Program of Works and Detailed Estimates: Central Philippines State University
Program of Works and Detailed Estimates: Central Philippines State University
Program of Works and Detailed Estimates: Central Philippines State University
Subtotal ₱ 400,000.00
TOTAL ₱ 640,000.00
2
GOVERNMENT FEES
Subtotal ₱ 300,000.00
TOTAL ₱ 300,000.00
3
TEMPORARY FACILITIES
Site office for engineer (with
aircon to be turnover) 1 l.s @ ₱ 50,000.00 ₱ 50,000.00
Temporary bunkhouse for
workers 1 l.s @ ₱ 60,000.00 ₱ 60,000.00
Temporary perimeter
enclosure 1 l.s @ ₱ 20,000.00 ₱ 20,000.00
Subtotal ₱ 130,000.00
TOTAL ₱ 130,000.00
OCCUPATIONAL SAFETY AND
4
HEALTH PROGRAM
Subtotal ₱ 282,950.00
TOTAL ₱ 282,950.00
5
SITE CLEARING AND LAY-OUTING
Removing of unnecessary
objects 1 l.s @ ₱ 280,000.00 ₱ 280,000.00
Subtotal ₱ 305,000.00
TOTAL ₱ 579,500.00
6
EXCAVATION AND DISPOSAL
Excavation for Footing and
Wall footing 681.072 cu.m. @ ₱ 500.00 ₱ 340,536.00
Disposal of Excavated
Materials 681.072 cu.m. @ ₱ 300.00 ₱ 204,321.60
Subtotal ₱ 544,857.60
TOTAL ₱ 544,857.60
7
BACKFILLING AND COMPACTION
Subtotal ₱ 594,960.00
TOTAL ₱ 773,448.00
8
GRAVEL BASE
Materials Aggregate Base Coarse (G1) 60.9 cu.m @ ₱ 650.00 ₱ 39,585.00
Subtotal ₱ 39,585.00
TOTAL ₱ 39,585.00
SOIL TREATMENT (RETICULATION
9
SYSTEM)
Subtotal ₱ 722,246.35
TOTAL ₱ 938,920.26
11
CONCRETE WORKS (4000 psi)
Materials Footing 166.04 cu.m ₱ 5,050.00 ₱ 838,502.00
Subtotal ₱ 4,337,584.38
TOTAL ₱ 5,638,859.69
STEEL REINFORCEMENTS
12
(GRADE 40)
Materials Footing 19670 kgs ₱ 47.00 ₱ 924,490.00
Subtotal ₱ 3,849,876.20
TOTAL ₱ 5,004,839.06
STEEL REINFORCEMENTS
13
(GRADE 33)
Materials Footing 54217.5 kgs ₱ 47.00 ₱ 2,548,222.50
Subtotal ₱ 5,071,725.35
TOTAL ₱ 6,593,242.96
14
MASONRY WORKS
Materials CHB (150mm) 993 sq.m ₱ 225.00 ₱ 223,425.00
Subtotal ₱ 1,228,225.40
Labor 1 l.s ₱ 368,467.62 ₱ 368,467.62
TOTAL ₱ 1,596,693.02
15
CONCRETE PLASTERING
Materials Portland Cement 1432.6 bags ₱ 260.00 ₱ 372,476.00
Subtotal ₱ 399,714.40
TOTAL ₱ 519,628.72
16
FLOOR TOPPING AND TILES
Materials Glazed Tiles 60x60cm 1583 pcs ₱ 280.00 ₱ 443,240.00
Subtotal ₱ 1,065,520.00
TOTAL ₱ 1,385,176.00
17
CEILING WORKS
Materials 4.5mm x 4ft x 8ft Hardiflex 800 shts @ ₱ 500.00 ₱ 400,000.00
Subtotal ₱ 639,500.00
TOTAL ₱ 831,350.00
FABRICATED MATERIALS AND
18
HARDWARES
TOTAL ₱ 1,500,000.00
BOOK SHEELVES AND OTHER
19
FURNITURES
SUMMARY
ITEM
NO.
1 MOBILIZATION AND DEMOBILIZATION INCL. EQUIPMENT
₱ 640,000.00
2 GOVERNMENT FEES
₱ 300,000.00
3 TEMPORARY FACILITIES
₱ 130,000.00
4 OCCUPATIONAL SAFETY AND HEALTH PROGRAM
₱ 282,950.00
5 SITE CLEARING AND LAY-OUTING
₱ 579,500.00
6 EXCAVATION AND DISPOSAL
₱ 544,857.60
7 BACKFILLING AND COMPACTION
₱ 773,448.00
8 GRAVEL BASE
₱ 39,585.00
9 SOIL TREATMENT (RETICULATION SYSTEM)
₱ 350,000.00
10 FORMWORKS AND FALSEWORKS
₱ 938,920.26
11 CONCRETE WOKRS (4000 psi)
₱ 5,638,859.69
12 STEEL REINFORCEMENTS (GRADE 40)
₱ 5,004,839.06
13 STEEL REINFORCEMENTS (GRADE 33)
₱ 6,593,242.96
14 MASONRY WORKS
₱ 1,596,693.02
15 CONCRETE PLASTERING
₱ 519,628.72
16 FLOOR TOPPING AND TILES
₱ 1,385,176.00
17 CEILING WORKS
₱ 831,350.00
18 FABRICATED MATERIALS AND HARDWARES
₱ 1,500,000.00
19 BOOK SHEELVES AND OTHER FURNITURES
₱ 1,500,000.00
20 RAILINGS
₱ 400,000.00
21 PAINTING WORKS
₱ 830,785.29
22 ELECTRICAL WORKS
₱ 3,500,000.00
23 PLUMBING WORKS
₱ 501,717.29
24 FIRE DETECTION AND ALARM SYSTEM
₱ 400,000.00
INDIRECT COST
Prepared by:
LIEZEL S. DIAZ
PMMO-Staff
Reviewed by:
Recommended by:
Funds Available:
Approved by: