APS Training Week 50 and 60 KW Inverter 1.27.2020
APS Training Week 50 and 60 KW Inverter 1.27.2020
APS Training Week 50 and 60 KW Inverter 1.27.2020
TRAINING PROGRAM
Training Week 1
CPS 50/60 KW
inverter
Training team
Program Manager – Bibin Babu
Service Manager – James Oswald
Application and Service
Engineering team.
Overall schematic of CPS 50/60 KW
inverters
Technical Data for 50/60 kw inverter
DC Input 50KW 60KW Environment
Max. DC Input Voltage 1000V 1000V Protection Degree NEMA 4x
Operating DC Input Cooling Variable speed cooling fans
200~950V 200~950V
Voltage Range Operating Temperature
MPPT Voltage Range 480~850V 540~850V -30℃ ~ +60℃
Range
Max. Input Current 68A/MPPT 68A/MPPT Operating Humidity 0~95%, Noncondensing
Start-up DC Input 4000M
330V/80W 330V/80W Operating Altitude
Voltage / Power (Derating from 2000M)
AC Output System
Rated AC Output Power 50KW 60KW Topology Transformer less
Max. AC Apparent Power 50kVA/55kVA 60kVA/66kVA
Max. Efficiency 98.80%
CEC Efficiency 98.5%
Rated Output Voltage 480V 480V Night Consumption <1W
Output Voltage Range 422~528V 422~528V
Display and Communication
Grid Connection Type N
3Φ/ N / PE 3Φ/ N / PE Display LCD+LED
optional
Communication Standard: RS485 (Modbus)
Max AC Output Current 60.2A/66.2A 72.2A/79.4A
Rated Output Frequency 60Hz 60Hz
Output Frequency Range 57~63Hz 57~63Hz
CPS inverter protection feature
AC output voltage and frequency monitoring
Anti-islanding detection with bi-directional frequency perturbation
DC input and AC output over-voltage protection
DC input and AC output over-current protection
DC input insulation to ground monitoring
DC injection of AC output
DC Arc-fault detection and circuit interruption
Leakage current to ground monitoring
Internal enclosure temperature monitoring
IGBT power module temperature monitoring
KVA overhead to produce rated Active Power at 0.91 power factor
Load rejection over voltage (LROV) protection
No neutral connection required - delta connection permitted with external AC GFCI
PVRSS certified rapid shutdown compliant to 2017 NEC (RSD version only).
Installation/ replacement of 50/60 kw
inverter
Cable Connection / termination
DC Cable
14-6AWG (Copper only) when terminating to the fuse holders- Can use I without the
ferrules.
6~2AWG (Copper or Aluminum) when using the Bypass Terminal kit accessory
AC Cable
AC Output terminal block #6-3/0 AWG (CU) #6-3/0 AWG (AL)
Internal grounding bar #6-4 AWG (CU)
External grounding point - #6-4 AWG (CU)
Cable Connection / termination
PV string checking procedure
Open fuse holder before connecting PV cable
Check polarity and voltage of each string should not exceed 1000V as it can cause
damage to power train in power head.
Distribute the cables evenly on all the three MPPTs.
When installing replacement 25A or 30A fuses, these fuses may not be installed in
adjacent fuse holders. An empty or unused fuse holder must be positioned
between each 25A/30A fuse within each MPPT
Use of fuses from other manufacturers or incorrectly sized fuses can cause either
equipment damage or create an unsafe working condition. Any damage resulting
from use of incompatible fuses is not covered by the CPS warranty
User Interface for 50/60 kw inverter
Main Screen For clearing protect 260 fault verify if the
For clearing Grid related fault verify if the
inverter Grid standard is set right. Otherwise
inverter PV input mode is set right. Otherwise
go to settings and change the Grid Standard.
go to settings and change the PV input mode.
When you are at the output data screen . Press down arrow key and you will be able to read the measurement data
User Interface for 50/60 kw inverter
Settings Please do not share the password ‘5555’ to unauthorized customers
Adjust Isolation
resistance threshold Voltage floating Voltage not floating
down problem in inverter problem with PV wiring
Trouble Shooting: Protect0070
GND: to B+ : to A- : to SHIELD: to
RS485_GND RS485_A+ RS485_B- chassis of
of inverter of inverter of inverter Inverter
Communication: 2 Wires or 3 Wires