Failure of Inner Shell of Double Walled Atmospheric Ammonia Tank
Failure of Inner Shell of Double Walled Atmospheric Ammonia Tank
Failure of Inner Shell of Double Walled Atmospheric Ammonia Tank
C
oromandel Fertilizers Limited (CFL) was I km = 3,280 ft or 0.62 miles
established as an integrated fertilizer plant, in 1°C = 1.8°F
1967, to manufacture various grades of 1 m3 = 1.3079 cubic yards.
NP/NPK fertilizer. The site initially had a 360 TPD
ammonia plant, 400 TPD urea plant, 600 TPD sulfuric Background of Incident
acid plant, 255 TPD phosphoric acid plant and two
identical 550 TPD granulation trains. The plant is At the inception, manufactured ammonia was stored
located on a 480 acre site and has a captive berth at the in 2 x 1,500 MT Horton spheres, operating at 2.3
port for handling cargo. After 33 years of operation, kg/C2g. In view of the expansion of production capac-
the naphtha based ammonia/urea plants have been ity, and the decision to gradually phase out the aging
closed down due to high feedstock prices, and ammo- Horton spheres, it was decided in 1996 to put up a
nia requirements are now met through a 5.5 KM import 5,000 MT double wall, double integrity atmospheric
pipeline between our jetty and ammonia storage facili- ammonia tank, along with refrigeration compressors.
ty. Urea is also outsourced, while sulfuric acid produc- This facility was completed in March 1998.
tion is currently 1,200 TPD, and phosphoric acid 450 The shell plates, bottom plates, anchor strips, and
TPD, to supply most of the acid requirements for mak- fasteners are all of low temperature carbon steel
ing 600,000 TPY of 28:28:0, 14:35:14 and 20:20:0 (LTCS-ASTM 517 or equivalent) whereas SS304 was
grade fertilizers. used for the expansion bellows. All piping used was of
Between April 2000 to March 2001, our company seamless LTCS. Further details are given in Table 1.
had a sales turnover of approximately $135 million, During fabrication, all joints were tested by
with a profit of $15.6 million before tax. Radiography/DP. After completion, the tank and asso-
Note: We have used metric units. Typical conver- ciated fittings were inspected per API-620, with an air
sions are: test up to 1,750 MM WC for the tank and cup, after
1 kg/cm2 = 0.967 atmospheres (0.980 bar) water filling for the inner cup hydro test, followed by
DESIGN CODE
SHELL & BOTTOM : a) API 620 APPENDIX 'R' (JUNE 1990)
b) API 650 (JULY 1993) FOR SHELL STABILITY
DESIGN DATA
SHIP DATEOFSHIP SHIP NAME INITIAL FINAL OPENING STOCK SHIP DISCHARGE QTYRECD
nm mm MT MT MT
1 18.4.99 M.T.HECTOR 607 15060 157 3771 3774
"" ' : •*
Ï ;
; iStarting Completion
1 i Water fling j 14.10.99 19.10.99
2 ^Drahing of ammonia Iquorto naphtha tank [18.10.99 19.10.99
3 ;Open'ngof roof top manwaycover Î16.10.99 16.10.99
4 ; Nirogen purging i 21 .10.99 22.10.99
5 iAdrritting compressed air ;23,10.99 24.10.99
6 | Ope nhg of bottonVoutsr man hole cover j25.10.99 25.10.99
7 :Blcwerœnnectbn& disconnection ! 26.10.99 27.10.99
8 ; Inside ma nway removal ; 27 .10. 99 27.10.99
9 ; Blower connecfon&disconnectbn i27 .10.99 30.10.99
1 0 Wash hg and drain'n g of water 1 01 .1 1 . 9902.11.99
1 1 : Clean hg and drainh g th e wate r torn floor ! 03 .1 1 . 9903.11.99
1 2 : Cursory inspection i 30 .1 0.99 31.10.99
1 3 iPlatecuffing for initial inspection (Bottomplate) i04.11.99 08.11.99
14:Totalplateremoval i 09 .11. 99 16.11.99
15jShellrepair J24.11.99 04.12.99
16 Concrete Kerb repa r il9.11.99 21.11.99
17 ;Bottomplate inspection i20.11.99 20.11.99
1 8 ;Sand removal i15.11.99 20.11.99
19;Sandfling 1 21 .11. 99 25.11.99
20 Inspection of hside courses i05.11.99 03.12.99
21 ; Inspection of outside courses i 24 .11. 99 09.12.99
22';Bottomplatefixing ;27 .11.99 02.12.99
23 ; Bottom p late welding hspection -30.11. 99 03.12.99
24 : Vacuum box testing !01 .12.99 05.12.99
25; course plate ;04.12.99 05.12.99
26 ; Final hspection before water fling ; 06 .1 2.99 06.12.99
27 ilnside cup manway welding ;07 .12.99 07.12.99
28 Water fling ofcupshell J08.12.99 11.12.99
29 ;Tank shellmanway doshg i 12.12.99 12.12.99
30 .Roof manway & roof plate doshg i08.12.99 12.12.99
31 iPneumate testing of lank she! ';13.12.99 14.12.99
32 ; Reiefvalves testing & vacuum breaker testhg • 14.12.99 14.12.99
33 Water drainhg i 14.12.99 17.12.99
34 . Nirogen purging i 19.12.99 20.12.99
35 Nirogen bbnkethg i20.12.99 29.12.99
36 Ammonia vapours into the tank ;29.12.99
37 Ammonia liquid hto the tank '•_