provisions in the project design in order to protect the surrounding communities
from the anticipated impacts of pre and post construction activities:
Significant efforts including change in design should be adopted to minimize
the physical and economical displacement of the PAPs ( legal title holders of
land & structures);
Local residents should be given priority while hiring during construction and
operation phase of the proposed project;
All efforts should be espoused to save existing plantation; A tree plantation
programme to compensate for the anticipated loss of vegetation during the
construction activities, and to help abate pollution caused by emissions, dust,
and noise during the operation;
Construction machinery should be placed at adequate locations away from the
sensitive areas to minimize the impacts related to the dust & noise;
Project site will be fenced with corrugated iron sheets to minimize the level of
noise and dust on the surrounding areas;
Project facilities should be located outside the existing residential areas. In
order to avoid restricting the mobility of the local stakeholders, construction
vehicles should remain confined within their designated areas of movement;
The utilities to be shifted due to the implementation of the proposed project
should be rehabilitated on priority basis to minimize the impacts on the
stakeholders;
NHA will make sure the payment for the acquisition of properties;
Solid waste generated during construction at site should be disposed of safely at
the waste disposal sites approved by the District Government; and
All necessary measures should be taken to ensure the safety of traffic during
construction, including barricades (including signs boards, pavement markings,
flags, and lights). All such barricades will be set up to facilitate the local traffic.
Proceedings of the meeting with DC Nasirabad and Executive District Officer (EDO)
Forest & Wildlife are presented below. The rest of the meetings were mostly of the sort
of information collection and dissemination.
As the project area lies under the Nasirabad District, the DC was approached and
the proposed project was discussed in detail.
He was informed with the help of project‟s area map about the proposed activities.
He spoke at length about the development activities in the area. He expressed
some concerns regarding the projects, which are discussed below.
The contractor should employ local people during the project execution, thereby
ensuring maximum project benefits for the local communities. He also
emphasized on the need to provide trainings to the unskilled workers so that in
future locals may also be hired for skilled jobs. He also stressed that the project
alignment should pass through uncultivated land so that the land would be
acquired at low cost and making project more beneficial to locals.
A consultation meeting was held with Executive District Officer of Forest and
Wildlife departments, Baluchistan at his office in Dera Murad Jamali. He was
informed about the proposed project. He informed that the proposed location of
the plant does not fall in any wildlife protected area or protected forest and
therefore the department has no objection or concern related to the project.
However he suggested that the natural vegetation and wildlife in the area should
be protected adopting proper mitigation measures.
Figure 6.4 Group Photo with Executive District Officer Wildlife & Forest
Other Meetings
People have hopes that the proponent and its contractors would employ
locals during the project. However, locals know their limitations, as they
are mostly illiterate and unskilled.
Most of the communities and to some extent the local influential people
are not concerned over the environmental issues. They are mostly
interested in getting maximum benefits in terms of employment, local
market boom and community development programmes.
The biggest aspiration of locals can be easily identified as
„employment‟.
Sr.
Stakeholder Name Organization Designation
No.
Deputy
1 Dr. Muhammad Yasir Bazai District Government
Commissioner
Forest & Wildlife
Executive District
2 Mr. Naeem Javaid Department
Officer (EDO)
Baluchistan
Sub Divisional
3 Mr. Muhammad Waryam Manjho QESCO (Operation),
Officer (SDO)
Sui Southern Gas Sub Divisional
4 Mr. Hadayat Ullah Khoso
Company, Officer (SDO)
Secretary Market
5 Mr. Muhammad Aslam Laghari District Government
Committee
Irrigation and Power
6 Engr. Ghulam Sarwar Executive Engineer
Department
Communications & Sub Divisional
7 Engr. Muhammad Farooq Tareen
Works Department Officer (SDO)
Medical
8 Dr. Mahmood Umrani DHQ Hospital
Superintendent
9 Mr. Tarra Chan District Government Head of Minorities
Figure 6.5 Group photo with Sub Divisional Officer C&W Dept.
In addition to the previously discussed commonly raised concerns, there were certain
issues at the project site which were raised by the respondents. The detailed schedule of
meetings at site with the stakeholders and the issues raised by them is given in Table
6.4.
Table 6.4 Schedule of Meetings With Stakeholders, Their Concerns/Apprehensions & Suggestions
Sr. No. of
Date Time Venue Concerns/Apprehensions Raised Suggestions
No. Participants
In the origination of the proposed Local resident who will suffer
project local residents will suffer from physical and economical
from physical and economical displacement must be
displacement. compensated on the basis of
Privacy Issues were also raised by current market rate for their land
local residents during the and land based assets. Criteria of
construction of the proposed project payments to the affectees should
due to the movement of labour. be translucent and fair.
Exposure of noise and dust particles As a solution labour should bound
will cause disturbance and health to work and stay in the designated
issues to the local residents area or camp sites.
Local throughout the construction stage The effects of noise and dust
due to the movement of pollution on the local residents
Residents construction machinery and should be minimized by making
12:30
1 7/2/2019 (Shopkeepers, 15 transportation of construction necessary arrangements. Dust
PM materials. pollution should be controlled by
shop owners, Some respondents expressed that water smattering on daily basis.
pedestrians) they do not trust on local So they demanded that criteria of
government in terms of dealing payments should be fair.
with fair compensation. Proper diversion route rather than
Traffic will be congested on the access road should be provided to
access road and main road during minimize the traffic problems of
the construction phase of the the people during the construction
proposed project as no alternate stage.
route is available. It will be difficult Local residents should be given
for all local residents to react their preference for jobs during
designations and more time will be construction and operation phase.
consumed. Solid waste produced should be
Due to lack of educational properly managed and disposed in
attainment, majority of local an identified designated area.
Sr. No. of
Date Time Venue Concerns/Apprehensions Raised Suggestions
No. Participants
residents are working as daily wage Appropriate detour plan should be
labour. developed to avoid the disruption
Solid waste produced during of pedestrians due to use of heavy
construction period is a major machinery in day timings and
concern of many stakeholders. should avoid disturbance for the
Due to the construction of the local residents living in the
proposed project, public utilities project vicinity.
will be disturbed. Efforts should be made to
During construction period complete the construction period.
pedestrians will face difficulties Government should provide the
while walking to nearby places in basic facilities like safe drinking
the vicinity of proposed project water as well as the educational
area. and medical facilities in the
The project is a good step for the proposed project area.
development of the proposed Accordingly a detailed health and
project area. safety plan must be developed and
No proper educational, medical and implemented to mitigate the
safe drinking water facilities are construction and operation risks
available in the project area. of the proposed project on the
Increase in traffic and safety local residents and surrounding
hazards will create problems to communities.
local population and surrounding
communities.
Dust & noise problems during Dust & noise problems during
Management construction stage. Construction stage can be
1:00
2 7/2/2019 of Al-Huda 11 Positive impact during operation minimized through water
PM stage. sprinkling on daily basis.
Public School Project should be completed in-
time.
Sr. No. of
Date Time Venue Concerns/Apprehensions Raised Suggestions
No. Participants
Management
of District Traffic would be choked due to Project should complete well in
2:00 school and office hours at the time.
3 7/2/2019 Headquarter 6 Highway. Water should be sprinkled
PM
Hospital Dera Dust & noise problem during the regularly to control the dust
construction period. emission
Murad Jamali
The major objective of GRM is to establish, implement and maintain a procedure for
handling environmental and social concerns of the project stakeholders and affected.
The procedure will include a redressal mechanism scaled to project‟s identified risks
and adverse impacts, focusing on stakeholders.
GRC meetings will be held in NHA, PD Office or other locations agreed by the
committee. If needed GRC members will conduct field visits to verify and review the
issues at dispute.
The GRC will directly work under the supervision of Director Environment (EALS).
The following members are recommended to form a GRC to resolve the grievances;
The flow chart of the proposed redress mechanism is shown in Figure 6.9 on the next
page:
Figure 6.9 Flow Diagram of Proposed Redress Mechanism
The Affected person (AP) / stakeholder may submit an application in the PD Office for
the redressal of his grievances. The PD will refer the matter to Director Environment
(EALS). Director Environment (EALS) will address the grievances preferably the same
day or he may take a maximum of one week to resolve the grievance. In case the
grievance is not addressed within a week time, the Affected Person (AP) may take the
matter to GRC.
There are several ways to approach GRC for the redressal of grievances;
Contact the PEGO of GRC over phone apprising him of his /her grievances;
Send an email or courier to the PEGO for taking up the matter in GRC.
GRC will investigate and review the grievance and convey the final decision to the AP.
In case the grievance is not related to the project, the GRC will not process it and
accordingly inform the grievant. All decision of the GRC will be conveyed to the
grievant in writing.
GRC can take up any matter of project related grievances for consideration of
resolution.
SECTION 7
7.ENVIRONMENTAL IMPACTS AND MITIGATION
MEASURES
7.1 GENERAL
This section identifies the overall impacts of construction/ rehabilitation works on the
physical, biological and socio-economic environment of the Project Area. This
assessment also includes the impact of traffic volume due to improved road conditions.
In addition, it also narrates the measures that will mitigate the Project‟s adverse
environmental effects. Following is a description of the perceived environmental
impacts (positive/negative) of the Project with their proposed mitigation measures.
The Project corridor is delineated according to two criteria: right of way (ROW); which
the NHA is legally entitled to, and Corridor of Impact (COI), i.e. the width of the
corridor that will be impacted, directly or indirectly, by the Project during the
construction and operational phases.
a) Project Right of Way (ROW)
The proposed Project corridor will have a well-defined ROW that will be 60
meters. Major construction works will generally remain confined within the
ROW. All the infrastructure and commercial activities within the proposed
ROW need to be relocated and have direct impact of the Project.
b) Corridor of Impact (COI)
Corridor of Impact (COI) was delineated as the extent, which has direct or
indirect impact of Project. Direct impacts of the Project, caused by relocation,
are envisioned within the ROW and indirect impacts, caused by noise, dust
emissions, camp sites and borrow sites could be beyond the ROW. After the
detail site visits, Indirect Corridor of Impact (COI) was defined as area covered
within 200 metres (100 metres on both sides of the Road section from its
centre).
7.3.1 Topography
The topography along the Project Area will change to some extent because of
construction of Project related structures such as embankments, culverts etc.
Visual changes to the topography will be of permanent and minor negative in
nature and do not require any mitigation measures, except that the Project design
should consider aesthetic concerns.
The Project-impact related activities will be land acquisition and clearing of the
Right of Way (ROW) that will result in disturbance to the affected
residents of the Project Area. Land acquisition is mainly required for
construction of Dera Murad Jamali Bypass is 671,453.6 square meter.
Dera Murad Jamali Bypass is proposed for avoiding the traffic congestion and
blocking within the city due to excessive traffic movement. Its construction will
not only save the travelling time but will also be beneficial to the
citizens of Dera Murad Jamali City. Following are the associated merits of Dera
Murad Jamali Bypass:
Time saving due to uninterrupted traffic;
Safety of the citizens;
Reduction in traffic congestion;
Reduction in noise and air pollution; and
Motivation to the travellers for using Project.
The proposed Project is expected to increase the land values, especially in areas
where no road infrastructure is present i.e. villages through which Dera Murad
Jamali Bypass is proposed to pass. Landowners will have an opportunity to sell
their land on increased prices and start a new business.
7.3.4 Flora
The construction of the bypass may affect the ecological habitat of the area. This
impact will be permanent and moderate negative in nature.
As the proposed Road passes through the flood prone areas, it may result in
changing the hydrologic regime of the area, resulting in flood damages to
local community and the proposed road. Also flood flows may damage
structures or cause drainage problems in urban areas.
Possible impacts due to flood are temporary but may have significant adverse
(major negative) impacts, i.e. erosion of road surface; damage to the crops,
bridges etc. Mitigation measures will include:
Provision of culverts to control flood damages and provision of safety
of embankments against floods; and
Provision of sufficient sizes of drains to take design flows.
Due to the proposed Project, public utilities affected may create disruption of
public services and inconvenience. This impact is temporary and may be
considered as moderately negative in nature. Mitigation measures will include:
Provision in design and budget for the relocation of the
existing utility infrastructures wherever required and necessary
All public utilities (e.g. water pipes, power/ telephone lines) are likely to
be affected by this bypass need to be relocated well ahead of time before
the actual commencement of bypass
7.4.1 Topography
This impact is temporary and minor negative in nature. Mitigation measure for
this impact is the proper landscaping, wherever required.
This impact is permanent and major negative in nature. Mitigation measure will
involve judicious compensation as per Resettlement Action Plan to be paid for
relocation of properties to the displaced population. Compensation should be
given before actual dislocation.
Potential sources of soil can be borrowed in huge quantity from Ubhan Shah
near Kot Diji and Arore near Rohri.
Borrow/ open pits and its excavation activities may result in land disputes, soil
erosion, loss of potential cropland, loss of vegetation, landscape degradation.
Borrow/ Open pits may also become potential sources of mosquito breeding and
may prove hazardous to human beings, livestock and wildlife. This will also
degrade hygienic condition of the Project Area.
Impact of air emission may be carried over long distances depending upon
the wind speed, direction, the temperature of the surrounding air and
atmospheric stability.
Emissions from crushers and quarry sites can cause health impacts, i.e.
coughing, flu, difficulty in inhaling, irritation in eyes and reduction in visibility.
This impact is temporary and minor negative in nature.
Due to construction activities soil erosion and contamination may occur. Soil
erosion may occur around roadside, contractor‟s camps and at embankment
works as a result of unmanaged run-off from equipment washing yards,
excavation of earth, cutting operation, embanking and clearing of vegetation
whereas contamination of soil by oil and chemicals at asphalt plant sites,
workshops areas and equipment washing yards may limit future use of lands for
agricultural purposes.
7.4.7 Noise
S. Noise-Level in
Equipment
No. dB (A)
1 Earth Moving Machinery 75-85
2 Material Handling Equipment 75
3 Stationary Equipment 75
4 Tools, Hammers and Drivers 80-95
Source: The General Services Administration, Construction Noise Specification, USEPA 1972
Observation Point
Noise
S. No. Equipment to the Source
dB(A)
(meters)
1 Wheeled loading 5 90
2 Grader 5 90
3 Vibration pavement roller 5 86
4 2-wheel vibration pavement roller 5 81
5 3-wheel pavement roller 5 81
6 Tire pavement roller 5 76
7 Bulldozer 5 86
8 Wheeled pneumatic dredger 5 84
9 Sprayer 5 87
10 Power generator 5 98
11 Impact drill 5 87
12 Impact pile driver 5 112
13 Truck 5 92
14 Concrete mixer 5 91
Observation Point
Noise
S. No. Equipment to the Source
dB(A)
(meters)
15 Concrete pump 5 85
16 Mobile lift 5 96
Pneumatic hammer and rock
17 5 98
crusher
18 Breaker 5 84
19 Pneumatic spanner 5 95
Source: Guangzhou City Center Inner Ring Road Project, Environmental Assessment Report (1997)
Surface water might get contaminated due to the disposal of construction waste
generated due to the Project activity; this contamination will not only
endanger the aquatic life but will also result in jeopardizing the health of
natives that use this water for meeting domestic requirement. In addition to
that, construction waste, if left unattended will result in forming leachate which
will percolate through the soil strata and will reach underground water table and
hence, will end up contaminating it.
This impact is temporary and minor negative in nature. Following are the
mitigation measures:
The surface and groundwater reserves must be adequately protected from
any source of contamination such as the construction and oily waste that
will degrade its potable quality.
The solid waste will be disposed of in designated landfill sites to sustain
the water quality for domestic requirements.
Regular water quality monitoring according to determined sampling
schedule
The contractor should ensure that construction debris do not find their way
into the drainage or irrigation canals which may get clogged
Work on irrigation canal areas will be kept to a minimum, protective walls
be (re-)constructed
To maintain the surface water flow/drainage, proper mitigation
measures will be taken along the road, like drainage structures in urban
areas
Prohibit washing of machinery and vehicles in surface waters, provide
sealed washing basins and collect wastewater in sedimentation/retention
pond
Construction work close to the streams or other water bodies will be
avoided, especially during monsoon period
7.4.9 Flora
There will be cutting of estimated 182 trees due to the proposed construction
activities. This impact will be temporary and major adverse in nature. A number
of trees will have to be cut, that will need mitigation during the operation phase.
Mitigation measures during construction include:
Contractor must be bound to establish the staff and labour camps,
and workshop at barren (non-vegetative) land
Camps should be confined by fencing around the area so that no waste
should approach the flora.
7.4.10 Fauna
People will face minor exit/entry problems during the construction activities.
The impact of construction on entry/exit problem is of minor nature as there is
no major shrine or mosque located in the immediate vicinity of ROW.
There is no waterlogged and wetland area in the Project Area or its immediate
vicinity. Main impact of the waterlogged area is that it reduces the bearing
capacity of the soil. If present, this effect is moderate negative in nature and
needs immediate attention. Mitigation measures will include dewatering, use of
sandpits and boulders.
As a result of bypass construction, prices of nearby lands will increase that will
be a positive thing for the local people. After the construction of Dera Murad
Jamali Bypass, local people will get a chance to open shops and hotels in its
vicinity. This will provide them more earning opportunities, which will enhance
economic profile of the area. This is a moderate positive impact.
Change in local lifestyle and culture may occur when the local and migrant
workers will come in contact during the construction works. This impact is
permanent and minor positive.
7.5.1 Noise
Bypass construction will result in less wear and tear to vehicles; it will also
result in less fuel consumption.
Bypass construction will help reduce traffic related emissions in the short term
by allowing a smoother traffic flow. However, in the longer run, increased
traffic levels may lead to higher values of emissions.
Helping the owners and occupants of the affected premises to identify and
implement special measures such as hedges and vegetation to reduce air
pollution.
Due to increase in speed and undisturbed flow of traffic, travelling time will be
saved to reach at destination. Trade will improve due to better transport
opportunities. This impact is permanent and major positive in nature.
Bypass construction will improve safety conditions and will reduce accidents
and loss of lives due to better traffic movements. This impact is permanent and
major positive in nature.
SECTION 8
8.ENVIRONMENTAL MANAGEMENT PLAN
8.1 INTRODUCTION
8.1.1 General
The EMP will help the NHA address the foreseen adverse environmental
impacts of the Project, enhance the Project‟s overall benefits and introduce
standards of good environmental practices. The primary objectives of the EMP
are to:
1 Define the responsibilities of Project proponents in accordance with the
three Project phases (design, construction and operation);
2 Facilitate the implementation of the mitigation measures by providing the
technical details of each Project impact, and proposing an
implementation schedule of the proposed mitigation measures;
3 Define a monitoring mechanism and identify monitoring parameters to
ensure that all proposed mitigation measures are completely and
effectively implemented;
4 Identify training requirements at various levels and provide a plan
for the implementation of training sessions;
5 Identify the resources required to implement the EMP and
outline corresponding financing arrangements; and
6 Providing a cost estimate for all proposed EMP actions.
The key environmental and social issues associated with this Project are as
follows: The key environmental and social issues associated with this part of the
project are as follows:
1 Resettling commercial structures owned by squatters presently
operating within the proposed construction limit of the project corridor;
General
This sub section describes the methodology required for the implementation of
EMP in conjunction with the NHA, Design Consultants, EIA Team,
Supervision Consultants and Contractors. The executing agency of the Project
will be National Highway Authority (NHA). General Manager (NHA) will be
the overall Incharge of the Project. The GM (NHA) will delegate the
supervisory responsibilities of the Project to the Project Director who will have
professional staff supported by a team of consultants including Environmental
Monitoring Specialists/Consultants.
Figure 8.1 Organisation Chart for Construction, Environmental Management Plan & Resettlement Action Plan
a) Project Director
EIA consultants will prepare a comprehensive EIA and EMP of the Project
in compliance with Pak EPA Guidelines.
The design consultants will ensure that all the mitigation measures
proposed for the design phase are incorporated in the design and included
in the contract documents.
EMP will be made a part of the contract agreement and the contractor will
ensure that all Project activities are in compliance with the EMP and
NEQS.
This section describes the implementation and supervision responsibilities for the
different phases of the Project.
The Director (Environment, Social and Land/Resettlement), NHA and his staff
with the assistance of EIA consultant are responsible for ensuring that the
Project design and specifications adequately reflect the EMP and the
Resettlement Policy Framework (RPF). He will ensure the Project‟s
compliance with environmental regulations and donor requirements; and ensure
stakeholder participation in the Project design.
Specifically, before the start of the Project, the NHA‟s Deputy Director (Social
and Land/Resettlement) will ensure that the following activities are carried out
in a transparent manner and according to the acceptable standards:
1 Identifying and verifying Project affected persons (PAPs) on the
basis of specified documents;
2 Identifying which public facilities and utilities need to be relocated.
3 Identifying alternative resettlement sites for PAPs outside the ROW.
4 Carrying out a consultation and dissemination campaign with regard to
compensation procedures, entitlement packages, and proposed
alternative resettlement sites.
5 Preparing individual entitlement files
6 Preparing and approving compensation budgets;
7 Ensuring that an adequate notice period is given to PAPs before shifting
8 Providing shifting assistance to displaced squatters and to assist squatter-
owners to salvage their facilities
b) Construction Phase
The NHA will appoint Supervision Consultants, who along with the Deputy
Director (Environment) will oversee the working of contractor in accordance
with the EMP.
The Supervision Consultant will liaise with the Project staff to monitor
environmental compliance during the construction
He will supervise the construction and provide technical support to
help ensure compliance with the EMP
The Supervision Consultants will assess the environmental impact of
highway construction
He will monitor the progress of work and adherence of the contractor
to the EMP and Resettlement Action Plan
He will direct the Contractor to work in such a manner that all Project
activities are in compliance with the EMP and NEQS
c) Operation Phase
The Deputy Director (Environment) and his staff will be responsible for the
following:
1 Coordinating with the operational staff working under the Regional
General Manager to monitor environmental compliance during bypass
operation
2 Advising on, and monitoring tree plantations along the bypass
3 Reporting on the progress of environmental compliance to the federal and
EPA Baluchistan
4 Assessing the long-term environmental impacts of bypass operation
5 Sustaining a working partnership among the NHA, EPA Baluchistan,
Agriculture, Forest and Wildlife departments of Baluchistan, NGOs and
other related public private sector organizations
6 Reporting to Director (Environment) about progress of the work
This section provides a monitoring plan that identifies the roles and responsibilities of
Project staff, involved in environmental and social monitoring, and list the parameters
that will be used in the monitoring process.
8.3.1 Objectives
The main objectives of monitoring during the operation phase will be to:
Appraise the adequacy of the EIA with respect to the Project‟s predicted
long-term impact on the corridor‟s physical, biological and socio-
economic environment
Evaluate the effectiveness of the mitigation measures proposed in the EMP
and recommend improvements, if and when necessary
Compile periodic accident data to support analyses that will help minimise
future risks
Monitor the survival rate of avenue plantations
a) Internal Monitoring
c) Supervision Consultant
Monitoring Parameters
Notice period given to PAPs before shifting them from their original
locations within the ROW
Number of vulnerable PAPs compensated under the EMP
Verification of shifting assistance provided to displaced squatters and
to squatter-owners allowed to salvage their facilities
Number and nature of consultations carried out, as well as targeted
stakeholders
PAPs' perspectives on compensation procedures, entitlement packages,
and proposed alternative resettlement sites
Record of any problems due to restricted access to the highway
during construction and whether ramps/ diversions have been
provided where required
Number of grievances recorded and redressed
Number of public facilities and utilities to be relocated
Number of mosques/ shrines/ graves to be relocated (if any) and
corresponding contribution of affected communities and NHA
Verification of relocation of mosques/ shrines/ graves.
No. of
Project Stage Parameters Details of Location Frequency Responsibility Duration Cost (Rs.)
Samples
Pre-Construction/ Design
Air Quality
Baseline once
SOx
5 metres from the edge prior to
NOX
of pavement downwind 2 construction @ NHA Continuous 24 hours 50,000/-
CO
at two selected locations Rs.25,000/
PM10
location
Community groundwater
Once before
sources near the edge of
Water construction
the ROW at three
Quality 3 starts @ Rs. NHA 90,000/-
selected locations on
E- Coli 30,000/test
existing/ proposed
for 3 locations
highway
Three locations: 5 m
from the 12 hours, readings
Noise Once before start
edge of the pavement, at taken at 15 sec
Levels on of
sensitive location like 3 NHA intervals over 15 min, 12,000/-
dB(A) construction @
basic health unit, school, every hour and then
Scale Rs.4000/- source
madrassa and residential/ averaged.
commercial area.
Construction
Once every 6
months during
Air Quality 35 metres from the hot Monitoring Continuous 12 hours
construction
PM10, co, mix plant in downwind 4 Consultants or over one full 300,000/-
period @ Rs.
No2, So2 direction (MC) working day
25000/
location
No. of
Project Stage Parameters Details of Location Frequency Responsibility Duration Cost (Rs.)
Samples
Once a every 6
Ground Community groundwater
months during
Water and source near the edge of
construction and
Waste the ROW three selected
3 the start of the MC - 270,000/-
Water locations on
operation
Quality existing/proposed
phase @ Rs.
highway
30,000/test
Once every 6
5 m from edge of the 24 hours, readings
months
Noise pavement at four selected taken at 15 sec
during
Levels on locations on 4 MC intervals, over 15 min, 48,000/-
construction
dB(A) scale existing/proposed every hour, and then
phase @
highway averaged
Rs.4000/source
Two selected locations in
Once a year in
contractor‟s equipment
Oil and construction
yards, as identified by 2 MC - 4,000/-
Grease phase @
the supervision
1,000/sample
consultant
Operation
5 m from the edge of the
Pavement downwind
background
Continuous 24 hours
Air Quality concentration near a Twice a year
(Assuming three years
SOx NOX residential area at a 2 for 1 year @ Rs. MC 150,000/-
past Project
CO PM10 sensitive location e.g. 25,000/location
monitoring)
hospital or school, taken
at 2 selected locations on
the bypass
No. of
Project Stage Parameters Details of Location Frequency Responsibility Duration Cost (Rs.)
Samples
Community ground
Water Twice a year 1
water sources near ROW
Quality 2 year @ MC - 180,000/-
– two selected locations
E- Coli Rs30,000/test
on proposed bypass
Two locations: 5 metres
from the edge of 24 hours, readings
Noise Twice a year 1
pavement, at sensitive taken at 15 sec, 15 24000/-
Levels on 2 year @ Rs.4000/ MC
location and a min, every hour and
dB(A) scale source
residential/ commercial then averaged
area
Total Monitoring
1,128,000
Cost
An environmental and social training and Technical Assistance (TA) programme will
be carried out to build the NHA‟s capacity to effectively implement this EMP, as well
as to facilitate the improved environmental management of future highway Projects by
increasing the environmental and social awareness of NHA staff in general. The NHA
with the collaboration of Monitoring Consultants (MC) will arrange the environmental
training sessions for their staff. The objective of these sessions will be to help establish
appropriate systems, and to train senior NHA staff responsible for managing
environment, operations, and planning, who can then impart training at a broader level
within and outside the NHA (i.e., the training of trainers). The Consultants will
organize training courses for NHA staff, in specialized areas such as air and noise
pollution monitoring; develop environment operation manuals in consultation with the
NHA‟s Environmental wing. The details of this training program are presented in Table
8.4.
Table 8.4 Personnel Training Programme/ TA Services
Monitoring consultants/
Short lectures relating
organizations specializing in Two seminars for
to Occupational Safety 2 days
Occupational, health and contractor‟s staff
and Health
safety issues
Sr.
Activity Basis Cost (Rs.)
No.
For 85 employees for the provision of dust
masks, safety shoes, gloves, first aid box,
ear plugs, safety helmets and safety jackets
Health & Safety of
1 (Hi Vis) And 6,720,500
Workers
Provision of dust bins, warning tap, safety
cones, safety sign boards and water
sprinkling
Environmental Monitoring
2 Air, water and noise 1,128,000
Cost
Cost of environmental
4 For the whole construction period 300,000
training
The estimated Environmental Mitigation and Monitoring cost will be Rs. 11,170,084 or
Rs. 11.170 Million.
SECTION 9
9.CONCLUSIONS
9.1 GENERAL
This chapter presents conclusions of the entire EIA Report. Present Project has been
conceived to provide fast and safe access to the traffic using Dera Murad Jamali
Bypass. The conclusions are based on the findings of detailed environmental
assessment, which has been carried out as a requirement of Federal EPA.
In order to check the feasibility of the Project, an EIA study was carried out by a team
of Asif Ali & Associates experts. After carrying out detailed field surveys, it was
felt that this Project will prove to be very beneficial in overcoming the problems
being faced on N-65 at Dera Murad Jamali.
Various options were considered for this Project that included “No project”, Alternate
transport modes” and “Construction of a Bypass”. These have been discussed in detail
in Chapter 4 of this Report. The last option was selected because it fulfils the Project
requirements in the best way.
Three alternatives were discussed for the improvement of the existing carriageway i.e.
Widening of the both sides of existing road with the same alignment; up-gradation of
the existing 2 lane road into 4 lane dual carriageway by extending on both sides
from centreline of the existing road; and construction of a completely new Bypass.
After the completion of this Project, a 2 lane bypass will be available for the traffic
passing around the Dera Murad Jamali city. It will increase safety and comfort of the
travellers and also reduce the travelling time.
Availability of resources and materials for the execution of present Project has been
discussed in Chapter 2 of this Report. All the resources are available in the vicinity of
the Project Area, except reinforcement, asphalt and cement that will be purchased from
Karachi.
During the field surveys, significant efforts were made to identify the main social,
cultural and environmental issues related to the execution of this Project.
Government departments and agencies were also contacted for obtaining salient
information. Following is the list of main issues and concerns:
Resettlement of the structures, i.e. houses, shops, electric poles etc. that fall
within the design Right of Way (ROW).
Cutting o f t ree s f a l l i n g w i t h i n t h e p r o p o s e d corridor.
Due to the change in the hydrologic regime, flood water can cause damage
to the local community and road.
Disturbance to the public movement during construction.
Reduction in the business activities during construction.
Noise and air pollution due to the operating of construction machinery
during construction phase of the Project.
Solid waste generation during construction.
Oil spillages from construction machinery, resulting in soil and
groundwater contamination.
In order to overcome the social, cultural and environmental issues discussed above,
following mitigation measures have been proposed (detail available in Chapter 7):
All the affectees should be compensated for their properties, falling in the
ROW, through judicious compensation packages. For this purpose all such
structures have been measured and evaluated for their costs estimation.
Trees that are within the corridor and have to be cut down should be
compensated by planting new trees in a ratio 4:1 to the cut trees.
Provision of culverts can be made to control flood damages and
ensuring safety of embankments against floods. Drains should be designed to
take the design flows.
Informatory signs and warning boards should be displayed. Zebra Crossings
and U turns provided at appropriate places will help people safely cross
the road after the construction
Compensation should be made to the affectees for loss in business/
commercial activities.
Air and dust pollution can be controlled by equipping asphalt, hot mix and
batching plants with fabric filters or wet scrubbers to reduce the level of
dust emissions. Haul trucks carrying asphalt concrete mix and/ or aggregate
fill materials should be kept covered with tarpauli to help contain construction
material being transported between sites.
Table 9.1 summarises the overall findings and recommendations of the present EIA
Study in matrix form.
Table 9.1 Findings and Recommendations of the EIA Study
After the execution of the Project, people living in the Project Area and the travellers of
the National Highway (N-65) will get the following benefits:
Overall safety of passengers will be increased.
Less time will be required for travelling and reaching the destination.
During the construction phase, local labour will be accommodated in the
construction activities.
Economic condition of the area is expected to get uplift due to better approach
to the nearby markets.
Inter-provincial trading will get a boost due to better communication passage.
National highway Authority (NHA) and National Highway & Motorway Police
(NHMP) will take care of the bypass after construction. NHA will look after its
surface condition and make sure that there are no encroachments within the
Right of Way (ROW).
National Highway and Motorway Police (NHMP) will be responsible for ensuring
smooth traffic flow on the road. They will advise NHA to provide the required facilities
for reducing the road accidents and hazards.
During the detailed survey, Consultants‟ EIA team identified the main stakeholders of
the proposed Project and discussed the Project with them in order to get knowledge
about their concerns and worries. Chapter 7 of this Report discusses public consultation
and information disclosure in detail. It also describes the measures suggested for
mitigating these concerns.
IO44/AELIAAAPL
Client: Asif Ali & Associates (Pvr) Limited.
Date ofissue of report: 27-04-2017
Date of sampling: 18-04-2017 to 19-04-2017 '
Nature/source of sample(s): Ambient Gaseous Monitoring At Start of project Area
Testing specifications: Dragger MiniWarn/ Impingers Method
RESULTS:
ffi ;*:€
.*=**=
# :
le
i
3
iiEentration
itored pglm3
Time-weighted
average
Concentration
s mlH
s-
HeaSurr :nients in a year taken twice a week 24 hourly at uniform interv,al-
**24 howly/8 hourly va ,,8! i"
^L^ . 98o/o of the in ayear.2o/o of the time, it may exceed but not on two
consecutive days.
Suite #4, 2nd Floor, LinkArcade, Model Town Link Road, Lahore, pakistan
Off: 042-35887 517, 35841 688, 35925G93 Fax: 042-35855508
E-mail: ectech_ectech@yahoo.com Website: wwwectech.com.pk
Asisbrm€m d ECTECH Environment Consultants.
The LaboEtory is ffiedited as Environment Labmtory by trle Envircnmental Proteslion Agency, Gwemment of the punjab, Lahore.
Table 4: Showi the data rdi CO concentration in ambient air
Reference point Date Pollutant Monitoring: CO BEQS for Ambient Air
Concentration
in ambient air
,+.hry ,\y
Manaeer (Laboratorv) Countersigned by:
(Dr. Muhammad Hanif)
chemistry; Post Doctorate - Analytical chemistry Advisor Laboratory:
Director General @), PCSIR Laboratories Complex, Lahore
Director General (ex) Ministry of Environmen!
Government of Pakistan
Suite # 4, 2nd Floor, LinkArcade, Model Town Link Road, Lahore, Pakistan
Off: 042-35887 517, 35841 688, 35925693 Fax: 042-35855508
E-mail: ectech_ectech@yahoo.com Website: www.ectech.com.pk
Asisrqcmm d ECTEGH Ewironment Consultants.
The LaboEtory is amdited as Eruironment Laboratory by the Envimnmental Prctectim Agency, Gwemment of the Punjab, Lahore
DERA MURAD JAMALI BYPASS
ON NATIONAL HIGHWAY N-65
\N. tuM
MauagcrllaDoratorv) Countersigned by:
(Dr. Muhammad Hanif)
Ph.D. - Ana\tical chemistry; Post Doctorate - Analytical chemistry Advisor Laboratory:
Director General (R), PCSIR Laboratories Complex, Lahore
Director General (ex) Ministry of Environmen!
Govemment of Pakistan
Suite # 4, 2nd Floor, Link Arcade, Model Town Link Road, Lahore, Pakistan
Off: 042-35887 517, 3584'1 688, 35925693 Fax: 042-3S8S5S08
E-ma i I : ectech_ectech@ya hoo.com Website : wunar,ectech.com. pk
Asisi8rffiem d ECTECH Environment Consultants,
The LaboEtory is amredited as Envircnment Labmtory by the Environmental Protec{imAgenry, Gdemment of the punjab, Lahore.
a-
DERA MURAD JAMALI BYPASS
ON NATIONAL HIGHWAY N-65
Reference: IO44IAELIAAAPL
Client: Asif Ali & Associates @vt) Limited.
Date of issue of report: 27-04-2017
Date of sampling: l8-0 4-2017 to 19 -0 4 -20 17
Natu relsource of sample(s): At RD 06+000 Km
re
7 48 48 54 47 50.03
9-04-20 7 lm 49 45 45, 447 '€/ 47 46 47 46.75
9-04-20 7 tm 44 44* 45 49 44 44 44 45.38
9-04-20 7 tm 44
gi44
ffi
=**=
-ffi ils 42 42 43 43 43.98
9-04-20
9-04-20
9-04-20
9-04-20
7
7
7
7
0:
06:ffil
07:0U
IIn
m
41*
4
43
5t
53
55
ere -&6
46
52
59
50
46
55
55
51
46
49
55
49
48
49
62
49
48
50
58
47.30
48.54
52.41
56.9s
9-04-20 7 08:00 ffia 5==rereffigrer 55ffi53 59 61 58 58 55 57.01
ae!
"?:re..f8€'
:€i==Ell-s
BEQS limiting Value For' l'i*,. dB(A) for Day & 55 dB(A) for Night
Commercial Area dB(A)
\.\*9
(Laboratorv)
Manaeer Countersigned by:
(Dr. Muhammad Hanif;
Ph.D. - Analytical chemistry; Post Doctorate - Analytical chemistry Advisor Laboratory:
Director General @), PCSIR Laboratories Complex, Lahore
Director General (ex) Ministry of Environmen!
Government of Pakistan
Suite # 4, 2nd Floor, Link Arcade, Model Town Link Road, Lahore, Pakistan
Off: 042-35887 517, 35841 688, 35925693 Fax: 042-35855508
E-maill ectech_ectech@yahoo.com Website: www.ectech.com.pk
Asisieronem of ECTECH Environment Consulhnb.
Ihe LaboEtory is ffiedited as Envircnment Labmtory by the Envjronmental Protetion Agency, Gwemment of the Punjab, Lahore.
DERA MURAD JAMALI BYPASS
ON NATIONAL HIGHWAY N-65
Reference: IO44IAEL/AAAPL .
"N'\-^4
(Laboratorv)
Manaeer Countersigned by:
(Dr. Muhammad Hanif)
Ph.D. - Analytical chemistry; Post Doctorate - Analytical chemistry Advisor Laboratory:
Director General (R), PCSIR Laboratories Complex, Lahore
Director General (ex) Ministry of Environment,
Government of Pakistan
Suite # 4, 2nd Floor, Link Arcade, Model Town Link Road, Lahore, Pakistan
Off: 042-35887 517, 35841 688, 35925693 Fax: 042-35855508
E-mail: ectech_ectech@yahoo.com Website: www.ectech.com.pk
Asisier mem of ECTEGH Environment Consultants.
The LaboEttry is arcredited as Environment Labmtory by the Envipnmental Proteciion Agency, Gwemment of the Punjab, LahoE
DERA MURAD JAMALI BYPASS
ON NATIONAL HIGHWAY N.65
Reference: IO44IAELIAAAPL
Client: Asif Ali & Associates (Pw) Limited.
Date of issue of report: 27-04-20t7
Date of sampling: 18-04-20 17 to 19 -04-20 17
Nature/source of sample(s) : Put Feeder Canal Water
Testing specifications: APHA.USA
I Temperature OC
20 :<30C
2. pH 8.3 6-9
3. Color *# :% TCU 8 <15
4 B iochemical Oxy sffimnffi# ms/l 26 80
5. Chemical Oxldffiffi&C(ref=r ms./l 85. <150
6. Total DissffiHffiLiEFfDS) ms/l 23s <350G
7. Totalsu trffilid (TSS) ms/l 65
'* ,'€**:tgos"
8. GreasffiffiEtr# "**€***=r me/l 0.01 i
9. PherffiEiiitpoundsG mc/l* .N.D j.
I
FluffiKr 'ffi-
nfr
lt m l. l0
12. Cr g m .0.25 1.0
t3. Affi Detergerf'ts m r N.D. 20
14. srffiffi -"€=*€:= m t07 600
15. Suffiffis .*@ re m 0.08 1.0
16. anffia ;# €**€ rr 25 40
17. cal@: ffi reiiiii/l N.D.
18. Cadnffi re ffi€"me/l 0.07 0.1
19. ChromrEgii" @**ffiis/l 0.04 1.0
20. copper "'%,. :ffi W me/l 0.22 1.0
21. Lead "q&'' '.ffi mp/l 0.42 0.5
)', Mercurv ?1, mgll N.D. 0.01
23. Selenium mdl N.D. 0.5
24. Nickel me/l 0.03 1.0
25. Silver mg/l 0.39 1.0
26. Znc ms,/l 0.06 5.0
27. Arsenic mE/l 0.52 1.0
28. Barium mg/l 0.02 1.5
29. lron ms,/1 0.56 8.0
30. Manganese me/l 0.6 1.5
31. Boron mdl 0.4 6.0
32. Total Chlorine ms/l 0.12 1.0
JJ. Pesticides ms,/l N.D. 0.15
N.D. : Not Detected
N\'}', '(u$rb
Manaser (Laboratorv) Countersigned by:
(Dr. Muhammad Hanifl
Ph-D. - Analytical chemistry; Post Doctorate - Analytical chemistry Advisor Laboratory:
Director General (R), PCSIR Laboratories Complex, Lahore
Director General (ex) Ministry of Environmen!
Govemment of Pakistan
Suite # 4, 2nd Floor, Link Arcade, Model Town Link Road, Lahore, Pakistan
Off: 042-35887 517, 35841 688, 35925693 Fax: 042-35855508
E-mail : ectech_ectech@yahoo.com Website: www.ectech.com.pk
Asisftrmem of ECTECH Environment Consultants.
The LaboEtory is ffiedited as Envircnment Labffitory by he Environmental Protection Agency, Gwemment of the Punjab, Lahore.
DERA MURAD JAMALI BYPASS
ON NATIONAL HIGHWAY N-65
Reference: IO44/AELIAAAPL
Client: Asif Ali & Associates (Pvt) Limited.
Date of issue of report: 27-04-2017
Date of sampling: I 8 -04-20 17 to 19 -04-20 l7
Nature/source of sample(s): Drinking Water Murad Abro Road
Testing specifications: APHA-USA
\\\\9 qM
Manaser (Laboratory) Countersigned by:
, (Dr. Muhammad Hanif)
Ph.D. -Analytical chemistry; Post Doctorate - Analytical chemistry Advisor Laboratory
Director General (R), PCSIR Laboratories Complex, Lahore
Director General (ex) Ministry of Environmen!
Govemment of Pakistan
Suite # 4, 2nd Floor, Link Arcade, Model Town Link Road, Lahore, Pakistan
Off: 042-35887517 ,35841 688, 35925693 Fax: 042-35855508
E-mail: ectech_ectech@yahoo.com Website: www.ectech.com.pk
Asisier ffi of ECTEGH Environment Consultants:
TfE LaboEtory is amredited as Envimnment LaboEtory by the Envipnmental Prctec{ion Agency, Gwemment of the Punjab, Lahore
ANNEXURE – B
DETAILS OF LAND ACQUISITION
LIST OF LAND ACQUSITION AREAS
Area (square
Sr. No Chainage Develoment type Side
meters)
1 3+665 812.63 House R
2 3+665 1504.04 House L
3 5+253 429.25 House R
4 5+253 1103.52 House L
5 6+064 368.56 House L
6 6+350 1440.30 House R
7 6+350 1346.76 House L
8 6+760 35.40 House L
9 7+275 1185.79 House R
10 7+275 146.41 House L
11 7+400 498.51 House L
12 8+050 844.39 House L
13 8+056 10.34 House R
14 8+587 75.43 House R
15 8+600 608.18 House R
16 9+400 239.73 House L
17 9+439 56.32 House L
18 10+447 339.98 House R
19 10+447 10.26 House L
Total (Square Meters) 11055.80
Total (Marlas) 437.11
Total (acres) 2.73
LIST OF UTILITIES TO BE RELOCATED
To minimize the adverse impacts arising due to expected increase in vehicular activity from
the proposed bypass and to enhance the landscape of the project area, tree plantation will be
undertaken at available spaces along roadside. As mitigation, four (4) numbers of plants are
to be raised in lieu of each tree removed for the proposed project. Since 182 trees are
expected to remove, therefore, planting of 728 trees are to be planted in linear pattern,
keeping the distance from plant to plant as 4 meters. The planting may be carried out by the
Contractor, which has the requisite expertise and experience for such tasks.
Trees Recommended
Following tree species are recommended, in general, for planting to create aesthetic as well as
shade effect along roadside. It is also recommended that 4 to 5 years old plants, grown in the
nursery, should be procured for the purpose.
Cost
The cost of raising 500 plants has been estimated as Rs. 839,000/- including price of plants,
earthwork, procurement of manures, continued supply of water to young plants throughout
the year and its maintenance for five (5) years. Break-up of expenditure of 500 plants@ Rs.
500/- per diem is as follows.
Tree Plantation Plan
FIRST YEAR
SECOND YEAR
1
Tree Plantation Plan
THIRD YEAR
Amount
Sr. No. Item Quantity Rate
(Rs.)
Cost of Plants 10% Restocking Rs.750-
100 No. 100 No. 75,000.00
1. plant
Rs. 10/-
Cost of planting 100 No. 1000.00
2. plant
Rs. 5/-
Carriage of plants 100 No. 500.00
3. plant
5
H/watering 40 times 20,000 no. 50,000
4. MD/1000
Reopening
1000 5MD 2,500.00
5. of Pits twice (500x2)
6. Unforeseen --- ---- 1000.00
Total 1,30,000.00
FOURTH YEAR
FIFTH YEAR