Epp 0407-10-01
Epp 0407-10-01
Epp 0407-10-01
Installation Instruction
EPP-0407-10/01
Insulated T-Adaptor
Connections up to
24 kV for 630A with
Surge Arrester for
Threaded Bushings
in accordance with
DIN 47636, HN52-S-61
and EN 50181
Note:
Minimum air clearance between adaptors: 25 mm.
between surge arrestors and ground: 47 mm.
between adaptors and ground: 38 mm
Bushing Profile The adaptor should only be used on bushings with dimensions as shown in
Drawing A1 or A2.
M12
A1 A2
30 30 40
12 91.5 12 90
General Instructions Use cable lugs with holes large enough to fit over the stud. Remove any oxide
layer from the palm of an aluminium lug. Remove any sharp edges from the lug
after installation on the cable.
Use a suitable contact compound with aluminium lugs or use tinned Al or
bi-metallic lugs. Allow the termination to cool before installing the adaptor.
Installation of Termination Install the termination in accordance with the appropriate Raychem Installation
Instruction. The sheds provided in the Termination Kit are not required when
used with RICS. Use cable lugs with a maximum length of 105 mm from the
palm hole centre up to the end as shown in Drawing B. The completed
termination includes a seal onto the cable lug which should extend to not less
than 50 mm from the palm hole centre.
If the Adaptor kit includes a shim tube, shrink this onto the completed termina-
tion as shown in Drawing B.
105
B
5
shim tube
50
termination
closure cap
equipment bushing
threaded stud
insert
main body
termination
surge arrester
80
1 2 3
Apply silicon grease generously to the Push the termination into the body of Line up the hole in the lug with the
end of the termination for a distance of the adaptor. The long end of the hole in the metal insert in the adaptor.
approximately 80 mm. adaptor should face the bushing.
Apply contact compound to the surface
of the adaptor insert at the short end of
the adaptor.
Insert the threaded stud of the adaptor Apply silicon grease generously to the Push the adaptor onto the bushing.
into the bushing and tighten it up. bushing and the mating (inside) Insert the washers and hex nut.
surface of the adaptor. Tighten the large hex nut on the stud
to the torque given below.
4 A1 5 6
4 A2
70
7 8 9
Place the washer over the rod against Apply silicon grease generously to the Push the surge arrester or insulating
the hex nut. end of the surge arrester or insulating plug into the adaptor body. Align the
plug for a distance of approximately surge arrester parallel with the
80 mm. termination cable.
Align cable lug and threaded rod. Insert the washer, spring washer and Place the string in the adaptor entry as
Connect the opposite end of the surge hex nut. Tighten the large hex nut on shown.
arrester and the earth lead of the cable the stud to the torque given below.
to earth.
Bushing Thread Torque (Nm)
Type min. max.
A1 M16 50 70
A1 M16/M12 35 40
A2 M12 35 40
10 11 12
The information contained in these installation instructions is for use only by installers trained to make electrical power
installations and is intended to describe the correct method of installation for this product. However, Raychem has no
control over the field conditions which influence product installation. It is the user's responsibility
to determine the suitability of the installation method in the user's field conditions.
Raychem's only obligations are those in Raychem's standard Conditions of Sale for this product and in no case will
Raychem be liable for any other incidental, indirect or consequential damages arising from the use or misuse of the
products.